CN209082839U - A kind of breathing exhaust roofing - Google Patents
A kind of breathing exhaust roofing Download PDFInfo
- Publication number
- CN209082839U CN209082839U CN201821741065.1U CN201821741065U CN209082839U CN 209082839 U CN209082839 U CN 209082839U CN 201821741065 U CN201821741065 U CN 201821741065U CN 209082839 U CN209082839 U CN 209082839U
- Authority
- CN
- China
- Prior art keywords
- exhaust passage
- exhaust
- gas vent
- insulating layer
- coat
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Roof Covering Using Slabs Or Stiff Sheets (AREA)
Abstract
The utility model relates to a kind of breathing exhaust building roofs, including screed-coat, insulating layer, gas vent, exhaust passage and thermal insulation material, the screed-coat is arranged after roof structure is constructed, and sealing compound is filled in the partitioning slot of screed-coat, and insulating layer is arranged on screed-coat;Exhaust passage is arranged in insulating layer, and exhaust passage includes longitudinal exhaust passage and lateral exhaust passage, and the bottom of exhaust passage is equipped with thermal insulation material, and slope standard is looked for as insulating layer in the top of the exhaust passage;Gas vent is arranged in the crosspoint of longitudinal exhaust passage and lateral exhaust passage and is arranged vertically upwards, and the aperture of gas vent is greater than the width of exhaust passage.With such a structure, roofing exhaust is combined with roof waterproof, by carrying out exhaust structure in advance, processing exhaust roofing thin portion measure, do not have to be completely dried that after thermal insulation construction, construction of waterproof layer can be carried out, saves construction period, the heat insulation house surface suitable for building engineering.
Description
Technical field
The utility model relates to building field more particularly to a kind of breathing exhaust roofings.
Background technique
Roofing is the important component part of building engineering, waterproof construction quality direct relation roof waterproof effect,
And the project whole duration is directly affected.Currently, roof waterproof difficult point is that insulating layer moisture can effectively be discharged, out
Now leakage is that roofing moisture enters heat preservation or insulating layer moisture is not discharged and is not easy to judge.Roof waterproof dismounting etc. is increased
Difficulty of construction, and extend the project under construction whole duration.
Utility model content
To solve existing technical problem, the utility model provides a kind of breathing exhaust building roof.
The utility model particular content is as follows: a kind of breathing exhaust building roof, including screed-coat, insulating layer, exhaust
Hole, exhaust passage and thermal insulation material, the screed-coat are arranged after roof structure is constructed, are filled in the partitioning slot of screed-coat
Sealing compound, insulating layer are arranged on screed-coat;Exhaust passage is arranged in insulating layer, exhaust passage include longitudinal exhaust passage and
Lateral exhaust passage, the bottom of exhaust passage are equipped with thermal insulation material, and slope is looked for as insulating layer in the top of the exhaust passage
Standard;Gas vent is arranged in the crosspoint of longitudinal exhaust passage and lateral exhaust passage and is arranged vertically upwards, the hole of gas vent
Diameter is greater than the width of exhaust passage.Practice of construction process is as follows: after roof structure has been constructed, first doing one layer of screed-coat, screed-coat
Partitioning slot is tamped with sealing compound, and insulating layer moisture is effectively prevent to enter the room, and exhaust passage lower part guarantee for a person given by a shopkeeper's adiabator does not generate cold
Bridge, exhaust passage top is as insulation to falls standard;After screed-coat is dry, according to roofing plane distribution, exhaust hole location is determined
It sets, then carries out the construction of the exhaust outlet of latter step.
Further, the part that the gas vent exposes at the top of roofing is surrounded by supporting layer and rigid layer, the supporting layer packet
The vertical portion being tightly attached on the outside of gas vent and the horizontal part positioned at vertical portion top are included, the outer of supporting layer is arranged in the rigid layer
Side, rigid layer include the horizontal segment for being laid in roof and the vertical section being arranged on the outside of gas vent vertical portion, horizontal segment and vertical
It is connected between degree by slope, vertical section is long less than the projection on the horizontal part of supporting layer and slope in the projected length of horizontal plane
Degree.
Further, the material of the insulating layer includes cement and expanded vermiculite, pitch expanded perlite, cement clinker, mine
One of cotton and rock wool are a variety of.
Further, the exhaust passage is connected to form using porous brick or building-block hole hole, two adjacent exhausts
The distance between hole is 6m, every 36m2One gas vent is set.
Further, when gas vent and flue, toilet exhaust passage conflict, flue, toilet exhaust passage replace exhaust
Hole.
The utility model has the beneficial effects that with such a structure, roofing exhaust being combined with roof waterproof, is passed through
Exhaust structure is carried out in advance, and processing exhaust roofing thin portion measure does not have to be completely dried that waterproof layer can be carried out after thermal insulation construction
Construction period, the heat insulation house surface suitable for building engineering are saved in construction.
Detailed description of the invention
Specific embodiment of the present utility model is furtherd elucidate with reference to the accompanying drawing.
Fig. 1 is the schematic diagram 1 of the breathing exhaust building roof of the utility model;
Fig. 2 is the schematic diagram 2 of the breathing exhaust building roof of the utility model.
Specific embodiment
In conjunction with Fig. 1-Fig. 2, a kind of breathing exhaust building roof of the utility model, including screed-coat 1, insulating layer, row
Stomata 3, exhaust passage 4 and thermal insulation material 5, screed-coat 1 is arranged after roof structure is constructed, in the partitioning slot of screed-coat 1
It is filled with sealing compound 2, insulating layer is arranged on screed-coat 1;Exhaust passage 4 is arranged in insulating layer, and exhaust passage 4 includes longitudinal row
Gas channel 4 and lateral exhaust passage 4, the bottom of exhaust passage 4 are equipped with thermal insulation material 5, and the top of exhaust passage 4 is as heat preservation
Layer looks for slope standard;Gas vent 3 is arranged in the crosspoint of longitudinal exhaust passage 4 and lateral exhaust passage 4 and is arranged vertically upwards,
The aperture of gas vent 3 is greater than the width of exhaust passage 4.Practice of construction process is as follows: after roof structure has been constructed, first doing one layer and looks for
Leveling 1,1 partitioning slot sealing compound 2 of screed-coat are tamped, and effectively prevent insulating layer moisture to enter the room, exhaust passage lower part guarantee for a person given by a shopkeeper
Adiabator 5 does not generate cold bridge, and exhaust passage top is as insulation to falls standard;After screed-coat 1 is dry, according to roofing plane point
Cloth determines 3 position of gas vent, then carries out the construction of the exhaust outlet of latter step.
The present embodiment is preferred, and the part that gas vent 3 exposes at the top of roofing is surrounded by supporting layer 6 and rigid layer 7, supporting layer 6
Supporting layer 6 is arranged in horizontal part including being tightly attached to the vertical portion in 3 outside of gas vent and positioned at vertical portion top, rigid layer 7
Outside, rigid layer 7 include be laid in roof horizontal segment and the vertical section being arranged on the outside of 3 vertical portion of gas vent, horizontal segment with
It is connected between vertical degree by slope, vertical section is less than the horizontal part of supporting layer 6 and the throwing on slope in the projected length of horizontal plane
Shadow length.
The present embodiment is preferred, the material of insulating layer include cement and expanded vermiculite, pitch expanded perlite, cement clinker,
One of mineral wool and rock wool are a variety of.
The present embodiment is preferred, and exhaust passage 4 is connected to form using porous brick or building-block hole hole, two adjacent rows
The distance between stomata 3 is 6m, every 36m2One gas vent 3 is set.
The present embodiment is preferred, when gas vent 3 and flue, toilet exhaust passage conflict, flue, toilet exhaust passage generation
For gas vent 3.
Elaborate many details in the above description in order to fully understand the utility model.But above description
It is only the preferred embodiment of the utility model, the utility model can be come with being much different from other way described herein
Implement, therefore the utility model is not limited by specific implementation disclosed above.Any those skilled in the art exist simultaneously
It does not depart under technical solutions of the utility model ambit, it is all practical new to this using the methods and technical content of the disclosure above
Type technical solution makes many possible changes and modifications or equivalent example modified to equivalent change.It is all without departing from this
The content of utility model technical solution any is simply repaired according to the technical essence of the utility model is made to the above embodiment
Change, equivalent variations and modification, in the range of still falling within technical solutions of the utility model protection.
Claims (5)
1. a kind of breathing exhaust building roof, it is characterised in that: including screed-coat, insulating layer, gas vent, exhaust passage and guarantor
Adiabator, the screed-coat are arranged after roof structure is constructed, and sealing compound are filled in the partitioning slot of screed-coat, insulating layer is set
It sets on screed-coat;Exhaust passage is arranged in insulating layer, and exhaust passage includes longitudinal exhaust passage and lateral exhaust passage, row
The bottom in gas channel is equipped with thermal insulation material, and slope standard is looked for as insulating layer in the top of the exhaust passage;Gas vent setting
It in the crosspoint of longitudinal exhaust passage and lateral exhaust passage and is arranged vertically upwards, the aperture of gas vent is greater than exhaust passage
Width.
2. breathing exhaust building roof according to claim 1, it is characterised in that: the gas vent exposes at the top of roofing
Part be surrounded by supporting layer and rigid layer, the supporting layer includes the vertical portion being tightly attached on the outside of gas vent and is located at vertical portion and pushes up
The outside of supporting layer is arranged in the horizontal part at end, the rigid layer, and rigid layer includes that the horizontal segment for being laid in roof and setting exist
Vertical section on the outside of gas vent vertical portion is connected between horizontal segment and vertical degree by slope, projection of the vertical section in horizontal plane
Length is less than the horizontal part of supporting layer and the projected length on slope.
3. breathing exhaust building roof according to claim 1, it is characterised in that: the material of the insulating layer includes water
One of mud expanded vermiculite, pitch expanded perlite, cement clinker, mineral wool and rock wool are a variety of.
4. breathing exhaust building roof according to claim 1, it is characterised in that: the exhaust passage uses porous brick
Or building-block hole hole is connected to form, the distance between two adjacent gas vents are 6m, every 36m2One gas vent is set.
5. breathing exhaust building roof according to claim 1, it is characterised in that: when gas vent and flue, toilet
When exhaust duct conflicts, flue, toilet exhaust passage replace gas vent.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821741065.1U CN209082839U (en) | 2018-10-25 | 2018-10-25 | A kind of breathing exhaust roofing |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821741065.1U CN209082839U (en) | 2018-10-25 | 2018-10-25 | A kind of breathing exhaust roofing |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209082839U true CN209082839U (en) | 2019-07-09 |
Family
ID=67120949
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821741065.1U Expired - Fee Related CN209082839U (en) | 2018-10-25 | 2018-10-25 | A kind of breathing exhaust roofing |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209082839U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113982203A (en) * | 2021-11-25 | 2022-01-28 | 中国三冶集团有限公司 | Light concrete roof exhaust passage prefabricated member and laying method thereof |
-
2018
- 2018-10-25 CN CN201821741065.1U patent/CN209082839U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113982203A (en) * | 2021-11-25 | 2022-01-28 | 中国三冶集团有限公司 | Light concrete roof exhaust passage prefabricated member and laying method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN211258650U (en) | Wall-separating type lining insulation structure | |
CN107965097B (en) | A kind of roof insulation system and its construction using foam glass board | |
CN106320616B (en) | A kind of insulation roofing exhaust pipe road system and construction method | |
CN201695586U (en) | Thermal insulation roofing exhaust pipe | |
CN209082839U (en) | A kind of breathing exhaust roofing | |
CN104499658A (en) | Active breathing type damp-proof and steam-exhausting inverted roof system and construction method thereof | |
CN107905388A (en) | A kind of waterproof method of precast concrete exterior wall cladding | |
CN102900204A (en) | Construction method of permeable roof system and permeable roof system as well as special construction member | |
CN214941771U (en) | Exhaust structure of heat-preservation impervious roof | |
CN209397798U (en) | A kind of compound water-proof thermal-insulation curtain wall | |
CN207419873U (en) | A kind of simulation thatch roof | |
CN205476141U (en) | Exhaust and antiseep structure of heat preservation roofing | |
CN210164152U (en) | Green energy-saving roof structure | |
CN209194598U (en) | A kind of Urban Underground parking space external wall anti-condensation device | |
CN208803643U (en) | A kind of double heat insulation house surface gland steam exhauster waterproofing node structures of double waterproofs | |
CN213509266U (en) | Roof slope layer finding exhaust structure | |
CN212201049U (en) | Roof parapet inlet for stom water cold bridge prevention structure | |
CN210887886U (en) | Dry construction hollow ceramic brick wall | |
CN207032707U (en) | A kind of exhaust apparatus for heat insulation house surface | |
CN108612264B (en) | Anti-condensation roof structure and method | |
CN207277713U (en) | Roof waterproof structure | |
CN207847187U (en) | Air film heat-insulating and energy-saving computer room | |
CN217150965U (en) | Archaizing cornice structure | |
CN207484858U (en) | A kind of roofing antiseep exhaust duct and exhaust pipe device | |
CN205259489U (en) | Building roof heat preservation exhaust steam system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190709 Termination date: 20191025 |
|
CF01 | Termination of patent right due to non-payment of annual fee |