CN209129335U - A kind of construction carrier - Google Patents

A kind of construction carrier Download PDF

Info

Publication number
CN209129335U
CN209129335U CN201821856295.2U CN201821856295U CN209129335U CN 209129335 U CN209129335 U CN 209129335U CN 201821856295 U CN201821856295 U CN 201821856295U CN 209129335 U CN209129335 U CN 209129335U
Authority
CN
China
Prior art keywords
support rod
carrier
bar
bottom plate
carrier bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821856295.2U
Other languages
Chinese (zh)
Inventor
姜宇梁
韩晓丽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201821856295.2U priority Critical patent/CN209129335U/en
Application granted granted Critical
Publication of CN209129335U publication Critical patent/CN209129335U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Mutual Connection Of Rods And Tubes (AREA)

Abstract

The utility model discloses a kind of construction carriers, including bottom plate, four edges of the bottom plate are symmetrically arranged with support rod, the left and right sides of the front/rear end of the bottom plate is symmetrically arranged with the first reinforcing bar, the top of first reinforcing bar is welded on the upper end of support rod, the lower end of the support rod is welded with the second reinforcing bar, second reinforcing bar is welded on the bottom end of the first reinforcing bar far from one end of support rod, the top of the support rod is arranged with three hole connector sleeves, the first carrier bar is provided between the connector sleeve of three hole, the second carrier bar is arranged at intervals between first carrier bar, the upper end of three hole connector sleeve is provided with fixed link, the left and right sides of the first carrier bar and location interval between fixed link is provided with the first pole-climbing, the utility model relates to carrier technical fields.This is used for construction carrier, has achieved the purpose that safety is good, fast assembling-disassembling, has improved the efficiency of construction.

Description

A kind of construction carrier
Technical field
The utility model relates to carrier technical field, specially a kind of construction carrier.
Background technique
In building construction process, since the height of floor is different, in construction, need constantly to adjust the position of construction personnel It sets, guarantees to smoothly complete operation in different height position.In traditional work progress, scaffold is set up in exterior wall, alternatively, It directlys adopt architectural stair and carries out operation.When using scaffold, the structure of scaffold is single, in use process, security protection Measure is insufficient, the case where falling tumble injury from scaffold easily occurs, has seriously endangered the health of construction personnel, meanwhile, foot hand In frame use process, the process of upper and lower scaffold is inconvenient and time-consuming and laborious, affects construction speed.Existing construction is held The security performance of carrier is insufficient, moreover, dismounting gets up to be inconvenient.
Summary of the invention
(1) the technical issues of solving
In view of the deficiencies of the prior art, the utility model provides a kind of construction carrier, solve safety it is poor, The problem of fast assembling-disassembling.
(2) technical solution
In order to achieve the above object, the utility model is achieved by the following technical programs: a kind of construction carrier, Including bottom plate, four edges of the bottom plate are symmetrically arranged with support rod, and bottom plate is run through the bottom of in the upper end of the support rod The upper end of plate, the left and right sides of the front/rear end of the bottom plate are symmetrically arranged with the first reinforcing bar, first reinforcing bar Top is welded on the upper end of support rod, and the lower end of the support rod is welded with the second reinforcing bar, and second reinforcing bar is far from branch One end of strut is welded on the bottom end of the first reinforcing bar, and the top of the support rod is arranged with three hole connector sleeves, three hole It is provided with the first carrier bar between connector sleeve, the second carrier bar is arranged at intervals between first carrier bar, described second holds The upper and lower ends for carrying bar are welded on the first carrier bar, and the upper end of three hole connector sleeve is provided with fixed link, described solid The upper and lower ends of fixed pole are arranged with three hole connector sleeves, the left and right sides and the position between fixed link of first carrier bar It sets and is arranged at intervals with the first pole-climbing, the left and right ends of first pole-climbing are welded in fixed link.
Preferably, the junction of the support rod and bottom plate is fixed by the way of spot welding.
Preferably, the position of the front end face upper end of the bottom plate is provided with third reinforcing bar, a left side for the third reinforcing bar In being obliquely installed upwards, the left and right ends of the third reinforcing bar are welded on support rod at end.
Preferably, single hole connector sleeve, first carrying are enclosed with outside the bottom end at left and right sides of second carrier bar Front end face between bar is provided with fender rod, and the left end of the fender rod is in be obliquely installed upwards, the left and right two of the fender rod End is fixedly connected by single hole connector sleeve with the second carrier bar.
Preferably, one end of the upper and lower surface of three hole connector sleeve and close first carrier bar offers the first connection Hole, the diameter of the support rod, the diameter of the first carrier bar, the diameter of the diameter of fixed link and the first connecting hole are all the same, institute It states single hole connector sleeve and offers the second connecting hole close to the side of fender rod, the diameter of the fender rod is straight with the second connecting hole Diameter is identical.
Preferably, the left and right sides of the bottom plate upper end and the location interval between support rod are provided with second and climb The left and right ends of bar, second pole-climbing are welded on support rod.
(3) beneficial effect
The utility model provides a kind of construction carrier.Have it is following the utility model has the advantages that
(1), support rod, the first carrier bar and fixed link are connected to by the construction carrier by three hole connector sleeves Together, and so on, assembling is built from level to level, by the single hole on the second carrier bar on the left of the upper end and upper layer of fender rod Connector sleeve connection, the single hole connector sleeve on the second carrier bar on the right side of the lower end of fender rod and lower layer is connected, protection building work The safety of people, while playing the role of reinforcing, the height for needing work can be quickly reached by the second pole-climbing and the first pole-climbing, First reinforcing bar, the second reinforcing bar and third reinforcing bar reinforce the chassis of carrier, increase stability and bearing capacity, lead to Crossing three hole connector sleeves and single hole connector sleeve can quickly be dismounted, the diameter of support rod, the diameter of the first carrier bar, fixed link Diameter and the first connecting hole diameter it is all the same, so, the structure and fixation that the first carrier bar, the second carrier bar are combined into The structure that bar, the first pole-climbing are combined into be it is identical, may be used interchangeably, save manufacturing cost, assemble more convenient fast Victory, three hole connector sleeves and single hole connector sleeve are structures common in current sectional furniture, have reached that safety is good, fast assembling-disassembling Purpose, improve the efficiency of construction.
Detailed description of the invention
Fig. 1 is the construction carrier configuration schematic diagram of the utility model;
Fig. 2 is the construction carrier left view of the utility model;
Fig. 3 is the construction carrier right view of the utility model;
Fig. 4 is first carrier bar and the second carrier bar top view of the utility model.
In figure: 1 bottom plate, 2 support rods, 3 first reinforcing bars, 4 second reinforcing bars, 5 three hole connector sleeves, 6 first carrier bars, 7 Second carrier bar, 8 fixed links, 9 first pole-climbings, 10 third reinforcing bars, 11 single hole connector sleeves, 12 fender rods, 13 first connecting holes, 14 second connecting holes, 15 second pole-climbings.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
Fig. 1-4 is please referred to, the utility model provides a kind of technical solution: a kind of construction carrier, including bottom plate 1, Four edges of bottom plate 1 are symmetrically arranged with support rod 2, and bottom plate 1 is run through to the upper end of bottom plate 1, bottom plate in the upper end of support rod 2 The left and right sides of 1 front/rear end is symmetrically arranged with the first reinforcing bar 3, and the top of the first reinforcing bar 3 is welded on support rod 2 Upper end, the lower end of support rod 2 are welded with the second reinforcing bar 4, and the second reinforcing bar 4 is welded on first far from one end of support rod 2 and adds The bottom end of solid rod 3, the top of support rod 2 are arranged with three hole connector sleeves 5, are provided with the first carrier bar between three hole connector sleeves 5 6, the second carrier bar 7 is arranged at intervals between the first carrier bar 6, and the upper and lower ends of the second carrier bar 7 are welded on the first carrying On bar 6, the upper end of three hole connector sleeves 5 is provided with fixed link 8, and the upper and lower ends of fixed link 8 are arranged with three hole connector sleeves 5, The left and right sides of the first carrier bar 6 and location interval between fixed link 8 is provided with the first pole-climbing 9, a left side for the first pole-climbing 9 Right both ends are welded in fixed link 8.
Support rod 2 and the junction of bottom plate 1 are fixed by the way of spot welding.
The position of the front end face upper end of bottom plate 1 is provided with third reinforcing bar 10, and the left end of third reinforcing bar 10 is in updip Tiltedly setting, the left and right ends of third reinforcing bar 10 are welded on support rod 2.
Single hole connector sleeve 11, the front end between the first carrier bar 6 are enclosed with outside the bottom end of second carrier bar, 7 left and right sides Face is provided with fender rod 12, and in being obliquely installed upwards, the left and right ends of fender rod 12 are connected by single hole for the left end of fender rod 12 Female connector 11 is fixedly connected with the second carrier bar 7.
One end of the upper and lower surface of three hole connector sleeves 5 and close first carrier bar 6 offers the first connecting hole 13, supports The diameter of bar 2, the diameter of the first carrier bar 6, the diameter of the diameter of fixed link 8 and the first connecting hole 13 are all the same, single hole connection Set 11 offers the second connecting hole 14, the diameter phase of the diameter of fender rod 12 and the second connecting hole 14 close to the side of fender rod 12 Together.
The left and right sides of 1 upper end of the bottom plate and location interval between support rod 2 is provided with the second pole-climbing 15, second climbs The left and right ends of bar 15 are welded on support rod 2.
In use, support rod 2, the first carrier bar 6 and fixed link 8 are linked together by three hole connector sleeves 5, with such It pushes away, assembling is built from level to level, by the single hole connector sleeve 11 on the second carrier bar 7 on the left of the upper end and upper layer of fender rod 12 Connection, the single hole connector sleeve 11 on the second carrier bar 7 on the right side of the lower end of fender rod 12 and lower layer is connected, and protects construction worker Safety, while playing the role of reinforcing, the height for needing work can be quickly reached by the second pole-climbing 15 and the first pole-climbing 9 Degree, the first reinforcing bar 3, the second reinforcing bar 4 and third reinforcing bar 10 reinforce the chassis of carrier, increase stability and hold Power is carried, can quickly be dismounted by three hole connector sleeves 5 and single hole connector sleeve 11, the diameter of support rod 2, the first carrier bar 6 Diameter, fixed link 8 diameter and the first connecting hole diameter it is all the same, so, the first carrier bar 6, the second carrier bar 7 combination At the structure that is combined into of structure and fixed link 8, the first pole-climbing 9 be it is identical, may be used interchangeably, save manufacturing cost, More convenient and quicker is assembled, three hole connector sleeves 5 and single hole connector sleeve 11 are structures common in current sectional furniture.
It should be noted that, in this document, relational terms such as first and second and the like are used merely to a reality Body or operation are distinguished with another entity or operation, are deposited without necessarily requiring or implying between these entities or operation In any actual relationship or order or sequence.Moreover, the terms "include", "comprise" or its any other variant are intended to Non-exclusive inclusion, so that the process, method, article or equipment including a series of elements is not only wanted including those Element, but also including other elements that are not explicitly listed, or further include for this process, method, article or equipment Intrinsic element.In the absence of more restrictions.By sentence " element limited including one ..., it is not excluded that There is also other identical elements in the process, method, article or apparatus that includes the element ".
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art, It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.

Claims (6)

1. a kind of construction carrier, including bottom plate (1), it is characterised in that: four edges of the bottom plate (1) are symmetrically set It is equipped with support rod (2), the upper end of bottom plate (1) to bottom plate (1) is run through in the upper end of the support rod (2), before the bottom plate (1) The left and right sides of rear end face is symmetrically arranged with the first reinforcing bar (3), and the top of first reinforcing bar (3) is welded on support rod (2) lower end of upper end, the support rod (2) is welded with the second reinforcing bar (4), and second reinforcing bar (4) is far from support rod (2) one end is welded on the bottom end of the first reinforcing bar (3), and the top of the support rod (2) is arranged with three hole connector sleeves (5), It is provided between three hole connector sleeve (5) the first carrier bar (6), is arranged at intervals with second between first carrier bar (6) The upper and lower ends of carrier bar (7), second carrier bar (7) are welded on the first carrier bar (6), three hole connector sleeve (5) upper end is provided with fixed link (8), and the upper and lower ends of the fixed link (8) are arranged with three hole connector sleeves (5), described The left and right sides of first carrier bar (6) and the location interval between fixed link (8) is provided with the first pole-climbing (9), described The left and right ends of one pole-climbing (9) are welded on fixed link (8).
2. a kind of construction carrier according to claim 1, it is characterised in that: the support rod (2) and bottom plate (1) Junction is fixed by the way of spot welding.
3. a kind of construction carrier according to claim 1, it is characterised in that: the front end face upper end of the bottom plate (1) Position be provided with third reinforcing bar (10), in being obliquely installed upwards, the third adds for the left end of the third reinforcing bar (10) The left and right ends of solid rod (10) are welded on support rod (2).
4. a kind of construction carrier according to claim 1, it is characterised in that: the second carrier bar (7) left and right two It is enclosed with outside the bottom end of side single hole connector sleeve (11), the front end face between first carrier bar (6) is provided with fender rod (12), in being obliquely installed upwards, the left and right ends of the fender rod (12) are connected by single hole for the left end of the fender rod (12) Female connector (11) is fixedly connected with the second carrier bar (7).
5. a kind of construction carrier according to claim 4, it is characterised in that: above and below three hole connector sleeve (5) One end of surface and close first carrier bar (6) offers the first connecting hole (13), the diameter of the support rod (2), first The diameter of the diameter of carrier bar (6), the diameter of fixed link (8) and the first connecting hole (13) is all the same, the single hole connector sleeve (11) side close to fender rod (12) offers the second connecting hole (14), the diameter and the second connecting hole of the fender rod (12) (14) diameter is identical.
6. a kind of construction carrier according to claim 1, it is characterised in that: the left and right two of bottom plate (1) upper end The side and location interval between support rod (2) is provided with the second pole-climbing (15), the left and right ends of second pole-climbing (15) It is welded on support rod (2).
CN201821856295.2U 2018-11-12 2018-11-12 A kind of construction carrier Expired - Fee Related CN209129335U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821856295.2U CN209129335U (en) 2018-11-12 2018-11-12 A kind of construction carrier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821856295.2U CN209129335U (en) 2018-11-12 2018-11-12 A kind of construction carrier

Publications (1)

Publication Number Publication Date
CN209129335U true CN209129335U (en) 2019-07-19

Family

ID=67244740

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821856295.2U Expired - Fee Related CN209129335U (en) 2018-11-12 2018-11-12 A kind of construction carrier

Country Status (1)

Country Link
CN (1) CN209129335U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111962957A (en) * 2020-08-18 2020-11-20 广东电网有限责任公司肇庆供电局 Assembling tool for erecting power line steel pipe pole

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111962957A (en) * 2020-08-18 2020-11-20 广东电网有限责任公司肇庆供电局 Assembling tool for erecting power line steel pipe pole

Similar Documents

Publication Publication Date Title
CN209129335U (en) A kind of construction carrier
CN205476387U (en) Scaffold
CN208456100U (en) A kind of connection structure of the protective net of climbing frame
CN207827674U (en) A kind of special cage of building block pile
CN207003981U (en) A kind of movable altitude operation protective frame with safety supports
CN219528334U (en) Scaffold for building construction
CN208668903U (en) A kind of fabricated scaffold
CN207847033U (en) A kind of scaffold for building convenient for adjusting
CN202899588U (en) Assembling scaffold structure
CN206034888U (en) Combination formula scaffold frame of new generation that board position is adjustable and have super high security performance of standing
CN2561868Y (en) Triangular stud scaffold
CN202882383U (en) Novel scaffold board
CN209194967U (en) A kind of construction combined type hanging cage
CN202876290U (en) Rock climbing graduation wall dual-purpose apparatus
CN218346727U (en) Scaffold for building engineering
CN221567841U (en) Modularized mounting platform for high-altitude welding and assembling of steel structure
CN212583162U (en) Assembled integral protection operation platform
CN205063350U (en) Portable assembled horizontal channel
CN206126696U (en) A detachable indoor hoist for buckling restrained brace
CN211622504U (en) Support frame for building
CN216971820U (en) Large tower crane standard section connecting mechanism with high assembling efficiency
CN210067399U (en) Operation platform device of attached lifting scaffold
CN212562404U (en) Overhanging scaffold
CN109898816A (en) A kind of housing construction scaffold
CN210839554U (en) Security protection device for construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190719

CF01 Termination of patent right due to non-payment of annual fee