CN208899979U - A kind of provisional protection column of the civil engineering convenient for assembly - Google Patents

A kind of provisional protection column of the civil engineering convenient for assembly Download PDF

Info

Publication number
CN208899979U
CN208899979U CN201821543652.XU CN201821543652U CN208899979U CN 208899979 U CN208899979 U CN 208899979U CN 201821543652 U CN201821543652 U CN 201821543652U CN 208899979 U CN208899979 U CN 208899979U
Authority
CN
China
Prior art keywords
welded
protection column
civil engineering
provisional protection
pedestal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821543652.XU
Other languages
Chinese (zh)
Inventor
李媛媛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhengzhou University
Original Assignee
Zhengzhou University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhengzhou University filed Critical Zhengzhou University
Priority to CN201821543652.XU priority Critical patent/CN208899979U/en
Application granted granted Critical
Publication of CN208899979U publication Critical patent/CN208899979U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model discloses a kind of civil engineerings to use convenient for assembled provisional protection column, including pedestal, the side of the pedestal offers placing groove, and tool box has been bolted in the other side of pedestal, deck is welded at the top of the pedestal, and card slot is provided at the top of deck, the inside of the card slot is plugged with mounting base, and rectangle frame is welded at the top of mounting base, the interior welds of the rectangle frame have guardrail web plate, the side of the rectangle frame is welded with two first connecting rods, and the other end of first connecting rod is welded with the link block of U-shaped structure, the other side of the rectangle frame is welded with two the second connecting rods.In the utility model, staff can pull pedestal that provisional protection column is quickly moved to the scene of building, it brings great convenience for staff, the inside of card slot is plugged in using mounting base, the guardrail that rectangle frame and guardrail web plate are constituted is holded up, the quick-assembling on provisional protection column is completed, it is easy to use.

Description

A kind of provisional protection column of the civil engineering convenient for assembly
Technical field
The utility model relates to technical field of civil engineering more particularly to a kind of civil engineering to use convenient for the interim anti-of assembly Guardrail.
Background technique
Civil engineering is to build the general designation of the science and technology of all kinds of land engineering facilities.It had both referred to applied material, had set The technical activities such as standby and the exploration, design, construction, maintenance, the maintenance that are carried out, also refer to the object of engineering construction.It is built in ground It is upper or underground, land, be directly or indirectly human lives, production, military affairs, Scientific Research Service various job facilities.
In civil engineering construction, construction personnel is usually existing in civil engineering construction in order to guarantee being normally carried out for engineering Guardrail is built in field, for civil engineering construction scene to be isolated, in some civil engineering places for needing temporary repair, builds interim Guardrail, for the isolating and protecting of short time, still, it is long that existing guardrail builds the time, meanwhile, guardrail material is not easy to carry, and is Civil engineering construction causes negative effect, causes the construction time long.
Utility model content
Purpose of the utility model is to solve disadvantages existing in the prior art, and a kind of civil engineering proposed is used Convenient for assembled provisional protection column.
To achieve the goals above, the utility model adopts the technical scheme that
A kind of civil engineering, which is used, offers placement convenient for assembled provisional protection column, including pedestal, the side of the pedestal Slot, and tool box has been bolted in the other side of pedestal, deck is welded at the top of the pedestal, and set at the top of deck Be equipped with card slot, the inside of the card slot is plugged with mounting base, and rectangle frame is welded at the top of mounting base, the rectangle frame it is interior Portion is welded with guardrail web plate, and the side of the rectangle frame is welded with two first connecting rods, and the other end weldering of first connecting rod It is connected to the link block of U-shaped structure, the other side of the rectangle frame is welded with two the second connecting rods, and the second connecting rod is another End is hinged with inserted block, and inserted block is plugged in the inside of link block, and the two sides inner wall of the card slot offers rectangular straight slot, and two Fixing bolt is plugged between rectangular straight slot, one end of the fixing bolt is welded with magnetic links.
Preferably, the inside of the link block is plugged with coupling bar, and circular through hole is offered at the top of inserted block.
Preferably, the universal wheel with service brake is bolted in the bottom four corners of the pedestal.
Preferably, there are two support plates for the bottom part down setting of the pedestal, and the bottom of two support plates is welded with Placement plate.
Preferably, the two sides of the pedestal are opened up there are two limiting slot, and U-shaped structure is offered at the top of support plate The groove of groove, support plate is plugged in the inside of limiting slot.
Preferably, the side of the mounting base offers circular perforations, and the interlude of fixing bolt is plugged in circular perforations Inside.
Preferably, case lid is hinged at the top of the tool box, and the other end of case lid is steady by hasp lock and tool box It is solidly connected.
The utility model has the following beneficial effects:
1, the utility model proposes civil engineering provisional protection column, by being provided with the pedestal with universal wheel, in the spare time When setting, the guardrail folding that rectangle frame and guardrail web plate are constituted is placed on inside placing groove, staff is allowed to pull bottom Provisional protection column is quickly moved to the scene of building by seat, is brought great convenience for staff.
2, the utility model proposes civil engineering provisional protection column pedestal is lifted when building, by support plate Groove is plugged in the inside of limiting slot, and the guardrail that rectangle frame and guardrail web plate are constituted is unfolded, is inserted using mounting base by firm banking It is connected to the inside of card slot, the guardrail that rectangle frame and guardrail web plate are constituted is holded up, the quick-assembling on provisional protection column is completed, is used It is simple and convenient.
3, the utility model proposes civil engineering provisional protection column, after the completion of provisional protection column is built, Ke Yi Fixing bolt and coupling bar are taken out in the inside in tool box, are fixed adjacent guardrail by inserted block and link block using coupling bar, benefit The phenomenon that fixing mounting base and deck with fixing bolt, provisional protection column is avoided to shake is improved civil engineering and is used convenient for spelling The stability on the provisional protection column of dress.
Detailed description of the invention
Fig. 1 be the utility model proposes a kind of sectional structure signal of civil engineering convenient for assembled provisional protection column Figure;
Fig. 2 be the utility model proposes a kind of side view structure signal of civil engineering convenient for assembled provisional protection column Figure;
Fig. 3 be the utility model proposes a kind of civil engineering use convenient for the link block and inserted block on assembled provisional protection column Structural schematic diagram.
In figure: 1 placement plate, 2 support plates, 3 limiting slots, 4 pedestals, 5 rectangle frames, 6 guardrail web plates, 7 first connecting rods, 8 connect Connect block, 9 coupling bars, 10 inserted blocks, 11 second connecting rods, 12 circular perforations, 13 mounting bases, 14 fixing bolts, 15 rectangular straight slot, 16 cards Slot, 17 decks, 18 tool boxes, 19 placing grooves, 20 universal wheels, 21 magnetic links.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.
Referring to Fig.1-3, a kind of civil engineering is used opens convenient for assembled provisional protection column, including pedestal 4, the side of pedestal 4 Placing groove 19 equipped with rectangular configuration, and tool box 18, the top welding of pedestal 4 has been bolted in the other side of pedestal 4 There is deck 17, and the top of deck 17 is provided with the card slot 16 that section is inverted T-type structure, the inside of card slot 16 is plugged with four to eight A mounting base 13 equidistantly distributed, and the top of mounting base 13 is welded with rectangle frame 5, the interior welds of rectangle frame 5 have guardrail Web plate 6, the side of rectangle frame 5 is welded with two first connecting rods 7, and the other end of first connecting rod 7 is welded with U-shaped structure Link block 8, the other side of rectangle frame 5 are welded with two the second connecting rods 11, and the other end of the second connecting rod 11 be hinged with it is slotting Block 10, inserted block 10 are plugged in the inside of link block 8, and the two sides inner wall of card slot 16 offers rectangular straight slot 15, and two rectangles Four to eight fixing bolts equidistantly distributed 14 are plugged between through slot 15, one end of fixing bolt 14 is welded with magnetic links 21, and Magnetic links 21 are connect with 17 magnetic absorption of deck.
In the utility model, the inside of link block 8 is plugged with coupling bar 9, and the top of inserted block 10 offers and coupling bar 9 The universal wheel 20 with service brake, the bottom of pedestal 4 is bolted in the circular through hole to match, the bottom four corners of pedestal 4 There are two the support plates 2 being vertically arranged for lower section setting, and the bottom of two support plates 2 is welded and horizontally disposed placement plate 1, The two sides of pedestal 4 open up that there are two the limiting slots 3 that are vertically arranged, and the top of support plate 2 offers the groove of U-shaped structure, The groove of support plate 2 is plugged in the inside of limiting slot 3, and the side of mounting base 13 offers circular perforations 12, and fixing bolt 14 Interlude is plugged in the inside of circular perforations 12, and the top in tool box 18 is hinged with case lid, and the other end of case lid passes through hasp Lock is bonded with tool box 18.
Working principle: by being provided with the pedestal 4 with universal wheel 20, when idle, by 6 structure of rectangle frame 5 and guardrail web plate At guardrail folding be placed on inside placing groove 19, allow staff that pedestal 4 is pulled quickly to move on provisional protection column The scene of building is moved, when building, pedestal 4 is lifted, the groove of support plate 2 is plugged in the inside of limiting slot 3, firm banking 4, the guardrail that rectangle frame 5 and guardrail web plate 6 are constituted is unfolded, and the inside of card slot 16 is plugged in using mounting base 13, by rectangle frame 5 The guardrail constituted with guardrail web plate 6 is holded up, and the quick-assembling for completing provisional protection column can after the completion of provisional protection column is built To take out fixing bolt 14 and coupling bar 9 in the inside in tool box 18, adjacent guardrail by inserted block 10 and is connected using coupling bar 9 The phenomenon that block 8 is fixed, using fixing bolt 14 fixes, provisional protection column is avoided to shake mounting base 13 and deck 17 is connect, is mentioned High civil engineering is used convenient for the stability on assembled provisional protection column.
The preferable specific embodiment of the above, only the utility model, but the protection scope of the utility model is not It is confined to this, anyone skilled in the art is within the technical scope disclosed by the utility model, practical according to this Novel technical solution and its utility model design are subject to equivalent substitution or change, should all cover the protection model in the utility model Within enclosing.

Claims (7)

1. a kind of civil engineering is used convenient for assembled provisional protection column, including pedestal (4), which is characterized in that the pedestal (4) Side offers placing groove (19), and the other side of pedestal (4) has been bolted tool box (18), the pedestal (4) Top is welded with deck (17), and card slot (16) are provided at the top of deck (17), and the inside of the card slot (16) is plugged with peace It fills seat (13), and is welded with rectangle frame (5) at the top of mounting base (13), the interior welds of the rectangle frame (5) have guardrail web plate (6), the side of the rectangle frame (5) is welded with two first connecting rods (7), and the other end of first connecting rod (7) is welded with U The link block (8) of type structure, the other side of the rectangle frame (5) are welded with two the second connecting rods (11), and the second connecting rod (11) the other end is hinged with inserted block (10), and inserted block (10) is plugged in the inside of link block (8), in the two sides of the card slot (16) Wall offers rectangular straight slot (15), and is plugged with fixing bolt (14) between two rectangular straight slot (15), the fixing bolt (14) One end be welded with magnetic links (21).
2. a kind of civil engineering according to claim 1 is used convenient for assembled provisional protection column, which is characterized in that the company The inside for connecing block (8) is plugged with coupling bar (9), and offers circular through hole at the top of inserted block (10).
3. a kind of civil engineering according to claim 1 is used convenient for assembled provisional protection column, which is characterized in that the bottom The universal wheel (20) with service brake is bolted in the bottom four corners of seat (4).
4. a kind of civil engineering according to claim 1 is used convenient for assembled provisional protection column, which is characterized in that the bottom There are two support plate (2) for the bottom part down setting of seat (4), and the bottom of two support plates (2) is welded with placement plate (1).
5. a kind of civil engineering according to claim 1 is used convenient for assembled provisional protection column, which is characterized in that the bottom The two sides of seat (4) are opened up there are two limiting slot (3), and the groove of U-shaped structure, support plate are offered at the top of support plate (2) (2) groove is plugged in the inside of limiting slot (3).
6. a kind of civil engineering according to claim 1 is used convenient for assembled provisional protection column, which is characterized in that the peace The side of dress seat (13) offers circular perforations (12), and the interlude of fixing bolt (14) is plugged in the interior of circular perforations (12) Portion.
7. a kind of civil engineering according to claim 1 is used convenient for assembled provisional protection column, which is characterized in that the work Case lid is hinged at the top of tool case (18), and the other end of case lid is bonded by hasp lock with tool box (18).
CN201821543652.XU 2018-09-20 2018-09-20 A kind of provisional protection column of the civil engineering convenient for assembly Expired - Fee Related CN208899979U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821543652.XU CN208899979U (en) 2018-09-20 2018-09-20 A kind of provisional protection column of the civil engineering convenient for assembly

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821543652.XU CN208899979U (en) 2018-09-20 2018-09-20 A kind of provisional protection column of the civil engineering convenient for assembly

Publications (1)

Publication Number Publication Date
CN208899979U true CN208899979U (en) 2019-05-24

Family

ID=66573078

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821543652.XU Expired - Fee Related CN208899979U (en) 2018-09-20 2018-09-20 A kind of provisional protection column of the civil engineering convenient for assembly

Country Status (1)

Country Link
CN (1) CN208899979U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113374287A (en) * 2021-06-25 2021-09-10 云南新劲宏铝塑幕墙装饰工程有限公司 Novel guardrail is used in steel construction engineering construction device
CN115199133A (en) * 2022-07-22 2022-10-18 鞍山三冶建筑工程有限公司 Fender is enclosed in construction

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113374287A (en) * 2021-06-25 2021-09-10 云南新劲宏铝塑幕墙装饰工程有限公司 Novel guardrail is used in steel construction engineering construction device
CN115199133A (en) * 2022-07-22 2022-10-18 鞍山三冶建筑工程有限公司 Fender is enclosed in construction

Similar Documents

Publication Publication Date Title
CN208899979U (en) A kind of provisional protection column of the civil engineering convenient for assembly
CN103991649A (en) Folding transportation bracket for large fuselage part section
CN206298834U (en) A kind of end bay construction of cast-in-place box girders section bed die system
CN212244278U (en) Museum combined fossil transport and display box
CN101602424A (en) A kind of frame packaging turnover
CN210195187U (en) Combined sliding scaffold
CN205051187U (en) Equipment adjustable switch board
CN110911978B (en) Spliced type preassembled box-type transformer substation and installation method thereof
CN212053219U (en) H-shaped steel structure connecting piece
CN211795552U (en) Commodity circulation management is with removing goods shelves
CN209261192U (en) A kind of Portable scaffold
CN209040682U (en) A kind of guard bar structure for foldable accommodating frame
CN213774436U (en) Steel plate mesh scaffold board
CN206205408U (en) A kind of supporting tool
CN218787038U (en) Road and bridge protector
CN213063009U (en) Civil engineering safety scaffold
CN205778699U (en) The device of installation and removal gear mud umbrella
CN211818201U (en) Building engineering faces limit protection support
CN212313452U (en) Tool box of low-flat-bed semitrailer
CN210273021U (en) Low-pressure starting end box assembled by sectional materials
CN214220536U (en) Quick-dismantling scaffold for building
CN210437592U (en) Special frame structure for FATP key machine
CN221029641U (en) High key Shi Ningping platform of suspension bridge combination beam
CN219316594U (en) Water conservancy is guard plate for building convenient to carry
CN213341171U (en) Low pressure combination formula skeleton for cubical switchboard

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190524

Termination date: 20190920

CF01 Termination of patent right due to non-payment of annual fee