CN209129025U - A civil engineering construction retaining wall - Google Patents

A civil engineering construction retaining wall Download PDF

Info

Publication number
CN209129025U
CN209129025U CN201821030089.6U CN201821030089U CN209129025U CN 209129025 U CN209129025 U CN 209129025U CN 201821030089 U CN201821030089 U CN 201821030089U CN 209129025 U CN209129025 U CN 209129025U
Authority
CN
China
Prior art keywords
wall
soil layer
rib
civil engineering
engineering construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821030089.6U
Other languages
Chinese (zh)
Inventor
刘柳
田祖安
李纯
赖莦丹
于颖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
INNER MONGOLIA KANGNING BLASTING Co Ltd
Original Assignee
INNER MONGOLIA KANGNING BLASTING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by INNER MONGOLIA KANGNING BLASTING Co Ltd filed Critical INNER MONGOLIA KANGNING BLASTING Co Ltd
Priority to CN201821030089.6U priority Critical patent/CN209129025U/en
Application granted granted Critical
Publication of CN209129025U publication Critical patent/CN209129025U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The utility model discloses a kind of Construction of Civil Engineering retaining walls, including several walls, these described walls are fixed together by the crossbeam of several vertical array distributions, the bottom of the wall is equipped with several equally distributed foundation, it is provided with the anchor pole of several horizontal arrays between two adjacent crossbeams, metalling is filled between the wall and soil layer.The retaining wall utilizes, and there is cambered surface side to be contacted by metalling with soil layer, it is different from the setting that the vertical plane that traditional wall uses directly is contacted with soil layer, the Force decomposition from soil layer can be fallen a part using cambered surface, compared with the set-up mode of conventionally employed vertical plane, the cross force that wall is subject to can reduce, the risk that wall collapses is thereby reduced, while can further buffer effect of the soil layer to wall using the gap between metalling medium stone;Multiple walls are fixed together also with crossbeam, ensure that the stability between multiple walls.

Description

一种土木工程施工挡土墙A civil engineering construction retaining wall

技术领域technical field

本实用新型涉及一种土木工程施工挡土墙。The utility model relates to a retaining wall for civil engineering construction.

背景技术Background technique

随着时代的发展,人们的生活水平不断地提高,人们对于工程建设的要求越来越高,挡土墙是指支撑路基填土或山坡土体、防止填土或土体变形的构筑物,在施工时经常会对填土进行阻挡,避免施工时发生塌方的事故,因此挡土墙被广泛运用于工程施工中,但是现有的挡土墙结构简单,大多是设置一堵混凝土墙,导致挡土墙的功能太过局限,且不能够很好的保证填土的安全,另外挡土墙主要承受的是土层对墙体的作用力,因此要求墙体的横向支撑要牢固,避免墙体倒塌。With the development of the times, people's living standards continue to improve, and people have higher and higher requirements for engineering construction. Retaining walls refer to structures that support roadbed fill or hillside soil and prevent fill or soil deformation. Filling is often blocked during construction to avoid landslide accidents during construction. Therefore, retaining walls are widely used in engineering construction. However, the existing retaining walls have simple structures, and most of them are set with a concrete wall. The function of the earth wall is too limited, and it cannot ensure the safety of the filling. In addition, the retaining wall mainly bears the force of the soil layer on the wall, so the lateral support of the wall is required to be firm to avoid the wall. collapse.

实用新型内容Utility model content

针对上述存在的技术不足,本实用新型的目的是提供一种土木工程施工挡土墙,提高墙体的横向支撑能力,加强对土层的阻挡,避免墙体的倒塌。In view of the above-mentioned technical deficiencies, the purpose of this utility model is to provide a retaining wall for civil engineering construction, which can improve the lateral support ability of the wall, strengthen the blocking of the soil layer, and avoid the collapse of the wall.

为解决上述技术问题,本实用新型采用如下技术方案:In order to solve the above-mentioned technical problems, the utility model adopts the following technical solutions:

本实用新型提供一种土木工程施工挡土墙,包括若干个墙体,这些所述墙体通过若干个竖向阵列分布的横梁固定在一起,对应的所述墙体上开设有供所述横梁穿过的安装孔,所述横梁水平布置在所述墙体内,所述墙体至少有一部分埋入土层内,所述墙体的底部固定设置有若干个均匀分布的底柱,所述底柱埋入土层内,相邻的两个所述横梁之间设置有若干个水平阵列的锚杆,所述锚杆与所述横梁相垂直,所述墙体的横截面由三条相互垂直的直线和一个圆弧线组成,该圆弧线对应的圆心角为锐角,对应的所述墙体具有弧面的一侧与土层之间填充有碎石层,所述锚杆依次穿过所述墙体和所述碎石层延伸到土层内。The utility model provides a retaining wall for civil engineering construction, comprising a plurality of walls, the walls are fixed together by a plurality of beams distributed in a vertical array, and the corresponding walls are provided with the beams for the beams Through the installation hole, the beam is horizontally arranged in the wall, at least a part of the wall is buried in the soil layer, the bottom of the wall is fixed with a number of evenly distributed bottom columns, the bottom of the wall is The column is buried in the soil layer, and several horizontal arrays of anchor rods are arranged between the two adjacent beams, and the anchor rods are perpendicular to the beams. and a circular arc line, the central angle corresponding to the circular arc line is an acute angle, the corresponding side of the wall with the arc surface and the soil layer is filled with a gravel layer, and the anchor rod passes through the The wall and the crushed stone layer extend into the soil layer.

优选地,所述横梁为正四棱柱状的钢管,所述横梁的一对侧壁上固定设置有若干个阵列分布的第一肋板,所述横梁的另一对侧壁上固定设置有若干个阵列分布的第二肋板,所述第一肋板与所述第二肋板相间排列,对应的所述横梁上开设有供所述第一肋板与所述第二肋板穿入的槽口,所述第一肋板与所述第二肋板均为结构相同的长方体状的钢板,所述第一肋板的长度不大于所述横梁的宽度,所述第一肋板的宽度不大于所述横梁的宽度的1/2,所述第一肋板的厚度与所述横梁的壁厚相等。Preferably, the beam is a regular square-shaped steel pipe, a pair of side walls of the beam are fixedly provided with a plurality of first ribs distributed in an array, and the other pair of side walls of the beam are fixedly provided with a number of first ribs The second ribs distributed in an array, the first ribs and the second ribs are arranged alternately, and the corresponding beams are provided with grooves for the first ribs and the second ribs to penetrate The first rib plate and the second rib plate are both cuboid-shaped steel plates with the same structure, the length of the first rib plate is not greater than the width of the beam, and the width of the first rib plate is not larger than the width of the beam. More than 1/2 of the width of the beam, the thickness of the first rib is equal to the wall thickness of the beam.

优选地,所述横梁的内腔中浇筑有混凝土,所述横梁的两端固定有限位钢板,所述限位钢板上螺纹装配有若干个均匀分布的螺栓,所述螺栓抵紧在所述墙体上。Preferably, concrete is poured into the inner cavity of the beam, limit steel plates are fixed at both ends of the beam, and several bolts evenly distributed are threaded on the limit steel plates, and the bolts are pressed against the wall. body.

优选地,所述墙体与所述底柱均为钢筋混凝土。Preferably, the wall body and the bottom column are both reinforced concrete.

本实用新型的有益效果在于:该挡土墙利用具有弧面一侧通过碎石层与土层接触,有别于传统墙体采用的竖直面直接与土层接触的设置,利用弧面能够将来自土层的作用力分解掉一部分,与传统采用竖直面的设置方式相比,墙体受到的横向力会减小,进而降低了墙体倒塌的风险,同时利用碎石层中碎石子之间的间隙能够进一步的缓冲土层对墙体的作用;此外利用横梁将多个墙体固定在一起,保证了多个墙体之间的稳定性。The beneficial effect of the utility model is that: the retaining wall utilizes an arc surface on one side to contact the soil layer through the gravel layer, which is different from the traditional wall in which the vertical surface directly contacts the soil layer. By decomposing a part of the force from the soil layer, compared with the traditional vertical plane setting, the lateral force on the wall will be reduced, thereby reducing the risk of wall collapse. The gap between the sub-layers can further buffer the effect of the soil layer on the wall; in addition, the beams are used to fix the multiple walls together to ensure the stability between the multiple walls.

附图说明Description of drawings

为了更清楚地说明本实用新型实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本实用新型的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the embodiments of the present utility model or the technical solutions in the prior art, the following briefly introduces the accompanying drawings that need to be used in the description of the embodiments or the prior art. Obviously, the accompanying drawings in the following description These are just some embodiments of the present invention, and for those of ordinary skill in the art, other drawings can also be obtained from these drawings without creative effort.

图1为本实用新型实施例提供的一种土木工程施工挡土墙的结构示意图;Fig. 1 is the structural representation of a kind of civil engineering construction retaining wall provided by the utility model embodiment;

图2为图1的侧视图;Fig. 2 is the side view of Fig. 1;

图3为横梁的主视图;Figure 3 is a front view of a beam;

图4为图3的侧视图;Fig. 4 is the side view of Fig. 3;

图5为图3的俯视图。FIG. 5 is a top view of FIG. 3 .

附图标记说明:1-墙体、11-底柱、2-碎石层、3-横梁、31-第一肋板、32-第二肋板、33-限位钢板、4-锚杆、5-土层。Description of reference numerals: 1-wall, 11-bottom column, 2-crushed stone layer, 3-beam, 31-first rib, 32-second rib, 33-limiting steel plate, 4-anchor rod, 5- Soil layer.

具体实施方式Detailed ways

下面将结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本实用新型一部分实施例,而不是全部的实施例。基于本实用新型中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本实用新型保护的范围。The technical solutions in the embodiments of the present utility model will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present utility model. Obviously, the described embodiments are only a part of the embodiments of the present utility model, rather than all the implementations. example. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative work fall within the protection scope of the present invention.

如图1至图5所示,一种土木工程施工挡土墙,包括若干个墙体1,这些所述墙体1通过若干个竖向阵列分布的横梁3固定在一起,对应的所述墙体1上开设有供所述横梁3穿过的安装孔,所述横梁3水平布置在所述墙体1内,所述墙体1至少有一部分埋入土层5内,所述墙体1的底部固定设置有若干个均匀分布的底柱11,所述底柱11埋入土层5内,相邻的两个所述横梁3之间设置有若干个水平阵列的锚杆4,所述锚杆4与所述横梁3相垂直,所述墙体1的横截面由三条相互垂直的直线和一个圆弧线组成,该圆弧线对应的圆心角为锐角,对应的所述墙体1具有弧面的一侧与土层5之间填充有碎石层2,所述锚杆4依次穿过所述墙体1和所述碎石层2延伸到土层5内。As shown in Figures 1 to 5, a retaining wall for civil engineering construction includes several wall bodies 1, and these wall bodies 1 are fixed together by a plurality of beams 3 distributed in a vertical array. The body 1 is provided with a mounting hole for the beam 3 to pass through, the beam 3 is horizontally arranged in the wall 1, and at least a part of the wall 1 is buried in the soil layer 5, and the wall 1 is The bottom is fixedly provided with a number of evenly distributed bottom columns 11, the bottom columns 11 are buried in the soil layer 5, and a number of horizontally arrayed anchor rods 4 are arranged between the two adjacent beams 3. The anchor rods 4 is perpendicular to the beam 3, the cross section of the wall 1 is composed of three mutually perpendicular straight lines and a circular arc, the central angle corresponding to the circular arc is an acute angle, and the corresponding wall 1 has an arc. A gravel layer 2 is filled between one side of the surface and the soil layer 5 , and the anchor rod 4 extends into the soil layer 5 through the wall 1 and the gravel layer 2 in sequence.

优选地,所述横梁3为正四棱柱状的钢管,所述横梁3的一对侧壁上固定设置有若干个阵列分布的第一肋板31,所述横梁3的另一对侧壁上固定设置有若干个阵列分布的第二肋板32,所述第一肋板31与所述第二肋板32相间排列,对应的所述横梁3上开设有供所述第一肋板31与所述第二肋板32穿入的槽口,所述第一肋板31与所述第二肋板32均为结构相同的长方体状的钢板,所述第一肋板31的长度不大于所述横梁3的宽度,所述第一肋板31的宽度不大于所述横梁3的宽度的1/2,所述第一肋板31的厚度与所述横梁3的壁厚相等。其中第一肋板31与第二肋板32是设置大大提高了横梁3的抗弯强度,有效的保证了多个墙体1之间的稳定性。Preferably, the beam 3 is a regular square-shaped steel pipe, a pair of side walls of the beam 3 are fixedly provided with a plurality of first ribs 31 distributed in an array, and the other pair of side walls of the beam 3 are fixed on A plurality of second ribs 32 distributed in an array are provided, the first ribs 31 and the second ribs 32 are arranged alternately, and the corresponding beams 3 are provided with the first ribs 31 and the second ribs 32. The slot into which the second rib 32 penetrates, the first rib 31 and the second rib 32 are both cuboid-shaped steel plates with the same structure, and the length of the first rib 31 is not greater than the length of the The width of the beam 3 , the width of the first rib 31 is not greater than 1/2 of the width of the beam 3 , and the thickness of the first rib 31 is equal to the wall thickness of the beam 3 . The first rib 31 and the second rib 32 are arranged to greatly improve the bending strength of the beam 3 and effectively ensure the stability between the multiple walls 1 .

优选地,所述横梁3的内腔中浇筑有混凝土,混凝土的浇筑进一步的提高了横梁3的稳定性,同时第一肋板31与第二肋板32相间并且垂直布置,使其与横梁3的侧壁之间具有空隙,进而方便混凝土的顺利浇筑,保证混凝土的均匀性;所述横梁3的两端固定有限位钢板33,所述限位钢板3上螺纹装配有若干个均匀分布的螺栓,所述螺栓抵紧在所述墙体1上。Preferably, concrete is poured into the inner cavity of the beam 3, and the pouring of the concrete further improves the stability of the beam 3. At the same time, the first rib plate 31 and the second rib plate 32 are alternately and vertically arranged, so that the beam 3 and the beam 3 are arranged vertically. There are gaps between the side walls of the beams, so as to facilitate the smooth pouring of concrete and ensure the uniformity of the concrete; the two ends of the beam 3 are fixed with limit steel plates 33, and the limit steel plates 3 are threaded with several evenly distributed bolts , the bolts are pressed against the wall body 1 .

优选地,所述墙体1与所述底柱11均为钢筋混凝土。Preferably, the wall body 1 and the bottom column 11 are both reinforced concrete.

优选地,所述锚杆4为注浆锚杆,该锚杆可以为聊城市万尊金属制品有限公司生产的锚杆,其具体型号和大小本申请不在做具体描述,使用者可以根据实际情况进行选择或者进行定制。Preferably, the anchor rod 4 is a grouting anchor rod, and the anchor rod can be an anchor rod produced by Liaocheng Wanzun Metal Products Co., Ltd. The specific model and size of the anchor rod are not described in this application, and the user can refer to the actual situation. Make a selection or customize.

本实用新型的具体施工步骤如下:The concrete construction steps of the present utility model are as follows:

S1:根据施工所挖的基坑的大小确定出所需墙体的尺寸,墙体为事先浇筑好的钢筋混凝土,墙体在制造时需预留供横梁穿过的安装孔以及供锚杆穿过的锚杆孔,同时底柱在墙体制造的时与墙体一体浇筑成型;S1: Determine the size of the required wall according to the size of the foundation pit dug for construction. The wall is reinforced concrete that has been poured in advance. The wall needs to reserve installation holes for the beam to pass through and for the anchor rod to pass through. At the same time, the bottom column is integrally cast with the wall when the wall is manufactured;

S2:利用横梁将多个墙体连接在一起,横梁在穿过多个墙体后,要保证横梁的两端均凸出于墙体之外,然后在横梁的两端焊接限位钢板,通过限位钢板的螺栓将墙体抵紧在一起;S2: Use beams to connect multiple walls together. After the beams pass through multiple walls, ensure that both ends of the beams protrude out of the walls, and then weld limit steel plates at both ends of the beams to pass The bolts of the limit steel plate press the walls together;

S4:将安装好的墙体吊入基坑内,在墙体吊入前,在基坑的底部事先挖好供底柱插入的孔;S4: Hang the installed wall into the foundation pit, and dig holes at the bottom of the foundation pit for insertion of the bottom column before the wall is hoisted;

S5:待墙体在基坑内安放好后,墙体具有弧面的一侧与土层之间填充有碎石层,碎石采用普通的建筑用的石子即可,只要其粒径不超过50mm即可;S5: After the wall is placed in the foundation pit, the side of the wall with the arc surface and the soil layer is filled with a gravel layer. The gravel can be made of ordinary construction stones, as long as the particle size does not exceed 50mm You can;

S6:待碎石层填装完成后,按照注浆锚杆的施工要求通过锚杆孔将注浆锚杆锚入土层内,待注浆锚杆安装完成后,利用混凝土将墙体之间的接缝处抹平,同时对墙体两端凸出来的横梁以及该横梁上的限位钢板和螺栓进行混凝土灌注,利用混凝土将其覆盖,避免横梁、限位钢板以及螺栓裸露出来。S6: After the filling of the gravel layer is completed, the grouting bolt is anchored into the soil layer through the bolt hole according to the construction requirements of the grouting bolt. Smooth the joints, and pour concrete into the beams protruding from both ends of the wall and the limit steel plates and bolts on the beams, and cover them with concrete to prevent the beams, limit steel plates and bolts from being exposed.

本实用新型中的该挡土墙利用具有弧面一侧通过碎石层与土层接触,有别于传统墙体采用的竖直面直接与土层接触的设置,利用弧面能够将来自土层的作用力分解掉一部分,与传统采用竖直面的设置方式相比,墙体受到的横向力会减小,进而降低了墙体倒塌的风险,同时利用碎石层中碎石子之间的间隙能够进一步的缓冲土层对墙体的作用;此外利用横梁将多个墙体固定在一起,保证了多个墙体之间的稳定性。The retaining wall in the utility model utilizes an arc surface to contact the soil layer through the gravel layer on one side, which is different from the traditional wall in which the vertical surface directly contacts the soil layer. Compared with the traditional setting method of vertical plane, the lateral force on the wall will be reduced, thereby reducing the risk of wall collapse. The gap can further buffer the effect of the soil layer on the wall; in addition, the beams are used to fix the multiple walls together to ensure the stability between the multiple walls.

显然,本领域的技术人员可以对本实用新型进行各种改动和变型而不脱离本实用新型的精神和范围。这样,倘若本实用新型的这些修改和变型属于本实用新型权利要求及其等同技术的范围之内,则本实用新型也意图包含这些改动和变型在内。Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present utility model fall within the scope of the claims of the present utility model and their equivalents, the present utility model is also intended to include these modifications and variations.

Claims (5)

1.一种土木工程施工挡土墙,其特征在于,包括若干个墙体(1),这些所述墙体(1)通过若干个竖向阵列分布的横梁(3)固定在一起,对应的所述墙体(1)上开设有供所述横梁(3)穿过的安装孔,所述横梁(3)水平布置在所述墙体(1)内,所述墙体(1)至少有一部分埋入土层(5)内,所述墙体(1)的底部固定设置有若干个均匀分布的底柱(11),所述底柱(11)埋入土层(5)内,相邻的两个所述横梁(3)之间设置有若干个水平阵列的锚杆(4),所述锚杆(4)与所述横梁(3)相垂直,所述墙体(1)的横截面由三条相互垂直的直线和一个圆弧线组成,该圆弧线对应的圆心角为锐角,对应的所述墙体(1)具有弧面的一侧与土层(5)之间填充有碎石层(2),所述锚杆(4)依次穿过所述墙体(1)和所述碎石层(2)延伸到土层(5)内。1. A retaining wall for civil engineering construction, characterized in that it comprises several wall bodies (1), and these wall bodies (1) are fixed together by several beams (3) distributed in a vertical array, and corresponding The wall (1) is provided with a mounting hole for the beam (3) to pass through, the beam (3) is horizontally arranged in the wall (1), and the wall (1) has at least A part is buried in the soil layer (5), the bottom of the wall body (1) is fixedly provided with a number of evenly distributed bottom columns (11), the bottom columns (11) are buried in the soil layer (5), adjacent Several anchor rods (4) in a horizontal array are arranged between the two beams (3), the anchor rods (4) are perpendicular to the beams (3), and the cross-section of the wall (1) It consists of three mutually perpendicular straight lines and a circular arc line, the central angle corresponding to the circular arc line is an acute angle, and the corresponding side of the wall (1) with the arc surface and the soil layer (5) is filled with debris. A stone layer (2), and the anchor rod (4) extends into the soil layer (5) through the wall (1) and the crushed stone layer (2) in sequence. 2.如权利要求1所述的一种土木工程施工挡土墙,其特征在于,所述横梁(3)为正四棱柱状的钢管,所述横梁(3)的一对侧壁上固定设置有若干个阵列分布的第一肋板(31),所述横梁(3)的另一对侧壁上固定设置有若干个阵列分布的第二肋板(32),所述第一肋板(31)与所述第二肋板(32)相间排列,对应的所述横梁(3)上开设有供所述第一肋板(31)与所述第二肋板(32)穿入的槽口,所述第一肋板(31)与所述第二肋板(32)均为结构相同的长方体状的钢板,所述第一肋板(31)的长度不大于所述横梁(3)的宽度,所述第一肋板(31)的宽度不大于所述横梁(3)的宽度的1/2,所述第一肋板(31)的厚度与所述横梁(3)的壁厚相等。2. A civil engineering construction retaining wall as claimed in claim 1, characterized in that the beam (3) is a regular square-shaped steel pipe, and a pair of side walls of the beam (3) are fixedly provided with A plurality of first ribs (31) distributed in an array, a plurality of second ribs (32) distributed in an array are fixedly arranged on the other pair of side walls of the beam (3), and the first ribs (31) ) and the second rib (32) are arranged alternately, and the corresponding beam (3) is provided with a notch for the first rib (31) and the second rib (32) to penetrate , the first rib (31) and the second rib (32) are both cuboid-shaped steel plates with the same structure, and the length of the first rib (31) is not greater than the length of the beam (3) Width, the width of the first rib (31) is not greater than 1/2 of the width of the beam (3), and the thickness of the first rib (31) is equal to the wall thickness of the beam (3) . 3.如权利要求2所述的一种土木工程施工挡土墙,其特征在于,所述横梁(3)的内腔中浇筑有混凝土,所述横梁(3)的两端固定有限位钢板(33),所述限位钢板(33)上螺纹装配有若干个均匀分布的螺栓,所述螺栓抵紧在所述墙体(1)上。3. A kind of retaining wall for civil engineering construction as claimed in claim 2, is characterized in that, the inner cavity of described beam (3) is poured with concrete, and both ends of described beam (3) are fixed with limited steel plates ( 33), the limiting steel plate (33) is threaded with several bolts that are evenly distributed, and the bolts are pressed against the wall body (1). 4.如权利要求1所述的一种土木工程施工挡土墙,其特征在于,所述墙体(1)与所述底柱(11)均为钢筋混凝土。4. The retaining wall for civil engineering construction according to claim 1, wherein the wall body (1) and the bottom column (11) are both reinforced concrete. 5.如权利要求1所述的一种土木工程施工挡土墙,其特征在于,所述锚杆(4)为注浆锚杆。5 . The retaining wall for civil engineering construction according to claim 1 , wherein the anchor rod ( 4 ) is a grouting anchor rod. 6 .
CN201821030089.6U 2018-07-02 2018-07-02 A civil engineering construction retaining wall Active CN209129025U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821030089.6U CN209129025U (en) 2018-07-02 2018-07-02 A civil engineering construction retaining wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821030089.6U CN209129025U (en) 2018-07-02 2018-07-02 A civil engineering construction retaining wall

Publications (1)

Publication Number Publication Date
CN209129025U true CN209129025U (en) 2019-07-19

Family

ID=67226553

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821030089.6U Active CN209129025U (en) 2018-07-02 2018-07-02 A civil engineering construction retaining wall

Country Status (1)

Country Link
CN (1) CN209129025U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110374191A (en) * 2019-07-31 2019-10-25 同济大学建筑设计研究院(集团)有限公司 A kind of outer wall of basement component and its construction method with protective function

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110374191A (en) * 2019-07-31 2019-10-25 同济大学建筑设计研究院(集团)有限公司 A kind of outer wall of basement component and its construction method with protective function

Similar Documents

Publication Publication Date Title
CN103711135B (en) Anti-slide pile with arch-connected structure
CN106522270A (en) Pile foundation and retaining wall anti-earthquake retaining structure comprising EPS buffer layers and construction method
CN107059882A (en) Arch anchor net and Anchor-Pile Retaining Structure structure
CN104988948A (en) Rib plate type retaining wall and construction method thereof
CN104831639A (en) Consolidation and release construction method for 0# blocks of ultra-wide non-uniform continuous beam
CN209129025U (en) A civil engineering construction retaining wall
CN209509554U (en) Increase basement underpinning structure under existing building newly
CN209053119U (en) A kind of combined earthquake-resistant cantilever retaining wall
CN106088133A (en) Transmission line of electricity composite foundation for desert area
CN209339171U (en) Transmission line assembled sheet pile composite foundation
CN210104765U (en) High and large retaining structure of soft geological side slope
CN204780635U (en) Super wide nonprismatic continuous beam 0# piece concreties and relieves construction structures
CN106337512A (en) The bottom reinforced concrete-filled steel tubular frame high-strength concrete composite shear wall and manufacturing method
CN212294679U (en) Combined lattice column-concrete precast pile inclined support structure
CN206337566U (en) Foundation ditch vertical prestressing anchor pole supporting construction
CN105863073B (en) Coupled column and base node structure and its construction method with horizontal anti-seismic performance
CN205677089U (en) There is coupled column and the base node structure of horizontal anti-seismic performance
CN212294729U (en) Steel construction outsourcing column foot structure
CN103643695B (en) A kind of prefabricated fish belly type nested type wing plate basis
CN210737587U (en) Cantilever type retaining wall structure
CN210946864U (en) Landscape structure foundation for soft stratum
CN211948542U (en) Anti-skid weight-balancing retaining wall assembly and retaining wall system
CN108193695A (en) A kind of enclosure structure of foundation pit of subway station support and construction method
CN209989819U (en) Foundation pit slope supporting structure
CN207862947U (en) A kind of enclosure structure of foundation pit of subway station support

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: A retaining wall for civil engineering construction

Effective date of registration: 20200911

Granted publication date: 20190719

Pledgee: Rural credit cooperative association of Dalat banner

Pledgor: INNER MONGOLIA KINERGY BLASTING Co.,Ltd.

Registration number: Y2020150000048

PE01 Entry into force of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20220901

Granted publication date: 20190719

Pledgee: Rural credit cooperative association of Dalat banner

Pledgor: INNER MONGOLIA KINERGY BLASTING CO.,LTD.

Registration number: Y2020150000048

PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: A civil engineering construction retaining wall

Effective date of registration: 20220905

Granted publication date: 20190719

Pledgee: Rural credit cooperative association of Dalat banner

Pledgor: INNER MONGOLIA KINERGY BLASTING CO.,LTD.

Registration number: Y2022150000092

PC01 Cancellation of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Granted publication date: 20190719

Pledgee: Rural credit cooperative association of Dalat banner

Pledgor: INNER MONGOLIA KINERGY BLASTING CO.,LTD.

Registration number: Y2022150000092

PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: A civil engineering construction retaining wall

Granted publication date: 20190719

Pledgee: Rural credit cooperative association of Dalat banner

Pledgor: INNER MONGOLIA KINERGY BLASTING CO.,LTD.

Registration number: Y2025980018332

PC01 Cancellation of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Granted publication date: 20190719

Pledgee: Rural credit cooperative association of Dalat banner

Pledgor: INNER MONGOLIA KINERGY BLASTING CO.,LTD.

Registration number: Y2025980018332

PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: A civil engineering construction retaining wall

Granted publication date: 20190719

Pledgee: Inner Mongolia Rural Commercial Bank Co.,Ltd. Dalat Banner Branch

Pledgor: INNER MONGOLIA KINERGY BLASTING CO.,LTD.

Registration number: Y2025980018842