CN209260153U - A kind of forging material quickly cooling device - Google Patents
A kind of forging material quickly cooling device Download PDFInfo
- Publication number
- CN209260153U CN209260153U CN201920039443.XU CN201920039443U CN209260153U CN 209260153 U CN209260153 U CN 209260153U CN 201920039443 U CN201920039443 U CN 201920039443U CN 209260153 U CN209260153 U CN 209260153U
- Authority
- CN
- China
- Prior art keywords
- water
- partition
- reservoir chamber
- rack
- forging material
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P10/00—Technologies related to metal processing
- Y02P10/20—Recycling
Abstract
The utility model discloses a kind of forging material quickly cooling devices, including rack, partition is fixedly connected with below the machine frame inside, machine frame inside below the partition is equipped with reservoir chamber, and water pump is equipped with inside the reservoir chamber, is equipped with support plate above the reservoir chamber, the machine frame inside top is fixedly connected with bracket, the bracket bottom end is equipped with drainpipe, and the drainpipe bottom end is equipped with spray head several groups, and machine frame inside top two sides are fixedly connected to fixing seat.The wind of air blower bulging is from exhaust manifold to exhaust branch pipe, finally steel surface is ejected to from exhaust branch pipe, so that the wind that the water of steel surface is blown out quickly dries up, accelerate the water evaporation of steel surface, so that vapor quickly takes away the heat of steel surface, accelerate the cooling velocity of steel, improves production efficiency, the gas of exhaust branch pipe discharge simultaneously quickly can carry out fast cooling to the water after spray, so that water temperature is unlikely excessively high when being recycled.
Description
Technical field
The utility model relates to forge material production equipment technology, specially a kind of forging material quickly cooling device.
Background technique
Bath water cooling treatment again after needing to be heated metal steel in metal heating processing technology.Such as application No. is
A kind of annealing device of metal forging material of CN201720367832.6, the pedestal including hollow structure weld on the pedestal
Have heat treatment box, and in heat treatment box vertically be equipped with partition, the both ends of partition respectively with the top inner wall of heat treatment box and bottom
Inner wall welding, the inside of heat treatment box is divided by partition heats room and the cooling chamber positioned at heating room side, and partition is outer
It is provided with opening on wall, and electric control valve is installed on the inner wall being open, heating room is connected with cooling chamber by electric control valve.
Above-mentioned apparatus has following defects that 1 when carrying out cooling treatment, directly carries out the cooling effect of spray head cold water treatment
Fruit is general;2, a large amount of vapor is generated indoors when cooling, is influenced the sight of operator, is unfavorable for the progress of work;3, it sprays
The water that head sprays can not be recycled, waste water resource, so providing a kind of forging material quickly cooling device to solve
State the problem very it is necessary to.
Utility model content
The purpose of this utility model is to provide a kind of forging material quickly cooling devices, to solve to propose in above-mentioned background technique
The problem of.
To achieve the above object, the utility model provides the following technical solutions: a kind of forging material quickly cooling device, including machine
Frame, the machine frame inside lower section are fixedly connected with partition, and the machine frame inside below the partition is equipped with reservoir chamber, the reservoir chamber
Inside is equipped with water pump, is equipped with support plate above the reservoir chamber, the machine frame inside top is fixedly connected with bracket, described
Bracket bottom end is equipped with drainpipe, and the drainpipe bottom end is equipped with spray head several groups, and machine frame inside top two sides are solid
Surely it is connected with fixing seat, air blower is installed below the fixing seat, the machine frame inside two sidewalls are mounted on exhaust manifold,
One side-lower of exhaust manifold is communicated with exhaust branch pipe several groups, and the air blower output end is connected to exhaust manifold upper end,
The water pump output end is connected to drainpipe by water pipe.
Steel after this setting heating are placed on above support plate, and water pump extracts the clear water inside reservoir chamber and extremely drains
Pipe, be ejected on steel surface from the spray head below drainpipe, while air blower bulging wind from exhaust manifold to exhaust branch pipe,
It finally is ejected to steel surface from exhaust branch pipe, so that the wind that the water of steel surface is blown out quickly dries up, accelerates steel surface
Water evaporation accelerate the cooling velocity of steel so that vapor quickly takes away the heat of steel surface, improve production efficiency, together
When exhaust branch pipe discharge gas can quickly to after spray water carry out fast cooling so that be recycled when the unlikely mistake of water temperature
It is high.
Preferably, the machine frame inside bottom end between bracket described in two groups is equipped with suspended hood, peace at the upper side of the rack
Equipped with exhaust pump, the exhaust pump output terminal is connected to suspended hood upper end by connecting tube.
This setting exhaust pump output terminal and connecting tube are connected to outdoor, so that the vapor quilt that steel surface water drenching generates
After suspended hood is drawn, outdoor is expelled to by exhaust pump, so that office work has good clearly environment.
Preferably, the suspended hood inner bottom is equipped with the second filter screen.
This second filter screen of setting is to have prevented larger object or scrap from entering to inside suspended hood.
Preferably, the partition is inverted trapezoidal structure, is equipped with the first filter screen above the partition, and be provided on partition
Second drainage hole several groups.
The water that this setting is fallen from support plate is entered in reservoir chamber after the first filter screen filtration from the second drainage hole
Portion can be recycled.
Preferably, the first drainage hole several groups are provided in the support plate.
Water after this setting spray is fallen into above partition from the first drainage hole.
Preferably, one side-lower of reservoir chamber is equipped with discharge outlet.
This is arranged when needing replacing clear water inside reservoir chamber, can be by discharge outlet for being discharged inside reservoir chamber
Waste water.
Detailed description of the invention
Fig. 1 is the utility model schematic view of the front view;
Fig. 2 is the utility model suspended hood present invention looks up structural representation;
Fig. 3 is the utility model support plate overlooking structure diagram.
In figure: 1, rack;2, partition;3, reservoir chamber;4, water pump;5, support plate;6, bracket;7, drainpipe;8, spray head;9,
Fixing seat;10, air blower;11, exhaust manifold;12, exhaust branch pipe;13, suspended hood;14, exhaust pump;15, the first drainage hole;
16, the second drainage hole;17, the first filter screen;18, the second filter screen;19, discharge outlet.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work
Every other embodiment obtained, fall within the protection scope of the utility model.
Fig. 1-3 is please referred to, the utility model provides a kind of technical solution: a kind of forging material quickly cooling device, including rack
1,1 lower inside of rack is fixedly connected with partition 2, is equipped with reservoir chamber 3, the storage inside the rack 1 of 2 lower section of partition
Water pump 4 is installed inside water chamber 3, support plate 5 is installed above the reservoir chamber 3,1 inner tip of rack is fixedly connected with
Bracket 6,6 bottom end of bracket are equipped with drainpipe 7, and 7 bottom end of drainpipe is equipped with 8 several groups of spray head, in the rack 1
Portion, two sides, top are fixedly connected to fixing seat 9, and air blower 10, the 1 inside two sides of rack are equipped with below the fixing seat 9
Wall is mounted on exhaust manifold 11, and 11 1 side-lower of exhaust manifold is communicated with 12 several groups of exhaust branch pipe, the air blower
10 output ends are connected to 11 upper end of exhaust manifold, and 4 output end of water pump is connected to drainpipe 7 by water pipe.
1 inner bottom of rack between bracket 6 described in two groups is equipped with suspended hood 13, installs at the upper side of the rack 1
There is exhaust pump 14,14 output end of exhaust pump is connected to 13 upper end of suspended hood by connecting tube, wherein 14 output end of exhaust pump
Outdoor is connected to by connecting tube.13 inner bottom of suspended hood is equipped with the second filter screen 18.The partition 2 is inverted trapezoidal
Structure is equipped with the first filter screen 17 above the partition 2, and is provided with 16 several groups of the second drainage hole on partition 2.The support
15 several groups of the first drainage hole are provided on plate 5.3 one side-lower of reservoir chamber is equipped with discharge outlet 19.
Working principle: the steel after heating are placed on 5 top of support plate, and water pump 4 extracts the clear water inside reservoir chamber 3 to row
Water pipe 7 is ejected on steel surface from the spray head 8 of the lower section of drainpipe 7, at the same the wind that bloats of air blower 10 from exhaust manifold 11 to
Exhaust branch pipe 12 is finally ejected to steel surface from exhaust branch pipe 12, so that the wind that the water of steel surface is blown out quickly dries up,
The water evaporation for accelerating steel surface accelerates the cooling velocity of steel so that vapor quickly takes away the heat of steel surface, improves
Production efficiency, while the gas that exhaust branch pipe 12 is discharged quickly can carry out fast cooling to the water after spray, so that clear water follows
Water temperature is unlikely excessively high when ring uses;14 output end of exhaust pump and connecting tube are connected to outdoor, so that steel surface water drenching generated
After vapor is drawn by suspended hood 13, outdoor is expelled to by exhaust pump 14, so that office work has good clearly environment;
Water after spray is fallen into above partition 2 from the first drainage hole 15;The water fallen from support plate 5 by the first filter screen 17 filter after from
Second drainage hole 16 is entered to inside reservoir chamber 3 and can be recycled.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art,
It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired
Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.
Claims (6)
1. a kind of forging material quickly cooling device, including rack (1), it is characterised in that: rack (1) lower inside is fixedly connected
Have partition (2), be equipped with reservoir chamber (3) inside the rack (1) below the partition (2), water is installed inside the reservoir chamber (3)
It pumping (4), is equipped with support plate (5) above the reservoir chamber (3), rack (1) inner tip is fixedly connected with bracket (6),
Bracket (6) bottom end is equipped with drainpipe (7), and drainpipe (7) bottom end is equipped with spray head (8) several groups, the rack
(1) inner tip two sides are fixedly connected to fixing seat (9), are equipped with air blower (10), the machine below the fixing seat (9)
The internal two sidewalls of frame (1) are mounted on exhaust manifold (11), and (11) one side-lower of exhaust manifold is communicated with exhaust branch pipe
(12) several groups, air blower (10) output end are connected to exhaust manifold (11) upper end, and water pump (4) output end passes through water
Pipe is connected to drainpipe (7).
2. a kind of forging material quickly cooling device according to claim 1, it is characterised in that: between bracket described in two groups (6)
Rack (1) inner bottom be equipped with suspended hood (13), exhaust pump (14), the row are installed at the upper side of the rack (1)
Air pump (14) output end is connected to suspended hood (13) upper end by connecting tube.
3. a kind of forging material quickly cooling device according to claim 2, it is characterised in that: suspended hood (13) inner bottom
End is equipped with the second filter screen (18).
4. a kind of forging material quickly cooling device according to claim 1, it is characterised in that: the partition (2) is inverted trapezoidal
Structure, partition (2) top is equipped with the first filter screen (17), and the second drainage hole (16) several groups are provided on partition (2).
5. a kind of forging material quickly cooling device according to claim 1, it is characterised in that: be provided on the support plate (5)
First drainage hole (15) several groups.
6. a kind of forging material quickly cooling device according to claim 1, it is characterised in that: under reservoir chamber (3) side
Side is equipped with discharge outlet (19).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920039443.XU CN209260153U (en) | 2019-01-10 | 2019-01-10 | A kind of forging material quickly cooling device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920039443.XU CN209260153U (en) | 2019-01-10 | 2019-01-10 | A kind of forging material quickly cooling device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209260153U true CN209260153U (en) | 2019-08-16 |
Family
ID=67584353
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201920039443.XU Active CN209260153U (en) | 2019-01-10 | 2019-01-10 | A kind of forging material quickly cooling device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209260153U (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110666141A (en) * | 2019-10-24 | 2020-01-10 | 金堆城钼业股份有限公司 | Ferromolybdenum ingot quenching device and quenching method thereof |
CN111069319A (en) * | 2019-11-26 | 2020-04-28 | 湖州吴兴珀莱机械厂 | Quick cooling device is used in steel pipe production |
CN111496613A (en) * | 2020-05-21 | 2020-08-07 | 陈晨 | High efficiency work piece processing is with cooling grinding device |
CN111981766A (en) * | 2020-07-31 | 2020-11-24 | 宿州市光明食品有限公司 | Quick cooling device is used in canned fruit production |
CN112375889A (en) * | 2020-11-11 | 2021-02-19 | 嘉兴恒瑞金属科技股份有限公司 | Tempering equipment for high-wear-resistance fastener |
CN112902523A (en) * | 2021-01-15 | 2021-06-04 | 江苏骏茂新材料科技有限公司 | Adjusting device for cooling in steel processing production |
CN114193694A (en) * | 2021-12-02 | 2022-03-18 | 苏州明睿威尔新型材料有限公司 | Bubble is moulded production with intelligent control temperature hydraulic pressure's frequency conversion cooling device |
CN114309095A (en) * | 2022-01-06 | 2022-04-12 | 浙江九钢金属制品有限公司 | Cooling bed with water cooling device for flat-bulb steel production |
-
2019
- 2019-01-10 CN CN201920039443.XU patent/CN209260153U/en active Active
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110666141A (en) * | 2019-10-24 | 2020-01-10 | 金堆城钼业股份有限公司 | Ferromolybdenum ingot quenching device and quenching method thereof |
CN110666141B (en) * | 2019-10-24 | 2021-08-24 | 金堆城钼业股份有限公司 | Ferromolybdenum ingot quenching device and quenching method thereof |
CN111069319A (en) * | 2019-11-26 | 2020-04-28 | 湖州吴兴珀莱机械厂 | Quick cooling device is used in steel pipe production |
CN111069319B (en) * | 2019-11-26 | 2022-06-03 | 东莞市必富模具钢材有限公司 | Quick cooling device is used in steel pipe production |
CN111496613A (en) * | 2020-05-21 | 2020-08-07 | 陈晨 | High efficiency work piece processing is with cooling grinding device |
CN111496613B (en) * | 2020-05-21 | 2021-09-17 | 沈阳卓信航福航空科技有限公司 | High efficiency work piece processing is with cooling grinding device |
CN111981766A (en) * | 2020-07-31 | 2020-11-24 | 宿州市光明食品有限公司 | Quick cooling device is used in canned fruit production |
CN112375889A (en) * | 2020-11-11 | 2021-02-19 | 嘉兴恒瑞金属科技股份有限公司 | Tempering equipment for high-wear-resistance fastener |
CN112902523A (en) * | 2021-01-15 | 2021-06-04 | 江苏骏茂新材料科技有限公司 | Adjusting device for cooling in steel processing production |
CN114193694A (en) * | 2021-12-02 | 2022-03-18 | 苏州明睿威尔新型材料有限公司 | Bubble is moulded production with intelligent control temperature hydraulic pressure's frequency conversion cooling device |
CN114193694B (en) * | 2021-12-02 | 2022-09-13 | 苏州明睿威尔新型材料有限公司 | Bubble is moulded production with intelligent control temperature hydraulic pressure's frequency conversion cooling device |
CN114309095A (en) * | 2022-01-06 | 2022-04-12 | 浙江九钢金属制品有限公司 | Cooling bed with water cooling device for flat-bulb steel production |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN209260153U (en) | A kind of forging material quickly cooling device | |
CN206185028U (en) | Aluminum hull stamping die with automatically function of cooling down | |
CN206646137U (en) | Desulfurization station dust arrester | |
CN207356839U (en) | A kind of new electric automatization dust-extraction unit | |
CN109554522A (en) | A kind of fastener quenching treatment equipment | |
CN209062317U (en) | A kind of gas cutting machine | |
CN210817215U (en) | Cooling device for ring rolling forging | |
CN208643474U (en) | A kind of lithium cell production cleaning device | |
CN209206424U (en) | Low pressure casting Temperature Field Control system | |
CN202902499U (en) | Non-draining cooling air conditioner | |
CN109520182A (en) | A kind of band cleaning device condenser | |
CN213747940U (en) | Tantalum-niobium smelting waste gas treatment equipment | |
CN210374261U (en) | Fan for defrosting of refrigerator | |
CN210546727U (en) | Multi-arm type ultrasonic cleaning machine | |
CN209848424U (en) | Metallurgical stove cooling water collection cycle recycles device | |
CN209722220U (en) | A kind of hard alloy cutter quenching unit | |
CN209085346U (en) | A kind of water-cooled flue structure of ferro-boron smelting furnace | |
CN206875644U (en) | A kind of temperature lowering ventilation system of steel refining plant | |
CN203610255U (en) | Paint mist purification system in high and large space | |
CN207703062U (en) | A kind of hot steam recovery system in galvanized pipe cooling process | |
CN106813254B (en) | Movable integrated control shock wave soot blower and method | |
CN220547804U (en) | Heavy workpiece welding device | |
CN207073975U (en) | One kind machining rapid heat radiation device | |
CN216173335U (en) | Atomization device | |
CN105299995B (en) | A kind of oil drilling machine cooling system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |