CN209040448U CN201821711239.XU CN201821711239U CN209040448U CN 209040448 U CN209040448 U CN 209040448U CN 201821711239 U CN201821711239 U CN 201821711239U CN 209040448 U CN209040448 U CN 209040448U
Authority
CN
China
Prior art keywords
horizontal tube
dewatering horizontal
slag
branched pipe
dewatering
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821711239.XU
Other languages
Chinese (zh)
Inventor
余科
付旭鹏
李国栋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201821711239.XU priority Critical patent/CN209040448U/en
Application granted granted Critical
Publication of CN209040448U publication Critical patent/CN209040448U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of high-building construction temporary drainage structures, including dewatering horizontal tube, branched pipe and slag gathering hopper, the dewatering horizontal tube is tipping tube, and the cross section of pipe is rectangle, the top of the slope side of the dewatering horizontal tube is provided with into water standpipe, for making water enter the dewatering horizontal tube through the water inlet standpipe, the side of the dewatering horizontal tube is provided with branched pipe, and the branched pipe both ends are connected with the dewatering horizontal tube, to enable the rainwater into the branched pipe to be back to the dewatering horizontal tube again, slag-drip opening is provided on the dewatering horizontal tube another side wall opposite with the branched pipe.Beneficial effect is: being cleared up by scraping slag component sundries, the soil etc. of filtering net surface, to guarantee the quick flow forward of rainwater;It is rotated using flow action driving water wheels, so that actuated by cams be made to scrape the movement of slag component, is avoided using being driven by electricity, to improve the safety in utilization and energy-saving effect of discharge structure.

Description

A kind of high-building construction temporary drainage structure
Technical field
The utility model relates to the realm of building construction, and in particular to a kind of high-building construction temporary drainage structure.
Background technique
The scene draining of high-building construction is to prevent that flood season waterlogging and ponding occurs, it is ensured that safety crosses flood and carries out scene The important measure and subsequent construction of civilized construction smoothly, one of the guarantee carried out safely
Applicants have discovered that at least there is following technical problem in the prior art: since top of high-rise buildings is in draining, Some sundries, soil etc. can flow into drainage channel with rainwater, so that drainage channel be blocked, lead to draining not in time, occur Waterlogging phenomenon.
Utility model content
The purpose of this utility model is that solve the above-mentioned problems and provides a kind of high-building construction temporary drainage Structure can block the technical problems such as drainage channel with sundries, the soil etc. that solve in rainwater in the prior art.The utility model mentions Preferred technical solution is included and can be effectively treated to sundries, the soil etc. in rainwater in many technical solutions supplied, To guarantee the technical effects such as be smoothly discharged of rainwater, elaboration as detailed below.
To achieve the above object, the utility model provides following technical scheme:
The utility model provides a kind of high-building construction temporary drainage structure, including dewatering horizontal tube, branched pipe sum aggregate Slag bucket, the dewatering horizontal tube is tipping tube, and the cross section of pipe is rectangle, and the top of the slope side of the dewatering horizontal tube is provided with vertical into water Pipe, for making water enter the dewatering horizontal tube through the water inlet standpipe, the side of the dewatering horizontal tube is provided with branched pipe, and institute It states branched pipe both ends to be connected with the dewatering horizontal tube, so that the rainwater into the branched pipe be enable to be back to institute again Dewatering horizontal tube is stated, slag-drip opening, the slag-drip opening two are provided on the dewatering horizontal tube another side wall opposite with the branched pipe Side is provided with inserting groove;
Filter screen is installed, and the filter screen passes through the upward outside of the slag-drip opening, the mistake in the dewatering horizontal tube The side that meets water of strainer, which is provided with, scrapes slag component, and the slag component slippage of scraping is mounted on the tube wall of the dewatering horizontal tube, is used for Sundries on the filter screen is cleared up, guarantees that the transverse drainage in-pipe flow is unimpeded;
The slag gathering hopper is detachably arranged on the outside of the slag-drip opening by the inserting groove, described scrapes slag for collecting Sundries, the soil etc. of component cleaning;
Protrusion is provided on the branched pipe, and the protrusion protrudes from the side of the branched pipe, inside the protrusion Water wheels are rotatably equipped with, the rotary shaft of the water wheels is vertically arranged, and the top of the protrusion is run through in the upper end of the rotary shaft, Cam is fixedly installed at the top of the rotary shaft, the cam rotation can drive the slag component of scraping to act, thus by institute The sundries on filter screen is stated to scrape into the slag gathering hopper.
Using a kind of above-mentioned high-building construction temporary drainage structure, water inlet standpipe described in catch-basin flows into the transverse drainage Pipe, and along the dewatering horizontal tube flow forward, a part of rainwater flows into the branched pipe when passing through the branched pipe, another Flow forward is continued in part, and when passing through the filter screen, sundries and part soil in rainwater are by baffle in the filter screen On, and the rainwater for entering the branched pipe will push the water wheels rotation when by the water wheels, to make the rotary shaft The cam rotation of top is driven, and then by scraping the movement of slag component described in the actuated by cams, on the filter screen Sundries, the soil of isolation are cleared up, and the slag gathering hopper is made it into, to guarantee that the rainwater in the dewatering horizontal tube can be fast Speed avoids roofing from waterlogging phenomenon occur by the filter screen, while the rainwater in the dewatering horizontal tube is passing through the deslagging Mouthful when, bottom a part can flow into the slag gathering hopper with the rainwater of silt, to make sediment deposition in the slag gathering hopper bottom, Rainwater, which passes through the filter screen, to be continued to flow away after importing the dewatering horizontal tube under, and the rainwater into the branched pipe is passing through institute The dewatering horizontal tube is imported again after stating water wheels, and continues to flow away downwards.
Preferably, the branched pipe is to share three sections, an isosceles trapezoid is formed jointly with the dewatering horizontal tube, it is described Protrusion is located on the interlude of the branched pipe, and the section is parallel with the dewatering horizontal tube.
Preferably, the protrusion semicircular in shape, the axle center of the water wheels is located at the semicircular the center point.
Preferably, the slag gathering hopper is the closed inverted trapezoidal structure of upper and lower ends.
Preferably, the slag component of scraping includes mandril, top plate and spring, the mandril is mounted on described in longitudinal sliding motion On the side wall of dewatering horizontal tube, one end of the mandril towards the branched pipe is equipped with the top plate, and the mandril protrudes into described One end on the inside of dewatering horizontal tube is equipped with scum board, and the scum board side wall is attached on the upstream face of the filter screen, described Spring is socketed on the periphery of the mandril, and between the top plate and the dewatering horizontal tube, the outside of the top plate The periphery of wall and the cam is tangent.
Preferably, the line on the cam between two centers of circle is greater than the caliber of the dewatering horizontal tube.
Beneficial effect is: 1, the utility model is clear to carry out such as sundries, the soil of filtering net surface by scraping slag component Reason, to guarantee the quick flow forward of rainwater;
2, it is rotated using flow action driving water wheels, so that actuated by cams be made to scrape the movement of slag component, avoids driving using electric power It is dynamic, to improve the safety in utilization and energy-saving effect of discharge structure.
Detailed description of the invention
In order to illustrate the embodiment of the utility model or the technical proposal in the existing technology more clearly, below will be to embodiment Or attached drawing needed to be used in the description of the prior art is briefly described, it should be apparent that, the accompanying drawings in the following description is only It is some embodiments of the utility model, for those of ordinary skill in the art, in the premise not made the creative labor Under, it is also possible to obtain other drawings based on these drawings.
Fig. 1 is the internal structure top view of the utility model;
Fig. 2 is the top view of the utility model;
Fig. 3 is the front view of the utility model;
Fig. 4 is that the utility model scrapes slag modular construction enlarged drawing.
The reference numerals are as follows:
1, water inlet standpipe;2, dewatering horizontal tube;3, branched pipe;201, slag-drip opening;202, inserting groove;4, protrusion;5, water wheels; 501, rotary shaft;6, cam;7, slag component is scraped;701, top plate;702, spring;703, mandril;704, scum board;8, slag gathering hopper; 9, filter screen.
Specific embodiment
To keep the purpose of this utility model, technical solution and advantage clearer, below by the technology to the utility model Scheme is described in detail.Obviously, the described embodiments are only a part of the embodiments of the utility model, rather than all Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are not before making creative work Obtained all other embodiment is put, the range that the utility model is protected is belonged to.
Shown in referring to figures 1-4, the utility model provides a kind of high-building construction temporary drainage structure, including draining Transverse tube 2, branched pipe 3 and slag gathering hopper 8, the dewatering horizontal tube 2 is tipping tube, and the cross section of pipe is rectangle, the dewatering horizontal tube 2 Top of the slope side be provided with into water standpipe 1, for making water enter the dewatering horizontal tube 2, the dewatering horizontal tube through the water inlet standpipe 1 2 side is provided with branched pipe 3, and 3 both ends of the branched pipe are connected with the dewatering horizontal tube 2, to make to enter described The rainwater of branched pipe 3 can be back to the dewatering horizontal tube 2 again, another opposite with the branched pipe 3 of the dewatering horizontal tube 2 Slag-drip opening 201 is provided on side wall, 201 two sides of slag-drip opening are provided with inserting groove 202;
Filter screen 9 is installed, and the filter screen 9 passes through the slag-drip opening 201 outside upwards in the dewatering horizontal tube 2, The side that meets water of the filter screen 9, which is provided with, scrapes slag component 7, and the pipe scraped slag component 7 and be slidably mounted on the dewatering horizontal tube 2 On wall, for clearing up sundries on the filter screen 9, guarantee that water flow is unimpeded in the dewatering horizontal tube 2;
The slag gathering hopper 8 is detachably arranged in 201 outside of slag-drip opening by the inserting groove 202, for collecting Sundries, the soil etc. for scraping the cleaning of slag component 7, can periodically topple over slag gathering hopper, guarantee its collecting function;
Protrusion 4 is provided on the branched pipe 3, and the protrusion 4 protrudes from the side of the branched pipe 3, the protrusion 4 Inner rotation is equipped with water wheels 5, and the rotary shaft 501 of the water wheels 5 is vertically arranged, and institute is run through in the upper end of the rotary shaft 501 The top of protrusion 4 is stated, the top of the rotary shaft 501 is fixedly installed with cam 6, and the rotation of cam 6 can drive described scrape Slag component 7 acts, to scraping the sundries on the filter screen 9 into the slag gathering hopper 8.
Preferably, the branched pipe 3 is to share three sections, an isosceles trapezoid, institute are formed jointly with the dewatering horizontal tube 2 It states protrusion 4 to be located on the interlude of the branched pipe 3, the section is parallel with the dewatering horizontal tube 2, so set, convenient for making water flow Level passes through water wheels 5.
4 semicircular in shape of protrusion, the axle center of the water wheels 5 are located at the semicircular the center point, so set, convenient for making Water flow only passes through from the side of water wheels 5, to guarantee that water wheels 5 persistently rotate in one direction.
The slag gathering hopper 8 is the closed inverted trapezoidal structure of upper and lower ends, so set, convenient for guaranteeing slag gathering hopper 8 and deslagging The leakproofness of 201 connection of mouth.
The slag component 7 of scraping includes mandril 703, top plate 701 and spring 702, and the mandril 703 is mounted in longitudinal sliding motion On the side wall of the dewatering horizontal tube 2, one end of the mandril 703 towards the branched pipe 3 is equipped with the top plate 701, described One end that mandril 703 protrudes into 2 inside of the dewatering horizontal tube is equipped with scum board 704, and 704 side wall of the scum board be attached to it is described On the upstream face of filter screen 9, the spring 702 is socketed on the periphery of the mandril 703, and be located at the top plate 701 with Between the dewatering horizontal tube 2, the lateral wall of the top plate 701 and the periphery of the cam 6 are tangent, so set, convenient for convex When the small nose circle of wheel 6 is rotated to 701 side of top plate, mandril 703 can be pushed to slide into dewatering horizontal tube 2 by top plate 701, from And be pushed into scum board 704 sundries on 9 surface of filter screen, soil in slag gathering hopper 8, when the small nose circle of cam 6 is to far from top plate When 701 side rotation, the elastic force effect of spring 702 makes scum board so that mandril 703 be made to slide to opposite direction with top plate 701 704 reset, and complete once to scrape slag movement, and with the lasting rotation of water wheels 5, scum board 704 is continual to move reciprocatingly, thus Sundries on filter screen 9 is cleared up, guarantees that water flow is unimpeded in dewatering horizontal tube 2.
Line on the cam 6 between two centers of circle is greater than the caliber of the dewatering horizontal tube 2, so set, convenient for protecting The caliber that cam 6 is greater than dewatering horizontal tube 2 to the pushing tow stroke of mandril 703 is demonstrate,proved, so as to make scum board 704 will be on filter screen 9 The push-in slag gathering hopper 8 such as sundries, soil in.
Using the above structure, water inlet standpipe 1 described in catch-basin flows into the dewatering horizontal tube 2, and along the dewatering horizontal tube 2 to Preceding flowing, for a part of rainwater by flowing into the branched pipe 3 when the branched pipe 3, another part continues flow forward, When across the filter screen 9, sundries and part soil in rainwater by baffle on the filter screen 9, and enter the branch The rainwater of pipe 3 will push the water wheels 5 and rotate when by the water wheels 5, so that the rotary shaft 501 be made to drive top The cam 6 rotates, and then drives the slag component 7 of scraping to act by the cam 6, to the isolation on the filter screen 9 Sundries, soil are cleared up, and the slag gathering hopper 8 is made it into, to guarantee that the rainwater in the dewatering horizontal tube 2 can quickly lead to The filter screen 9 is crossed, avoids roofing from waterlogging phenomenon occur, while the rainwater in the dewatering horizontal tube 2 is passing through the slag-drip opening When 201, bottom a part can flow into the slag gathering hopper 8 with the rainwater of silt, to make sediment deposition at 8 bottom of slag gathering hopper Portion, rainwater, which passes through the filter screen 9, to be continued to flow away after importing the dewatering horizontal tube 2 under, and the rainwater into the branched pipe 3 exists It imports the dewatering horizontal tube 2 again after the water wheels 5, and continues to flow away downwards.
Above description is only a specific implementation of the present invention, but the protection scope of the utility model is not limited to In this, anyone skilled in the art within the technical scope disclosed by the utility model, can readily occur in variation Or replacement, it should be covered within the scope of the utility model.Therefore, the protection scope of the utility model should be with the power Subject to the protection scope that benefit requires.

Claims (6)

1. a kind of high-building construction temporary drainage structure, it is characterised in that: including dewatering horizontal tube (2), branched pipe (3) sum aggregate slag It struggles against (8), the dewatering horizontal tube (2) is tipping tube, and the cross section of pipe is rectangle, and the top of the slope side of the dewatering horizontal tube (2) is arranged Have into water standpipe (1), for making water enter the dewatering horizontal tube (2) through the water inlet standpipe (1), the dewatering horizontal tube (2) Side is provided with branched pipe (3), and the branched pipe (3) both ends are connected with the dewatering horizontal tube (2), to make to enter institute The rainwater for stating branched pipe (3) can be back to the dewatering horizontal tube (2) again, the dewatering horizontal tube (2) and the branched pipe (3) It is provided on opposite another side wall slag-drip opening (201), slag-drip opening (201) two sides are provided with inserting groove (202);
It is equipped with filter screen (9) in the dewatering horizontal tube (2), and the filter screen (9) is outer upwards across the slag-drip opening (201) Side, the side that meets water of the filter screen (9), which is provided with, scrapes slag component (7), and the slag component (7) of scraping is slidably mounted on the draining On the tube wall of transverse tube (2), for clearing up sundries on the filter screen (9), guarantee that the dewatering horizontal tube (2) interior water flow is smooth It is logical;
The slag gathering hopper (8) is detachably arranged on the outside of the slag-drip opening (201) by the inserting groove (202), for receiving The sundries, soil etc. of slag component (7) cleaning are scraped described in collection;
It is provided with protrusion (4) on the branched pipe (3), and the protrusion (4) protrude from the side of the branched pipe (3), it is described Protrusion (4) inner rotation is equipped with water wheels (5), and the rotary shaft (501) of the water wheels (5) is vertically arranged, and the rotary shaft (501) top of the protrusion (4) is run through in upper end, is fixedly installed with cam (6) at the top of the rotary shaft (501), described Cam (6) rotation can drive described scrape slag component (7) to act, to scraping the sundries on the filter screen (9) into the collection In slag bucket (8).
2. a kind of high-building construction temporary drainage structure according to claim 1, it is characterised in that: the branched pipe (3) To share three sections, one isosceles trapezoid of molding, the protrusion (4) are located at the branched pipe (3) jointly with the dewatering horizontal tube (2) Interlude on, the section is parallel with the dewatering horizontal tube (2).
3. a kind of high-building construction temporary drainage structure according to claim 1, it is characterised in that: the protrusion (4) is in The axle center of semicircle, the water wheels (5) is located at the semicircular the center point.
4. a kind of high-building construction temporary drainage structure according to claim 1, it is characterised in that: the slag gathering hopper (8) For the closed inverted trapezoidal structure of upper and lower ends.
5. a kind of high-building construction temporary drainage structure according to claim 1, it is characterised in that: described to scrape slag component It (7) include mandril (703), top plate (701) and spring (702), the mandril (703) is mounted on the transverse drainage in longitudinal sliding motion On the side wall for managing (2), one end of mandril (703) towards the branched pipe (3) is equipped with the top plate (701), the top One end that bar (703) protrudes on the inside of the dewatering horizontal tube (2) is equipped with scum board (704), and the scum board (704) side wall pastes On the upstream face of the filter screen (9), the spring (702) is socketed on the periphery of the mandril (703), and is located at institute It states between top plate (701) and the dewatering horizontal tube (2), the periphery phase of the lateral wall and the cam (6) of the top plate (701) It cuts.
6. a kind of high-building construction temporary drainage structure according to claim 5, it is characterised in that: on the cam (6) Line between two centers of circle is greater than the caliber of the dewatering horizontal tube (2).
CN201821711239.XU 2018-10-22 2018-10-22 A kind of high-building construction temporary drainage structure Expired - Fee Related CN209040448U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821711239.XU CN209040448U (en) 2018-10-22 2018-10-22 A kind of high-building construction temporary drainage structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821711239.XU CN209040448U (en) 2018-10-22 2018-10-22 A kind of high-building construction temporary drainage structure

Publications (1)

Publication Number Publication Date
CN209040448U true CN209040448U (en) 2019-06-28

Family

ID=67036924

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821711239.XU Expired - Fee Related CN209040448U (en) 2018-10-22 2018-10-22 A kind of high-building construction temporary drainage structure

Country Status (1)

Country Link
CN (1) CN209040448U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111778794A (en) * 2020-06-30 2020-10-16 四川航天建筑工程有限公司 Construction structure and construction method for roadbed earthwork engineering in rainy season

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111778794A (en) * 2020-06-30 2020-10-16 四川航天建筑工程有限公司 Construction structure and construction method for roadbed earthwork engineering in rainy season

Similar Documents

Publication Publication Date Title
CN209179132U (en) A kind of municipal administration storm-water system
CN209630694U (en) A kind of regeneration concrete sewage precipitation device
CN209040448U (en) A kind of high-building construction temporary drainage structure
CN112791508B (en) Purifier is collected to rainwater in sponge city
CN208578136U (en) A kind of initial rainwater separator
CN208168189U (en) A kind of rain inlet structure of environment-friendly type for building
CN208995911U (en) A kind of discharge structure for bridge draining
CN208650000U (en) A kind of wet type grass planting ditch
CN212714364U (en) Greening drainage channel for water storage irrigation
CN215211452U (en) Sponge urban rainwater regulation and storage structure
CN214459610U (en) Road and bridge drainage ditch with good drainage effect
CN211873238U (en) Sponge city rainwater shunting hinders dirty anti-reflux discharging equipment
CN209193734U (en) A kind of sponge urban water system of one residential
CN210976031U (en) Ecological garden road drainage device
CN208965676U (en) A kind of anti-blocking drain pipe road system
CN208685750U (en) A kind of town road rainwater collection irrigation system
CN211312791U (en) Decontamination shunting device for preventing and treating agricultural non-point source pollution
CN208649999U (en) A kind of dry type grass planting ditch
CN210031499U (en) Bridge drainage system
CN208899613U (en) Basketry inlet for stom water for sponge city
CN207538185U (en) Trench deslagging device
CN201264913Y (en) Drossing apparatus of column type center drive sludge scraping and sucking machine
CN214784495U (en) Sponge formula rain flood drainage system
CN217299239U (en) Gutter inlet filter equipment for municipal works
CN220413015U (en) Rainwater infiltration purifies regulation pond

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190628

Termination date: 20211022

CF01 Termination of patent right due to non-payment of annual fee