Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821741065.1U
Other languages
Chinese (zh)
Inventor
张春雷
严云德
俞芳应
黄金超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU XIANGSEN CONSTRUCTION ENGINEERING Co Ltd
Original Assignee
JIANGSU XIANGSEN CONSTRUCTION ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU XIANGSEN CONSTRUCTION ENGINEERING Co Ltd filed Critical JIANGSU XIANGSEN CONSTRUCTION ENGINEERING Co Ltd
Priority to CN201821741065.1U priority Critical patent/CN209082839U/en
Application granted granted Critical
Publication of CN209082839U publication Critical patent/CN209082839U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Roof Covering Using Slabs Or Stiff Sheets (AREA)

Abstract

The utility model relates to a kind of breathing exhaust building roofs, including screed-coat, insulating layer, gas vent, exhaust passage and thermal insulation material, the screed-coat is arranged after roof structure is constructed, and sealing compound is filled in the partitioning slot of screed-coat, and insulating layer is arranged on screed-coat;Exhaust passage is arranged in insulating layer, and exhaust passage includes longitudinal exhaust passage and lateral exhaust passage, and the bottom of exhaust passage is equipped with thermal insulation material, and slope standard is looked for as insulating layer in the top of the exhaust passage;Gas vent is arranged in the crosspoint of longitudinal exhaust passage and lateral exhaust passage and is arranged vertically upwards, and the aperture of gas vent is greater than the width of exhaust passage.With such a structure, roofing exhaust is combined with roof waterproof, by carrying out exhaust structure in advance, processing exhaust roofing thin portion measure, do not have to be completely dried that after thermal insulation construction, construction of waterproof layer can be carried out, saves construction period, the heat insulation house surface suitable for building engineering.

Description

A kind of breathing exhaust roofing
Technical field
The utility model relates to building field more particularly to a kind of breathing exhaust roofings.
Background technique
Roofing is the important component part of building engineering, waterproof construction quality direct relation roof waterproof effect, And the project whole duration is directly affected.Currently, roof waterproof difficult point is that insulating layer moisture can effectively be discharged, out Now leakage is that roofing moisture enters heat preservation or insulating layer moisture is not discharged and is not easy to judge.Roof waterproof dismounting etc. is increased Difficulty of construction, and extend the project under construction whole duration.
Utility model content
To solve existing technical problem, the utility model provides a kind of breathing exhaust building roof.
The utility model particular content is as follows: a kind of breathing exhaust building roof, including screed-coat, insulating layer, exhaust Hole, exhaust passage and thermal insulation material, the screed-coat are arranged after roof structure is constructed, are filled in the partitioning slot of screed-coat Sealing compound, insulating layer are arranged on screed-coat;Exhaust passage is arranged in insulating layer, exhaust passage include longitudinal exhaust passage and Lateral exhaust passage, the bottom of exhaust passage are equipped with thermal insulation material, and slope is looked for as insulating layer in the top of the exhaust passage Standard;Gas vent is arranged in the crosspoint of longitudinal exhaust passage and lateral exhaust passage and is arranged vertically upwards, the hole of gas vent Diameter is greater than the width of exhaust passage.Practice of construction process is as follows: after roof structure has been constructed, first doing one layer of screed-coat, screed-coat Partitioning slot is tamped with sealing compound, and insulating layer moisture is effectively prevent to enter the room, and exhaust passage lower part guarantee for a person given by a shopkeeper's adiabator does not generate cold Bridge, exhaust passage top is as insulation to falls standard;After screed-coat is dry, according to roofing plane distribution, exhaust hole location is determined It sets, then carries out the construction of the exhaust outlet of latter step.
Further, the part that the gas vent exposes at the top of roofing is surrounded by supporting layer and rigid layer, the supporting layer packet The vertical portion being tightly attached on the outside of gas vent and the horizontal part positioned at vertical portion top are included, the outer of supporting layer is arranged in the rigid layer Side, rigid layer include the horizontal segment for being laid in roof and the vertical section being arranged on the outside of gas vent vertical portion, horizontal segment and vertical It is connected between degree by slope, vertical section is long less than the projection on the horizontal part of supporting layer and slope in the projected length of horizontal plane Degree.
Further, the material of the insulating layer includes cement and expanded vermiculite, pitch expanded perlite, cement clinker, mine One of cotton and rock wool are a variety of.
Further, the exhaust passage is connected to form using porous brick or building-block hole hole, two adjacent exhausts The distance between hole is 6m, every 36m2One gas vent is set.
Further, when gas vent and flue, toilet exhaust passage conflict, flue, toilet exhaust passage replace exhaust Hole.
The utility model has the beneficial effects that with such a structure, roofing exhaust being combined with roof waterproof, is passed through Exhaust structure is carried out in advance, and processing exhaust roofing thin portion measure does not have to be completely dried that waterproof layer can be carried out after thermal insulation construction Construction period, the heat insulation house surface suitable for building engineering are saved in construction.
Detailed description of the invention
Specific embodiment of the present utility model is furtherd elucidate with reference to the accompanying drawing.
Fig. 1 is the schematic diagram 1 of the breathing exhaust building roof of the utility model;
Fig. 2 is the schematic diagram 2 of the breathing exhaust building roof of the utility model.
Specific embodiment
In conjunction with Fig. 1-Fig. 2, a kind of breathing exhaust building roof of the utility model, including screed-coat 1, insulating layer, row Stomata 3, exhaust passage 4 and thermal insulation material 5, screed-coat 1 is arranged after roof structure is constructed, in the partitioning slot of screed-coat 1 It is filled with sealing compound 2, insulating layer is arranged on screed-coat 1;Exhaust passage 4 is arranged in insulating layer, and exhaust passage 4 includes longitudinal row Gas channel 4 and lateral exhaust passage 4, the bottom of exhaust passage 4 are equipped with thermal insulation material 5, and the top of exhaust passage 4 is as heat preservation Layer looks for slope standard;Gas vent 3 is arranged in the crosspoint of longitudinal exhaust passage 4 and lateral exhaust passage 4 and is arranged vertically upwards, The aperture of gas vent 3 is greater than the width of exhaust passage 4.Practice of construction process is as follows: after roof structure has been constructed, first doing one layer and looks for Leveling 1,1 partitioning slot sealing compound 2 of screed-coat are tamped, and effectively prevent insulating layer moisture to enter the room, exhaust passage lower part guarantee for a person given by a shopkeeper Adiabator 5 does not generate cold bridge, and exhaust passage top is as insulation to falls standard;After screed-coat 1 is dry, according to roofing plane point Cloth determines 3 position of gas vent, then carries out the construction of the exhaust outlet of latter step.
The present embodiment is preferred, and the part that gas vent 3 exposes at the top of roofing is surrounded by supporting layer 6 and rigid layer 7, supporting layer 6 Supporting layer 6 is arranged in horizontal part including being tightly attached to the vertical portion in 3 outside of gas vent and positioned at vertical portion top, rigid layer 7 Outside, rigid layer 7 include be laid in roof horizontal segment and the vertical section being arranged on the outside of 3 vertical portion of gas vent, horizontal segment with It is connected between vertical degree by slope, vertical section is less than the horizontal part of supporting layer 6 and the throwing on slope in the projected length of horizontal plane Shadow length.
The present embodiment is preferred, the material of insulating layer include cement and expanded vermiculite, pitch expanded perlite, cement clinker, One of mineral wool and rock wool are a variety of.
The present embodiment is preferred, and exhaust passage 4 is connected to form using porous brick or building-block hole hole, two adjacent rows The distance between stomata 3 is 6m, every 36m2One gas vent 3 is set.
The present embodiment is preferred, when gas vent 3 and flue, toilet exhaust passage conflict, flue, toilet exhaust passage generation For gas vent 3.
Elaborate many details in the above description in order to fully understand the utility model.But above description It is only the preferred embodiment of the utility model, the utility model can be come with being much different from other way described herein Implement, therefore the utility model is not limited by specific implementation disclosed above.Any those skilled in the art exist simultaneously It does not depart under technical solutions of the utility model ambit, it is all practical new to this using the methods and technical content of the disclosure above Type technical solution makes many possible changes and modifications or equivalent example modified to equivalent change.It is all without departing from this The content of utility model technical solution any is simply repaired according to the technical essence of the utility model is made to the above embodiment Change, equivalent variations and modification, in the range of still falling within technical solutions of the utility model protection.

Claims (5)

1. a kind of breathing exhaust building roof, it is characterised in that: including screed-coat, insulating layer, gas vent, exhaust passage and guarantor Adiabator, the screed-coat are arranged after roof structure is constructed, and sealing compound are filled in the partitioning slot of screed-coat, insulating layer is set It sets on screed-coat;Exhaust passage is arranged in insulating layer, and exhaust passage includes longitudinal exhaust passage and lateral exhaust passage, row The bottom in gas channel is equipped with thermal insulation material, and slope standard is looked for as insulating layer in the top of the exhaust passage;Gas vent setting It in the crosspoint of longitudinal exhaust passage and lateral exhaust passage and is arranged vertically upwards, the aperture of gas vent is greater than exhaust passage Width.
2. breathing exhaust building roof according to claim 1, it is characterised in that: the gas vent exposes at the top of roofing Part be surrounded by supporting layer and rigid layer, the supporting layer includes the vertical portion being tightly attached on the outside of gas vent and is located at vertical portion and pushes up The outside of supporting layer is arranged in the horizontal part at end, the rigid layer, and rigid layer includes that the horizontal segment for being laid in roof and setting exist Vertical section on the outside of gas vent vertical portion is connected between horizontal segment and vertical degree by slope, projection of the vertical section in horizontal plane Length is less than the horizontal part of supporting layer and the projected length on slope.
3. breathing exhaust building roof according to claim 1, it is characterised in that: the material of the insulating layer includes water One of mud expanded vermiculite, pitch expanded perlite, cement clinker, mineral wool and rock wool are a variety of.
4. breathing exhaust building roof according to claim 1, it is characterised in that: the exhaust passage uses porous brick Or building-block hole hole is connected to form, the distance between two adjacent gas vents are 6m, every 36m2One gas vent is set.
5. breathing exhaust building roof according to claim 1, it is characterised in that: when gas vent and flue, toilet When exhaust duct conflicts, flue, toilet exhaust passage replace gas vent.
CN201821741065.1U 2018-10-25 2018-10-25 A kind of breathing exhaust roofing Expired - Fee Related CN209082839U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821741065.1U CN209082839U (en) 2018-10-25 2018-10-25 A kind of breathing exhaust roofing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821741065.1U CN209082839U (en) 2018-10-25 2018-10-25 A kind of breathing exhaust roofing

Publications (1)

Publication Number Publication Date
CN209082839U true CN209082839U (en) 2019-07-09

Family

ID=67120949

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821741065.1U Expired - Fee Related CN209082839U (en) 2018-10-25 2018-10-25 A kind of breathing exhaust roofing

Country Status (1)

Country Link
CN (1) CN209082839U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113982203A (en) * 2021-11-25 2022-01-28 中国三冶集团有限公司 Light concrete roof exhaust passage prefabricated member and laying method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113982203A (en) * 2021-11-25 2022-01-28 中国三冶集团有限公司 Light concrete roof exhaust passage prefabricated member and laying method thereof

Similar Documents

Publication Publication Date Title
CN211258650U (en) Wall-separating type lining insulation structure
CN107965097B (en) A kind of roof insulation system and its construction using foam glass board
CN106320616B (en) A kind of insulation roofing exhaust pipe road system and construction method
CN201695586U (en) Thermal insulation roofing exhaust pipe
CN209082839U (en) A kind of breathing exhaust roofing
CN104499658A (en) Active breathing type damp-proof and steam-exhausting inverted roof system and construction method thereof
CN107905388A (en) A kind of waterproof method of precast concrete exterior wall cladding
CN102900204A (en) Construction method of permeable roof system and permeable roof system as well as special construction member
CN214941771U (en) Exhaust structure of heat-preservation impervious roof
CN209397798U (en) A kind of compound water-proof thermal-insulation curtain wall
CN207419873U (en) A kind of simulation thatch roof
CN205476141U (en) Exhaust and antiseep structure of heat preservation roofing
CN210164152U (en) Green energy-saving roof structure
CN209194598U (en) A kind of Urban Underground parking space external wall anti-condensation device
CN208803643U (en) A kind of double heat insulation house surface gland steam exhauster waterproofing node structures of double waterproofs
CN213509266U (en) Roof slope layer finding exhaust structure
CN212201049U (en) Roof parapet inlet for stom water cold bridge prevention structure
CN210887886U (en) Dry construction hollow ceramic brick wall
CN207032707U (en) A kind of exhaust apparatus for heat insulation house surface
CN108612264B (en) Anti-condensation roof structure and method
CN207277713U (en) Roof waterproof structure
CN207847187U (en) Air film heat-insulating and energy-saving computer room
CN217150965U (en) Archaizing cornice structure
CN207484858U (en) A kind of roofing antiseep exhaust duct and exhaust pipe device
CN205259489U (en) Building roof heat preservation exhaust steam system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190709

Termination date: 20191025

CF01 Termination of patent right due to non-payment of annual fee