CN209011444U - One kind going out roofing and marks time node waterproof structure - Google Patents

One kind going out roofing and marks time node waterproof structure Download PDF

Info

Publication number
CN209011444U
CN209011444U CN201821606545.7U CN201821606545U CN209011444U CN 209011444 U CN209011444 U CN 209011444U CN 201821606545 U CN201821606545 U CN 201821606545U CN 209011444 U CN209011444 U CN 209011444U
Authority
CN
China
Prior art keywords
layer
concrete
indoor
threshold
waterproof
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821606545.7U
Other languages
Chinese (zh)
Inventor
居锐
其他发明人请求不公开姓名
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201821606545.7U priority Critical patent/CN209011444U/en
Application granted granted Critical
Publication of CN209011444U publication Critical patent/CN209011444U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model provide it is a kind of go out roofing mark time node waterproof structure, include floor, plain concrete layer, cement mortar screeding layer, concrete threshold, indoor cement sand bed, bear down on one, step is marked time, complex waterproof layer, protective layer;The floor is reinforced concrete structure, which is divided into indoor, outside two parts, indoor water silt particle pulp layer is equipped on indoor, and outside is successively equipped with plain concrete layer, cement mortar screeding layer, complex waterproof layer from bottom to up;The interior side end, which is also built, concrete threshold, is additionally provided with and bears down on one on the threshold;The step is marked time to be built on complex waterproof layer by concrete and be formed;The step marks time, bears down on one, matcoveredn is built in concrete threshold outer surface.

Description

One kind going out roofing and marks time node waterproof structure
Technical field
The utility model relates to building field, more particularly to it is a kind of go out roofing mark time node waterproof structure.
Background technique
Roofworks is one of major part of building engineering, it had both included material used in engineering, equipment and institute The technical activities such as design, construction, the maintenance of progress.Roofing is marked time to move towards the channel of roofing from interior out, the anti-water capacity herein It is easily ignored, causes the infiltration at the place of marking time, leak to enter the room, influence the quality of roof.
Utility model content
The purpose of this utility model is that in view of the drawbacks of the prior art and insufficient, provide it is a kind of go out roofing node of marking time it is anti- Water-bound, the design of joints is reasonable, has paid attention to the thin portion waterproof of building, ensure that waterproofness, effectively prevent rainwater It is entered the room from the place of marking time, improves the use quality of roofing, and easy for construction.
In order to achieve the above purposes, the technical solution adopted by the utility model is: it is a kind of go out roofing mark time node waterproof structure, Include floor, plain concrete layer, cement mortar screeding layer, concrete threshold, indoor cement sand bed, bear down on one, step is marked time, Complex waterproof layer, protective layer;The floor is reinforced concrete structure, which is divided into indoor, outside two parts, indoor Indoor water silt particle pulp layer is equipped on side, outside is successively equipped with plain concrete layer from bottom to up, cement mortar screeding layer, answers Close waterproof layer;The interior side end, which is also built, concrete threshold, is additionally provided with and bears down on one on the threshold;The step mark time by Concrete builds formation on complex waterproof layer;The step, which marks time, bears down on one, concrete threshold outer surface is built protection Layer.
Preferably, the cement mortar screeding layer leans on indoor end to be provided with 45 ° of chamferings, the width of the chamfering in outside Degree is set as 100mm.
Preferably, the cement mortar screeding layer is provided with the gradient to outdoor 2%.
Preferably, the complex waterproof layer is built by polyurethanes coating waterproof layer and self-adhesive waterproof roll material enhancement layer It is formed, which is laid with full entire floor outside, and self-adhesive waterproof roll material enhancement layer is laid on step Mark time bottom, bottom of bearing down on one, at the top of concrete threshold and outdoor unit side, and complex waterproof layer one end beared down on one be pressed abd fixed on it is mixed On solidifying soil threshold.
Preferably, the protective layer is provided with the gradient to outdoor 2%.
The beneficial effects of the utility model are: the design of joints is reasonable, the thin portion waterproof of building is paid attention to, ensure that Waterproofness effectively prevents rainwater and enters the room from the place of marking time, and improves the use quality of roofing, and easy for construction.
Detailed description of the invention
Attached drawing described herein is to be used to provide a further understanding of the present invention, and constitutes one of the application Point, but do not constitute the restriction to the utility model.
Fig. 1 one kind goes out roofing and marks time node waterproof structural schematic diagram.
Wherein: 1 is floor, and 2 be plain concrete layer, and 3 be cement mortar screeding layer, and 4 be concrete threshold, and 5 be indoor water Silt particle pulp layer, 6 is bear down on one, and 7 mark time for step, and 8 be complex waterproof layer, and 9 be protective layer.
Specific embodiment
In conjunction with attached drawing, the utility model is described in further detail.
The node waterproof structure as shown, a kind of roofing out is marked time, includes floor 1, plain concrete layer 2, cement mortar Screed-coat 3, concrete threshold 4, indoor cement sand bed 5, the 6, step that bears down on one are marked time 7, complex waterproof layer 8, protective layer 9;It is described Floor 1 is reinforced concrete structure, which divides for indoor, outside two parts, is equipped with indoor water silt particle on indoor Pulp layer 5, outside are successively equipped with plain concrete layer 2, cement mortar screeding layer 3, complex waterproof layer 8 from bottom to up;The room Medial end, which is also built, concrete threshold 4, is additionally provided on the threshold and bears down on one 6;The step mark time 7 by concrete compound It builds and is formed on waterproof layer 8;Build matcoveredn 9 in the step 7,6,4 outer surface of concrete threshold of bearing down on one of marking time.
When it is implemented, the cement mortar screeding layer 3 leans on indoor end to be provided with 45 ° of chamferings, the chamfering in outside Width be set as 100mm.
When it is implemented, the cement mortar screeding layer 3 is provided with the gradient to outdoor 2%.
When it is implemented, the complex waterproof layer 8 is by polyurethanes coating waterproof layer and self-adhesive waterproof roll material enhancement layer It builds and is formed, which is laid with full entire 1 outside of floor, and self-adhesive waterproof roll material enhancement layer is laid on Step is marked time 7 bottoms, 6 bottoms of bearing down on one, the top of concrete threshold 4 and outdoor unit side, and 8 one end of complex waterproof layer is beared down on one 6 pressures It fastens on concrete threshold 4.
When it is implemented, the protective layer 9 is provided with the gradient to outdoor 2%.

Claims (5)

  1. It marks time node waterproof structure 1. one kind goes out roofing, it is characterised in that: include that floor, plain concrete layer, cement mortar are looked for Leveling, concrete threshold, indoor cement sand bed, bear down on one, step is marked time, complex waterproof layer, protective layer;The floor is reinforcing bar Concrete structure, the floor are divided into indoor, outside two parts, indoor water silt particle pulp layer, outside are equipped on indoor It is successively equipped with plain concrete layer, cement mortar screeding layer, complex waterproof layer from bottom to up;The interior side end, which is also built, to be had Concrete threshold is additionally provided on the threshold and bears down on one;The step is marked time to be built on complex waterproof layer by concrete and be formed;Institute State that step marks time, bears down on one, matcoveredn is built in concrete threshold outer surface.
  2. The node waterproof structure 2. a kind of roofing out according to claim 1 is marked time, it is characterised in that: the cement mortar is looked for Leveling leans on indoor end to be provided with 45 ° of chamferings in outside, and the width of the chamfering is set as 100mm.
  3. The node waterproof structure 3. a kind of roofing out according to claim 1 is marked time, it is characterised in that: the cement mortar is looked for Leveling is provided with the gradient to outdoor 2%.
  4. The node waterproof structure 4. a kind of roofing out according to claim 1 is marked time, it is characterised in that: the complex waterproof layer It is built and is formed by polyurethanes coating waterproof layer and self-adhesive waterproof roll material enhancement layer, which is laid with full Entire floor outside, self-adhesive waterproof roll material enhancement layer be laid on step mark time bottom, bottom of bearing down on one, at the top of concrete threshold And outdoor unit side, and complex waterproof layer one end is beared down on one and is pressed abd fixed on concrete threshold.
  5. The node waterproof structure 5. a kind of roofing out according to claim 1 is marked time, it is characterised in that: the protective layer setting Oriented outdoor 2% gradient.
CN201821606545.7U 2018-09-29 2018-09-29 One kind going out roofing and marks time node waterproof structure Expired - Fee Related CN209011444U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821606545.7U CN209011444U (en) 2018-09-29 2018-09-29 One kind going out roofing and marks time node waterproof structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821606545.7U CN209011444U (en) 2018-09-29 2018-09-29 One kind going out roofing and marks time node waterproof structure

Publications (1)

Publication Number Publication Date
CN209011444U true CN209011444U (en) 2019-06-21

Family

ID=66834831

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821606545.7U Expired - Fee Related CN209011444U (en) 2018-09-29 2018-09-29 One kind going out roofing and marks time node waterproof structure

Country Status (1)

Country Link
CN (1) CN209011444U (en)

Similar Documents

Publication Publication Date Title
CN207597441U (en) A kind of basement side wall horizontal construction joint water proof structure
CN102747750B (en) Construction method for post-pouring settlement belt protective measures of basement top plates
CN207277119U (en) A kind of colorful water permeable concrete pavement structure
CN105201025B (en) Basement waterproofing construction and its construction method
CN104264717A (en) Basement rigid material and flexible material combined waterproof construction method
JP6203157B2 (en) Permeable pavement structure
CN107059924A (en) Subway open-cut station comprehensive protection system and its construction method under strong corrosive environment
CN207484193U (en) Permeable road structure
CN207143633U (en) A kind of pervious concrete grass planting land earth construction
CN209011444U (en) One kind going out roofing and marks time node waterproof structure
CN207796262U (en) A kind of water pipe finishing waterproof assembling structure
CN208996333U (en) A kind of inverted roof balcony node waterproof structure
CN206616785U (en) Inverted roof provided with steam passing away
CN209194466U (en) A kind of Reservoir Bank leakage preventing structure
CN207260455U (en) A kind of anti-aging roof structure of waterproof heat insulation
CN206521812U (en) A kind of anti-leakage structure of toilet
CN208965683U (en) A kind of balcony drainage outlet node waterproof structure
CN204298707U (en) Splashproof pervious floor tile
CN209585309U (en) Subsided rest room waterproof construction
CN209011441U (en) One kind going out roofing air hose node waterproof structure
CN206329009U (en) Factory loading dock ground leakage preventing structure
CN208950185U (en) Low outer high access point node waterproof construction in a kind of inverted insulating roof
CN205907921U (en) Waterproof structure of parapet wall
CN206428708U (en) It is a kind of to use six ribs block with holes and the combination protective slope structure of soil nailing
CN205604307U (en) Concrete base plate watertightness structure that has underground continuous wall

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190621

CF01 Termination of patent right due to non-payment of annual fee