CN208950317U - A kind of concrete casting device - Google Patents

A kind of concrete casting device Download PDF

Info

Publication number
CN208950317U
CN208950317U CN201821441089.5U CN201821441089U CN208950317U CN 208950317 U CN208950317 U CN 208950317U CN 201821441089 U CN201821441089 U CN 201821441089U CN 208950317 U CN208950317 U CN 208950317U
Authority
CN
China
Prior art keywords
side panels
triangular side
partition panel
hold
concrete casting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821441089.5U
Other languages
Chinese (zh)
Inventor
蒋锦洋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Hong Construction Group Co Ltd
Original Assignee
Guangzhou Hong Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Hong Construction Group Co Ltd filed Critical Guangzhou Hong Construction Group Co Ltd
Priority to CN201821441089.5U priority Critical patent/CN208950317U/en
Application granted granted Critical
Publication of CN208950317U publication Critical patent/CN208950317U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model discloses a kind of concrete casting devices, including device noumenon and partition panel, device noumenon includes two pieces of triangular side panels, support rod, adjustable slant board and hold-down bars, triangular side panels are parallel to each other and connected by support rod, the lower edge of triangular side panels is equipped with the hook groove to match with hold-down bars, hold-down bars is set in hook groove, the top both ends of adjustable slant board are rotated with the upper bevel edge angle of two pieces of triangular side panels respectively to be connected, lower end is mutually leaned on hold-down bars, on the outside of the vertical right-angle side of two pieces of triangular side panels and the two sides cooperation of partition panel is equipped with the sliding equipment that partition panel can be made to realize upper and lower displacement, the lower end of partition panel is abutted with the lower end of adjustable slant board.The utility model avoids the case where pouring the later period and need to cutting any excess concrete, lost labor and material, accelerates construction speed, after partition, cleaning can also be discharged in remaining concrete in time in device noumenon, and it is convenient for disassembly and assembly to pour device, repeat and recycle.

Description

A kind of concrete casting device
Technical field
The utility model designs a kind of construction auxiliary device more particularly to a kind of concrete casting device.
Background technique
It is well known that should be set in the wall of multistory brick-and-concrete structure building to enhance the globality of building and stability Reinforced concrete structural column is set, and is connected with each layer collar tie beam, the space frame for capableing of bending resistance shearing resistance is formed, is to prevent house from falling A kind of effective measures collapsed.In the prior art, it in secondary structure constructional column casting concrete, needs to pour in capital Liu Kou mixed Solidifying native, in work progress, device nail carries out disturbing concrete in template, the concrete when concreting is completed, in device Hardening is formed together also with constructional column concrete, the concrete chisel removal again that constructional column is extra after demoulding.The conventional method In the case where constructional column is large number of, can not be reused with the device that Template nail goes out, and the later period need to cut any excess concrete, Artificial and material is not only wasted, also increases difficulty of construction, and not can guarantee quality.
For example, one kind disclosed " constructional column concreting funnel ", notification number in Chinese patent literature CN205296852U, including funnel body are provided with the rotor plate for completely cutting off constructional column and funnel body on funnel body, turn The driving rod piece of driving rotor plate is provided on movable plate, driving rod piece is downwardly extending, and the upper end of rotor plate is provided with sliding Axis, is provided with the slip hole with sliding axis connection on funnel body, and worker can push up cunning by driving rod piece when use It moves axis to slide in slip hole, keeps rotor plate mobile in the direction where funnel inner recess, recess can then be sealed, so that leakage Bucket ontology is separated with constructional column.Although the utility model can complete separating for funnel body and constructional column on ground, due to Funnel is poured when construction to be fixed on construction column template, pours funnel to reuse this, worker still needs to climb up construction Column will pour funnel and take off, also, concrete is more sticky, and concrete, which can partially remain in, when constructional column pours full pours funnel In, a large amount of concrete have been remained among rotor plate and recess at this time, so that rotor plate is sealed recess quite laborious, secondly, repeating benefit After remaining in the concrete formation hardening poured in funnel slip hole after the use of last time used time, rotor plate can be hindered in slip hole Interior sliding, and concrete is still remained in and is poured in funnel after having poured, and this makes when pouring funnel to construction personnel's disassembly At big inconvenience.
Summary of the invention
The utility model is that need the later period that need to cut in casting process extra in order to overcome conventional concrete to pour device Concrete, lost labor and material, and the problem of can not reuse, propose it is a kind of be equipped with partition panel and can separate pour Device and constructional column, and remain in the concrete casting device that the concrete poured in device is discharged in time after capable of having poured.
To achieve the goals above, the utility model uses following technical scheme:
A kind of concrete casting device of the utility model, including device noumenon and partition panel, described device ontology include Two pieces of triangular side panels, support rod, adjustable slant board and hold-down bars, the triangular side panels are vertical parallel mutually and pass through support rod Connection, the oblique edge of triangular side panels are equipped with the hook groove to match with hold-down bars, and the hold-down bars is set in hook groove, described The thickness of adjustable slant board less than the distance between two pieces of triangular side panels, the top both ends of adjustable slant board respectively with two pieces of triangles The upper bevel edge angle of side plate rotates connection, and bottom is mutually leaned on by self gravity with hold-down bars, and two pieces of triangular side panels are straight vertically The cooperation of on the outside of the arm of angle and two sides of partition panel is equipped with the sliding equipment that partition panel can be made to realize upper and lower displacement, the lower end of partition panel with The lower end of adjustable slant board abuts.
Its working principle is that device noumenon is fixed on construction column template first, the adjustable slant board in device noumenon makes It is fixed with the hold-down bars being located in the hook groove of triangular side panels lower end, then carries out smashing for concrete and pour, after smashing and pouring, dress It sets and has been also filled with concrete in ontology, the guide rod of partition panel is inserted into from top to bottom is located at triangular side panels right-angle side at this time In the guiding groove in outside, guiding groove plays the role of guidance partition path, and partition panel is inserted into after bottom abuts with adjustable slant board, The partition of the concrete and constructional column inner concrete in device noumenon is completed at this time.After the completion of partition, by removing hold-down bars, Since adjustable slant board upper end and the rotation of the upper bevel edge angle of triangular side panels connect, the concrete in device noumenon relies on itself at this time Gravity, squeeze adjustable slant board, fallen from the lower openings of device noumenon, construction personnel clears up immediately.
Preferably, when the partition panel lower end is abutted with the lower end of adjustable slant board, the sealing of container lower end, upper end opening.
When partition panel, which is inserted into bottom, to abut with the lower end of adjustable slant board, the lower mouth of container is completely sealed at this time, coagulation Soil will not be leaked out from the lower mouth of container.
Preferably, oblique edge is equipped with aperture on the triangular side panels, adjustable slant board top is equipped with matches with the opening The rotating rod of conjunction, the both ends of the rotating rod are inserted on triangular side panels in the aperture of oblique edge.
Rotating rod is inserted in the aperture that oblique edge is equipped on triangular side panels, is able to drive adjustable slant board and is freely revolved Turn.
Preferably, the vertical right-angle side two sides of triangular side panels are vertically to extension board is externally provided with, extension board is equipped with Screw hole.
Preferably, the slot mechanism includes the guiding groove being set on the outside of two pieces of vertical right-angle sides of triangular side panels and sets Guide rod in partition panel two sides, guide rod are inserted in guiding groove.
Cylindrical guide slot can preferably play the role of guidance positioning, and guide rod is bonded with the inner wall of guiding groove, makes Partition panel is fixedly more preferable, is not easy to loosen.
Due to being equipped with extension board on the outside of triangular side panels, and extension board is equipped with screw hole, and spiral shell can be passed through by pouring device Silk rotation is fixed on construction column template, also, when pouring completion, by unscrew screw can finishing device ontology tear open It unloads, it is convenient and efficient.
Preferably, two pieces of triangular side panels inboard, uprights are equipped with the vertical slot to match with partition panel.
Due to being equipped with vertical slot on the inside of triangular side panels, better concrete partition can be played in partition panel insertion vertical slot and is made With, and vertical slot can also further function as the effect in guidance partition path.
Preferably, the lower end of the partition panel is equipped with sharp sword structure.
Since concrete is more sticky, thickness is gradually reduced from top to bottom for the lower end of partition panel, when sharp sword structure is presented, energy Enough so that construction personnel more easily separates concrete.
Preferably, being connected between the triangular side panels by two support rods, the support rod is set to triangle in parallel The vertical right-angle side upper and lower ends of shape side plate.
Triangular side panels are connected using two support rods, so that device noumenon is more firm, also, due to two support rods Triangular side panels are respectively arranged on along vertical right-angle side upper and lower ends, so that support rod will not influence concrete in device noumenon It smashes and pours.
Preferably, the partition panel top is equipped with handle.
Partition panel top setting handle enables to construction personnel to use safety more convenient when partition panel.
Therefore, the utility model has the following beneficial effects: (1) avoids and pours the later period and need to cut any excess concrete, wave The case where taking artificial and material, accelerate construction speed;(2) after separating, remaining concrete can be arranged in time in device noumenon It clears up out;(3) it is convenient for disassembly and assembly to pour device, repeats and recycles.
Detailed description of the invention
Fig. 1 is a kind of structural schematic diagram of the utility model.
Fig. 2 is utility model device body construction schematic diagram.
Fig. 3 is the utility model partition panel structural schematic diagram.
Fig. 4 is utility model device ontology decomposition diagram.
Fig. 5 is utility model device ontology side view.
Fig. 6 is the utility model partition panel side view.
In figure: device noumenon 1, partition panel 2, triangular side panels 3, support rod 4, adjustable slant board 5, hold-down bars 6, guiding groove 7, Guide rod 8, extension board 9, screw hole 10, rotating rod 11, handle 12, hook groove 13, vertical slot 14, sharp sword structure 15.
Specific embodiment
The utility model is further described with specific embodiment with reference to the accompanying drawing.
Embodiment 1: as shown in Fig. 1,3,4,5,6, a kind of concrete casting device, including device noumenon 1 and partition panel 2, Described device ontology 1 includes two pieces of triangular side panels 3, support rod 4, adjustable slant board 5 and hold-down bars 6, and the triangular side panels 3 are mutually Parallel and connected by two support rods 4, support rod 4 is set to the vertical right-angle side upper and lower ends of triangular side panels 3 in parallel.Triangle The lower edge of shape side plate 3 is equipped with the hook groove 13 to match with hold-down bars 6, and hold-down bars 6 is set in hook groove 13.Triangular side panels 3 Along vertical right-angle side two sides vertically to extension board 9 is externally provided with, extension board is equipped with screw hole 10.Bevel edge angle on triangular side panels 3 Place is equipped with aperture, and 5 top of adjustable slant board is equipped with the rotating rod 11 cooperated with the opening, and the both ends of the rotating rod 11 are inserted in three Connection, 5 lower end of adjustable slant board and the hold-down bars 6 being located in hook groove 13 are rotated on angular side plate 3 in the aperture of oblique edge It mutually leans on, the thickness of adjustable slant board 5 is less than the distance between two pieces of triangular side panels 3, outside two pieces of triangular side panels, 3 right-angle side Side is equipped with vertical guiding groove 7, and the two sides of the partition panel 2 are equipped with the guide rod 8 to match with guiding groove 7, under partition panel 2 Sharp sword structure 15 is presented in end, and abuts with the following of adjustable slant board 5, and the upper end of partition panel 2 is equipped with handle 12.
When in use, the extension board 9 in device noumenon 1 is fixed by screws on construction column template first, device sheet Adjustable slant board 5 in body 1 is fixed using the hold-down bars 6 being located in 3 lower end hook groove 13 of triangular side panels, then carries out concrete Smash and pour, after smashing and pouring, concrete has been also filled in device noumenon 1, at this time from top to bottom by the guide rod 8 of partition panel 2 It is inserted into the guiding groove 7 being located on the outside of 3 right-angle side of triangular side panels, guiding groove 7 plays the role of guidance partition path, will be every Disconnected plate 2 is inserted into after bottom abuts with adjustable slant board 5, completes the concrete and constructional column inner concrete in device noumenon 1 at this time Partition.After the completion of partition, hold-down bars 6 is removed, the concrete in device noumenon 1 relies on the gravity of itself at this time, squeezes activity Inclined plate 5 is fallen from the lower openings of device noumenon 1, and construction personnel clears up immediately.After concrete emptying in device noumenon, Gu Determine stick 6 and be placed in again in 3 lower end hook groove 13 of triangular side panels to fix adjustable slant board 5, and the screw on extension board 9 is unscrewed, it is complete At the disassembly for pouring device, the reuse next time for pouring device is carried out.
Embodiment 2: it is erected as shown in Fig. 2, being additionally provided on the inside of two pieces of triangular side panels 3 with what the thickness of partition panel 2 matched Slot 14.When partition panel 2, which is inserted into, to be separated, partition panel 2 can be inserted into bottom and adjustable slant board 5 along the vertical slot 14 in triangular side panels 3 Lower end abut, compared with Example 1, vertical slot 14 can not only further function as the effect in guidance partition path, and due to reality The gap for applying 1 partition panel 2 of example and two pieces of 3 insides of triangular side panels will affect the partition effect of partition panel 2, therefore add vertical slot 14 Also preferably partition effect can be played.

Claims (9)

1. a kind of concrete casting device, which is characterized in that including device noumenon (1) and partition panel (2), described device ontology It (1) include two pieces of triangular side panels (3), support rod (4), adjustable slant board (5) and hold-down bars (6), the triangular side panels (3) are mutual Mutually vertical to connect in parallel and by support rod (4), the oblique edge of triangular side panels (3) is equipped with to match with hold-down bars (6) Hook groove (13), the hold-down bars (6) be set to hook groove (13) in, less than two pieces triangle sides of thickness of the adjustable slant board (5) The spacing of plate (3), the top both ends of adjustable slant board (5) are rotated with the upper bevel edge angle of two pieces of triangular side panels respectively to be connected, bottom It is mutually leaned on by self gravity and hold-down bars (6), the vertical right-angle side outside of two pieces of triangular side panels (3) and partition panel (2) Two sides cooperation is equipped with the sliding equipment that partition panel can be made to realize upper and lower displacement, under the lower end of partition panel (2) and adjustable slant board (5) End abuts.
2. a kind of concrete casting device according to claim 1, which is characterized in that partition panel (2) lower end and work When the lower end of dynamic inclined plate (5) abuts, the sealing of device lower end, upper end opening.
3. a kind of concrete casting device according to claim 1, which is characterized in that on the triangular side panels (3) tiltedly Edge is equipped with aperture, and adjustable slant board (5) top is equipped with the rotating rod (11) that cooperates with the opening, and the two of the rotating rod (11) End is inserted on triangular side panels (3) in the aperture of oblique edge.
4. a kind of concrete casting device according to claim 1 or 3, which is characterized in that the triangular side panels (3) are perpendicular Vertically to being externally provided with extension board (9), extension board is equipped with screw hole (10) for straight right-angle side two sides.
5. a kind of concrete casting device according to claim 1, which is characterized in that the sliding equipment includes being set to two Guiding groove (7) on the outside of the vertical right-angle side of block triangular side panels (3) and the guide rod (8) set on partition panel (2) two sides, guide rod (8) it is inserted in guiding groove (7).
6. a kind of concrete casting device according to claim 1 or 5, which is characterized in that two pieces of triangular side panels (3) inside is equipped with the vertical slot (14) to match with the thickness of partition panel (2).
7. a kind of concrete casting device according to claim 1 or 3, which is characterized in that the lower end of the partition panel (2) Equipped with sharp sword structure (15).
8. a kind of concrete casting device according to claim 1, which is characterized in that between the triangular side panels (3) It is connected by two support rods (4), the support rod (4) is set to triangular side panels (3) two above and below vertical right-angle side in parallel End.
9. a kind of concrete casting device according to claim 7, which is characterized in that partition panel (2) upper end is equipped with Handle (12).
CN201821441089.5U 2018-09-04 2018-09-04 A kind of concrete casting device Active CN208950317U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821441089.5U CN208950317U (en) 2018-09-04 2018-09-04 A kind of concrete casting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821441089.5U CN208950317U (en) 2018-09-04 2018-09-04 A kind of concrete casting device

Publications (1)

Publication Number Publication Date
CN208950317U true CN208950317U (en) 2019-06-07

Family

ID=66736856

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821441089.5U Active CN208950317U (en) 2018-09-04 2018-09-04 A kind of concrete casting device

Country Status (1)

Country Link
CN (1) CN208950317U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110397280A (en) * 2019-07-30 2019-11-01 中建城市建设发展有限公司 Pour funnel
CN112431417A (en) * 2019-08-25 2021-03-02 河北建设集团股份有限公司 Constructional column concrete design pouring device
CN113293931A (en) * 2021-06-04 2021-08-24 中冶建工集团有限公司 Masonry wall constructional column construction method
CN115056325A (en) * 2022-06-30 2022-09-16 中建五局华东建设有限公司 Secondary structure pouring mold

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110397280A (en) * 2019-07-30 2019-11-01 中建城市建设发展有限公司 Pour funnel
CN112431417A (en) * 2019-08-25 2021-03-02 河北建设集团股份有限公司 Constructional column concrete design pouring device
CN113293931A (en) * 2021-06-04 2021-08-24 中冶建工集团有限公司 Masonry wall constructional column construction method
CN115056325A (en) * 2022-06-30 2022-09-16 中建五局华东建设有限公司 Secondary structure pouring mold

Similar Documents

Publication Publication Date Title
CN208950317U (en) A kind of concrete casting device
CN105500515B (en) Concrete block forming device
CN103485537A (en) Construction method and structure of embedded reinforcement of super high-rise horizontal secondary structure
CN206016251U (en) A kind of elevator side wall Construction Support template
CN114150844A (en) Wall thin-layer plastering method
CN210658433U (en) Upward-inclined retaining wall turnover construction formwork
CN207484986U (en) A kind of construction floating tool
US3016595A (en) Movable arc form and building method
CN216075124U (en) Concrete pouring device for piling foundation piles
CN116572365A (en) Construction template and construction method of assembled constructional column
CN217439572U (en) A concrete placement equipment for building engineering construction
CN109653769A (en) The tamping agency and method of side wall concrete during a kind of Tunnel Second Lining mould is built
CN114083683A (en) Concrete production equipment and production method
JP5730826B2 (en) Construction method of soil cement column easy to remove
CN110318538A (en) Constructional column pours the loading hopper and constructional column casting method of mold
CN207290398U (en) A kind of building structural post molding machine
CN218493083U (en) Hang adjustable template support instrument in hole fast
CN220150862U (en) Template reinforcing apparatus of outside composite wall
CN206180488U (en) Cable pit moving die carrier
CN110271079A (en) A kind of build concrete ramming device
CN207582960U (en) Water stop screw for building outer wall
CN212773621U (en) Concrete breaker for building engineering
CN108824363A (en) A kind of ant proof protecting slope of dam brick bottom cement filling device
CN209556353U (en) A kind of hollow wall on site construction template
CN208105519U (en) The anti-wallboard for pouring leakage

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant