CN208916169U - Feed device for civil engineering building site - Google Patents

Feed device for civil engineering building site Download PDF

Info

Publication number
CN208916169U
CN208916169U CN201821731393.3U CN201821731393U CN208916169U CN 208916169 U CN208916169 U CN 208916169U CN 201821731393 U CN201821731393 U CN 201821731393U CN 208916169 U CN208916169 U CN 208916169U
Authority
CN
China
Prior art keywords
blanking tube
chute feeder
shaft
motor
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821731393.3U
Other languages
Chinese (zh)
Inventor
江顺武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Mincheng Construction Engineering Co Ltd
Original Assignee
Guangzhou Mincheng Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Mincheng Construction Engineering Co Ltd filed Critical Guangzhou Mincheng Construction Engineering Co Ltd
Priority to CN201821731393.3U priority Critical patent/CN208916169U/en
Application granted granted Critical
Publication of CN208916169U publication Critical patent/CN208916169U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Chutes (AREA)

Abstract

The utility model discloses the feed device for civil engineering building site, including chute feeder, blanking tube is arranged in the bottom surface of chute feeder, and end cap is arranged in the top of blanking tube;The bottom surface annular of blanking tube is evenly distributed with four first through hole, and one end of guide pipe is fixed on blanking tube bottom, and four conveyer belts are located at the underface of four one end of guide pipe far from blanking tube;Blanking tube bottom is also equipped with the first motor on the outside of blanking tube, and the output shaft of first motor is fixedly connected with turntable;One the second through-hole is set on turntable;The least significant end of chute feeder is left and right two parts by partition bifurcated, further includes the shaft being arranged on chute feeder, shaft is equal with the distance between chute feeder two sides side wall, and guide plate is fixedly connected in shaft;It further include the baffle being removably mounted in chute feeder.For the utility model to solve the problems, such as material transfer labor intensive in the prior art and inconvenient adjustment conveying direction, realizing reduces manpower consumption, the purpose convenient for being transported through to different directions.

Description

Feed device for civil engineering building site
Technical field
The utility model relates to the realm of building construction, and in particular to the feed device for civil engineering building site.
Background technique
The workload that the earthwork refers to shoveling, bankets, transports, is usually all calculated with cubic meter.Earth work is architectural engineering One of major project in construction, digging watchman's wooden clapper including all native (stone) sides are filled, transport and are drained, precipitation etc..Building work Cheng Zhong, earth and rock works have: levelling of the land, road excavation, civil air defense constructions and installations is excavated, terrace bankets, and roadbed filling and foundation pit return It fills out.Reasonable arrangement construction plan is wanted, tries not to be arranged in rainy season, while in order to reduce earth and rock works operating expenses, implementing It does not account for or accounts for less farmland and arable land and be conducive to the principle built up fields with changing, to make the rational allocation scheme of the cubic metre of earth and stone, plan as a whole It arranges.In the prior art, a large amount of earthwork and required production material caused by civil construction generally all by cart or The equipment such as fork truck are transported through, labor intensive inefficiency, while inconvenient quickly adjustment transhipment direction.
Utility model content
The purpose of this utility model is to provide the feed devices for civil engineering building site, are turned with solving material in the prior art The problem of transporting labor intensive and inconvenient adjustment conveying direction, realizing reduces manpower consumption, convenient for what is be transported through to different directions Purpose.
The utility model is achieved through the following technical solutions:
For the feed device in civil engineering building site, including inclined chute feeder from top to bottom, the bottom surface setting of the chute feeder Blanking tube, the blanking tube are connected to chute feeder, and end cap is arranged in the top of blanking tube;The axis vertical of blanking tube, blanking tube Bottom surface annular is evenly distributed with four first through hole, and four first through hole are respectively connected to a guide pipe, and one end of the guide pipe is fixed It further include four towards different conveyer belts, four conveyer belts are located at four guide pipes far from blanking in blanking tube bottom The underface of one end of cylinder;The blanking tube bottom is also equipped with the first motor on the outside of blanking tube, the first motor Output shaft pass through the bottom surface of blanking tube, be fixedly connected with the turntable inside the blanking tube, under the outer diameter of the turntable is equal to The internal diameter of barrel, the output shaft and turntable, blanking tube of first motor are coaxial;One the second through-hole is set on the turntable, when When turntable rotates, second through-hole is successively Chong Die with four first through hole;The least significant end of the chute feeder passes through partition bifurcated For left and right two parts, it further includes setting that wherein the partition is fixed on chute feeder, partition extends along the long axis direction of chute feeder Shaft on chute feeder, the shaft are located at the one end of partition upward, between shaft and chute feeder two sides side wall away from From equal, further include the second motor for driving the shaft, guide plate is fixedly connected in the shaft, the guide plate Length is equal to the distance between shaft and chute feeder side side wall;It further include the baffle being removably mounted in chute feeder, it is described Baffle is between shaft and blanking tube.
Aiming at the problem that material transfer labor intensive in the prior art and inconvenient adjustment conveying direction, the utility model proposes For the feed device in civil engineering building site, the present apparatus includes inclined chute feeder from top to bottom, for the earthwork or material to be poured into it In, so that the earthwork or material is glided under the effect of gravity along chute feeder, until sliding to blanking tube.Wherein, end cap and blanking Connection type between cylinder top is such as threadedly coupled, clamping, bolt using the connection type of any lid in the prior art Connection etc., is not limited thereto.Since end cap is arranged in the top of blanking tube.Therefore when opening end cap, earthwork material etc. It can then enter in blanking tube, fall along blanking tube, until falling on turntable.Turntable is driven by first motor, therefore is passed through First through hole needed for first motor controls the second through-hole face on turntable, the earthwork at this time can be from the second through-hole on turntable In pass through, and by corresponding first through hole enter corresponding guide pipe in, along corresponding guide pipe slide, thus from guiding It manages one end far from blanking tube to drop out, finally falls on corresponding conveyer belt, the earthwork is sent to required side by conveyer belt To.Wherein, when turntable rotates, second through-hole is successively Chong Die with four first through hole, therefore regardless of turntable rotates, The center of circle that the center of circle of second through-hole should all be located at four first through hole is formed by circle.Conveyer belt in the utility model is Any conveyer belt in the prior art, such as common crawler belt belt conveyer belt.Since four conveyer belts directions are different, because This can be centered on blanking tube point, towards the arrangement conveyer belt of divergent shape everywhere, by the earthwork or material transmission to difference Direction.When the direction of transfer of the earthwork or material need to be adjusted, it is only necessary to by first motor driving turntable rotation, so that on turntable Second through-hole goes to the first through hole for being aligned required direction, and the adjustment to the earthwork or material transfer conveying direction, pole can be completed Big reduces manpower consumption, improves transfer efficiency, while quite convenient for being transported through to different directions.It further include detachable The baffle being mounted in chute feeder, the baffle is between shaft and blanking tube, will therefore when stating transportation route in use Baffle is mounted in chute feeder, significantly more efficient material can be avoided to glide along chute feeder, it is ensured that the earthwork or material all enter In blanking tube.When transporting material without using blanking tube, the end cap at the top of blanking tube is closed, the baffle is unloaded, by baffle It is taken out out of chute feeder, the earthwork at this time or material can slide directly down along chute feeder.Pass through the second motor-driven rotatable shaft Rotation, so that guide plate be driven to be rotated with shaft, the length of guide plate is equal between shaft and chute feeder side side wall Distance, therefore guide plate can block the side for being branched into two-part chute feeder, as guide plate shelters from feeding Opening position of the slot position on the right side of partition, material can only just glide from the chute feeder on the left of partition at this time;Similarly, such as guide plate The opening position that chute feeder is located on the left of partition is sheltered from, material can only just glide from the chute feeder on the right side of partition at this time, from And pass through the common cooperation of partition, the second motor, shaft, guide plate, so that the material directly to glide along chute feeder, also can It glides in the least significant end selection both direction of chute feeder, to also can be realized by chute feeder defeated to the difference of material It send, further increases transhipment of the utility model for material, conveying capacity, greatly improve the applicable model of the utility model It encloses.
Preferably, the first through hole, the aperture of the second through-hole are equal;Four guide pipes are in divergent shape in blanking tube bottom Distribution.Convenient for the complete face between first through hole and the second through-hole, fall convenient for the without hindrance extension of the earthwork quickly through turntable.
Preferably, the conveyer belt is feed belt.
Further, the shaft passes through the bottom of chute feeder, and second motor is fixedly mounted on the top of partition.Turn Axis passes through the bottom of chute feeder, so that pivot structure is stablized, can also ensure that the stabilization of shaft in rotation process.And the second motor It is fixedly mounted on the top of partition, and partition is fixed on chute feeder, therefore can also be provided by partition for the second motor Station is installed, is easily installed so that the second motor is also stable.
Preferably, the guide pipe from the one end being connected with blanking tube, to far from blanking tube one end, incline gradually downward Tiltedly.Convenient for making movement of the earthwork in the utility model more rapid efficient using gravity.
Preferably, the first motor, the second motor are stepper motor;The first motor is bolted on down The bottom of barrel.
Preferably, the baffle is limited by being fixed on the block of chute feeder two sides side wall.Chute feeder two sides side wall Two blocks of respectively two blocks of setting, every side side wall are distributed up and down.It is totally four blocks by two sides, recycles feeding The gravity that slot originally tilts down enables baffle to be directly placed in chute feeder and obstructs to groove body, while directly taking The effect for removing baffle can be realized in baffle out.
The utility model compared with prior art, has the following advantages and benefits:
1, the utility model is used for the feed device in civil engineering building site, and when opening end cap, the earthwork or material are in gravity Under glide along chute feeder, until sliding at blanking tube, the earthwork or material enter in blanking tube, fall along blanking tube, directly To falling on turntable.By first motor control turntable on the second through-hole face needed for first through hole, the earthwork at this time or Material can pass through from the second through-hole on turntable, and be entered in corresponding guide pipe by corresponding first through hole, along Corresponding guide pipe sliding, to drop out from guide pipe far from one end of blanking tube, finally falls on corresponding conveyer belt, by Conveyer belt is by material transmission to required direction.When the direction of transfer of material need to be adjusted, it is only necessary to drive turntable by first motor Rotation can be completed so that the second through-hole on turntable goes to the first through hole in direction needed for being aligned to material transfer conveying side To adjustment, greatly reduce manpower consumption, improve transfer efficiency, while turning quite convenient for carrying out the earthwork to different directions Fortune.
2, when transporting material without using blanking tube, the end cap at the top of blanking tube is closed, the baffle is unloaded, by baffle It is taken out out of chute feeder, the earthwork at this time or material can slide directly down along chute feeder.Pass through the second motor-driven rotatable shaft Rotation, so that guide plate be driven to be rotated with shaft, the length of guide plate is equal between shaft and chute feeder side side wall Distance, therefore guide plate can block the side for being branched into two-part chute feeder, as guide plate shelters from feeding Opening position of the slot position on the right side of partition, material can only just glide from the chute feeder on the left of partition at this time;Similarly, such as guide plate The opening position that chute feeder is located on the left of partition is sheltered from, material can only just glide from the chute feeder on the right side of partition at this time, from And pass through the common cooperation of partition, the second motor, shaft, guide plate, so that the material directly to glide along chute feeder, also can It glides in the least significant end selection both direction of chute feeder, to also can be realized by chute feeder defeated to the difference of material It send, further increases transhipment of the utility model for material, conveying capacity, greatly improve the applicable model of the utility model It encloses.
Detailed description of the invention
Attached drawing described herein is used to provide to further understand the utility model embodiment, constitutes the one of the application Part does not constitute the restriction to the utility model embodiment.In the accompanying drawings:
Fig. 1 is the structural schematic diagram of the utility model specific embodiment;
Fig. 2 is the cross-sectional view of the utility model specific embodiment;
Fig. 3 is the bottom view of blanking tube in the utility model specific embodiment;
Fig. 4 is the top view of the utility model specific embodiment turntable.
Label and corresponding parts title in attached drawing:
1- chute feeder, 2- blanking tube, 3- first through hole, 4- guide pipe, 5- conveyer belt, 6- first motor, 7- turntable, 8- Two through-holes, 9- partition, 10- shaft, the second motor of 11-, 12- guide plate, 13- baffle, 14- block, 15- end cap.
Specific embodiment
For the purpose of this utility model, technical solution and advantage is more clearly understood, below with reference to embodiment and attached drawing, The utility model is described in further detail, and the exemplary embodiment and its explanation of the utility model are only used for explaining this Utility model is not intended to limit the scope of the present invention.
Embodiment 1:
Feed device for civil engineering building site as shown in Figures 1 to 4, including inclined chute feeder 1 from top to bottom, it is described Blanking tube 2 is arranged in the bottom surface of chute feeder 1, and the blanking tube 2 is connected to chute feeder 1, and end cap 15 is arranged in the top of blanking tube 2;Under The axis vertical of barrel 2, the bottom surface annular of blanking tube 2 are evenly distributed with four first through hole 3, and four first through hole 3 are respectively oriented to one Pipe 4 is connected to, and one end of the guide pipe 4 is fixed on 2 bottom of blanking tube, further includes four towards different conveyer belts 5, four pass The underface for sending band 5 to be located at four one end of guide pipe 4 far from blanking tube 2;2 bottom of blanking tube, which is also equipped with, to be located at The first motor 6 in 2 outside of blanking tube, the output shaft of the first motor 6 pass through the bottom surface of blanking tube 2 and are located in blanking tube 2 The turntable 7 in portion is fixedly connected, and the outer diameter of the turntable 7 is equal to the internal diameter of blanking tube 2, the output shaft and turntable 7 of first motor 6, Blanking tube 2 is coaxial;On the turntable 7 be arranged second through-hole 8, when turntable 7 rotate when, second through-hole 8 successively with Four first through hole 3 are overlapped;The least significant end of the chute feeder 1 is left and right two parts by 9 bifurcated of partition, wherein the partition 9 It is fixed on chute feeder 1, it further includes the shaft 10 being arranged on chute feeder 1, institute that partition 9 extends along the long axis direction of chute feeder 1 It states shaft 10 and is located at the one end of partition 9 upward, shaft 10 is equal with the distance between 1 two sides side wall of chute feeder, further includes For driving the second motor 11 of the shaft 10, guide plate 12, the length of the guide plate 12 are fixedly connected in the shaft 10 Degree is equal to the distance between shaft 10 and 1 side side wall of chute feeder;It further include the baffle 13 being removably mounted in chute feeder 1, The baffle 13 is between shaft 10 and blanking tube 2.
Embodiment 2:
Feed device for civil engineering building site as shown in Figures 1 to 4, on the basis of embodiment 1, the first through hole 3, the aperture of the second through-hole 8 is equal;Four guide pipes 4 are distributed in 2 bottom of blanking tube in divergent shape.The shaft 10 passes through feeding The bottom of slot 1, second motor 11 are fixedly mounted on the top of partition 9.The guide pipe 4 is from one to be connected with blanking tube 2 It holds, to one end far from blanking tube 2, tilts gradually downward.The first motor 6, the second motor 11 are stepper motor;It is described First motor 6 is bolted on the bottom of blanking tube 2.The baffle 13 is by being fixed on the gear of 1 two sides side wall of chute feeder Block 14 is limited.Two blocks 14 are respectively arranged in 1 two sides side wall of chute feeder, and about 14 two blocks of every side side wall are distributed.
Above-described specific embodiment, to the purpose of this utility model, technical scheme and beneficial effects carried out into One step is described in detail, it should be understood that being not used to limit the foregoing is merely specific embodiment of the present utility model Determine the protection scope of the utility model, within the spirit and principle of the utility model, any modification for being made equally is replaced It changes, improve, should be included within the scope of protection of this utility model.

Claims (7)

1. being used for the feed device in civil engineering building site, which is characterized in that including inclined chute feeder (1) from top to bottom, the feeding Blanking tube (2) are arranged in the bottom surface of slot (1), and the blanking tube (2) is connected to chute feeder (1), and end cap is arranged in the top of blanking tube (2) (15);The bottom surface annular of the axis vertical of blanking tube (2), blanking tube (2) is evenly distributed with four first through hole (3), four first through hole (3) it is respectively connected to a guide pipe (4), one end of the guide pipe (4) is fixed on blanking tube (2) bottom, further includes four courts To different conveyer belts (5), four conveyer belts (5) be located at four guide pipes (4) far from blanking tube (2) one end just under Side;Blanking tube (2) bottom is also equipped with the first motor (6) on the outside of blanking tube (2), the first motor (6) Output shaft passes through the bottom surface of blanking tube (2), the turntable (7) internal with blanking tube (2) are located at is fixedly connected, the turntable (7) Outer diameter is equal to the internal diameter of blanking tube (2), and the output shaft and turntable (7), blanking tube (2) of first motor (6) are coaxial;The turntable (7) on be arranged second through-hole (8), when turntable (7) rotation when, second through-hole (8) successively with four first through hole (3) Overlapping;The least significant end of the chute feeder (1) is left and right two parts by partition (9) bifurcated, wherein the partition (9) is fixed on and send On hopper (1), partition (9) extends along the long axis direction of chute feeder (1), further includes the shaft (10) being arranged on chute feeder (1), The shaft (10) is located at the one end of partition (9) upward, the distance between shaft (10) and chute feeder (1) two sides side wall phase Deng, further include the second motor (11) for driving the shaft (10), be fixedly connected on the shaft (10) guide plate (12), The length of the guide plate (12) is equal to the distance between shaft (10) and chute feeder (1) side side wall;It further include detachably pacifying Baffle (13) in chute feeder (1), the baffle (13) are located between shaft (10) and blanking tube (2).
2. the feed device according to claim 1 for civil engineering building site, which is characterized in that the first through hole (3), The aperture of two through-holes (8) is equal;Four guide pipes (4) are distributed in blanking tube (2) bottom in divergent shape.
3. the feed device according to claim 1 for civil engineering building site, which is characterized in that the shaft (10) passes through and send The bottom of hopper (1), second motor (11) are fixedly mounted on the top of partition (9).
4. the feed device according to claim 1 for civil engineering building site, which is characterized in that the guide pipe (4) from One end of one end, extremely separate blanking tube (2) that blanking tube (2) is connected, tilts gradually downward.
5. the feed device according to claim 1 for civil engineering building site, which is characterized in that the first motor (6), Two motors (11) are stepper motor;The first motor (6) is bolted on the bottom of blanking tube (2).
6. the feed device according to claim 1 for civil engineering building site, which is characterized in that the baffle (13) passes through solid The block (14) for being scheduled on chute feeder (1) two sides side wall is limited.
7. the feed device according to claim 6 for civil engineering building site, which is characterized in that chute feeder (1) two sides side wall Respectively two blocks (14) of setting, two blocks (14) of every side side wall are distributed up and down.
CN201821731393.3U 2018-10-23 2018-10-23 Feed device for civil engineering building site Active CN208916169U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821731393.3U CN208916169U (en) 2018-10-23 2018-10-23 Feed device for civil engineering building site

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821731393.3U CN208916169U (en) 2018-10-23 2018-10-23 Feed device for civil engineering building site

Publications (1)

Publication Number Publication Date
CN208916169U true CN208916169U (en) 2019-05-31

Family

ID=66710476

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821731393.3U Active CN208916169U (en) 2018-10-23 2018-10-23 Feed device for civil engineering building site

Country Status (1)

Country Link
CN (1) CN208916169U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112849946A (en) * 2021-03-02 2021-05-28 马骁 Embedded scraper conveyor feeding mechanism and embedded scraper conveyor thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112849946A (en) * 2021-03-02 2021-05-28 马骁 Embedded scraper conveyor feeding mechanism and embedded scraper conveyor thereof

Similar Documents

Publication Publication Date Title
CN106385899A (en) Rapid solid fertilizer applying apparatus used for gardens
CN209848991U (en) Environment-friendly building solid waste treatment device
CN208916169U (en) Feed device for civil engineering building site
CN203247633U (en) Grooving machine and grooving main machine unit thereof
CN208916167U (en) A kind of cubic metre of earth of transfer device
CN205529829U (en) A automatic filleting machine of walking for curb
CN204297514U (en) A kind of bucket elevator
CN106368715A (en) Deslagging method for construction during assembling period of double-shield TBM
CN203570324U (en) Traction self-propelled concrete sprayer with spraying nozzle capable of automatically rotating
KR100744193B1 (en) Portable concrete manufacturing apparatus
CN208516511U (en) A kind of architectural engineering dumper
CN202239209U (en) Automatic production system for gooseneck tunnel of container
CN204238212U (en) A kind of construction equipment of column type series large diameter pile
CN202250102U (en) Material supply device of pulp shooting machine
CN213137306U (en) Multi-functional landscape engineering construction is with cement conveyer
CN209179772U (en) Tunneling boring chain type tunnels assembled development machine
CN102392657A (en) Feeder for shotcrete machines
CN214741453U (en) Be used for collecting space area to administer portable sand ware of throwing
CN214242993U (en) Energy-concerving and environment-protective type cement stabilization rubble conveyer
CN219342724U (en) Backfill road bed with construction waste processing apparatus
CN206765103U (en) A kind of underground project dug underground concrete mixing plant
CN107386080B (en) It is a kind of to collect automatically, repair and use equipment
CN209353343U (en) Concrete shotcrete machine
CN205412721U (en) Embankment dam impervious core gravel earth material fusion device
CN213173251U (en) Construction of water drainage tank of anti-spillage pollution is with floating device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant