CN209066477U CN201821527921.3U CN201821527921U CN209066477U CN 209066477 U CN209066477 U CN 209066477U CN 201821527921 U CN201821527921 U CN 201821527921U CN 209066477 U CN209066477 U CN 209066477U
Authority
CN
China
Prior art keywords
reinforced earth
earth bulkhead
cantilevered reinforced
cantilevered
green
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821527921.3U
Other languages
Chinese (zh)
Inventor
蒋楚生
肖世国
贺钢
李庆海
司文明
齐远
李昭颖
邹川
许颖
曾惜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Eryuan Engineering Group Co Ltd CREEC
Original Assignee
China Railway Eryuan Engineering Group Co Ltd CREEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Eryuan Engineering Group Co Ltd CREEC filed Critical China Railway Eryuan Engineering Group Co Ltd CREEC
Priority to CN201821527921.3U priority Critical patent/CN209066477U/en
Application granted granted Critical
Publication of CN209066477U publication Critical patent/CN209066477U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The multistage assembled cantilevered reinforced earth bulkhead of green effectively reduces the horizontal displacement of wall top to adapt to higher embankment engineering, is conducive to limit subgrade deformation, improves slope stability, and can reach the environment protecting for covering short wall back, green side slope by slope vegetation protection.By step classification setting cantilevered reinforced earth bulkhead on the embankment soil body, cantilevered reinforced earth bulkheads at different levels are formed by armored concrete cantilever retaining wall segment is horizontally-spliced, step is formed between the top of next stage cantilevered reinforced earth bulkhead and the bottom of upper one group of cantilevered reinforced earth bulkhead, between the top and embankment soil body slope surface of most upper formation grade cantilevered reinforced earth bulkhead, plantation green plants forms greenbelt in step;The adjacent two armored concrete cantilever retaining wall segment of cantilevered reinforced earth bulkhead at the same level is formed by connected structure and is connected;Layering setting TGXG formula lacing wire in the embankment soil body, the outer end of each TGXG formula lacing wire is fixedly connected with the armstand of corresponding cantilevered reinforced earth bulkhead.

Description

The multistage assembled cantilevered reinforced earth bulkhead of green
Technical field
The utility model relates to Cantilever Retaining Wall, in particular to one kind is banketed higher, can favorably control subgrade deformation, side slope The assembled cantilevered reinforced earth bulkhead of stable multistage.
Background technique
With the rapid development of national economic development, mountain railway will be more and more with highway engineering.High-fill roadbed exists It is very common in road engineering in a mountainous area construction, in land used limitation strictly or in the lower situation of foundation bearing capacity, Cantilever Retaining Wall (L-type barricade) is a kind of common retaining structure.
Current specifications regulation, traditional cantilever retaining wall height are not preferably greater than 6m.Meanwhile in pressure and the vehicle lotus of banketing Under load effect, horizontal deflection on the top of wall is generally large, especially more significant under dynamic seismic effect, thus roadbed can be caused to generate Relatively large sedimentation and deformation.
Traditional cantilever retaining wall has the disadvantage that: wall height is no more than 6m, it is difficult to be suitable for higher embankment engineering;Wall It is relatively large to push up horizontal displacement, it is unfavorable to roadbed Deformation control under long-term operation state;Cantilever height is larger to cause wall to bear Biggish moment of flexure and shearing;It can only carry out cast-in-place, work progress is relatively complicated;It is difficult to realize the entirety of the roadbed side slope of institute's supporting and retaining system Afforestation effect.
Similar structure has two-stage stack-type Cantilever Retaining Wall, multistage Gravity Retaining Wall and step reinforced earth gear both at home and abroad at present Wall.Two-stage stack-type Cantilever Retaining Wall does not set platform between two-stage wall, is unfavorable for the overall stability of side slope, and be also not easy to Carry out slope vegetation protection.Multistage Gravity Retaining Wall quantity of masonry is larger, and higher to embankment requirement for bearing capacity, can only use cast-in-place side Formula, work progress be not quick.Step reinforced earth bulkhead has the advantages that light-duty shatter-proof, but overall structure resistance capacity to deformation It is relatively weak.
Utility model content
The technical problem to be solved by the utility model is to provide a kind of multistage assembled cantilevered reinforced earth bulkhead of green, with Higher embankment engineering is adapted to, the horizontal displacement of wall top is effectively reduced, is conducive to limit subgrade deformation, improves slope stability, And the environment protecting for covering short wall back, green side slope can be reached by slope vegetation protection.
It is as follows that the utility model solves technical solution used by its technical problem:
The assembled cantilevered reinforced earth bulkhead of multistage green of the utility model, it is characterized in that: pressing step on the embankment soil body Formula classification setting cantilevered reinforced earth bulkhead, cantilevered reinforced earth bulkheads at different levels are by armored concrete cantilever retaining wall segment cross To being spliced, between the top of next stage cantilevered reinforced earth bulkhead and the bottom of upper one group of cantilevered reinforced earth bulkhead, most Step is formed between the top and embankment soil body slope surface of upper formation grade cantilevered reinforced earth bulkhead, plants green plants in step Form greenbelt;The adjacent two armored concrete cantilever retaining wall segment of cantilevered reinforced earth bulkhead at the same level passes through connected structure Form connection;Layering setting TGXG formula lacing wire in the embankment soil body, the outer end of each TGXG formula lacing wire and corresponding cantilever The armstand of formula reinforced earth bulkhead is fixedly connected.
The connected structure is the company being vertically arranged at intervals on the armstand end face of armored concrete cantilever retaining wall segment Connect the reinforcing bar formula connecting pin in hole insertion connecting hole.
The beneficial effects of the utility model are embodied in following several respects:
One, it is adapted to the higher embankment engineering of 8m or more, the moment of flexure and shearing of wall receiving can be effectively reduced;
Two, wall is laid using step, the horizontal displacement of wall top can be effectively reduced, be more advantageous to the change of control roadbed Shape;
Three, platform is set before barricades at different levels, not only facilitates raising slope stability, but also can be on platform upper berths at different levels If vegetation, the environment protecting for covering short wall back, green side slope is reached by slope vegetation protection;
Four, the light-duty sectional of wall body structure is prefabricated, and can be used pin-connected panel construction, autocrane can lifting construction, It is not only lower to ground requirement for bearing capacity, and work progress is quick, reduces the interference to ambient enviroment, and has good anti- Pinking, this is advantage not available for multistage Gravity Retaining Wall.
Detailed description of the invention
This specification includes following four width attached drawing:
Fig. 1 is the cross-section diagram of the assembled cantilevered reinforced earth bulkhead of the multistage green of the utility model;
Fig. 2 is armored concrete cantilever retaining wall section in the assembled cantilevered reinforced earth bulkhead of the multistage green of the utility model The end view drawing of section;
Fig. 3 is armored concrete cantilever retaining wall section in the assembled cantilevered reinforced earth bulkhead of the multistage green of the utility model The end view drawing of section;
Fig. 4 is the partial top view of the assembled cantilevered reinforced earth bulkhead of the multistage green of the utility model.
Component and corresponding label: armored concrete cantilever retaining wall segment 10, armstand 11, toe of wall plate are shown in figure 12, wall heel slab 13, tenon 14, wall top 15, connecting hole 16, reinforcing bar formula connecting pin 17, the embankment soil body 20, TGXG formula lacing wire 21, step 22, water proof clay layer 23, concrete precast block 24, greenbelt 25.
Specific embodiment
The present invention will be further described with reference to the accompanying drawings and examples.
Referring to Fig.1, the assembled cantilevered reinforced earth bulkhead of multistage green of the utility model, presses step on the embankment soil body 20 Formula classification setting cantilevered reinforced earth bulkhead, cantilevered reinforced earth bulkheads at different levels are by armored concrete cantilever retaining wall segment 10 It is horizontally-spliced to form, between the top of next stage cantilevered reinforced earth bulkhead and the bottom of upper one group of cantilevered reinforced earth bulkhead, Most upper one forms formation step 22 between 20 slope surface of top and the embankment soil body of grade cantilevered reinforced earth bulkhead, plantation in step 22 Green plants forms greenbelt 25.The adjacent two armored concrete cantilever retaining wall segment 10 of cantilevered reinforced earth bulkhead at the same level It is formed and is connected by connected structure.Layering setting TGXG formula lacing wire 21, each TGXG formula lacing wire 21 in the embankment soil body 20 Outer end be fixedly connected with the armstand 11 of corresponding cantilevered reinforced earth bulkhead.
Referring to Fig. 2,10 one-piece casting of armored concrete cantilever retaining wall segment forms armstand 11,12 and of toe of wall plate Wall heel slab 13.It referring to Figure 1 and Figure 3, can be in armored concrete cantilevered earth-retaining for the cantilevered reinforced earth bulkhead of most next stage Tenon 14 is set on wall segment 10, i.e., downwardly convex tenon 14 is being set close to 11 side of armstand on the bottom surface of wall heel slab 13.And The above cantilevered reinforced earth bulkheads at different levels do not set tenon 14 generally.The height of every level-one cantilevered reinforced earth bulkhead (push up by armstand 11 Face is to toe of wall plate 12,13 bottom surface of wall heel slab) it is generally 2-2.2m.
Referring to Fig. 2 and Fig. 3, the connected structure is vertically to be arranged at intervals on armored concrete cantilever retaining wall segment 10 The reinforcing bar formula connecting pin 17 in connecting hole 16 and insertion connecting hole 16 on 11 end face of armstand.
Referring to Fig. 3, the step 22 be located at next stage cantilevered reinforced earth bulkhead 11 back side of armstand and upper one group of cantilever Between 12 front end face of toe of wall plate of formula reinforced earth bulkhead.Referring to Fig.1, water proof clay layer 23, platform is arranged in the bottom of the step 22 The laterally spaced insertion concrete precast block 24 in 22 top of rank, concrete precast block 24 and neighbouring two-stage cantilevered reinforced earth Barricade is connected, in backfilling planting soil in step 22 between adjacent concrete prefabricated section 24.
Referring to Fig.1, the TGXG formula being arranged in the cantilevered reinforced earth bulkhead wall behind embankment soil body at different levels 20 is drawn Muscle 21 is two layers or three layers, to limit horizontal deflection on the top of wall and improve the overall stability of road structure.
The assembled cantilevered reinforced earth bulkhead of the multistage green of the utility model is a kind of Novel retaining wall structure, and total is not Only it is adapted to higher embankment engineering, moreover it is possible to effectively reduce the moment of flexure and shearing of wall receiving;Wall is laid using step, The horizontal displacement that wall top can be effectively reduced is more advantageous to the deformation of control roadbed;The lacing wire of TGXG formula is set in upper wall body, Horizontal deflection on the top of wall can effectively be limited and improve the overall stability of roadbed;Platform is set between neighbouring two-stage barricade, is laid with Greenbelt not only facilitates and improves roadbed side slope stability, but also can be reached by greenbelt vegetation covering short wall back, Afforest the environment protecting of roadbed side slope.
Some originals of the assembled cantilevered reinforced earth bulkhead of the multistage green of the utility model that only explains through diagrams described above Reason is not intended to shown in being confined to the utility model and in the specific structure and the scope of application, therefore all possibility The corresponding modification being utilized and equivalent, belong to the applied the scope of the patents of the utility model.

Claims (7)

1. the multistage assembled cantilevered reinforced earth bulkhead of green, it is characterized in that: by step classification setting on the embankment soil body (20) Cantilevered reinforced earth bulkhead, cantilevered reinforced earth bulkheads at different levels are horizontally-spliced by armored concrete cantilever retaining wall segment (10) It forms, between the top of next stage cantilevered reinforced earth bulkhead and the bottom of upper one group of cantilevered reinforced earth bulkhead, a most upper shape Step (22) are formed between the top and the embankment soil body (20) slope surface of grade cantilevered reinforced earth bulkhead, plantation is green in step (22) Color plant forms greenbelt (25);The adjacent two armored concrete cantilever retaining wall segment of cantilevered reinforced earth bulkhead at the same level (10) it is formed and is connected by connected structure;The layering setting lacing wire of TGXG formula (21), each TGXG in the embankment soil body (20) The outer end of formula lacing wire (21) is fixedly connected with the armstand (11) of corresponding cantilevered reinforced earth bulkhead.
2. the assembled cantilevered reinforced earth bulkhead of multistage green as described in claim 1, it is characterized in that: the armored concrete is outstanding Arm-type retaining wall segment (10) one-piece casting forms armstand (11), toe of wall plate (12) and wall heel slab (13).
3. the assembled cantilevered reinforced earth bulkhead of multistage green as claimed in claim 2, it is characterized in that: the wall heel slab (13) Downwardly convex tenon (14) are being set close to armstand (11) side on bottom surface.
4. the assembled cantilevered reinforced earth bulkhead of multistage green as claimed in claim 2 or claim 3, it is characterized in that: the connected structure For the connecting hole (16) being vertically arranged at intervals on armored concrete cantilever retaining wall segment (10) armstand (11) end face and insert Enter the reinforcing bar formula connecting pin (17) in connecting hole (16).
5. the assembled cantilevered reinforced earth bulkhead of multistage green as described in claim 1, it is characterized in that: the step (22) is located at Toe of wall plate (12) front end at armstand (11) back side of next stage cantilevered reinforced earth bulkhead and upper one group of cantilevered reinforced earth bulkhead Between face.
6. the assembled cantilevered reinforced earth bulkhead of multistage green as claimed in claim 5, it is characterized in that: the bottom of the step (22) Water proof clay layer (23) are arranged in portion, the laterally spaced insertion concrete precast block (24) in step (22) top, concrete precast block (24) it is connected with neighbouring two-stage cantilevered reinforced earth bulkhead, between adjacent concrete prefabricated section (24) in step (22) Backfill planting soil.
7. the assembled cantilevered reinforced earth bulkhead of multistage green as described in claim 1, it is characterized in that: the cantilevered at different levels adds The TGXG formula lacing wire (21) being arranged in the muscle Tu Dangqiangqiang behind embankment soil body (20) is two layers or three layers.
CN201821527921.3U 2018-09-18 2018-09-18 The multistage assembled cantilevered reinforced earth bulkhead of green Active CN209066477U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821527921.3U CN209066477U (en) 2018-09-18 2018-09-18 The multistage assembled cantilevered reinforced earth bulkhead of green

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821527921.3U CN209066477U (en) 2018-09-18 2018-09-18 The multistage assembled cantilevered reinforced earth bulkhead of green

Publications (1)

Publication Number Publication Date
CN209066477U true CN209066477U (en) 2019-07-05

Family

ID=67092800

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821527921.3U Active CN209066477U (en) 2018-09-18 2018-09-18 The multistage assembled cantilevered reinforced earth bulkhead of green

Country Status (1)

Country Link
CN (1) CN209066477U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109235486A (en) * 2018-09-18 2019-01-18 中铁二院工程集团有限责任公司 The multistage assembled cantilevered reinforced earth bulkhead of green
CN111119229A (en) * 2019-11-01 2020-05-08 中铁二院工程集团有限责任公司 Multi-stage reinforced retaining wall comprehensive protection system suitable for large-scale waste slag yard and stability checking and calculating method and construction method thereof
CN112982653A (en) * 2021-03-17 2021-06-18 中冶建工集团有限公司 Construction method of mountain-based building stable structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109235486A (en) * 2018-09-18 2019-01-18 中铁二院工程集团有限责任公司 The multistage assembled cantilevered reinforced earth bulkhead of green
CN111119229A (en) * 2019-11-01 2020-05-08 中铁二院工程集团有限责任公司 Multi-stage reinforced retaining wall comprehensive protection system suitable for large-scale waste slag yard and stability checking and calculating method and construction method thereof
CN112982653A (en) * 2021-03-17 2021-06-18 中冶建工集团有限公司 Construction method of mountain-based building stable structure

Similar Documents

Publication Publication Date Title
CN109235486A (en) The multistage assembled cantilevered reinforced earth bulkhead of green
CN209066477U (en) The multistage assembled cantilevered reinforced earth bulkhead of green
CN206655248U (en) A kind of assembly concrete empty van soil-baffling structure
CN207436092U (en) Multistage pin-connected panel L-type greening barricade construction
KR100660379B1 (en) Plantable reinforced earth wall and its block and construction method of reinforced earth wall
CN101768975B (en) Greening retaining wall building block and method for constructing retaining wall with building block
CN111622261A (en) Box retaining wall of pile foundation
CN210104786U (en) Road shoulder retaining component capable of greening
CN108487234B (en) Construction method of cast-in-situ pile plate type platform wall
CN212611713U (en) Bearing platform type pile plate wall structure
CN111395063B (en) Light soil roadbed structure, roadbed system and design method
CN212129216U (en) Assembled antidetonation is resisted freeze thawing and is warp rigid and flexible type retaining wall of buckled plate
CN110205982B (en) Channel structure for improving flood control standard of existing river levee and construction method thereof
CN201574509U (en) Greening retaining wall building block
CN218148503U (en) Arch high-fill culvert load reduction structure
CN214530709U (en) Branch structure is administered to river-adjacent large-scale landslide of collecting reservoir bank renovation as an organic whole
CN201962697U (en) Frame retaining wall with composite structure
CN210263127U (en) A panel modular unit and reinforced earth retaining wall for reinforced earth retaining wall
CN204803901U (en) Side slope arrangement structure that friction pile and prestressed anchorage hitch of buckling closed
CN111794268B (en) Composite retaining wall and construction method thereof
CN100593604C (en) Flexible explosion-proof dike and construction method thereof
CN109355990B (en) Ultra-fine sand roadbed structure for hydraulic filling in low-lying marsh areas
CN210134292U (en) Z-shaped retaining wall supporting structure for overhanging road shoulder of high-speed railway foundation
CN209837087U (en) Assembled ecological anchoring plate retaining wall
CN208844608U (en) A kind of assembled ecological anchor rod retaining wall structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant