CN209145293U - A kind of construction concrete casting device - Google Patents

A kind of construction concrete casting device Download PDF

Info

Publication number
CN209145293U
CN209145293U CN201821802366.0U CN201821802366U CN209145293U CN 209145293 U CN209145293 U CN 209145293U CN 201821802366 U CN201821802366 U CN 201821802366U CN 209145293 U CN209145293 U CN 209145293U
Authority
CN
China
Prior art keywords
pipe
pouring
mounting frame
bottom end
feeding pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821802366.0U
Other languages
Chinese (zh)
Inventor
龚炜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201821802366.0U priority Critical patent/CN209145293U/en
Application granted granted Critical
Publication of CN209145293U publication Critical patent/CN209145293U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

本实用新型公开了一种建筑施工用混凝土浇筑装置,包括第一安装架和第二安装架,所述第一安装架的底端设有浇筑管,所述浇筑管的侧面设有输料管,所述输料管的顶端设有进料管,所述浇筑管、输料管和进料管的内部均连通设置,所述第二安装架的底端设有电机。本建筑施工用混凝土浇筑装置,通过把输送的管道和进料管进行连接,然后再使得电机工作,从而使得混凝土能够从浇筑管落下进行浇筑作业,同时通过对电动伸缩杆的工作进行控制,从而对振动棒的高度进行调节,能够在混凝土浇筑过程中有效进行振捣作业,无需反复的进行浇筑,保证了浇筑的效果,提高了工作的效率,便于人们的使用。

The utility model discloses a concrete pouring device for building construction, which comprises a first installation frame and a second installation frame, the bottom end of the first installation frame is provided with a pouring pipe, and the side of the pouring pipe is provided with a material conveying pipe The top end of the material conveying pipe is provided with a feeding pipe, the insides of the pouring pipe, the material conveying pipe and the feeding pipe are all connected and arranged, and the bottom end of the second mounting frame is provided with a motor. The concrete pouring device for building construction connects the conveying pipe and the feeding pipe, and then makes the motor work, so that the concrete can be poured from the pouring pipe for pouring. Adjusting the height of the vibrating rod can effectively carry out the vibrating operation during the concrete pouring process, without repeated pouring, which ensures the effect of pouring, improves the work efficiency, and is convenient for people to use.

Description

一种建筑施工用混凝土浇筑装置Concrete pouring device for building construction

技术领域technical field

本实用新型涉及浇筑装置技术领域,具体为一种建筑施工用混凝土浇筑装置。The utility model relates to the technical field of pouring devices, in particular to a concrete pouring device for building construction.

背景技术Background technique

混凝土是由胶凝材料、水和粗骨料、细骨料按照一定的比例配置,经过均匀拌合、浇筑、振捣密实,并且在一定的温度和适度条件下养护硬化而成的人工石材,混凝土浇筑是指将混凝土浇筑入模直至塑化的过程,目前在施工工地对混凝土进行浇筑时,需要先浇筑,然后再使用振动棒进行振捣,振捣完成后还要再浇筑再振捣,由此进行反复工作,浇筑的速度较慢,从而影响工作的效率。Concrete is an artificial stone made of cementitious materials, water, coarse aggregates and fine aggregates in a certain proportion, which is uniformly mixed, poured, vibrated and compacted, and cured and hardened at a certain temperature and moderate conditions. Concrete pouring refers to the process of pouring concrete into the mold until plasticization. At present, when pouring concrete on a construction site, it needs to be poured first, and then vibrated with a vibrating rod. After the vibration is completed, it must be poured and then vibrated. As a result, repeated work is carried out, and the pouring speed is slow, thereby affecting the efficiency of the work.

实用新型内容Utility model content

本实用新型要解决的技术问题是克服现有的缺陷,提供一种建筑施工用混凝土浇筑装置,使其能够在浇筑的同时进行混凝土振捣,从而无需再次进行浇筑作业,加快了浇筑的速度,提高了工作的效率,可以有效解决背景技术中的问题。The technical problem to be solved by the utility model is to overcome the existing defects and provide a concrete pouring device for building construction, so that the concrete can be vibrated at the same time of pouring, so that the pouring operation is not required again, and the pouring speed is accelerated. The work efficiency is improved, and the problems in the background technology can be effectively solved.

为实现上述目的,本实用新型提供如下技术方案:一种建筑施工用混凝土浇筑装置,包括第一安装架和第二安装架,所述第一安装架的底端设有浇筑管,所述浇筑管的侧面设有输料管,所述输料管的顶端设有进料管,所述浇筑管、输料管和进料管的内部均连通设置,所述第二安装架的底端设有电机,所述电机的输出轴贯穿且延伸至输料管的内部并连接有输送架,所述第一安装架的顶端对应浇筑管的位置处设有安装板,所述安装板的底端通过电动伸缩杆与第一安装架的表面连接,所述安装板的底端对应浇筑管的位置处连接有振动棒,所述第一安装架的表面设有控制开关组,所述控制开关组的输出端电连接电机、电动伸缩杆和振动棒的输入端。In order to achieve the above purpose, the present utility model provides the following technical solutions: a concrete pouring device for building construction, comprising a first installation frame and a second installation frame, the bottom end of the first installation frame is provided with a pouring pipe, and the pouring The side of the pipe is provided with a feeding pipe, the top of the feeding pipe is provided with a feeding pipe, the insides of the pouring pipe, the feeding pipe and the feeding pipe are all connected and arranged, and the bottom end of the second mounting frame is provided with a feeding pipe. There is a motor, the output shaft of the motor penetrates and extends to the inside of the conveying pipe and is connected with a conveying frame, the top of the first mounting frame is provided with a mounting plate at the position corresponding to the pouring pipe, and the bottom end of the mounting plate is provided with a mounting plate. The electric telescopic rod is connected to the surface of the first installation frame, the bottom end of the installation plate is connected with a vibrating rod at the position corresponding to the pouring pipe, the surface of the first installation frame is provided with a control switch group, and the control switch group The output end of the electric motor is electrically connected to the input end of the motor, the electric telescopic rod and the vibrating rod.

作为本实用新型的一种优选技术方案,所述第一安装架的两侧均是通过轴承座连接有滚轮,所述第二安装架的两侧对应第一安装架两侧结构设置。As a preferred technical solution of the present invention, both sides of the first installation frame are connected with rollers through bearing seats, and the two sides of the second installation frame are arranged corresponding to the two sides of the first installation frame.

作为本实用新型的一种优选技术方案,所述安装板的底端设有连接盘,所述连接盘的底端设有螺杆,所述振动棒的顶端对应螺杆的位置处设有通孔,螺杆贯穿且延伸至振动棒的顶端下方并连接有螺母。As a preferred technical solution of the present invention, the bottom end of the mounting plate is provided with a connecting plate, the bottom end of the connecting plate is provided with a screw rod, and the top end of the vibrating rod is provided with a through hole at the position corresponding to the screw rod, The screw rod penetrates and extends below the top end of the vibrating rod and is connected with a nut.

作为本实用新型的一种优选技术方案,所述进料管的顶端设有法兰盘,所述法兰盘上设有固定孔,所述固定孔内转动连接有固定柱。As a preferred technical solution of the present invention, the top of the feed pipe is provided with a flange plate, the flange plate is provided with a fixing hole, and a fixing column is rotatably connected in the fixing hole.

作为本实用新型的一种优选技术方案,所述第二安装架上设有连接孔,所述连接孔内转动连接有连接柱。As a preferred technical solution of the present invention, the second mounting frame is provided with a connecting hole, and a connecting column is rotatably connected in the connecting hole.

与现有技术相比,本实用新型的有益效果是:本建筑施工用混凝土浇筑装置,通过把输送的管道和进料管进行连接,然后再使得电机工作,从而使得混凝土能够从浇筑管落下进行浇筑作业,同时通过对电动伸缩杆的工作进行控制,对振动棒的高度进行了调节,能够在浇筑过程中有效进行连续振捣作业,保证了浇筑的效果,无需反复的进行浇筑,提高了工作的效率,便于人们的使用。Compared with the prior art, the beneficial effect of the present utility model is: the concrete pouring device for building construction, by connecting the conveying pipeline and the feeding pipe, and then making the motor work, so that the concrete can be dropped from the pouring pipe. For the pouring operation, at the same time, by controlling the work of the electric telescopic rod, the height of the vibrating rod is adjusted, which can effectively carry out continuous vibrating operation during the pouring process, ensuring the effect of pouring, without repeated pouring and improving the work. efficiency and easy for people to use.

附图说明Description of drawings

图1为本实用新型结构示意图;Fig. 1 is the structural representation of the utility model;

图2为本实用新型剖面结构示意图。Figure 2 is a schematic diagram of the cross-sectional structure of the utility model.

图中:1第一安装架、2第二安装架、3浇筑管、4输料管、5进料管、6电机、7输送架、8电动伸缩杆、9安装板、10振动棒、11控制开关组、12滚轮、13连接盘、14螺杆、15螺母、16法兰盘、17固定孔、18固定柱、19连接孔、20连接柱。In the picture: 1. the first mounting frame, 2. the second mounting frame, 3. pouring pipe, 4. feeding pipe, 5. feeding pipe, 6. motor, 7. conveying frame, 8. electric telescopic rod, 9. mounting plate, 10. vibrating rod, 11. Control switch group, 12 rollers, 13 connecting plates, 14 screws, 15 nuts, 16 flanges, 17 fixing holes, 18 fixing columns, 19 connecting holes, 20 connecting columns.

具体实施方式Detailed ways

下面将结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本实用新型一部分实施例,而不是全部的实施例。基于本实用新型中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本实用新型保护的范围。The technical solutions in the embodiments of the present utility model will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present utility model. Obviously, the described embodiments are only a part of the embodiments of the present utility model, rather than all the implementations. example. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative work fall within the protection scope of the present invention.

请参阅图1-2,本实用新型提供一种技术方案:一种建筑施工用混凝土浇筑装置,包括第一安装架1和第二安装架2,第一安装架1的底端设有浇筑管3,浇筑管3的侧面设有输料管4,输料管4的顶端设有进料管5,进料管5的顶端设有法兰盘16,法兰盘16上设有固定孔17,固定孔17内转动连接有固定柱18,便于把进料管5与外界的输送管道进行连接,浇筑管3、输料管4和进料管5的内部均连通设置,第二安装架2的底端设有电机6,电机6的输出轴贯穿且延伸至输料管4的内部并连接有输送架7,第一安装架1的顶端对应浇筑管3的位置处设有安装板9,安装板9的底端通过电动伸缩杆8与第一安装架1的表面连接,安装板9的底端对应浇筑管3的位置处连接有振动棒10,安装板9的底端设有连接盘13,连接盘13的底端设有螺杆14,振动棒10的顶端对应螺杆14的位置处设有通孔,螺杆14贯穿且延伸至振动棒10的顶端下方并连接有螺母15,便于使用者根据浇筑的深度对振动棒10的规格进行选择,从而便于进行振捣作业,第一安装架1的两侧均是通过轴承座连接有滚轮12,第二安装架2的两侧对应第一安装架1两侧结构设置,便于对整体进行移动,从而便于使用者进行浇筑作业,第二安装架2上设有连接孔19,连接孔19内转动连接有连接柱20,便于把整体与其它的牵引装置进行连接,从而便于使用者对整体进行移动,第一安装架1的表面设有控制开关组11,控制开关组11的输出端电连接电机6、电动伸缩杆8和振动棒10的输入端,控制开关组11上与电机6、电动伸缩杆8和振动棒10一一对应设有调节按钮,控制开关组11控制电机6、电动伸缩杆8和振动棒10工作均采用现有技术中常用的方法。Please refer to Figures 1-2, the present utility model provides a technical solution: a concrete pouring device for building construction, comprising a first mounting frame 1 and a second mounting frame 2, and a pouring pipe is provided at the bottom end of the first mounting frame 1 3. The side of the pouring pipe 3 is provided with a feeding pipe 4, the top of the feeding pipe 4 is provided with a feeding pipe 5, the top of the feeding pipe 5 is provided with a flange 16, and the flange 16 is provided with a fixing hole 17 , a fixed column 18 is rotatably connected in the fixed hole 17, which is convenient for connecting the feeding pipe 5 with the external conveying pipe. The bottom end is provided with a motor 6, the output shaft of the motor 6 penetrates and extends to the inside of the conveying pipe 4 and is connected with a conveying frame 7, the top of the first mounting frame 1 is provided with a mounting plate 9 at the position corresponding to the pouring pipe 3, The bottom end of the mounting plate 9 is connected with the surface of the first mounting frame 1 through the electric telescopic rod 8, the bottom end of the mounting plate 9 is connected with a vibrating rod 10 at the position corresponding to the pouring pipe 3, and the bottom end of the mounting plate 9 is provided with a connecting plate 13. The bottom end of the connecting plate 13 is provided with a screw 14, the top of the vibrating rod 10 is provided with a through hole at the position corresponding to the screw 14, the screw 14 penetrates and extends to the bottom of the top of the vibrating rod 10 and is connected with a nut 15, which is convenient for users The specification of the vibrating rod 10 is selected according to the pouring depth, so as to facilitate the vibrating operation. Both sides of the first mounting frame 1 are connected with rollers 12 through bearing seats, and the two sides of the second mounting frame 2 correspond to the first mounting frame. The structure on both sides of the frame 1 is arranged to facilitate the movement of the whole, so as to facilitate the user to perform the pouring operation. The second installation frame 2 is provided with a connecting hole 19, and the connecting hole 19 is rotatably connected with a connecting column 20, which is convenient for connecting the whole with other The traction device is connected to facilitate the user to move the whole. The surface of the first mounting frame 1 is provided with a control switch group 11 , and the output end of the control switch group 11 is electrically connected to the input of the motor 6 , the electric telescopic rod 8 and the vibrating rod 10 . At the end, the control switch group 11 is provided with an adjustment button corresponding to the motor 6, the electric telescopic rod 8 and the vibrating rod 10 one-to-one, and the control switch group 11 controls the motor 6, the electric telescopic rod 8 and the vibrating rod 10 to work using the prior art. Commonly used methods.

在使用时:通过连接柱20牵引设备与第二安装架2进行连接,然后通过法兰盘16把外界的输送管与进料管5进行连接,通过牵引装置整体移动到相应的位置处,然后使得电机6工作,使得混凝土能够从浇筑管3中落下,再通过对电动伸缩杆8的工作进行控制,由此使得振动棒10能够进入到浇筑后的混凝土中,然后再使得振动棒10工作,从而进行振捣作业。When in use: connect the pulling device with the second mounting frame 2 through the connecting column 20, then connect the external conveying pipe with the feeding pipe 5 through the flange 16, move it to the corresponding position through the pulling device as a whole, and then Make the motor 6 work so that the concrete can fall from the pouring pipe 3, and then control the operation of the electric telescopic rod 8, so that the vibrating rod 10 can enter the concrete after pouring, and then make the vibrating rod 10 work, Thereby the vibrating operation is carried out.

本实用新型通过对电机6的工作进行控制,由此能够对混凝土进行输送,便于使用者进行浇筑作业。同时在进行浇筑时,通过对振动棒10的工作进行控制,由此能够进行振捣作业,从而使得浇筑与振捣同时进行,后期无需人工再进行振捣作业,提高了工作的效率,降低了工人的劳动强度。By controlling the work of the motor 6, the utility model can transport the concrete, which is convenient for the user to perform the pouring operation. At the same time, during pouring, by controlling the work of the vibrating rod 10, the vibrating operation can be carried out, so that the pouring and vibrating can be carried out at the same time, and no manual vibrating operation is required in the later stage, which improves the work efficiency and reduces the cost of vibration. labor intensity of workers.

尽管已经示出和描述了本实用新型的实施例,对于本领域的普通技术人员而言,可以理解在不脱离本实用新型的原理和精神的情况下可以对这些实施例进行多种变化、修改、替换和变型,本实用新型的范围由所附权利要求及其等同物限定。Although the embodiments of the present invention have been shown and described, it will be understood by those skilled in the art that various changes and modifications can be made to these embodiments without departing from the principles and spirit of the present invention , alternatives and modifications, the scope of the present invention is defined by the appended claims and their equivalents.

Claims (5)

1.一种建筑施工用混凝土浇筑装置,包括第一安装架(1)和第二安装架(2),其特征在于:所述第一安装架(1)的底端设有浇筑管(3),所述浇筑管(3)的侧面设有输料管(4),所述输料管(4)的顶端设有进料管(5),所述浇筑管(3)、输料管(4)和进料管(5)的内部均连通设置,所述第二安装架(2)的底端设有电机(6),所述电机(6)的输出轴贯穿且延伸至输料管(4)的内部并连接有输送架(7),所述第一安装架(1)的顶端对应浇筑管(3)的位置处设有安装板(9),所述安装板(9)的底端通过电动伸缩杆(8)与第一安装架(1)的表面连接,所述安装板(9)的底端对应浇筑管(3)的位置处连接有振动棒(10),所述第一安装架(1)的表面设有控制开关组(11),所述控制开关组(11)的输出端电连接电机(6)、电动伸缩杆(8)和振动棒(10)的输入端。1. A concrete pouring device for building construction, comprising a first mounting frame (1) and a second mounting frame (2), characterized in that: the bottom end of the first mounting frame (1) is provided with a pouring pipe (3) ), the side of the pouring pipe (3) is provided with a feeding pipe (4), the top of the feeding pipe (4) is provided with a feeding pipe (5), the pouring pipe (3), the feeding pipe (4) and the interior of the feeding pipe (5) are communicated with each other, the bottom end of the second mounting frame (2) is provided with a motor (6), and the output shaft of the motor (6) penetrates and extends to the conveying material The inside of the pipe (4) is connected with a conveying frame (7), the top of the first mounting frame (1) is provided with a mounting plate (9) at the position corresponding to the pouring pipe (3), and the mounting plate (9) The bottom end of the mounting plate (9) is connected to the surface of the first mounting frame (1) through an electric telescopic rod (8), and a vibrating rod (10) is connected to the bottom end of the mounting plate (9) corresponding to the position of the pouring pipe (3). The surface of the first mounting frame (1) is provided with a control switch group (11), and the output end of the control switch group (11) is electrically connected to the motor (6), the electric telescopic rod (8) and the vibration rod (10). input. 2.根据权利要求1所述的一种建筑施工用混凝土浇筑装置,其特征在于:所述第一安装架(1)的两侧均是通过轴承座连接有滚轮(12),所述第二安装架(2)的两侧对应第一安装架(1)两侧结构设置。2. A concrete pouring device for building construction according to claim 1, characterized in that both sides of the first mounting frame (1) are connected with rollers (12) through bearing seats, and the second mounting frame (1) is connected with rollers (12) on both sides. The two sides of the mounting frame (2) are structurally arranged corresponding to the two sides of the first mounting frame (1). 3.根据权利要求1所述的一种建筑施工用混凝土浇筑装置,其特征在于:所述安装板(9)的底端设有连接盘(13),所述连接盘(13)的底端设有螺杆(14),所述振动棒(10)的顶端对应螺杆(14)的位置处设有通孔,螺杆(14)贯穿且延伸至振动棒(10)的顶端下方并连接有螺母(15)。3. A concrete pouring device for building construction according to claim 1, wherein the bottom end of the mounting plate (9) is provided with a connecting plate (13), and the bottom end of the connecting plate (13) is provided with a connecting plate (13). A screw (14) is provided, the top of the vibrating rod (10) is provided with a through hole at the position corresponding to the screw (14), the screw (14) penetrates and extends to the bottom of the top of the vibrating rod (10) and is connected with a nut ( 15). 4.根据权利要求1所述的一种建筑施工用混凝土浇筑装置,其特征在于:所述进料管(5)的顶端设有法兰盘(16),所述法兰盘(16)上设有固定孔(17),所述固定孔(17)内转动连接有固定柱(18)。4. A concrete pouring device for building construction according to claim 1, characterized in that: the top of the feed pipe (5) is provided with a flange (16), and the flange (16) is on the A fixing hole (17) is provided, and a fixing column (18) is rotatably connected in the fixing hole (17). 5.根据权利要求1所述的一种建筑施工用混凝土浇筑装置,其特征在于:所述第二安装架(2)上设有连接孔(19),所述连接孔(19)内转动连接有连接柱(20)。5 . The concrete pouring device for building construction according to claim 1 , wherein the second mounting frame ( 2 ) is provided with a connecting hole ( 19 ), and the connecting hole ( 19 ) is rotatably connected in the inside. 6 . There are connecting posts (20).
CN201821802366.0U 2018-11-02 2018-11-02 A kind of construction concrete casting device Expired - Fee Related CN209145293U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821802366.0U CN209145293U (en) 2018-11-02 2018-11-02 A kind of construction concrete casting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821802366.0U CN209145293U (en) 2018-11-02 2018-11-02 A kind of construction concrete casting device

Publications (1)

Publication Number Publication Date
CN209145293U true CN209145293U (en) 2019-07-23

Family

ID=67272252

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821802366.0U Expired - Fee Related CN209145293U (en) 2018-11-02 2018-11-02 A kind of construction concrete casting device

Country Status (1)

Country Link
CN (1) CN209145293U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113106855A (en) * 2021-04-20 2021-07-13 樊涛 Bridge support building and pouring forming equipment and method
CN118128304A (en) * 2024-05-08 2024-06-04 星原建设集团有限公司 Feeding device for assembled concrete building construction

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113106855A (en) * 2021-04-20 2021-07-13 樊涛 Bridge support building and pouring forming equipment and method
CN113106855B (en) * 2021-04-20 2022-12-30 唐山市华运铁路交通器材有限公司 Bridge support building and pouring forming equipment and method
CN118128304A (en) * 2024-05-08 2024-06-04 星原建设集团有限公司 Feeding device for assembled concrete building construction

Similar Documents

Publication Publication Date Title
CN211037850U (en) Concrete pouring equipment for construction
CN205630987U (en) High -efficient agitating unit of mortar for building
CN216196715U (en) Concrete vibrating device for building construction
CN211286675U (en) A concrete pouring device
CN214462669U (en) Concrete pouring device
CN115107142A (en) Civil concrete slab automatic manufacturing device and using method thereof
CN118636271A (en) A kind of prefabricated concrete component production equipment for assembled buildings and intermittent casting method thereof
CN209649028U (en) A kind of Route for pedestrians cement pre-fabricated panel producing device
CN219952771U (en) A construction engineering wall masonry device
CN221321815U (en) A steel bar positioning structure for building construction
CN219294270U (en) Concrete prefabricated part mould
CN219486114U (en) Concrete mixing device is used in bridge road bridge construction
CN216968190U (en) Prefabricated wallboard pouring equipment
CN113338122A (en) Concrete vibrating device for highway engineering
CN221834602U (en) A building concrete prefabricated panel forming machine
CN219095523U (en) A kind of sand and gravel feeding device for concrete preparation
CN223343700U (en) Movable masonry constructional column top concrete one-time forming device
CN219748374U (en) Concrete pouring device
CN115648383B (en) A semi-automatic model pile preparation instrument
CN223523428U (en) Concrete column forming composite formwork
CN208105089U (en) A kind of culvert building wall device
CN222666485U (en) Foam concrete pouring device
CN223824612U (en) Adjustment mechanism and building pouring device
CN219691121U (en) Concrete shakes even device
CN223964170U (en) Concrete crack control structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190723

CF01 Termination of patent right due to non-payment of annual fee