CN209163252U - Building element - Google Patents

Building element Download PDF

Info

Publication number
CN209163252U
CN209163252U CN201821261629.1U CN201821261629U CN209163252U CN 209163252 U CN209163252 U CN 209163252U CN 201821261629 U CN201821261629 U CN 201821261629U CN 209163252 U CN209163252 U CN 209163252U
Authority
CN
China
Prior art keywords
clinch
layer
building element
socket part
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821261629.1U
Other languages
Chinese (zh)
Inventor
邓缤
胡鸣
谢伦光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Bozhilin Robot Co Ltd
Original Assignee
Guangdong Bozhilin Robot Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Bozhilin Robot Co Ltd filed Critical Guangdong Bozhilin Robot Co Ltd
Priority to CN201821261629.1U priority Critical patent/CN209163252U/en
Application granted granted Critical
Publication of CN209163252U publication Critical patent/CN209163252U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model relates to a kind of building element, building element include concrete layer, be bonded in the concrete layer side waterproof layer and be bonded in the waterproof layer side protective layer;Reserved position is not formed by the part that the protective layer covers in the waterproof layer; the reserved position includes the second clinch of the first clinch, the first pre- socket part of connection first clinch, the second pre- socket part of the connection first pre- socket part and the connection second pre- socket part; the edge at the edge and the concrete layer of the prominent protective layer of first clinch and concrete layer, the first pre- socket part and the second pre- socket part is mutually neat;The waterproof layer is made of flexible material.Concrete layer, waterproof layer, protective layer are combined together, ensure that the quality of component, simplifies site construction technology, and waterproof effect is good.

Description

Building element
Technical field
The utility model relates to technical field of buildings, more particularly to building element.
Background technique
It is constructed due to traditional building roof each process and is affected by external environmental factor, the construction period is longer, and each It holds each other back between process, influences the control of construction speed and construction quality, quality risk is larger.In addition, being applied using traditional Work mode, the adhesion strength between waterproof layer and structure sheaf is limited, is extremely difficult to eliminate channeling water layer effect, it is anti-to influence building roof Water effect.
Utility model content
Based on this, it is necessary in view of the above-mentioned problems, a kind of building element is provided, concrete layer, waterproof layer, protective layer knot It is combined, ensure that the quality of component, simplify site construction technology, and waterproof effect is good.
A kind of building element, including concrete layer, the side for being bonded in concrete layer waterproof layer and be bonded in waterproof layer Side protective layer;The part of unprotected layer covering forms reserved position in waterproof layer, and reserving position includes the first overlap joint Portion, the second pre- socket part of the first pre- socket part for connecting the first clinch, the second pre- socket part for connecting the first pre- socket part and connection the Two clinch, the prominent protective layer of the first clinch and concrete layer, the edge and concrete of the first pre- socket part and the second pre- socket part The edge of layer is mutually neat;Waterproof layer is made of flexible material.
Above-mentioned building element when construction, passes through the first clinch of adjacent two pieces building element and the second pre- socket part is wrong Seam overlap joint, the first clinch are overlapped in the upper surface of the second pre- socket part, then using Concrete Filled in the upper of the first clinch Surface, waterproof layer have been effectively isolated external and concrete layer, it is therefore prevented that the problem of channeling water, and the utility model building element handle Concrete layer, waterproof layer, protective layer are combined together, and be ensure that the quality of component, are simplified site construction technology, ensure that whole The construction quality of a Roof system, while reducing the maintenance cost of later period building, the utility model building element can be applied In the roofing or top plate of concrete structure, bond effect is good.
The width of the second pre- socket part is equal to the width of the first clinch in one of the embodiments,.
The width of the first clinch is 80~120mm in one of the embodiments,.
The edge of the prominent protective layer of second clinch and concrete layer in one of the embodiments,.
The width of the first pre- socket part is equal to the width of the second clinch in one of the embodiments,.
The width of the second clinch is 80~120mm in one of the embodiments,.
Protective layer is close to the edge and concrete layer of the side of the first clinch close to first in one of the embodiments, The edge of the side of clinch is mutually neat.
Notch is equipped between the first clinch and the second clinch in one of the embodiments,.
Waterproof layer is waterproof roll in one of the embodiments,.
Building element is cuboid in one of the embodiments, and overlapped that seam is wrong for the long side fissure of displacement of two building elements Open the breadth of 1/3~1/2 waterproof layer.
Detailed description of the invention
Fig. 1 is the schematic diagram of a preferred embodiment of building element of the present invention;
Fig. 2 is the top view of Fig. 1 building element;
Fig. 3 is the overlap joint schematic diagram of four building elements;
Fig. 4 is the construction schematic diagram of Fig. 1 building element.
Specific embodiment
The utility model will be described more fully below for the ease of understanding the utility model,.But this is practical It is novel to realize in many different forms, however it is not limited to embodiment described herein.On the contrary, providing these implementations The purpose of example is to make the understanding of the disclosure of the utility model more thorough and comprehensive.
Unless otherwise defined, all technical and scientific terms used herein are led with the technology for belonging to the utility model The normally understood meaning of the technical staff in domain is identical.Terminology used in the description of the utility model herein only be The purpose of description specific embodiment, it is not intended that in limitation the utility model.
It is referring to FIG. 1 to FIG. 4, the building element 100 of one preferred embodiment of the utility model, including concrete layer 20, It is bonded in the waterproof layer 30 of the side of concrete layer 20 and is bonded in the protective layer 40 of the side of waterproof layer 30.
The area that protective layer 40 covers waterproof layer 30 is less than the surface area of waterproof layer 30, that is, has the table of part waterproof layer 30 Face is exposed to outside.The part that unprotected layer 40 covers in waterproof layer 30 forms reserved position, and reserved position is taken including first Socket part 31, the first pre- socket part 32 for connecting the first clinch 31, the second pre- socket part 33 for connecting the first pre- socket part 32 and connection the Second clinch 34 of two pre- socket parts 33.Wherein, the edge of the prominent protective layer 40 of the first clinch 31 and concrete layer 20, first The edge at the edge and concrete layer 20 of pre- socket part 32 and the second pre- socket part 33 is mutually neat.
It is taken by the first clinch 31a and the second pre- socket part 33b fissure of displacement of adjacent two pieces building element 100a, 100b It connects, then using Concrete Filled in the upper surface of the first clinch 31a, waterproof layer 30 has been effectively isolated external and concrete layer 20, it is therefore prevented that the problem of channeling water.
Concrete layer 20 is plain concrete construction layer or reinforced concrete structure layer.
Waterproof layer 30 is made of flexible material, and such as waterproof roll or other similar materials, such waterproof layer 30 can be with Multiple angles are bent into without easy to crack, facilitate construction.
In one embodiment, the width K3 of the second pre- socket part 33 is equal to the width K1 or the second pre-terminated of the first clinch 31 The width K3 in portion 33 is slightly smaller than the width K1 of the first clinch 31, after so that the first clinch 31 is overlapped in the second pre- socket part 33, the The problem of edge of one clinch 31 abuts adjacent protective layer 40, reduces seam leakage.
In one embodiment, the width K1 of the first clinch 31 is 80~120mm, guarantees to overlap firm, building element 100 While connecting firm, it is not take up excessive component area, in case the concrete for causing overlapping part to fill is excessive and is easy stripping It falls, or constitutes the illusion for the major part that overlapping part is component.
In one embodiment, the edge of the prominent protective layer 40 of the second clinch 34 and concrete layer 20, then two pieces builds structure Part 100 can the fissure of displacement overlap joint of the second clinch 34 and the first pre- socket part 32 link together, overlapped with 31 fissure of displacement of the first clinch Second pre- socket part 33 cooperates, and realizes the connection of three or more building elements 100.
In one embodiment, the width K2 of the first pre- socket part 32 is equal to the width K4 or the first pre-terminated of the second clinch 34 The width K2 in portion 32 is slightly smaller than the width K4 of the second clinch 34, after so that the second clinch 34 is overlapped in the first pre- socket part 32, the The problem of edge of two clinch 34 abuts adjacent protective layer 40, reduces seam leakage.
In one embodiment, the width K4 of the second clinch 34 is 80~120mm, guarantees to overlap firm, building element 100 While connecting firm, it is not take up excessive component area, in case the concrete for causing overlapping part to fill is excessive and is easy stripping It falls, or constitutes the illusion for the major part that overlapping part is component.In addition, the overlap joint of the width K4 of the second clinch 34 and first The width K1 in portion 31 is equal or close, then the filling width of concrete is suitable, and shape is more beautiful.
In one embodiment, protective layer 40 close to the side of the first clinch 31 edge and concrete layer 20 close to first The edge of the side of clinch 31 is mutually neat, in this way, two pieces building element 100 is taken by the first clinch 31 with the second pre- socket part 33 After connecing, the second pre- socket part 33 can support the first clinch 31 completely, it is easier to control two pieces building element 100 against degree.
In one embodiment, notch 35 is equipped between the first clinch 31 and the second clinch 34, which is from the The square block of one clinch 31 and junction excision K1 × K4 of the second clinch 34 is formed, i.e. the portion close to the first clinch 31 The width K1 for being equal to the first clinch 31 into width is cut, incision width is equal to the second overlap joint close to the part of the second clinch 34 The width K4 in portion 34.As shown in figure 3, as four building element 100a, 100b, 100c, 100d, first building element 100a The first clinch 31a will fill the notch of third part building element 100c, with the first of third part building element 100c the overlap joint The upper surface of portion 31a is mutually neat, so that the waterproof layer 30a of two pieces the building element 100a, 100c after overlap joint, 30c be made to be formed One entirety avoids the more one piece of waterproof layer of the corner of the first clinch 31 and the second clinch 34, causes to arch upward, influences to overlap matter While amount, construct not simple enough, and cause the waste of material.
The preparation method of above-mentioned building element, comprising the following steps:
Casting concrete layer, before concrete layer initial set, by waterproof layer paving in the surface of concrete layer, constant temperature and pressure Under the conditions of steam curing, the pressure of maintenance is 0.2~0.5Mpa, and temperature 45 C~65 DEG C, curing time is 10~15 hours.It is mixed Solidifying soil layer conserves jointly with waterproof layer, and waterproof layer is made preferably to be bonded in the surface of concrete layer, not easily to fall off.
Then it in the side paving protective layer of the separate concrete layer of waterproof layer, sufficiently conserving, the pressure of maintenance is 0.6~ 1.0Mpa, temperature are 95~105 DEG C, and conserving is 5~6 hours, obtains building element.
The construction method of above-mentioned building element, comprising the following steps:
Steel truss, support fixing piece, several building elements are provided;
Steel truss is positioned by design drawing and is fixed, then by building element by supporting fixing piece to be fixed on steel truss On, wherein the second pre- socket part fissure of displacement overlap joint that the first clinch of a building element is adjacent thereto, is then filled out in fissure of displacement lap-joint Fill concrete.
Such as assume to overlap two pieces building element 100a, 100b, first building element 100a is fixed on steel On truss, as shown in figure 4, by the first of the second of the second building element 100b the pre- socket part 33b and first building element 100a Clinch 31a fissure of displacement overlap joint, the first clinch 31a are overlapped in the upper surface of the second pre- socket part 33b, two pieces building element 100a, The concrete layer 20a of 100b, 20b are mutually abutted, then in the upper surface fill concrete of the fissure of displacement overlapped the first clinch 31a 50, the concrete 50 of filling selects expansive concrete, not only plays the role of protecting waterproof layer, but also protective layer can be prevented hot Swollen shrinkage is cracked;Concrete 50 to be filled solidifies, that is, completes the overlap joint of two pieces building element 100a, 100b.
The bridging method phase of second clinch and the bridging method of the first pre- socket part and the first clinch and the second pre- socket part Together.
In one embodiment, the fissure of displacement overlapped lap-joint carries out filleting using watertight rubber band, can be embedded water stop rubber The mode filleting of adhesive tape, then carry out gluing encapsulation process using structure sealant, prevents the fissure of displacement overlapped that lap-joint generates leakage The problem of.
In one embodiment, after two pieces building element fissure of displacement overlap joint, also built using measures such as fixing piece anchors to control two pieces The piece between component is built, to reach height, stability or the other requirements of design.
In one embodiment, building element is cuboid, and overlapped that seam is staggered 1/3~1/ for the long side fissure of displacement of building element The breadth of 2 waterproof layers.
Concrete layer, waterproof layer, protective layer are combined together as an integrated member by the utility model building element, The quality that ensure that component, simplifies site construction technology, ensure that the construction quality of entire Roof system, while after reducing The maintenance cost of phase building, the utility model building element can be applied to the roofing or top plate of concrete structure, bond effect Well.
Each technical characteristic of embodiment described above can be combined arbitrarily, for simplicity of description, not to above-mentioned reality It applies all possible combination of each technical characteristic in example to be all described, as long as however, the combination of these technical characteristics is not deposited In contradiction, all should be considered as described in this specification.
A kind of embodiment of the utility model above described embodiment only expresses, the description thereof is more specific and detailed, But it cannot be understood as the limitations to utility model patent range.It should be pointed out that for the common skill of this field For art personnel, without departing from the concept of the premise utility, various modifications and improvements can be made, these are belonged to The protection scope of the utility model.Therefore, the scope of protection shall be subject to the appended claims for the utility model patent.

Claims (10)

1. a kind of building element, which is characterized in that including concrete layer, the side for being bonded in the concrete layer waterproof layer and It is bonded in the protective layer of the side of the waterproof layer;Reserved portion is not formed by the part that the protective layer covers in the waterproof layer Position, the reserved position include the first clinch, the first pre- socket part of connection first clinch, connection first pre-terminated Second clinch of the pre- socket part of the second of portion and the connection second pre- socket part, the prominent protective layer of first clinch and The edge at the edge and the concrete layer of concrete layer, the first pre- socket part and the second pre- socket part is mutually neat;The waterproof layer It is made of flexible material.
2. building element according to claim 1, which is characterized in that the width of the second pre- socket part is equal to described first The width of clinch.
3. building element according to claim 1 or 2, which is characterized in that the width of first clinch be 80~ 120mm。
4. building element according to claim 1, which is characterized in that second clinch protrudes the protective layer and mixes The edge of solidifying soil layer.
5. building element according to claim 4, which is characterized in that the width of the first pre- socket part is equal to described second The width of clinch.
6. building element according to claim 4 or 5, which is characterized in that the width of second clinch be 80~ 120mm。
7. building element according to claim 1, which is characterized in that the protective layer close to first clinch one The edge of side is mutually neat close to the edge of the side of first clinch with the concrete layer.
8. building element according to claim 1, which is characterized in that set between first clinch and the second clinch It is jagged.
9. building element according to claim 1, which is characterized in that the waterproof layer is waterproof roll.
10. building element according to claim 1, which is characterized in that the building element is cuboid, two buildings The breadth of the long side fissure of displacement of component overlapped seam is staggered 1/3~1/2 waterproof layer.
CN201821261629.1U 2018-08-06 2018-08-06 Building element Active CN209163252U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821261629.1U CN209163252U (en) 2018-08-06 2018-08-06 Building element

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821261629.1U CN209163252U (en) 2018-08-06 2018-08-06 Building element

Publications (1)

Publication Number Publication Date
CN209163252U true CN209163252U (en) 2019-07-26

Family

ID=67329335

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821261629.1U Active CN209163252U (en) 2018-08-06 2018-08-06 Building element

Country Status (1)

Country Link
CN (1) CN209163252U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109184089A (en) * 2018-08-06 2019-01-11 恒城建设科技有限公司 Building element and preparation method thereof and construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109184089A (en) * 2018-08-06 2019-01-11 恒城建设科技有限公司 Building element and preparation method thereof and construction method

Similar Documents

Publication Publication Date Title
CN104057686A (en) Preparation method of pre-laid waterproof coiled material for concrete mortar bonding construction
CN104847382B (en) A kind of self-adhering type complex waterproof layer and its laying method for tunnel
CN204983421U (en) Polyurethane waterproofing membrane and production facility, composite waterproof layer thereof
CN103195104B (en) A kind of building method adopting anti-row's combination at building structure waterproof position
CN105089208A (en) Polyurethane waterproof roll, production equipment and process, composite waterproof layer and practice thereof
CN211547827U (en) Waterproof structure at joint of concrete bottom plates of new and old buildings
CN104929155A (en) Hermetically sealing waterproof construction method for basement
CN105401962B (en) The hermetically sealed waterproof construction method of side wall, engineering top surface
CN213507880U (en) Asphalt pavement structure for preventing reflection cracks
CN104612254A (en) Reaction joining waterproof roll paving waterproof construction method
CN209163252U (en) Building element
CN109184089A (en) Building element and preparation method thereof and construction method
CN207892138U (en) A kind of fabricated roofing piece waterproof construction
CN205224122U (en) Basement waterproofing bottom plate
CN110206073A (en) Lattice stanchion and main structure node waterproof construction method
CN109372024A (en) A kind of sole plate waterproof structure for deformation seams and construction method
CN104947809A (en) Full-seal waterproof system of concrete construction project
CN105584135A (en) A pre-paving wet-paving waterproof coiled material with a crosslinking reaction layer
CN214090786U (en) Reduce ceramic tile laying structure of cement thermal expansion stress
CN106193468A (en) Spliced thermal-insulating waterproof shoe plate, spliced thermal-insulating waterproof shoe plate combinative structure and construction method thereof
CN206983415U (en) One kind overlays polymer membranes
KR102092819B1 (en) The waterproof sheet with improved root isolation, the manufacturing method and the construction method thereof
CN104847022B (en) A kind of flexible water structure and its construction method
CN208762966U (en) The connected structure of asphalt concrete face slab and geomembrane
CN201933382U (en) Bituminous concrete pavement composite sandwich construction for delaying upward extension of reflective cracks

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20191118

Address after: 201-21, floor 2, East office, No.11, Junye East Road, Beijiao Industrial Park, Shunjiang neighborhood committee, Beijiao Town, Shunde District, Foshan City, Guangdong Province

Patentee after: Guangdong Boyue Intelligent Construction Technology Co., Ltd

Address before: 528300 East Office Building 201-11, No. 11 Junye East Road, Beijiao Town, Shunde District, Foshan City, Guangdong Province

Patentee before: Guangdong Bozhilin Robot Co., Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210210

Address after: 528300 a2-05, 2nd floor, building A1, 1 Panpu Road, Biguiyuan community, Beijiao Town, Shunde District, Foshan City, Guangdong Province

Patentee after: GUANGDONG BOZHILIN ROBOT Co.,Ltd.

Address before: 528311 201-21, 2nd floor, East office, No.11 Junye East Road, Beijiao Industrial Park, Shunjiang neighborhood committee, Beijiao Town, Shunde District, Foshan City, Guangdong Province

Patentee before: Guangdong Boyue Intelligent Construction Technology Co.,Ltd.

TR01 Transfer of patent right