- CN208981529U CN208981529U CN201821654082.1U CN201821654082U CN208981529U CN 208981529 U CN208981529 U CN 208981529U CN 201821654082 U CN201821654082 U CN 201821654082U CN 208981529 U CN208981529 U CN 208981529U
- Authority
- CN
- China
- Prior art keywords
- balcony
- prefabricated
- composite beam
- hole
- plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model relates to a kind of bands to lift the prefabricated overlapping balcony slab of hole, belong to building structure field, the utility model is made of balcony slab, composite beam, connection reinforcing bar, the balcony slab is prefabricated balcony plate, inside is equipped with hollow out and can connect with embedded bar, the prefabricated balcony plate medial shaft rib is placed in composite beam groove, and is placed in embedded bar in prefabricated balcony plate.After coincideing well on the inside of prefabricated balcony plate with composite beam groove, the two is tightened with screw, opens up injected hole in prefabricated balcony plate inside front, prefabricated balcony plate and composite beam are consolidated into integrally connected with slip casting method.Four cavities are opened up in balcony slab plate face, for disposing hook to make balcony slab convenient for high-altitude carrying.The utility model combines the integrated cantilever for being formed and being consolidated to connect with composite beam in balcony slab by both screw and grouting method, the simple and direct stabilization of structure, securely and reliably, and it is easy to operate.
Description
Technical field
The utility model belongs to the connection structure of a kind of balcony slab and composite beam, belongs to building structure field.
Background technique
As national economy rapidly develops, China's building industry is also rapidly developed, and wherein assembled architecture also obtains
Tremendous development and progress.Since component can solve the presence of traditional architecture production method in factory's execution standardization operation
Building energy consumption is high, the problems such as resource consumption is big, production efficiency is low, be increasingly subject to the concern of industry and society.With assembled
The development of building, in addition to main structure itself needs innovation and development, because existing in terms of the connection structure of prefabricated balcony plate and main body
The problem of it is also very important, if connection is improper, will cause balcony and the serious accidents such as topple, fall off.It is allocated and transported simultaneously in high-altitude
In the process, there is also some security risks.For the development for adapting to and promoting assembled architecture, it is necessary to which researching and developing has superperformance
The connection structure of prefabricated balcony plate and main body, and there is the convenience of allocation and transportation.
Utility model content
The purpose of the utility model is to provide the structures of a kind of balcony slab and composite beam connected and high-altitude is facilitated to allocate and transport, should
Connection structure is safe and reliable, calculates simple, and main structure does not influence balcony calculating, can centralized calculation, form series, directly choosing
With being conducive to plant produced and preparation, meet batch production direction.
To achieve the above object, the utility model uses following technical scheme:
The utility model includes prefabricated balcony plate, composite beam, connection reinforcing bar and screw rod, on the inside of the prefabricated balcony plate with it is folded
It closes beam groove to match, be connected with composite beam groove by connection reinforcing bar, screw rod on the inside of prefabricated balcony plate, connection reinforcing bar includes folded
Close beam lower rebar, composite beam upper reinforcement, balcony slab reserved steel bar and balcony slab main reinforcement;Composite beam lower rebar and screw rod connect
It connects, composite beam upper reinforcement is matched with the reserved steel bar hole of balcony slab inside upper part hollow out and merged and balcony slab reserved steel bar, sun
The connection of platen main reinforcement.
It is described to pass through pre-buried bulkhead nut in prefabricated balcony plate plate face and reserved lifting hole is set for disposing suspension hook.
The balcony slab inside upper part hollow out is bonded by injected hole slip casting with composite beam.
The composite beam groove is equipped with composite beam reserving hole, is equipped with prefabricated balcony plate preformed hole on the inside of prefabricated balcony plate
Hole, screw rod passes through composite beam reserving hole and prefabricated balcony plate reserving hole and embedded nut is cooperatively connected.
The utility model have the characteristics that it is following and the utility model has the advantages that
(1) connection structure of the utility model balcony slab and composite beam is provided with prefabricated connector in prefabricated balcony plate,
By connection reinforcing bar and screw connection between prefabricated balcony plate and composite beam, by injecting cement slurry wherein, in balcony slab
Firm integrated cantilever connection is formed between composite beam.
(2) hole that four liftings have been reserved in prefabricated balcony plate plate face, for disposing hook to make balcony slab convenient for height
Sky is carried, securely and reliably.
(3) method reassembled by prefabricated balcony plate avoids concrete and pours in conjunction with the mode of screw rod fastening and slip casting
Bring construction trouble is built, greatly improves the quality of balcony construction, it is a kind of green construction method that efficiency, which significantly improves,.
Detailed description of the invention:
Fig. 1 is the connection schematic diagram of the utility model prefabricated balcony plate and composite beam.
Fig. 2 is the structural schematic diagram of the utility model prefabricated balcony plate and composite beam.
Fig. 3 is the utility model prefabricated balcony plate front reinforcing bar hole distribution schematic diagram.
In figure: 1- composite beam lower rebar, 2- composite beam reserving hole, 3- embedded nut, 4- composite beam upper reinforcement, 5-
Screw rod, 6- balcony slab inside upper part hollow out, 7- suspension hook, 8- bulkhead nut, 9- prefabricated balcony plate, 10- prefabricated balcony plate preformed hole
Hole, 11- balcony slab reserved steel bar, the reserved lifting hole of 12-, 13- balcony slab main reinforcement, 14- reserved steel bar hole, 15- injected hole.
Specific embodiment
The technical solution of the application is illustrated below with reference to embodiment and attached drawing:
Embodiment 1
The connection structure of the utility model balcony slab and composite beam, as shown in Figure 1-3, the specific embodiment party of the utility model
Formula are as follows:
The prefabricated of prefabricated balcony plate 9 is first carried out, pre-buried bulkhead nut 8 is installed in corresponding hole location when prefabricated, thus
Four reserved lifting holes 12 are formed after the completion of balcony slab is prefabricated, for after disposing suspension hook 7, balcony slab to make by major part screw
It unscrews to form coniform hole, suspension hook 7 is inserted into 12 and is tightened with nut 8, prefabricated balcony version is carried out by loop wheel machine accurate
Handling.
Then prefabricated balcony plate is installed to composite beam, composite beam upper reinforcement 4 is precisely inserted into reserved on balcony slab
Reinforcing bar hole 14, and connect with balcony slab reserved steel bar 11, balcony slab main reinforcement 13;It adjusts prefabricated balcony plate reserving hole 10 and folds
Screw rod 5 is inserted into hole and connect with embedded nut 3 by the position for closing beam reserving hole 2;Composite beam lower rebar 1 is connected in screw rod 5
Together, prefabricated balcony plate is tightened with composite beam.
It is in the milk in balcony slab inside upper part hollow out 6 by injected hole 15, realizes prefabricated balcony plate and the firm company of composite beam
It is integrated.Then suspension hook 7 is unloaded, and fills up hole with concrete.
Claims (4)
1. a kind of band lifts the prefabricated overlapping balcony slab of hole, which is characterized in that including prefabricated balcony plate (9), composite beam, connection steel
Muscle and screw rod (5), prefabricated balcony plate (9) inside are matched with composite beam groove, prefabricated balcony plate (9) inside and composite beam
Groove by connection reinforcing bar, screw rod (5) connection, connection reinforcing bar include composite beam lower rebar (1), composite beam upper reinforcement (4),
Balcony slab reserved steel bar (11) and balcony slab main reinforcement (13);Composite beam lower rebar (1) is connect with screw rod (5), composite beam top
Reinforcing bar (4) is matched with the reserved steel bar hole (14) of balcony slab inside upper part hollow out (6) to be merged and balcony slab reserved steel bar (11), sun
Platen main reinforcement (13) connection.
2. band according to claim 1 lifts the prefabricated overlapping balcony slab of hole, which is characterized in that balcony slab inside upper part is engraved
Empty (6) are bonded by injected hole (15) slip casting with composite beam.
3. band according to claim 1 lifts the prefabricated overlapping balcony slab of hole, which is characterized in that in prefabricated balcony plate (9)
Pass through pre-buried bulkhead nut (8) in plate face and reserved lifting hole (12) is set for disposing suspension hook (7).
4. band according to claim 1 lifts the prefabricated overlapping balcony slab of hole, which is characterized in that composite beam groove is equipped with
Composite beam reserving hole (2), prefabricated balcony plate (9) inside are equipped with prefabricated balcony plate reserving hole (10), and screw rod (5) passes through overlapping
Beam reserving hole (2) and prefabricated balcony plate reserving hole (10) and embedded nut (3) are cooperatively connected.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821654082.1U CN208981529U (en) | 2018-10-12 | 2018-10-12 | A kind of band lifting prefabricated overlapping balcony slab of hole |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821654082.1U CN208981529U (en) | 2018-10-12 | 2018-10-12 | A kind of band lifting prefabricated overlapping balcony slab of hole |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208981529U true CN208981529U (en) | 2019-06-14 |
Family
ID=66787125
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821654082.1U Active CN208981529U (en) | 2018-10-12 | 2018-10-12 | A kind of band lifting prefabricated overlapping balcony slab of hole |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208981529U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112411738A (en) * | 2020-10-21 | 2021-02-26 | 浙大城市学院 | Prefabricated balcony laminated slab and construction method thereof |
CN113513178A (en) * | 2021-03-02 | 2021-10-19 | 江苏吴中建设集团有限公司 | Rack-shaped seam assembly type beam plate |
-
2018
- 2018-10-12 CN CN201821654082.1U patent/CN208981529U/en active Active
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112411738A (en) * | 2020-10-21 | 2021-02-26 | 浙大城市学院 | Prefabricated balcony laminated slab and construction method thereof |
CN113513178A (en) * | 2021-03-02 | 2021-10-19 | 江苏吴中建设集团有限公司 | Rack-shaped seam assembly type beam plate |
CN113513178B (en) * | 2021-03-02 | 2022-11-01 | 江苏吴中建设集团有限公司 | Rack-shaped seam assembly type beam plate |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208981529U (en) | A kind of band lifting prefabricated overlapping balcony slab of hole | |
CN206873792U (en) | A kind of assembled staircase structure | |
CN206267422U (en) | A kind of assembly concrete superposed column | |
CN107044175A (en) | The vertical linked system of fabricated shear wall with concealed beam sleeper and its installation method | |
CN106088327A (en) | Manufacture method based on the assembling frame post that 3D prints | |
CN108582466A (en) | A kind of steel reinforcement cage of prefabricated box girder mould | |
CN108716189A (en) | Large span T-steel structure beam sections for joining island bridge install closure method | |
CN205501843U (en) | Consolidate rigid framed arch bridge | |
CN209040349U (en) | A kind of ring muscle fastening shear wall structure being easily installed | |
CN206529712U (en) | Assembled steel reinforced concrete aliform type culvert opening | |
CN109083184A (en) | A kind of prefabricated cushion cap of land sectional type and its production and installation method | |
CN208533894U (en) | A kind of lightweight precast concrete stair | |
CN209260578U (en) | Longitudinal temporary connecting structure of suspension bridge concrete stiffening girder installation | |
CN107601974A (en) | A kind of carbon fiber reinforced concrete thin plate and preparation method thereof | |
CN107152112A (en) | A kind of modularization Prefabricated stacking floor and its construction method for being used to drop plate region | |
CN205840190U (en) | A kind of pin key connects the mounting structure of prefabricated bench | |
CN205954675U (en) | Prefabricated pipeline concrete buttress | |
CN207244957U (en) | A kind of modularization Prefabricated stacking floor for being used to drop plate region | |
CN209194780U (en) | A kind of modular non-bearing self-heat preserving assembly type wall | |
CN209538373U (en) | A kind of prefabricated overlapping balcony slab of cracking resistance | |
CN208328970U (en) | A kind of environmentally friendly connection structure of precast concrete foundation and steel-pipe pile | |
CN209369106U (en) | A kind of integral prefabricated masonry structure | |
CN209025446U (en) | A kind of aluminum dipping form material transfer entrance construction device | |
CN207194165U (en) | The connecting node of composite beam and superposed member | |
CN208392315U (en) | A kind of steel reinforcement cage of prefabricated box girder mould |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |