A kind of anti-soil losses construction of slope greening
Technical field
The utility model relates to slope greening technical field, specially a kind of anti-soil losses construction of slope greening.
Background technique
The prior art is made into skeleton with various shape concrete, stone masonry, inside fills out planting soil and carries out slope greening or adopt
Slope greening is carried out with geotechnical grid.Reach and prevents soil loss, the purpose of stable side slope.
The prior art is artificial, material, transports consumption greatly, and long in time limit, slope greening rate is low, and appearance is bad, causes into
This height and low efficiency;In addition it if the water inside the period in rainy season, side slope cannot be discharged in time, easily makes slope instability and comes down,
Cause immeasurable loss.In consideration of it, it is proposed that a kind of anti-soil losses construction of slope greening.
Utility model content
The purpose of this utility model is to provide a kind of anti-soil losses constructions of slope greening, to solve above-mentioned background technique
The problem of slope greening of middle proposition low efficiency at high cost, dilutional hyponatremia easily comes down in side slope.
To achieve the above object, the utility model provides the following technical solutions:
A kind of anti-soil losses construction of slope greening, including slopes, the side of the slopes are equipped with honeycomb restraint system,
The side of the honeycomb restraint system is equipped with vegetable layer, and the top side of the slopes offers intercepting ditch, the intercepting ditch it is outer
Side is provided with several water-absorbing bags, and the honeycomb restraint system includes several honeycomb groups, at the center of internal several honeycomb groups
Equipped with Special anchor rod, the side of the Special anchor rod is connected with rib, and the top and bottom end of the honeycomb restraint system are all connected with
There is fixing anchor bar, the two sides of the honeycomb restraint system are respectively connected with Lian Jian, and the side of the water-absorbing bag offers several through-holes,
The inside of the water-absorbing bag is placed with water-absorbing resin, and one end of the water-absorbing bag is connected with capping.
Preferably, the slope ratio of the slopes delays in 1:0.5.
Preferably, pass through ultrasonic bonding between each honeycomb group.
Preferably, each honeycomb group is formed by two honeycomb boards by ultrasonic bonding, each honeycomb boards
Through slot is offered at center, the two sides of the through slot offer several nest holes.
Preferably, the top of the Special anchor rod is equipped with limited post, and the side of the limited post offers limit hole, described
The Basolateral of Special anchor rod is equipped with external screw thread, the Special anchor rod and the close grafting of the slopes.
Preferably, the rib and the through slot and the limit hole are mating, and the top surface of the rib is equidistant
Several card slots are offered, the side of each card slot is connected with fixture block.
Preferably, the fixing anchor bar top and the even key are mating with the through slot, the fixing anchor bar
Bottom end and the slopes are mating.
Preferably, the top distance of the intercepting ditch and the honeycomb restraint system is greater than 5M, the water-absorbing bag with it is described
The grafting of slopes top.
Compared with prior art, the utility model has the beneficial effects that
1, the anti-soil losses construction of the slope greening, by the way that honeycomb restraint system is arranged in the outside of slopes, and in honeycomb
Banket earth on restraint system upper berth, and vegetable layer plantation is got on, so that slope greening substantially reduces cost and improves greening efficiency.
2, the anti-soil losses construction of the slope greening, opens up intercepting ditch by the top end in slopes, and prolong intercepting ditch
The edge of slopes is extended to, so that the water above slopes is flow in intercepting ditch, drains into bottom of slope, is arranged by the top surface of slopes and is inhaled
Water bag, so that secondary avoid soil erosion of side slope, avoids inestimable so that the water inside slopes is absorbed by water-absorbing resin
Loss.
Detailed description of the invention
Fig. 1 is the overall structure diagram of the utility model;
Fig. 2 is the overall structure sectional view of the utility model;
Fig. 3 is the honeycomb restraint system partial structural diagram of the utility model;
Fig. 4 is the honeycomb group structural schematic diagram of the utility model;
Fig. 5 is the Special anchor rod structural schematic diagram of the utility model;
Fig. 6 is the bead structures schematic diagram of the utility model;
Fig. 7 is the water-absorbing bag partial cutaway view of the utility model;
Fig. 8 is the fixing anchor bar structural schematic diagram of the utility model;
Fig. 9 is company's bond structure schematic diagram of the utility model.
In figure: 1, slopes;2, honeycomb restraint system;20, honeycomb group;200, honeycomb boards;201, through slot;202, nest hole;21,
Special anchor rod;210, limited post;211, limit hole;212, external screw thread;22, rib;220, card slot;221, fixture block;23, fixed anchor
Bar;24, Lian Jian;3, vegetable layer;4, intercepting ditch;5, water-absorbing bag;50, through-hole;51, water-absorbing resin;52, it covers.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work
Every other embodiment obtained, fall within the protection scope of the utility model.
In the description of the present invention, it should be understood that term " center ", " longitudinal direction ", " transverse direction ", " length ", " width
Degree ", " thickness ", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outside",
The orientation or positional relationship of the instructions such as " clockwise ", " counterclockwise " be based on the orientation or positional relationship shown in the drawings, be only for
Convenient for description the utility model and simplify description, rather than the equipment of indication or suggestion meaning or element must have specifically
Orientation is constructed and operated in a specific orientation, therefore should not be understood as limiting the present invention, in addition in the utility model
Description in, " several " are meant that two or more, unless otherwise specifically defined.
Embodiment 1
A kind of anti-soil losses construction of slope greening, in order to reduce the cost of slope greening, by slope greening efficiency, originally
Inventor is provided with honeycomb restraint system 2, as a kind of preferred embodiment, as shown in Figure 1, Figure 2, Fig. 3, Fig. 4, Fig. 5, Fig. 6, Fig. 8 and
Shown in Fig. 9, including slopes 1, the side of slopes 1 are equipped with honeycomb restraint system 2, and the side of honeycomb restraint system 2 is equipped with plant
Tegillum 3, the top side of slopes 1 offer intercepting ditch 4, and the outside of intercepting ditch 4 is provided with several water-absorbing bags 5, and honeycomb restraint system 2 is wrapped
Several honeycomb groups 20 are included, are equipped with Special anchor rod 21 at the center of internal several honeycomb groups 20, the side of Special anchor rod 21 is connected with
Rib 22, the top and bottom end of the honeycomb restraint system 2 are respectively connected with fixing anchor bar 23, and the two of the honeycomb restraint system 2
Side is respectively connected with Lian Jian 24.
In the present embodiment, honeycomb restraint system 2 is formed using the compound metalworking of macromolecule, has high-intensitive and high antioxygen
Change performance, so that long service life, each of which unit expands into diamond-plaid, and specification is 356-150, after banketing, so that whole
Body is in honeycomb, increases slope stabilization.
Specifically, the slope ratio of slopes 1 delays in 1:0.5.
Further, by ultrasonic bonding between each honeycomb group 20, this is welded as the prior art, and firm welding is steady
It is fixed.
In addition to this, each honeycomb group 20 is formed by two honeycomb boards 200 by ultrasonic bonding, each honeycomb boards 200
Center at offer through slot 201, the two sides of through slot 201 offer several nest holes 202, can increase aeration, while also having
Certain support strength, the stabilized soil filled in it, avoids being lost well.
It is worth noting that, the top of Special anchor rod 21 is equipped with limited post 210, the side of limited post 210 offers limit
The Basolateral in hole 211, Special anchor rod 21 is equipped with external screw thread 212, Special anchor rod 21 and the close grafting of slopes 1, passes through external screw thread
212 make Special anchor rod 21 and soil stable connection, are not easy to loosen.
It is worth noting that rib 22 and through slot 201 and limit hole 211 are mating, the top surface of rib 22 is equidistant
Several card slots 220 are offered, the side of each card slot 220 is connected with fixture block 221, and the width of fixture block 221 is greater than the width of through slot 201
Degree, so that two honeycomb boards 200 are supported to open and assume diamond in shape, consequently facilitating filling soil.
It is worth noting that 23 top of fixing anchor bar and Lian Jian 24 are mating with through slot 201, the bottom of fixing anchor bar 23
End is mating with slopes 1, is fixed by fixing anchor bar 23 and Lian Jian 24 to the upper and lower side of honeycomb restraint system 2 and two sides, just
In strut sizing honeycomb restraint system 2.
Embodiment 2
As second of embodiment of the utility model, in order to avoid the water inside slopes is cumulative, and cause to come down,
The present inventor is provided with intercepting ditch 4 and water-absorbing bag 5, as a kind of preferred embodiment, as shown in fig. 7, the side of water-absorbing bag 5 opens up
There are several through-holes 50, the inside of water-absorbing bag 5 is placed with water-absorbing resin 51, and one end of water-absorbing bag 5 is connected with capping 52.
In the present embodiment, water-absorbing bag 5 is made of nylon, wear-resisting, corrosion resistant, and toughness is high, to be hardly damaged, extension makes
Use the service life.
Specifically, the top of intercepting ditch 4 and honeycomb restraint system 2 distance is greater than 5M, so that the surface water warp of 1 top of slopes
Intercepting ditch 4 is discharged under slope, avoids enter into slopes 1, the stabilization of slopes 1, water-absorbing bag 5 and 1 top grafting of slopes is influenced, so that slope
Water inside body 1 flows into water-absorbing bag 5, is absorbed by water-absorbing resin 51, avoids 1 top of slopes from accumulating excessive water, thus right
Slopes 1 play second protection effect.
Honeycomb restraint system 2 is directly routed to by the anti-soil losses construction of the slope greening of the utility model when being laid with
In slopes 1, by the way that honeycomb group 20 is unfolded, and Special anchor rod 21 is knocked in slopes 1 between honeycomb boards 200, make 201 He of through slot
Limit hole 211 is corresponding, and rib 22 is inserted into one by one in all through slots 201 and limit hole 211, so that honeycomb boards 200 are limited admittedly
Be scheduled in slopes 1, and the upper and lower side of honeycomb restraint system 2 and two sides difference grafting fixing anchor bar 23 and Lian Jian 24 so that
The sizing of honeycomb restraint system 2 avoids it is whole slip away, at this time can back-up sand and fill soil, make its fill up each honeycomb boards 200 it
Between, it can be laid with vegetable layer 3, be laid with time saving, the short time limit that saves trouble, cost is effectively reduced and improve greening efficiency.
The anti-soil losses construction of the slope greening of the utility model opens up intercepting ditch in the top end of slopes 1 when being laid with
4, and bottom of slope is extended to, and water-absorbing resin 51 is put into water-absorbing bag 5, it is adhered in capping 52 by winding, avoids rainwater straight
It taps into being inserted into water-absorbing bag 5 one by one in the hole that the top surfaces of slopes 1 is drilled, to absorb the water of 1 inside stream of slopes, Mei Geyi
The section time extracts the replacement water-absorbing resin 51 of water-absorbing bag 5 and can continue to use, so that it is a large amount of effectively to completely cut off infiltration inside slopes 1
Water, and cause to come down, it causes damages.
Basic principles, main features, and advantages of the present invention has been shown and described above.Current row
The technical staff of industry is described in above embodiments and description it should be appreciated that the present utility model is not limited to the above embodiments
Be only the utility model preference, be not intended to limit the utility model, do not departing from the spirit and scope of the utility model
Under the premise of, the utility model also has various changes and improvements, these changes and improvements both fall within claimed it is practical
In novel range.The protection scope of the present invention is defined by the appended claims and their equivalents.