CN209271842U
CN209271842U CN201821824452.1U CN201821824452U CN209271842U CN 209271842 U CN209271842 U CN 209271842U CN 201821824452 U CN201821824452 U CN 201821824452U CN 209271842 U CN209271842 U CN 209271842U
Authority
CN
China
Prior art keywords
furnace body
furnace
exhaust gas
top surface
spraying
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821824452.1U
Other languages
Chinese (zh)
Inventor
冼炳英
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Jiang Sheng Aluminum Industry Co Ltd
Original Assignee
Guangdong Jiang Sheng Aluminum Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Jiang Sheng Aluminum Industry Co Ltd filed Critical Guangdong Jiang Sheng Aluminum Industry Co Ltd
Priority to CN201821824452.1U priority Critical patent/CN209271842U/en
Application granted granted Critical
Publication of CN209271842U publication Critical patent/CN209271842U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P70/00—Climate change mitigation technologies in the production process for final industrial or consumer products
    • Y02P70/10—Greenhouse gas [GHG] capture, material saving, heat recovery or other energy efficient measures, e.g. motor control, characterised by manufacturing processes, e.g. for rolling metal or metal working

Landscapes

  • Waste-Gas Treatment And Other Accessory Devices For Furnaces (AREA)

Abstract

The utility model discloses a kind of spraying aluminum profile curing ovens.It includes furnace body, and the furnace body, which is equipped in entrance and exit and furnace body, is equipped with direct tunnel formula hot air circulation drying tunnel and suspension conveying line;The furnace body top surface of the corresponding furnace body entrance is equipped with the first extractor fan;The furnace body top surface of the corresponding furnace body outlet is equipped with the second extractor fan;First extractor fan and the second extractor fan convey air hose by exhaust gas respectively and connect with a waste gas purification apparatus.It further include a residual heat using device, second extractor fan conveys air hose by exhaust gas and connect with the residual heat using device, which conveys air hose by exhaust gas and connect with the waste gas purification apparatus.The utility model can effectively collect exhaust gas caused by the curing oven course of work and can focus on and recycle heat, have preferable effects of energy saving and emission reduction.

Description

一种铝型材喷涂固化炉An aluminum profile spraying curing furnace

技术领域technical field

本实用新型涉及一种用于铝型材喷涂生产线的铝型材喷涂固化炉。The utility model relates to an aluminum profile spraying curing furnace used in an aluminum profile spraying production line.

背景技术Background technique

目前,铝型材喷涂生产线主要由前处理设备、喷涂机和固化炉组成,其中固化炉是用于对喷涂在铝型材表面的涂膜层进行加热固化。由于固化炉能耗较大且会产生夹杂油漆成分并带有热量的废气。而现有的固化炉虽然有废气收集装置,但多未经处理而直接排空,由此对周边环境造成污染,也造成一定的能源损耗。At present, the aluminum profile spraying production line is mainly composed of pretreatment equipment, spraying machine and curing furnace, wherein the curing furnace is used to heat and cure the coating layer sprayed on the surface of aluminum profiles. Because the curing furnace consumes a lot of energy and produces waste gas containing paint components and heat. However, although the existing curing furnaces have exhaust gas collection devices, most of them are directly emptied without treatment, which causes pollution to the surrounding environment and also causes certain energy consumption.

实用新型内容Utility model content

本实用新型的目的在于提供一种铝型材喷涂固化炉,以有效解决现有技术的不足之处。The purpose of the utility model is to provide an aluminum profile spraying curing furnace to effectively solve the shortcomings of the prior art.

为达到上述目的,本实用新型采用如下技术方案:In order to achieve the above object, the utility model adopts the following technical solutions:

一种铝型材喷涂固化炉,包括炉体,所述炉体设有入口和出口,及炉体内设有直通隧道式热风循环烘道和悬挂输送线;对应所述炉体入口的炉体顶面设有第一抽风装置;对应所述炉体出口的炉体顶面设有第二抽风装置;所述第一抽风装置和第二抽风装置分别通过废气输送风管与一个废气净化装置连接。An aluminum profile spraying and curing furnace, comprising a furnace body, the furnace body is provided with an inlet and an outlet, and the furnace body is provided with a straight-through tunnel type hot air circulation drying tunnel and a hanging conveying line; the top surface of the furnace body corresponding to the furnace body entrance A first exhaust device is provided; a second exhaust device is provided on the top surface of the furnace body corresponding to the outlet of the furnace body; the first exhaust device and the second exhaust device are respectively connected to an exhaust gas purification device through an exhaust gas conveying duct.

进一步,本实用新型还包括一个余热利用装置,所述第二抽风装置通过废气输送风管与该余热利用装置连接,该余热利用装置通过废气输送风管与所述废气净化装置连接。Further, the utility model also includes a waste heat utilization device, the second exhaust device is connected to the waste heat utilization device through a waste gas delivery duct, and the waste heat utilization device is connected to the waste gas purification device through a waste gas delivery duct.

作为优选,所述炉体对应所述入口设有入口隔室,所述第一抽风装置对应设置在入口隔室的炉体顶面。Preferably, the furnace body is provided with an inlet compartment corresponding to the entrance, and the first ventilation device is correspondingly arranged on the top surface of the furnace body of the inlet compartment.

作为优选,所述炉体对应所述出口设有出口隔室,所述第二抽风装置对应设置在出口隔室的炉体顶面。Preferably, the furnace body is provided with an outlet compartment corresponding to the outlet, and the second exhaust device is correspondingly arranged on the top surface of the furnace body of the outlet compartment.

作为优选,所述出口隔室的底面设有若干个鼓风机。Preferably, several blowers are provided on the bottom surface of the outlet compartment.

作为优选,所述隧道式热风循环烘道包括前炉段和后炉段,所述前炉段和后炉段之间设有中间隔室,对应所述中间隔室的炉体顶面设有第三抽风装置,所述第三抽风装置通过废气输送风管与所述余热利用装置连接。As a preference, the tunnel-type hot air circulation drying tunnel includes a front furnace section and a rear furnace section, an intermediate compartment is provided between the front furnace section and the rear furnace section, and a furnace body top surface corresponding to the intermediate compartment is provided with A third ventilation device, the third ventilation device is connected to the waste heat utilization device through an exhaust gas delivery duct.

进一步,本实用新型还包括一个送风装置,所述送风装置对应所述前炉段前端的炉体顶面设置并通过送风管与所述余热利用装置连接。Further, the utility model also includes an air supply device, which is arranged corresponding to the top surface of the furnace body at the front end of the front furnace section and connected to the waste heat utilization device through an air supply pipe.

本实用新型通过采用上述结构,能有效收集固化炉工作过程所产生的废气并能集中处理及回收热量,具有较好的节能减排效果。By adopting the above-mentioned structure, the utility model can effectively collect the waste gas produced in the working process of the curing furnace, and can centrally process and recover heat, and has better energy-saving and emission-reducing effects.

附图说明Description of drawings

图1是本实用新型的立体结构示意图。Fig. 1 is the three-dimensional structure schematic diagram of the present utility model.

图2是本实用新型的侧视结构示意图。Fig. 2 is a side view structural diagram of the utility model.

图中:In the picture:

炉体1;入口11;出口12;入口隔室13;出口隔室14;中间隔室15;前炉段16;后炉段17;悬挂输送线2;第一抽风装置31;第二抽风装置32;第三抽风装置33;废气输送风管4;废气净化装置5;余热利用装置6;送风装置61;送风管62;鼓风机7。Furnace body 1; entrance 11; exit 12; entrance compartment 13; exit compartment 14; middle compartment 15; front furnace section 16; rear furnace section 17; 32 ; the third ventilation device 33 ; the waste gas conveying air pipe 4 ; the waste gas purification device 5 ; the waste heat utilization device 6 ; the air supply device 61 ; the air supply pipe 62 ; the blower 7 .

现结合附图和实施例对本实用新型作进一步详细说明。Now in conjunction with accompanying drawing and embodiment the utility model is described in further detail.

具体实施方式Detailed ways

如图1所示,本实用新型所述的一种铝型材喷涂固化炉,包括炉体1,炉体设有入口11和出口12,及炉体有直通隧道式热风循环烘道(图中未画出)、悬挂输送线2、第一抽风装置31、第二抽风装置32、第三抽风装置33、废气输送风管4、废气净化装置5、余热利用装置6、送风装置61、送风管62和若干个鼓风机7等部件。As shown in Figure 1, a kind of aluminum profile spray curing furnace described in the utility model comprises furnace body 1, and furnace body is provided with inlet 11 and outlet 12, and furnace body has straight-through tunnel type hot air circulation oven (not shown in the figure) draw), suspension conveying line 2, the first exhaust device 31, the second exhaust device 32, the third exhaust device 33, the waste gas conveying duct 4, the waste gas purification device 5, the waste heat utilization device 6, the air supply device 61, the air supply Pipe 62 and several air blowers 7 and other components.

所述的炉体1自入口11至出口12依次分隔成入口隔室13、前炉段16、中间隔室15、后炉段17和出口隔室14。The furnace body 1 is sequentially divided into an inlet compartment 13 , a front furnace section 16 , a middle compartment 15 , a rear furnace section 17 and an outlet compartment 14 from the entrance 11 to the exit 12 .

所述的第一抽风装置31设置在入口隔室13的炉体顶面,并通过废气输送风管4与废气净化装置5连接。The first ventilation device 31 is arranged on the top surface of the furnace body of the inlet compartment 13 , and is connected to the exhaust gas purification device 5 through the exhaust gas delivery duct 4 .

所述的第二抽风装置32设置在出口隔室14的炉体顶面,并通过废气输送风管4与余热利用装置6连接。The second exhaust device 32 is arranged on the top surface of the furnace body of the outlet compartment 14 , and is connected to the waste heat utilization device 6 through the exhaust gas conveying air pipe 4 .

所述的第三抽风装置33设置在中间隔室15的炉体顶面,并通过废气输送风管4与余热利用装置连接。The third ventilation device 33 is arranged on the top surface of the furnace body of the middle compartment 15 and is connected to the waste heat utilization device through the waste gas conveying air pipe 4 .

所述的余热利用装置6通过废气输送风管4与废气净化装置5连接。The waste heat utilization device 6 is connected to the exhaust gas purification device 5 through the exhaust gas conveying air pipe 4 .

所述的送风装置6设置在前炉段16前端的炉体顶面,并通过送风管61与余热利用装置6连接。The air supply device 6 is arranged on the top surface of the furnace body at the front end of the fore furnace section 16 , and is connected to the waste heat utilization device 6 through the air supply pipe 61 .

所述的若干个鼓风机7设置在出口隔室14的底面。Said several blowers 7 are arranged on the bottom surface of the outlet compartment 14 .

本实用新型的工作过程如下:The working process of the present utility model is as follows:

从喷涂机出来的铝型材由悬挂输送线经入口送入固化炉,并依次经过入口隔室、前炉段、中间隔室、后炉段和出口隔室进行加热固化处理。在这个过程中,铝型材从喷涂机带出的废气在入口隔室处被第一抽风装置抽送到废气净化装置进行集中处理;在前炉段所产生的高温废气在中间隔室处被第三抽风装置抽送到余热利用装置进行热交换处理后降温输送到废气净化装置进行集中处理;在后炉段所产生的高温废气在出口隔室处被第二抽风装置抽送到余热利用装置进行热交换处理后降温输送到废气净化装置进行集中处理。而余热利用装置将通过热交换生成的热风通过送风管及送风装置送入前炉段,对铝型材进行预加热。设置在出口隔室处的鼓风机产生自下而上的风,从而在出口12处形成风帘,能进一步防止废气从固化炉内逸出。The aluminum profiles coming out of the spraying machine are sent to the curing furnace through the entrance by the hanging conveyor line, and then go through the entrance compartment, the front furnace section, the middle compartment, the back furnace section and the exit compartment for heating and curing treatment. In this process, the exhaust gas brought by the aluminum profile from the spraying machine is pumped to the exhaust gas purification device by the first exhaust device at the inlet compartment for centralized treatment; the high-temperature exhaust gas generated in the front furnace section is pumped by the third The exhaust device is pumped to the waste heat utilization device for heat exchange treatment, then cooled and transported to the exhaust gas purification device for centralized treatment; the high-temperature exhaust gas generated in the rear furnace section is pumped to the waste heat utilization device by the second exhaust device at the outlet compartment for heat exchange treatment After cooling, it is transported to the exhaust gas purification device for centralized treatment. The waste heat utilization device sends the hot air generated by heat exchange into the forehearth section through the air supply pipe and the air supply device to preheat the aluminum profiles. A blower arranged at the outlet compartment generates a bottom-up wind, thereby forming an air curtain at the outlet 12, which further prevents exhaust gases from escaping from the curing oven.

Claims (7)

1.一种铝型材喷涂固化炉,包括炉体,所述炉体设有入口和出口,及炉体内设有直通隧道式热风循环烘道和悬挂输送线,其特征在于,对应所述炉体入口的炉体顶面设有第一抽风装置;对应所述炉体出口的炉体顶面设有第二抽风装置;所述第一抽风装置和第二抽风装置分别通过废气输送风管与一个废气净化装置连接。1. An aluminum profile spraying curing furnace, comprising a furnace body, the furnace body is provided with an inlet and an outlet, and the furnace body is provided with a straight-through tunnel type hot air circulation drying channel and a suspension conveyor line, it is characterized in that, corresponding to the furnace body The top surface of the furnace body at the entrance is provided with a first draft device; the top surface of the furnace body corresponding to the outlet of the furnace body is provided with a second draft device; Exhaust gas cleaning device connection. 2.根据权利要求1所述的一种铝型材喷涂固化炉,其特征在于,还包括一个余热利用装置,所述第二抽风装置通过废气输送风管与该余热利用装置连接,该余热利用装置通过废气输送风管与所述废气净化装置连接。2. A spraying and curing furnace for aluminum profiles according to claim 1, characterized in that it also includes a waste heat utilization device, the second exhaust device is connected with the waste heat utilization device through a waste gas delivery duct, and the waste heat utilization device It is connected with the exhaust gas purification device through the exhaust gas conveying air pipe. 3.根据权利要求1所述的一种铝型材喷涂固化炉,其特征在于,所述炉体对应所述入口设有入口隔室,所述第一抽风装置对应设置在入口隔室的炉体顶面。3. A spraying and curing furnace for aluminum profiles according to claim 1, wherein the furnace body is provided with an entrance compartment corresponding to the entrance, and the first exhaust device is corresponding to the furnace body arranged in the entrance compartment top surface. 4.根据权利要求1所述的一种铝型材喷涂固化炉,其特征在于,所述炉体对应所述出口设有出口隔室,所述第二抽风装置对应设置在出口隔室的炉体顶面。4. A spraying and curing furnace for aluminum profiles according to claim 1, characterized in that, the furnace body is provided with an outlet compartment corresponding to the outlet, and the second exhaust device corresponds to the furnace body arranged in the outlet compartment top surface. 5.根据权利要求4所述的一种铝型材喷涂固化炉,其特征在于,所述出口隔室的底面设有若干个鼓风机。5. A spraying and curing furnace for aluminum profiles according to claim 4, characterized in that, the bottom surface of the outlet compartment is provided with several air blowers. 6.根据权利要求2所述的一种铝型材喷涂固化炉,其特征在于,所述隧道式热风循环烘道包括前炉段和后炉段,所述前炉段和后炉段之间设有中间隔室,对应所述中间隔室的炉体顶面设有第三抽风装置,所述第三抽风装置通过废气输送风管与所述余热利用装置连接。6. A spraying and curing furnace for aluminum profiles according to claim 2, wherein the tunnel-type hot air circulation drying tunnel includes a front furnace section and a rear furnace section, and a furnace section is arranged between the front furnace section and the rear furnace section. There is an intermediate compartment, and a third exhaust device is provided on the top surface of the furnace body corresponding to the intermediate compartment, and the third exhaust device is connected to the waste heat utilization device through an exhaust gas conveying duct. 7.根据权利要求6所述的一种铝型材喷涂固化炉,其特征在于,还包括一个送风装置,所述送风装置对应所述前炉段前端的炉体顶面设置并通过送风管与所述余热利用装置连接。7. A spraying and curing furnace for aluminum profiles according to claim 6, characterized in that it also includes an air supply device, the air supply device is set corresponding to the top surface of the furnace body at the front end of the fore furnace section and passes the air supply The pipe is connected with the waste heat utilization device.
CN201821824452.1U 2018-11-06 2018-11-06 A kind of spraying aluminum profile curing oven Expired - Fee Related CN209271842U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821824452.1U CN209271842U (en) 2018-11-06 2018-11-06 A kind of spraying aluminum profile curing oven

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821824452.1U CN209271842U (en) 2018-11-06 2018-11-06 A kind of spraying aluminum profile curing oven

Publications (1)

Publication Number Publication Date
CN209271842U true CN209271842U (en) 2019-08-20

Family

ID=67600438

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821824452.1U Expired - Fee Related CN209271842U (en) 2018-11-06 2018-11-06 A kind of spraying aluminum profile curing oven

Country Status (1)

Country Link
CN (1) CN209271842U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116809353A (en) * 2023-06-25 2023-09-29 佛山市三水凤铝铝业有限公司 A kind of curing oven and its use method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116809353A (en) * 2023-06-25 2023-09-29 佛山市三水凤铝铝业有限公司 A kind of curing oven and its use method

Similar Documents

Publication Publication Date Title
CN108149000A (en) A kind of energy-saving continuous heat system and its heat treatment method
CN108148999A (en) A kind of pre-heating system and its pre-heating mean suitable for continuous annealing and galvanizing
CN106440836A (en) Ceramic energy-saving furnace kiln capable of high-efficiently replaying, recovering and cooling waste heat
CN203944539U (en) A kind of shell surface film curing drying plant
CN101697295B (en) Method and equipment for utilizing catalytic heat energy of microwire enameling machine
CN104611871A (en) Textile shaping and drying all-in-one machine
CN103212527A (en) Novel automobile baking finish house by utilizing negative pressure and circulating air
CN209388781U (en) A kind of horizontal enameling machine
CN204866318U (en) Automatic drying device sprays paint
CN206215485U (en) A high-efficiency and energy-saving high-temperature infrared curing device
CN207259539U (en) A kind of combustion gas trolley tempering furnace
CN204560764U (en) Tunnel hot-air oven
CN201317871Y (en) Distributed mounting and connecting structure of waste heat recovery device of forming machine
CN203281489U (en) Negative pressure environment-friendly car baking finish house
CN209362925U (en) An independent version coating oven device
CN201868156U (en) An energy-saving enameled wire drying furnace heated by hot air circulation
CN206131029U (en) Automobile coating radiation area heating furnace waste heat recovery device
CN206897771U (en) A kind of vertical spraying curing oven
CN214426196U (en) An energy-saving hot blast stove
CN207616861U (en) A kind of drying system for eliminating ceramic tile blank alligatoring
CN205228190U (en) Cyclic utilization cooling waste heat improves energy -conserving kiln of combustion -supporting wind -warm syndrome degree
CN204902458U (en) Disappearance mould baking house of cycle operation
CN206598427U (en) A kind of environmentally friendly integral core conveying belt plasticizing apparatus of direct combustion gas blowout formula
CN209456521U (en) A high-energy-efficiency bright annealing furnace for steel pipes
CN222057948U (en) Breeze assisted circulation radiation furnace

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190820

CF01 Termination of patent right due to non-payment of annual fee