CN209094525U - One kind using pouring device for tin bar processing - Google Patents

One kind using pouring device for tin bar processing Download PDF

Info

Publication number
CN209094525U
CN209094525U CN201821657170.7U CN201821657170U CN209094525U CN 209094525 U CN209094525 U CN 209094525U CN 201821657170 U CN201821657170 U CN 201821657170U CN 209094525 U CN209094525 U CN 209094525U
Authority
CN
China
Prior art keywords
formwork
placing
metal
slot
tin bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821657170.7U
Other languages
Chinese (zh)
Inventor
蔡伟佳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Yongjiarun Metal Co Ltd
Original Assignee
Shenzhen Yongjiarun Metal Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Yongjiarun Metal Co Ltd filed Critical Shenzhen Yongjiarun Metal Co Ltd
Priority to CN201821657170.7U priority Critical patent/CN209094525U/en
Application granted granted Critical
Publication of CN209094525U publication Critical patent/CN209094525U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses one kind to be used for tin bar processing pouring device, including casting platform, metal carrying handle and the second metal jacking block, the outside installation settings of the casting platform has cooling trough, and the inside installation settings of cooling trough has the first formwork for placing, the inside installation of first formwork for placing offers first and pours slot, and first the inside installation settings for pouring slot have the first metal jacking block, the metal carrying handle is fixed on the outside of the second formwork for placing, and second the inside installation of formwork for placing offer second and pour slot, the second metal jacking block is mounted on the second inside for pouring slot, the lower section installation settings of the casting platform has alloy limited block.This is used for tin bar processing pouring device and uses cooling trough and metal carrying handle, take by metal carrying handle the first formwork for placing and the second formwork for placing, time needed for shortening the first formwork for placing and the second formwork for placing bottom coohng.

Description

One kind using pouring device for tin bar processing
Technical field
The utility model relates to tin bar technical field of processing equipment, specially a kind of to use pouring device for tin bar processing.
Background technique
Tin bar is one of scolding tin product, and tin bar, which is divided into, slicker solder item and two kinds of lead-free tin bar, is for wiring board Welding, currently, needing to pour Xi Shui in mold into, tin bar is cooled and shaped in mold during the manufacturing of tin bar Afterwards, it fits like a glove with mold.
Therefore tin bar is removed from the molds just relatively difficult, using turning mold around, hammer taps some, makes tin Item is damaged in production process falling ground, however this way is time-consuming and laborious, and tin bar manufacturing cost is high, and is producing A large amount of heat is generated in the process, causes to cool down the required time longer.
Utility model content
The purpose of this utility model is to provide one kind to be used for tin bar processing pouring device, to solve above-mentioned background technique The tin bar manufacturing cost of middle proposition is high, and generates a large amount of heat in process of production, causes to cool down the required time longer The problem of.
To achieve the above object, the utility model provides the following technical solutions: one kind processes for tin bar and uses pouring device, Including casting platform, metal carrying handle and the second metal jacking block, the outside installation settings of the casting platform has cooling trough, and cold But the inside installation settings of sink has the first formwork for placing, and the inside installation of first formwork for placing offers first and pours Slot, and the first inside installation settings for pouring slot has the first metal jacking block, the metal carrying handle is fixed on second and pours mould The outside of plate, and the inside installation of the second formwork for placing offers second and pours slot, the second metal jacking block is mounted on Second pours the inside of slot, and the lower section installation settings of the casting platform has alloy limited block, and the inside peace of alloy limited block Installing is equipped with the first metallic carrier rod, is mounted with plastic support plate below first metallic carrier rod, and under plastic support plate Side is mounted with alloy band iron, and the lower section installation settings of the alloy band iron has hydraulic stem, and the lower section installation of hydraulic stem is solid Surely there is hydraulic cylinder, the described second lower section installation settings for pouring slot has the second metallic carrier rod, the casting platform installation settings It is pouring above desk body, and is pouring and be mounted with sealed container door on the outside of desk body.
Preferably, the cooling trough is symmetrical about casting platform center line, and the outside surrounding of casting platform is adopted With chamfering formula structure, and the width of cooling trough is the half of casting platform width.
Preferably, it described first pours slot and equidistantly distributes on the first formwork for placing, and the setting of the first formwork for placing Quantity is two groups, and is respectively mounted on the outside of the first formwork for placing and the second formwork for placing and is provided with metal carrying handle.
Preferably, the second metal jacking block is connect with the second formwork for placing by alloy limited block, and the second metal roof Block and alloy limited block constitute detaching structure, and the second metal jacking block is to be welded and fixed with the second metallic carrier rod.
Preferably, first metallic carrier rod is to be mutually perpendicular to, and plastic support plate and hydraulic stem are hinged with plastic support plate It is fixed, and hydraulic stem and hydraulic cylinder are stretching structure.
Preferably, the longitudinal section of second metallic carrier rod is to be inverted " C " character form structure, and the second metallic carrier rod is straight Diameter is consistent with the diameter of the first metallic carrier rod.
Compared with prior art, the utility model has the beneficial effects that this is used for tin bar processing pouring device,
1. using cooling trough and metal carrying handle, the first formwork for placing and second of being taken by metal carrying handle pours mould Plate, the time needed for shortening the first formwork for placing and the second formwork for placing bottom coohng, and using cooling trough to casting platform It is rapidly cooled, avoids tin bar is cooling in process of production from consuming the excessive time;
2. using plastic support plate and hydraulic stem, a degree of dynamics is applied to plastic support plate by hydraulic stem, thus Reduce tin bar in process of production, the difficulty that tin bar is removed from the molds reduces tin bar and manufactures consumed cost and labour people The labor intensity of member;
3. the first metallic carrier rod and the second metallic carrier rod are used, by the first metallic carrier rod and the second metallic carrier rod come to not The formwork for placing of same type exerts a force, and tin bar is avoided to fall during being removed from the molds, and promotes different type tin bar Produce the convenience taken out.
Detailed description of the invention
Fig. 1 is the utility model positive structure diagram;
Fig. 2 is that the utility model first pours slot positive structure diagram;
Fig. 3 is that the utility model second pours slot positive structure diagram;
Fig. 4 is the utility model side structure schematic view.
In figure: 1, casting platform;2, cooling trough;3, the first formwork for placing;4, first slot is poured;5, the first metal roof Block;6, metal carrying handle;7, the second formwork for placing;8, second slot is poured;9, the second metal jacking block;10, alloy limited block;11, One metallic carrier rod;12, plastic support plate;13, alloy band iron;14, hydraulic stem;15, hydraulic cylinder;16, the second metallic carrier rod;17, Pour desk body;18, sealed container door.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
Please refer to Fig. 1-4, the utility model provides a kind of technical solution: one kind is for tin bar processing pouring device, packet It includes casting platform 1, cooling trough 2, the first formwork for placing 3, first pour slot 4, the first metal jacking block 5, metal carrying handle 6, second Formwork for placing 7, second pour slot 8, the second metal jacking block 9, alloy limited block 10, the first metallic carrier rod 11, plastic support plate 12, close Golden band iron 13, hydraulic cylinder 15, the second metallic carrier rod 16, pours desk body 17 and sealed container door 18, casting platform 1 at hydraulic stem 14 Outside installation settings have cooling trough 2, and the inside installation settings of cooling trough 2 has the first formwork for placing 3, and first pours mould The inside installation of plate 3 offers first and pours slot 4, and the first inside installation settings for pouring slot 4 has the first metal jacking block 5, gold Belong to the outside that carrying handle 6 is fixed on the second formwork for placing 7, and the inside installation of the second formwork for placing 7 offers second and pours Slot 8, the second metal jacking block 9 are mounted on the second inside for pouring slot 8, and the lower section installation settings of casting platform 1 has alloy limit Position block 10, and the inside installation settings of alloy limited block 10 has the first metallic carrier rod 11, the lower section installation of the first metallic carrier rod 11 It is fixed with plastic support plate 12, and the lower section of plastic support plate 12 is mounted with alloy band iron 13, the lower section installation of alloy band iron 13 It is provided with hydraulic stem 14, and the lower section of hydraulic stem 14 is mounted with hydraulic cylinder 15, second pours the lower section installation settings of slot 8 There is the second metallic carrier rod 16, casting platform 1, which is mounted on, pours 17 top of desk body, and the outside installation for pouring desk body 17 is fixed There is sealed container door 18.
Cooling trough 2 is symmetrical about 1 center line of casting platform, and the outside surrounding of casting platform 1 uses chamfering formula Structure, and the width of cooling trough 2 is the half of 1 width of casting platform, by cooling trough 2 to 1 outside four of casting platform Zhou Jinhang is cooling, promotes efficiency cooling in tin bar casting process.
First, which pours slot 4, equidistantly distributes on the first formwork for placing 3, and the quantity of the first formwork for placing 3 setting is two Group, and be respectively mounted on the outside of the first formwork for placing 3 and the second formwork for placing 7 and be provided with metal carrying handle 6, pass through metal carrying handle of taking 6 come the first formwork for placing 3 and the second formwork for placing 7 progress installing and dismounting, and to the first formwork for placing 3 and the second formwork for placing 7 Bottom is cooled down.
Second metal jacking block 9 is connect with the second formwork for placing 7 by alloy limited block 10, and the second metal jacking block 9 and conjunction Golden limited block 10 constitutes detaching structure, and the second metal jacking block 9 is to be welded and fixed with the second metallic carrier rod 16, passes through second Metal jacking block 9 ejects the tin bar inside the second formwork for placing 7, reduces the difficulty that tin bar ejects inside the second formwork for placing 7.
First metallic carrier rod 11 is to be mutually perpendicular to, and plastic support plate 12 and hydraulic stem 14 are hinged solid with plastic support plate 12 It is fixed, and hydraulic stem 14 and hydraulic cylinder 15 are stretching structure, and hydraulic stem 14 applies plastic support plate 12 with hydraulic cylinder 15 Plus-pressure promotes tin bar convenience derived from the first formwork for placing 3.
The longitudinal section of second metallic carrier rod 16 is to be inverted " C " character form structure, and the diameter of the second metallic carrier rod 16 and the The diameter of one metallic carrier rod 11 is consistent, by the second metallic carrier rod 16 and the first metallic carrier rod 11 to the first formwork for placing 3 and Two pour the tin bar ejection inside slot 8, reduce consumed cost and labor intensity in production process.
Working principle: when being used for tin bar processing pouring device using this, according to Fig. 1, operator will be cooled down Liquid be poured into inside cooling trough 2, then Xi Shui is poured into and first pours slot 4 and second inside the first formwork for placing 3 Second inside formwork for placing 7 pours slot 8, then pours slot 4 for first and second pours slot 8 and transfer out extra heat, And absorbed extra heat by cooling trough 2, according to fig. 2 and shown in Fig. 3, by alloy band iron 13 to plastic support plate 12 and hydraulic stem 14 be fixed, then plastic support plate 12 and the first metallic carrier rod 11 and the second metallic carrier rod 16 are fixed, Hydraulic cylinder 15 adjusts the length of the first metallic carrier rod 11 and the second metallic carrier rod 16 by control pump oil amount, passes through first Metallic carrier rod 11 and the second metallic carrier rod 16 are lifted up plastic support plate 12, plastic support plate 12 drive the first metallic carrier rod 11 and Second metallic carrier rod 16 moves upwards, and is run up using the first metal jacking block 5 and the second metal jacking block 9, passes through the first gold medal Belong to that jacking block 5 and the second metal jacking block 9 pour slot 4 to first and the second tin bar for pouring inside slot 8 ejects, according to Fig. 4 institute Show, operator pours the sealed container door 18 in 17 outside of desk body by opening, and then directly dismantles alloy limited block 10, operates Personnel are directly taken out the first formwork for placing 3 or the second formwork for placing 7 by metal carrying handle 6 of taking on the outside of casting platform 1, So as to shorten the time needed for 7 bottom coohng of the first formwork for placing 3 or the second formwork for placing.
Although the utility model is described in detail with reference to the foregoing embodiments, come for those skilled in the art Say, it is still possible to modify the technical solutions described in the foregoing embodiments, or to part of technical characteristic into Row equivalent replacement, within the spirit and principle of the utility model, any modification, equivalent replacement, improvement and so on should all It is included within the scope of protection of this utility model.

Claims (6)

1. one kind is for tin bar processing pouring device, including casting platform (1), metal carrying handle (6) and the second metal jacking block (9), it is characterised in that: the outside installation settings of the casting platform (1) has cooling trough (2), and the inside of cooling trough (2) Installation settings has the first formwork for placing (3), and the inside installation of first formwork for placing (3) offers first and pours slot (4), and The first inside installation settings for pouring slot (4) has the first metal jacking block (5), and the metal carrying handle (6) is fixed on second and pours The outside of building mould (7), and the inside installation of the second formwork for placing (7) offers second and pours slot (8), second metal roof Block (9) is mounted on the second inside for pouring slot (8), and the lower section installation settings of the casting platform (1) has alloy limited block (10), and the inside installation settings of alloy limited block (10) has the first metallic carrier rod (11), first metallic carrier rod (11) Lower section is mounted with plastic support plate (12), and alloy band iron (13), the conjunction are mounted with below plastic support plate (12) The lower section installation settings of golden band iron (13) has hydraulic stem (14), and is mounted with hydraulic cylinder below hydraulic stem (14) (15), the described second lower section installation settings for pouring slot (8) has the second metallic carrier rod (16), and casting platform (1) installation is set It sets and is pouring above desk body (17), and pour and be mounted with sealed container door (18) on the outside of desk body (17).
2. according to claim 1 a kind of for tin bar processing pouring device, it is characterised in that: the cooling trough (2) symmetrical about casting platform (1) center line, and the outside surrounding of casting platform (1) uses chamfering formula structure, and cold But the width of sink (2) is the half of casting platform (1) width.
3. according to claim 1 a kind of for tin bar processing pouring device, it is characterised in that: described first pours slot (4) it equidistantly distributes on the first formwork for placing (3), and the quantity of the first formwork for placing (3) setting is two groups, and first pours It is respectively mounted on the outside of building mould (3) and the second formwork for placing (7) and is provided with metal carrying handle (6).
4. according to claim 1 a kind of for tin bar processing pouring device, it is characterised in that: second metal roof Block (9) is connect with the second formwork for placing (7) by alloy limited block (10), and the second metal jacking block (9) and alloy limited block (10) detaching structure is constituted, and the second metal jacking block (9) is to be welded and fixed with the second metallic carrier rod (16).
5. according to claim 1 a kind of for tin bar processing pouring device, it is characterised in that: first metal roof Bar (11) is to be mutually perpendicular to, and plastic support plate (12) and hydraulic stem (14) are hinged fixed and hydraulic with plastic support plate (12) Bar (14) and hydraulic cylinder (15) are stretching structure.
6. according to claim 1 a kind of for tin bar processing pouring device, it is characterised in that: second metal roof The longitudinal section of bar (16) is to be inverted " C " character form structure, and the diameter of the second metallic carrier rod (16) and the first metallic carrier rod (11) Diameter it is consistent.
CN201821657170.7U 2018-10-12 2018-10-12 One kind using pouring device for tin bar processing Expired - Fee Related CN209094525U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821657170.7U CN209094525U (en) 2018-10-12 2018-10-12 One kind using pouring device for tin bar processing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821657170.7U CN209094525U (en) 2018-10-12 2018-10-12 One kind using pouring device for tin bar processing

Publications (1)

Publication Number Publication Date
CN209094525U true CN209094525U (en) 2019-07-12

Family

ID=67154963

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821657170.7U Expired - Fee Related CN209094525U (en) 2018-10-12 2018-10-12 One kind using pouring device for tin bar processing

Country Status (1)

Country Link
CN (1) CN209094525U (en)

Similar Documents

Publication Publication Date Title
CN201922002U (en) Lead-antimony alloy ingot casting unit
CN105522141A (en) Piston gravity casting machine
CN209094525U (en) One kind using pouring device for tin bar processing
CN103691963A (en) Device and method for manufacturing electroplating anode copper ball
CN209223158U (en) A kind of anode copper sheet production and processing system
CN208390948U (en) A kind of casting die with replaceable transition chute
CN208357774U (en) A kind of automation low pressure casting wheel hub process units
CN206256105U (en) A kind of vertical quenching frock of big gauge modules
CN201320594Y (en) Cast iron mold used for casting cast iron ingot
CN205887992U (en) Easy demoulding's chain transmission type alloy pig mould
CN205043101U (en) Quick cooling device of aluminium ingot
CN205008546U (en) Prepare casting device of high -quality aluminum alloy ingot casting in succession
CN101987355A (en) Aluminium liquid casting device
CN206839144U (en) Casting machine
CN208825826U (en) A kind of aluminium ingot mark laser print apparatus
CN210418163U (en) Transmission device on aluminum ingot production line
CN205684662U (en) A kind of hydraulic part liquid foundry work dress
CN109513887B (en) Treatment method suitable for conventional ingot type steel ingot for ultrahigh-temperature soft core forging
CN201493465U (en) Metallurgy solution continuous pouring molding device
CN112743051A (en) Continuous casting machine for casting and molding ferroalloy production
CN206936321U (en) A kind of combining structure of metal liquid die forging
CN206405424U (en) A kind of casting ladle for being capable of current limliting
CN105108165B (en) The process of splitting type iron alloy grain casting machine and ferroalloy production casting grain
CN204939581U (en) A kind of opposite opened esr wide plate billet crystallizer
CN110170624A (en) A kind of steel pawl crystallizer and its manufacturing method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190712

Termination date: 20191012

CF01 Termination of patent right due to non-payment of annual fee