CN209061755U - A kind of Quick dredging underground filling pipe-line system - Google Patents

A kind of Quick dredging underground filling pipe-line system Download PDF

Info

Publication number
CN209061755U
CN209061755U CN201821701879.2U CN201821701879U CN209061755U CN 209061755 U CN209061755 U CN 209061755U CN 201821701879 U CN201821701879 U CN 201821701879U CN 209061755 U CN209061755 U CN 209061755U
Authority
CN
China
Prior art keywords
pipeline
filling
connect
pipe
cement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821701879.2U
Other languages
Chinese (zh)
Inventor
李进成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hubei Yihua Mining Co Ltd Jiang Jia Dun
Original Assignee
Hubei Yihua Mining Co Ltd Jiang Jia Dun
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hubei Yihua Mining Co Ltd Jiang Jia Dun filed Critical Hubei Yihua Mining Co Ltd Jiang Jia Dun
Priority to CN201821701879.2U priority Critical patent/CN209061755U/en
Application granted granted Critical
Publication of CN209061755U publication Critical patent/CN209061755U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Underground Or Underwater Handling Of Building Materials (AREA)

Abstract

The utility model provides a kind of Quick dredging underground filling pipe-line system, the bottom of aggregate bin and at least one cement bin is connect through pipeline with aggregate measuring bucket and cement-weighting bucket respectively, aggregate measuring bucket and cement-weighting bucket bottom are connect through pipeline with forced stirrer respectively, action of forced stirring motor spindle is connect through delivery pump with filling conveying pipeline, again with packing job face after the filling conveying pipeline connection that the traverse column that filling conveying pipeline is connected to underground part are set, the filling conveying pipeline that traverse column are set, which is arranged side by side, isometric wash tub pipe.Using the technical solution of the utility model whether unclog the pipe when, or when normal filling is rinsed, the concrete in all pipelines can be charged mineral building, not will cause the waste of resource, the concrete for entering emergency lagoon simultaneously is reduced, and can also be mitigated to the pressure of environmental protection.

Description

A kind of Quick dredging underground filling pipe-line system
Technical field
The utility model relates to the dredgers during underground work because filling blocking.
Background technique
When using industrial pump long distance delivery concrete to packing job face, it is easy to because concrete proportioning is improper, behaviour The factors such as make mistakes and have a power failure cause plugging.Logical convenient to relax, Filling Station is in design, and every five meter Zhi Liu meters of underground feeding pipe Flanged joint is taken, and emergency lagoon is set on the way in filling pipeline, when plugging occurs,
It needs to dismantle flange at plugging, dredges at plugging, then pipe laying connecting flange, continues packing job.
The application has found that defect is very big during testing.When carrying out filling experiment for the first time, in pump concrete Shi Fasheng pipeline jam accident can be dredged according to design, and pipe flange is dismantled at plugging, and then high pressure water rinses dredging and installs It completes to spend about two hours, because dredging overlong time, concrete flowability is deteriorated at non-plugging, restarts pumping system and is filled When filling out, because the excessive autostop of pressure, concrete can not pump, about 800 meters of wholes of entire pipeline block system, last all to tear open It unloads and is dredged, spend the time about two days.
Find that original dredging scheme has the following deficiencies: in analysis
1, pressure is up to 8-10MPa when filling pipeline works normally, therefore need to use high-intensitive flange and bolt, and lean on wall Wall side Bolt dismantling is difficult, and disassembly process difficulty is big, and consuming time is long for disassembly, dredging and installation, restarts after system not necessarily It can normally pump, entire filling pipeline can be caused all to block when serious;
2, after plugging, the concrete of cleaning flows into emergency lagoon, results in waste of resources, and the water cleaned is muddy, gives mine environmental protection Department increases burden;
3, when normal sand off, need to be rinsed with water filling pipeline, 800 meters of pipe full water about 15m3, this part water Mineral building is rushed in, concrete is washed, the decline of concrete concentration causes strong required for being not achieved after the concrete hardening of filling Degree, and be easy to appear and run mould accident.
Summary of the invention
In view of the above-mentioned problems, the utility model provides the dredging state during a kind of underground work, is dismantling and dredging When filling pipeline, other than plugging position is completely filled with concrete, concrete is not completely filled with filling pipeline normal segments, Due to gravity, there is certain interval between separate ground side concrete and pipeline.Concrete scheme is as follows:
A kind of bottom of Quick dredging underground filling pipe-line system, aggregate bin and at least one cement bin respectively through pipeline with Aggregate measuring bucket and the connection of cement-weighting bucket, aggregate measuring bucket and cement-weighting bucket bottom connect through pipeline and forced stirrer respectively It connects, action of forced stirring motor spindle is connect through delivery pump with filling conveying pipeline, and the traverse column that filling conveying pipeline is connected to underground part are set Filling conveying pipeline (the filling expects pipe of the row is preferably 800 meters) connection after again with packing job face, traverse column set Filling conveying pipeline, which is arranged side by side, isometric wash tub pipe.Slurry caching is provided between the forced stirrer and delivery pump Storehouse.
Above-mentioned wash tub pipe one end is connect with clear water reserviors, and the other end is connect with annular emergency lagoon.Fill conveying pipeline and punching At least provided with 8 connecting tubes between wash water pipe, ball valve, further preferably 10 ball valves are provided in each connecting tube.
Forced stirrer top is provided with flusher, i.e., connect through water supply water route with water weighing hopper at the top of head-tank, Water weighing hopper bottom is connect with forced stirrer;Head-tank bottom connects after the pipeline in emergency water route and water supply water route converges To forced stirrer.
Compressed air system is provided at the top of aggregate bin and cement bin, i.e. air compressor machine is connect with air accumulator, air accumulator warp Pipeline is connect with the pulse dust collector of the top of aggregate bin and cement bin setting respectively;Wherein air accumulator through pipeline also with aggregate meter The pulse dust collector connection being arranged at the top of batch box.
It is had the following beneficial effects: using the technical solution of the utility model
1. save the cost: in former scheme, every a pair of high-intensitive flange of five to six meter amperes dress, 800 meters about 150 pairs, M32*80 Bolt and mating nut need 1200 sets, and totle drilling cost=150 pair * 2*100+1200 covers * 15=48000 yuan;New paragon: totle drilling cost=10* 1500(ball valve price)+800 meters * 30 yuan/meters=39000 yuan;And new paragon pipeline construction reduces flanged joint, welding and peace Dress up this attenuating;Because the cushion that flanged joint uses due to pumping when pressure it is very big, be often easy it is bad, therefore reduce flange use Amount can be such that late maintenance cost reduces.Conveying in feeding pipe is concrete, when flowing at elevated pressures, can be caused to tube wall Certain abrasion, and pipe bent position abrasion is more serious, pipe bent position still takes flanged joint in new paragon, facilitates later period opposite grinding More serious bend pipe is damaged to be replaced.
2. easy to operate: application method being described in process flow, after taking new method, the work of worker is only For operation ball valve can, all ball valves are changed to electronic, pneumatic operated valve, then the labor intensity of worker can further drop Low, working efficiency also greatly improves, and reduces the time used in unclog the pipe.
3. concrete can be all of not will cause waste: whether when unclog the pipe, or when normal filling is rinsed, Concrete in all pipelines can be charged mineral building, not will cause the waste of resource, while entering the concrete of emergency lagoon It reduces, the pressure of environmental protection can also be mitigated.
4. final step is to squeeze into pressure tailing normally in filling step, with the concrete in pressure tailing ramjet duct to mine Room is then pumped into water, by pressure tailing and concrete pumping to work surface, monitors in pipe outlet, when water reaches work surface, stops Only industrial pump closes gate valve at work surface, opens simultaneously gate valve at emergency lagoon, and open flush water pump, opens and rinses water route 1# ball valve is rinsed entire pipeline, and the sewage of flushing flows into emergency lagoon rather than flows into mineral building, can avoid water to concrete Wash away, thus avoid filling concrete required intensity is not achieved.
Detailed description of the invention
Fig. 1 is Quick dredging underground filling pipe-line system structure chart, wherein 1. aggregate bins, 21. cement bins one, 22. cement Storehouse two, 31. pulse dust collectors one, 32. pulse dust collectors two, 33. pulse dust collectors three, 34 pulse dust collectors four, 35 pulses Deduster five, 41. screw conveyors one, 42 screw conveyors two, 51. aggregate measuring buckets, 52. cement-weighting buckets, the metering of 53. water Bucket, 6 forced stirrers, 7 slurry buffering chambers, 8. delivery pumps, 9. filling conveying pipelines, 10. wash tub pipes, 11. packing jobs Face, 12. clear water reserviors, 13. annular emergency lagoons, 14. head-tanks, 15. air compressor machines, 16. air accumulators, 17. ball valves, 18. give Expect device.
Specific embodiment
A kind of Quick dredging underground filling pipe-line system, the bottom difference of aggregate bin 1, cement bin 1, cement bin 2 22 It is connect through pipeline with aggregate measuring bucket 51 and cement-weighting bucket 52, aggregate measuring bucket 51 and 52 bottom of cement-weighting bucket are respectively through pipe Line is connect with forced stirrer 6,6 bottom of forced stirrer through delivery pump 8 with filling conveying pipeline 9 connect, forced stirrer 6 with it is defeated It send and is provided with slurry buffering chamber 7 between pump 8.The filling conveying pipeline 9 that the traverse column that filling conveying pipeline 9 is connected to underground part are set connects Again with packing job face 11 after connecing, the filling conveying pipeline that traverse column are set, which is arranged side by side, isometric wash tub pipe 10.
Described 10 one end of wash tub pipe is connect with clear water reserviors 12, and the other end is connect with annular emergency lagoon 13.
At least provided with 8 connecting tubes 18 between the filling conveying pipeline 9 and wash tub pipe 10, in each connecting tube 18 It is provided with ball valve.
6 top of forced stirrer is provided with flusher, i.e. 14 top of head-tank is through water supply water route and water weighing hopper 53 Connection, 53 bottom of water weighing hopper is connect with forced stirrer 6;Pipeline of 14 bottom of head-tank through meet an urgent need water route and water supply water route Forced stirrer 6 is connected to after converging.
Compressed air system is provided at the top of the aggregate bin 1 and cement bin, i.e. air compressor machine 15 and air accumulator 16 connects It connects, air accumulator 16 is connect with the pulse dust collector being arranged at the top of aggregate bin 1 and cement bin respectively through pipeline;Wherein air accumulator 16 passes through Pipeline is also connect with the pulse dust collector being arranged at the top of aggregate measuring bucket.
In the above-mentioned technical proposal of the utility model, innovative point part includes the design of flushing scheme: i.e. along filling Piece flushing pipe of pipeline construction, flushing pipe one end pump water with 37kw from sump, and the other end is answered filling pipeline beginning Anxious pond is also connected to 37kw water pump.It is connected between flushing pipe and filling pipeline using high pressure resistant ball valve, every 80 meters of connections one Place, and every 100 meter ampere fills 40 gate valve of φ on flushing pipe, flange easy to disassemble is fetched water when rinsing, as shown in Figure 1.
The process flow of this scheme are as follows: when plugging occurs, it is first determined plugging position, when 3# pressure transmitter exception, Plugging has occurred between 3#, 4# ball valve position, then first turns on 1# ball valve and is dredged, when mineral building flushing water is close to clearly When clear close 1# ball valve, open 2# ball valve, when mineral building flushing water close to it is limpid when close 2# ball valve, unlatching 3# ball valve, work as mineral building Flushing water close to it is limpid when close 3# ball valve, open 4# ball valve, need to be tapped at plugging with Quick dredging, dredge to finish and work as Mineral building flushing water close to it is limpid when close 4# ball valve, this process expends about half an hour, then restarts filling system and continue to pump.Such as Concrete flowability variation cannot restart system, close the gate valve at filling pipeline gate valve, open fill pipeline beginning at mineral building, and 10# ball valve, 9# ball valve, 8# ball valve are successively opened, until opening 1# ball valve, the gate valve water outlet at filling pipeline beginning to be opened is limpid Afterwards, 1# ball valve is closed, entire pipeline cleaning and dredging finish.When normal pump concrete to sand off, to prevent filling pipe In water wash away the concrete of mineral building, then allow people to observe filling pipeline outlet, then stop pumping when seeing ejected wash water, close mineral building The gate valve for locating filling pipeline gate valve, open fill pipeline beginning, is then turned on 1# ball valve, and flushing water flows into filling pipeline beginning Emergency lagoon precipitating filtering, when filling pipeline beginning, gate valve goes out to close the lock of 1# ball valve and filling pipeline beginning when saliva becomes limpid Valve, entire filling operation are completed.

Claims (6)

1. a kind of Quick dredging underground filling pipe-line system, which is characterized in that the bottom of aggregate bin (1) and at least one cement bin It is connect respectively through pipeline with aggregate measuring bucket (51) and cement-weighting bucket (52), aggregate measuring bucket (51) and cement-weighting bucket (52) Bottom is connect through pipeline with forced stirrer (6) respectively, and forced stirrer (6) bottom is through delivery pump (8) and filling conveying pipeline (9) Connection, filling conveying pipeline (9) be connected to underground part traverse column set filling conveying pipeline (9) connection after again with packing job face (11), the filling conveying pipeline that traverse column are set, which is arranged side by side, isometric wash tub pipe (10).
2. Quick dredging underground filling pipe-line system according to claim 1, which is characterized in that wash tub pipe (10) one end It is connect with clear water reserviors (12), the other end is connect with annular emergency lagoon (13).
3. Quick dredging underground filling pipe-line system according to claim 2, which is characterized in that filling conveying pipeline (9) with At least provided with 8 connecting tubes (18) between wash tub pipe (10), ball valve is provided on each connecting tube (18).
4. Quick dredging underground filling pipe-line system according to claim 1, which is characterized in that on forced stirrer (6) Portion is provided with flusher, i.e., connect through water supply water route with water weighing hopper (53) at the top of head-tank (14), water weighing hopper (53) Bottom is connect with forced stirrer (6);Head-tank (14) bottom connects after the pipeline in emergency water route and water supply water route converges To forced stirrer (6).
5. Quick dredging underground filling pipe-line system according to claim 1, which is characterized in that aggregate bin (1) and cement Compressed air system is provided at the top of storehouse, i.e. air compressor machine (15) is connect with air accumulator (16), and air accumulator (16) is distinguished through pipeline It is connect with the pulse dust collector being arranged at the top of aggregate bin (1) and cement bin;Wherein air accumulator (16) through pipeline also with aggregate measuring The pulse dust collector connection that bucket top is arranged.
6. Quick dredging underground filling pipe-line system according to claim 1, which is characterized in that forced stirrer (6) with Slurry buffering chamber (7) are provided between delivery pump (8).
CN201821701879.2U 2018-10-19 2018-10-19 A kind of Quick dredging underground filling pipe-line system Active CN209061755U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821701879.2U CN209061755U (en) 2018-10-19 2018-10-19 A kind of Quick dredging underground filling pipe-line system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821701879.2U CN209061755U (en) 2018-10-19 2018-10-19 A kind of Quick dredging underground filling pipe-line system

Publications (1)

Publication Number Publication Date
CN209061755U true CN209061755U (en) 2019-07-05

Family

ID=67095459

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821701879.2U Active CN209061755U (en) 2018-10-19 2018-10-19 A kind of Quick dredging underground filling pipe-line system

Country Status (1)

Country Link
CN (1) CN209061755U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109277378A (en) * 2018-10-19 2019-01-29 湖北宜化江家墩矿业有限公司 A kind of Quick dredging underground filling pipe-line system
CN113738440A (en) * 2021-08-16 2021-12-03 新疆喀拉通克矿业有限责任公司 Method and device for processing paste filling pipeline

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109277378A (en) * 2018-10-19 2019-01-29 湖北宜化江家墩矿业有限公司 A kind of Quick dredging underground filling pipe-line system
CN113738440A (en) * 2021-08-16 2021-12-03 新疆喀拉通克矿业有限责任公司 Method and device for processing paste filling pipeline

Similar Documents

Publication Publication Date Title
CN209061755U (en) A kind of Quick dredging underground filling pipe-line system
CN109277378A (en) A kind of Quick dredging underground filling pipe-line system
CN205061732U (en) Concrete thick liquid recovery unit
CN106836657B (en) Repairing device and method for insufficient grouting of grouting sleeve or device for connecting reinforcing steel bars
CN112297230A (en) Automatic cleaning device for concrete mixing tank
CN110439610B (en) Remote slurry filling and conveying system and method for coal mine goaf
CN101812994A (en) Synchronous grouting system
CN110617104A (en) Cleaning-free process technology for pumping paste filling mining pipeline
CN211426167U (en) Cement viscosity measuring device
CN211486768U (en) Self-cleaning filter
CN112144499A (en) Silt normal position curing system
CN109834838B (en) Automatic slurry preparation system and preparation method thereof
CN112267468A (en) Grouting device for rectifying and reinforcing building
CN2913807Y (en) Pipe conveying apparatus for coating spreading machine
CN211602359U (en) Slip casting pipeline on-way pressure loss test system
CN112620260B (en) Backwashing method for concrete pipeline of spraying and mixing system
CN213571881U (en) Silt normal position curing system
CN110593340B (en) Anti-sticking wheel mortar injection system and method
CN103977991A (en) Method, device and system for cleaning concrete conveying pump pipe
CN211074136U (en) Full-automatic underground filling injection system
CN111397844A (en) Slip casting pipeline on-way pressure loss test system
CN218467658U (en) Uninterrupted grouting secondary mixing drum and inter-pump slurry suction manifold arrangement system
CN209165013U (en) Portable tank lubricant main pipeline flusher
CN207189989U (en) A kind of concrete grout retracting device is with sending pulp grinder structure
CN221095958U (en) Device for repairing internal defects of concrete structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant