CN209150670U - A kind of cable testing bridge - Google Patents
A kind of cable testing bridge Download PDFInfo
- Publication number
- CN209150670U CN209150670U CN201821681077.XU CN201821681077U CN209150670U CN 209150670 U CN209150670 U CN 209150670U CN 201821681077 U CN201821681077 U CN 201821681077U CN 209150670 U CN209150670 U CN 209150670U
- Authority
- CN
- China
- Prior art keywords
- cable
- protection cap
- testing bridge
- angle steel
- plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Laying Of Electric Cables Or Lines Outside (AREA)
Abstract
The utility model discloses a kind of cable testing bridges, comprising: interval pre-determined distance horizontal homogeneous is distributed in multiple support frames on wall, and multiple support frames topmost pass through the first angle steel and are connected with each other integrally;Single support frame as described above includes the vertical plate being fixed on the wall vertically and uniformly distributed multiple cable support plates on vertical plate;Protection cap is set on the outside of the cable support plate, can on the facades such as tunnel, wall direct cabling, stability is good, highly-safe.
Description
Technical field
The utility model relates to electrical equipment technical field, in particular to a kind of cable testing bridge.
Background technique
Conventional wire cable gantry is generally embedded in underground or in earth's surface;With the continuous development of power equipment industry, usually need
This demand is unable to satisfy in the facades cabling such as wall, tunnel, current cable testing bridge.
Utility model content
The utility model is intended to solve at least some of the technical problems in related technologies.
For this purpose, electricity can be laid in facades such as wall, tunnels the purpose of this utility model is that propose a kind of cable testing bridge
Cable, stability is good, highly-safe.
To achieve the above object, the utility model embodiment proposes a kind of cable testing bridge, comprising: interval pre-determined distance water
The flat multiple support frames being evenly distributed on wall, multiple support frames topmost pass through the first angle steel and are connected with each other integrally;It is single
A support frame as described above includes the vertical plate being fixed on the wall vertically and uniformly distributed multiple cable support plates on vertical plate;It is described
Protection cap is set on the outside of cable support plate.
Preferably, the vertical plate uses the second angle steel with through-hole, and the through-hole fixes vertical plate for expansion bolt
On wall, the cable support plate uses third angle steel, and the third angle steel is weldingly fixed on second angle steel with logical
The side in hole.
Specifically, the protection cap includes the first protection cap, the second protection cap and third protection cap, each protection cap
Both ends below cable support plate on welding be equipped with for connecting both aforementioned connecting plate.
More specifically, first protection cap includes the first short slab, inclined plate and the first long slab, the end of first long slab
Equipped with the first L-type bending plate.
More specifically, second protection cap uses the second long slab, it is curved that the both ends of second long slab are equipped with the second L-type
Folded plate.
More specifically, the third protection cap includes third long slab and the second short slab, the end of the third long slab is equipped with
Third L-type bending plate.
Preferably, the width and the connecting plate of each protection cap is of same size.
Preferably, each support frame as described above further includes two for setting up the fourth angle steel of strong and weak electricity partition, the power
Electric partition uses I-steel, is set up on adjacent support frame.
Preferably, each support frame as described above further includes the 5th angle steel, and the 5th angle steel is set to support frame as described above end
It plays a supportive role between the cable support plate.
Preferably, each support frame as described above interval pre-determined distance is 1m.
Compared with prior art, the utility model has the following beneficial effects: 1, stable structure, by using multiple supports
The cable support plate being arranged in frame interconnection and support frame, cable can be stratified and set in support plate, will not be collinear
Cable effectively separates, and has protection cap, carries out effective protection to cable;2, highly-safe, it, can be with by the way that strong and weak electricity partition is arranged
Effectively strong and weak electricity is layered, increases the safety of cable testing bridge.
Detailed description of the invention
The above-mentioned and/or additional aspect and advantage of the utility model from the description of the embodiment in conjunction with the following figures will
Become obvious and be readily appreciated that, wherein
Fig. 1 is the structural schematic diagram being laid on wall according to the cable testing bridge of the utility model embodiment;
Fig. 2 is the side view being laid on wall according to the cable testing bridge of the utility model embodiment;
Fig. 3 is the side view of the first protection cap in the cable testing bridge according to the utility model embodiment;
Fig. 4 is the side view of the second protection cap in the cable testing bridge according to the utility model embodiment;
Fig. 5 is the side view of third protection cap in the cable testing bridge according to the utility model embodiment;
Fig. 6 is the dimensional drawing that various pieces on wall are laid on according to the cable testing bridge of the utility model embodiment;
Fig. 7 is the front view being laid on sound barrier according to the cable testing bridge of the utility model one embodiment;
Fig. 8 is that strong and weak isolation board is set up in two neighboring support in the cable testing bridge according to the utility model one embodiment
Front view between frame.
Specific embodiment
The embodiments of the present invention are described below in detail, examples of the embodiments are shown in the accompanying drawings, wherein from beginning
Same or similar element or element with the same or similar functions are indicated to same or similar label eventually.Below by ginseng
The embodiment for examining attached drawing description is exemplary, and is only used for explaining the utility model, and should not be understood as to the utility model
Limitation.
The cable testing bridge of the utility model embodiment described with reference to the accompanying drawing.
As shown in figures 1-8, a kind of cable testing bridge that the utility model embodiment proposes, comprising: interval pre-determined distance is horizontal
The multiple support frames 1 being evenly distributed on wall, multiple 1 the tops of support frame are connected with each other integrally by the first angle steel 10;
Single support frame 1 includes the vertical plate 2 and uniformly distributed multiple cable support plates 3 on vertical plate 2 being fixed on the wall vertically;Line
Protection cap 4 is set on the outside of cable support plate 3.
For example, as shown in fig. 7, if needing to set up cable outside sound barrier at this time, due to sound barrier width
For 2m, in order to prevent therefore cable, is spaced 1m from left to right and is laid with support frame 1 therefrom under clan.Specific paving mode is,
The vertical fixing support rack 1 by way of the bolt of M16 or welding respectively in the H profile steel of the two sides of sound barrier is supported, in addition
Pass through the vertical fixing support rack 1 of bolt of M16 in the middle part of sound barrier, it should be noted that in order to enhance load-bearing and stability, in
The lower end of the support frame 1 in portion extends to underground, and lower end is welded the angle steel of 63*40, fixed by M12 expansion bolt.
The upper end of three support frames 1 is both placed on the face the first angle steel (40*40), and fixes (shape by M16 expansion bolt
At a word of falling mountain) so that the upper end of three support frames 1 is fixed on sound barrier together, but also three 1 quilts of support frame
It is fixed as an entirety, stability is more preferable.
Wherein, sound barrier could alternatively be the facades such as wall, tunnel.
Preferably, as shown in Figure 1, vertical plate 2 is using the second angle steel for having through-hole, through-hole consolidates vertical plate for expansion bolt
It is scheduled on wall, cable support plate 3 uses third angle steel, and third angle steel is weldingly fixed on the side that the second angle steel has through-hole.
Wherein, the second angle steel can be the angle steel of 63*40, and length can be 1780mm, and third angle steel can be the angle of 40*40
Steel, length can be 225mm.Wherein, the third angle steel of strong and weak electricity layering up is that 150mm is uniformly distributed at second jiao with spacing
Steel band has the side of through-hole;The third angle steel of strong and weak electricity layering down is that 170mm is uniformly distributed with spacing to be had in the second angle steel
The side of through-hole.
Specifically, as depicted in figs. 1 and 2, protection cap 4 includes the first protection cap 41, the second protection cap 42 and third protection
Lid 43, welding is equipped with for connecting both aforementioned connecting plate 6 on the cable support plate 3 below the both ends of each protection cap.
Wherein, connecting plate 6 can be the band steel of 40*5.
More specifically, as shown in figure 3, the first protection cap 41 include the first short slab 411, inclined plate 412 and the first long slab 413,
The end of first long slab 413 is equipped with the first L-type bending plate 414.
Wherein, the length of the first short slab 411 is 30mm, and the length of inclined plate 412 is 210mm, and the length of the first long slab 413 is
" horizontal with perpendicular " of 530mm, the first L-type bending plate 414 are 15mm.
More specifically, the both ends of second long slab 422 are all provided with as shown in figure 4, the second protection cap 42 uses the second long slab 422
There are the second L-type bending plate (421,422).
Wherein, the length of the second long slab 422 is 530mm, and the horizontal of the second L-type bending plate (421,422) is 13mm, erects and is
6mm。
More specifically, as shown in figure 5, third protection cap 43 includes third long slab 431 and the second short slab 432, third long slab
431 end is equipped with third L-type bending plate 433.
Wherein, the length of third long slab 431 is 560mm, and the length of the second short slab 432 is 30mm, third L-type bending plate
433 " horizontal with perpendicular " is 15mm.
Wherein, the first protection cap 41, the second protection cap 42 and third protection cap 43 are integrally formed, the bending of the first L-type
Plate 414 is different with the overbending direction of third L-type bending plate 433, and the second L-type bending plate 421 is curved with the first L-type bending plate 414
Folding direction is identical (in attached drawing 2 shown in B), and the second L-type bending plate 422 and the overbending direction of third L-type bending plate 433 are identical (attached
In Fig. 2 shown in A).By the setting of bending plate, so that being looked on the outside of protection cap less than inside, guarantee safety.
Preferably, the width and connecting plate 6 of each protection cap is of same size.
Specifically, on sound barrier above-mentioned, after installing three support frames 1, then connect above each support frame 1
Connect protection cap 4, it should be noted that the first protection cap 41 and third protection cap 43 are first installed, the second protection cap 42 is finally installed.
Wherein, the first short slab 411 is fixed on the another side of the first angle steel 10, it is then that the both ends of the first long slab 413 are fixed online
On the band steel of 3 top of cable support plate, then the second short slab 432 is fixed in the cable support plate 3 of 1 bottom of support frame
Then the both ends of third long slab 431 are fixed on the band steel of 3 top of cable support plate, then by the two of the second long slab 42 by side
End is also secured on the band steel of 3 top of cable support plate.It should be noted that the fixation between protection cap 4 and support frame 1 is adopted
It is fixed with forked tail filament fourth, and then safety ensure that so that cable will not drop out outward by the setting of protection cap 4.
Preferably, as shown in figs. 1 and 8, each support frame 1 further includes two for setting up the fourth angle of strong and weak electricity partition 11
Steel 8, strong and weak electricity partition 11 use I-steel, are set up on adjacent support frame 1.
That is, fourth angle steel 8 is arranged before and after on certain block cable support plate 3 on each support frame 1, by I-shaped
Steelframe is set on two fourth angle steel 8, to realize that forceful electric power cable and weak-current cable are layered, promotes safety.
Preferably, each support frame 1 further includes the 5th angle steel 9, and the 5th angle steel 9 is set to 1 end of support frame and cable branch
It plays a supportive role between fagging 3, the 5th angle steel is the angle steel of 40*40.
Preferably, it is 1m that each support frame 1, which is spaced pre-determined distance,.
To sum up, the cable testing bridge proposed according to the utility model embodiment passes through interval pre-determined distance horizontal homogeneous distribution
Multiple support frames on wall, and topmost pass through the first angle steel in multiple support frames and be connected with each other integrally;And lead to
It crosses uniformly distributed multiple cable support plates on vertical plate to be supported cable, and cable is avoided by the setting of protection cap
It is skidded off from support plate, to realize the direct cabling on the facades such as tunnel, wall, stability is good, highly-safe.
In the description of the present invention, it should be understood that term " center ", " longitudinal direction ", " transverse direction ", " length ", " width
Degree ", " thickness ", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outside",
The orientation or positional relationship of the instructions such as " clockwise ", " counterclockwise ", " axial direction ", " radial direction ", " circumferential direction " is based on the figure
Orientation or positional relationship is merely for convenience of describing the present invention and simplifying the description, rather than the dress of indication or suggestion meaning
It sets or element must have a particular orientation, be constructed and operated in a specific orientation, therefore should not be understood as to the utility model
Limitation.
For this purpose, term " first ", " second " are used for descriptive purposes only and cannot be understood as indicating or suggesting relative importance
Or implicitly indicate the quantity of indicated technical characteristic.Define " first " as a result, the feature of " second " can be expressed or
Implicitly include at least one this feature.The meaning of " plurality " is at least two, such as two in the description of the present invention,
It is a, first-class, unless otherwise specifically defined.
In the present invention unless specifically defined or limited otherwise, term " installation ", " connected ", " connection ", " Gu
It is fixed " etc. terms shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or integral;It can be
Mechanical connection, is also possible to be electrically connected;It can be connected directly, two members can also be can be indirectly connected through an intermediary
The interaction relationship of connection or two elements inside part, unless otherwise restricted clearly.For the ordinary skill of this field
For personnel, the concrete meaning of above-mentioned term in the present invention can be understood as the case may be.
In the present invention unless specifically defined or limited otherwise, fisrt feature is in the second feature " on " or " down "
It can be that the first and second features directly contact or the first and second features are by intermediary mediate contact.Moreover, first is special
Sign can be fisrt feature above the second feature " above ", " above " and " above " and be directly above or diagonally above the second feature, or only
Indicate that first feature horizontal height is less than second feature.
In the description of this specification, reference term " one embodiment ", " some embodiments ", " example ", " specifically show
The description of example " or " some examples " etc. means particular features, structures, materials, or characteristics described in conjunction with this embodiment or example
It is contained at least one embodiment or example of the utility model.In the present specification, schematic expression of the above terms
Necessarily it is directed to identical embodiment or example.Moreover, particular features, structures, materials, or characteristics described can be
It can be combined in any suitable manner in any one or more embodiment or examples.In addition, without conflicting with each other, this field
Technical staff can carry out the feature of different embodiments or examples described in this specification and different embodiments or examples
Combination and combination.
Although the embodiments of the present invention have been shown and described above, it is to be understood that above-described embodiment is
Illustratively, it should not be understood as limiting the present invention, those skilled in the art are in the scope of the utility model
Inside it can make changes, modifications, alterations, and variations to the above described embodiments.
Claims (10)
1. a kind of cable testing bridge characterized by comprising interval pre-determined distance horizontal homogeneous is distributed in multiple supports on wall
Frame (1), multiple support frames (1) are topmost connected with each other by the first angle steel (10) integral;Individually support frame as described above (1) includes
The vertical plate (2) being fixed on the wall vertically and uniformly distributed multiple cable support plates (3) on vertical plate (2);The cable branch
Protection cap (4) are set on the outside of fagging (3).
2. cable testing bridge as described in claim 1, which is characterized in that the vertical plate (2) uses the second angle steel for having through-hole,
Vertical plate (2) is fixed on the wall by the through-hole (5) for expansion bolt (7), and the cable support plate (3) uses the third angle
Steel, the third angle steel are weldingly fixed on the side that second angle steel has through-hole.
3. cable testing bridge as described in claim 1, which is characterized in that the protection cap (4) includes the first protection cap (41), the
Two protection caps (42) and third protection cap (43) are welded on the cable support plate (3) below the both ends of each protection cap
Equipped with for connecting both aforementioned connecting plate (6).
4. cable testing bridge as claimed in claim 3, which is characterized in that first protection cap (41) includes the first short slab
(411), the end of inclined plate (412) and the first long slab (413), first long slab (413) is equipped with the first L-type bending plate (414).
5. cable testing bridge as claimed in claim 3, which is characterized in that second protection cap (42) uses the second long slab, institute
The both ends for stating the second long slab are equipped with the second L-type bending plate (421,422).
6. cable testing bridge as claimed in claim 3, which is characterized in that the third protection cap (43) includes third long slab
(431) and the second short slab (432), the end of the third long slab are equipped with third L-type bending plate (433).
7. cable testing bridge as claimed in claim 3, which is characterized in that the width and the connecting plate (6) of the protection cap (4)
It is of same size.
8. cable testing bridge as described in claim 1, which is characterized in that each support frame as described above (1) further includes two for frame
If the fourth angle steel (8) of strong and weak electricity partition, the strong and weak electricity partition uses I-steel, is set up on adjacent support frame (1).
9. cable testing bridge as described in claim 1, which is characterized in that each support frame as described above (1) further includes the 5th angle steel
(9), the 5th angle steel (9) is set between support frame as described above end and the cable support plate (3) and plays a supportive role.
10. cable testing bridge as described in claim 1, which is characterized in that each support frame as described above (1) is spaced pre-determined distance and is
1m。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821681077.XU CN209150670U (en) | 2018-10-17 | 2018-10-17 | A kind of cable testing bridge |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821681077.XU CN209150670U (en) | 2018-10-17 | 2018-10-17 | A kind of cable testing bridge |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209150670U true CN209150670U (en) | 2019-07-23 |
Family
ID=67270018
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821681077.XU Expired - Fee Related CN209150670U (en) | 2018-10-17 | 2018-10-17 | A kind of cable testing bridge |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209150670U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112736812A (en) * | 2021-01-29 | 2021-04-30 | 黄河勘测规划设计研究院有限公司 | Method for laying cable in large-span lock chamber |
CN113140989A (en) * | 2021-04-28 | 2021-07-20 | 苏交科集团股份有限公司 | Bracket for bridge installation and installation method thereof |
-
2018
- 2018-10-17 CN CN201821681077.XU patent/CN209150670U/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112736812A (en) * | 2021-01-29 | 2021-04-30 | 黄河勘测规划设计研究院有限公司 | Method for laying cable in large-span lock chamber |
CN113140989A (en) * | 2021-04-28 | 2021-07-20 | 苏交科集团股份有限公司 | Bracket for bridge installation and installation method thereof |
CN113140989B (en) * | 2021-04-28 | 2022-06-07 | 苏交科集团股份有限公司 | Bracket for bridge installation and installation method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN209150670U (en) | A kind of cable testing bridge | |
CN103410670A (en) | Trussed wind turbine tower and wind turbine unit with same | |
CN103469735B (en) | The mounting method of curve ultrahigh hollow column plate type pier top solid section template | |
CN203583974U (en) | 750KV outdoor A-shaped column, lattice type column and power distribution device | |
CN208563078U (en) | Separation type bicycle occupation bridge structure | |
KR20150138741A (en) | Steel crossarm for power distribution | |
CN205329549U (en) | Corbel frame device is deposited to steel case roof beam temporarily | |
CN204781944U (en) | A mode structure of infilled wall constructional column | |
CN204753342U (en) | Clad steel cable bridge | |
CN209675684U (en) | The improvement structure of tubular hydropower generator main lead | |
CN105469955A (en) | Converging and supporting structure of dry electric reactor | |
CN207739482U (en) | A kind of haunch contignation for garage | |
CN102296700B (en) | Integrated house | |
CN215518842U (en) | Multilayer reinforcing bar construction structures of different elevations of super thick raft foundation | |
CN201556854U (en) | Cable distribution box of low-pressure cabinet | |
CN105449605B (en) | High intensity bus bridge framework | |
CN110144959A (en) | The round assembled underground pipe gallery of slip casting method construction | |
CN202247909U (en) | Bridge arch shaped steel purlin | |
CN201786363U (en) | Supporting steel frame for cable tunnels | |
CN104878857B (en) | A kind of lightweight prefabricated combined wall body | |
CN209029835U (en) | A kind of assemble type underground composite cable straight trip gallery | |
CN205212369U (en) | High strength generating line bridge frame | |
CN210404469U (en) | Transformer substation base and track traffic power supply system with same | |
CN218713326U (en) | Node structure for basement outer wall and steel rib column | |
CN104836123B (en) | The framework girder construction that a kind of band is encorbelmented |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190723 Termination date: 20201017 |
|
CF01 | Termination of patent right due to non-payment of annual fee |