CN208830444U - Inspection shaft steel combined template - Google Patents

Inspection shaft steel combined template Download PDF

Info

Publication number
CN208830444U
CN208830444U CN201821561730.9U CN201821561730U CN208830444U CN 208830444 U CN208830444 U CN 208830444U CN 201821561730 U CN201821561730 U CN 201821561730U CN 208830444 U CN208830444 U CN 208830444U
Authority
CN
China
Prior art keywords
external mold
internal model
inspection shaft
clinch
strut
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821561730.9U
Other languages
Chinese (zh)
Inventor
龙慧
涂伟
罗加鹏
马跃武
王林
李刚
赖世友
吴启东
陆继东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yunnan Construction Investment Tenth Construction Co Ltd
Original Assignee
Yunnan Construction Investment Tenth Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yunnan Construction Investment Tenth Construction Co Ltd filed Critical Yunnan Construction Investment Tenth Construction Co Ltd
Priority to CN201821561730.9U priority Critical patent/CN208830444U/en
Application granted granted Critical
Publication of CN208830444U publication Critical patent/CN208830444U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of inspection shaft steel combined templates, internal model and external mold including coaxial arrangement, more than two limit stays are provided between the internal model and external mold, the supporting part that the every limit stay includes clinch and is arranged in below clinch, the clinch both ends are separately positioned in internal model and touch outside, and the supporting part is against between internal model and external mold.The application template is combined using standard component, and a set of steel template recycles, and improves the number of turnover, saves material;It installs and removes more convenient quick, greatly shorten the construction period;Template is steel part, and concrete appearance is ideal after demoulding, reduces cost payout.

Description

Inspection shaft steel combined template
Technical field
The utility model relates to the technical field of construction of municipal works, and in particular to inspection shaft steel combined template.
Background technique
With the continuous propulsion of building industrialization progress, steel typified form, can be multiple for cast-in-place construction It is used in turn, good save the cost, reduces the cost that template is purchased.In concrete pouring construction, itself is utilized Rigidity, can reliably bear the self weight and lateral pressure of young concrete, do not have to bracing reinforcement, make its concrete members at Type.Rain, the processing of sewage inspection well template, and generated various load in the construction process;Guarantee engineering structure and component Each section geomery and mutual alignment are correct;It with simple structure, is convenient to mount and dismount, assembled seam is close, plate when guarantee pours Stitch not spillage.
Utility model content
The purpose of this utility model is to provide a kind of inspection shaft steel combined templates, solve inspection shaft in the prior art The problem of construction material cost is big, and construction is more troublesome.
In order to solve the above technical problems, the utility model uses following technical scheme:
A kind of inspection shaft steel combined template, internal model and external mold including coaxial arrangement, between the internal model and external mold More than two limit stays are provided with,
The supporting part that the every limit stay includes clinch and is arranged in below clinch, the clinch both ends It is separately positioned in internal model and touches outside, the supporting part is against between internal model and external mold.
The clinch and supporting part limited in stay cooperates, supporting part be used to adjust it is inside and outside the distance between touch, make Internal model is obtained to be arranged concentrically with external mold;Clinch prevents supporting part from falling between inside and outside touch, and influences the quality for checking the borehole wall.
Preferably, the internal model and external mold include the template of more than two arcs, pass through company between adjacent forms Fitting connection, it is conveniently stripped.
Preferably, the connector includes the connection sheet being axially arranged on corresponding templates edge, adjacent forms Corresponding connection sheet is bolted, convenient for disassembly and assembly.
Preferably, the clinch at least one end is provided with the gag lever post vertical with supporting part, the gag lever post and The clip slot for clamping internal model or external mold is formed between supporting part, the clip slot is arranged along the vertical direction, can keep inside and outside and touch It is vertically arranged.
Preferably, being provided with the bracket of Anti-inclining outside the external mold.
Preferably, the bracket includes sequentially connected first strut of head and the tail, the second strut and third strut, In,
First strut being axially fixed on external mold along external mold;
Second strut is radially arranged in the bottom of the first strut along external mold.
Preferably, the bracket is symmetricly set on external mold bottom there are two more than, inside and outside touch can be kept to set vertically It sets.
The typified form of the application includes internal model and external mold, before use, measuring and being arranged the normal control wire in place, draw The grey linear dimension of stake, standard level stake and fluting completes preliminary examination formality after qualification is reviewed in management.
It is cheated by prescribed requirement using machinery, the earth excavation of slot, uses people at away from design foundation pit bottom absolute altitude 200mm Work, which is repaired, compiles clear bottom.
Concrete cushion construction is carried out after related side's check of foundation subsoil, bed course Zhou Biankuan goes out bottom plate 100mm.
Inspection shaft central cross line is drawn in mat surface mark, baseplate reinforcing bar is carried out and borehole wall joint bar, template, concrete is applied Work.
Concrete inspection well construction
1,1. the spacing of borehole wall vertical reinforcement is modified in the binding of borehole wall reinforcing bar, installs borehole wall horizontal reinforcement, and bar spacing meets Design and code requirement, reinforcing bar crosspoint are fastened using 20-22# wire;2. cushion block used in control protective layer will be processed in advance, Guarantee that intensity meets the requirements when using, laying cushion block, vertically and horizontally spacing is not more than 80 ㎝.
2, template is installed
Template divides internal model and external mold.Pit shaft internal model uses two pieces of templates, and adjacent two pieces of templates are assembled using selling sheet, then with company Connecting bolt@200 connects it as an entirety.Pit shaft external mold is assembled using three to four pieces of template+selling sheets, using connection spiral shell Bolt@200 is linked as an entirety.
When template is installed, strict control structural outer rim size returns number, lattice side with well center, and is monitored and adjusted with level Template elevation of top surface.
In order to guarantee borehole wall bulk and inner and outer template position, it is arranged two pairs in die head pit shaft center of circle diameter symmetry Limit stay.
Before pouring borehole wall concrete, it need to start after template, reinforcing bar and built-in fitting acceptance(check) and after storehouse is blown in cleaning It carries out.
Manually match trolley when casting to be directly sent to pour a little.Coagulation under the mode of inspection shaft casting concrete chute Soil, placement layer by layer, and should finish sublevel concreting before front layer concrete initial set.
It is vibrated using poker vibrator, to accomplish tightly to insert slow group, plug and pound a spacing≤40 ㎝;Bottom plate item face wooden float It flattens.When the borehole wall reserves platform concreting, the interval time of 40-60min is poured, with underplate concrete to prevent plugging and pounding not It is real.
It should be set when casting concrete and specially see muscle, see mould personnel, and often observe template, reinforcing bar, pre-buried hole, built-in pipe With joint bar whether there is or not movement, deformation or stopping state, timely processing of finding the problem.
The dismounting of template can be torn open after concrete strength can guarantee that its surface corner angle is not damaged because of form removal It removes.The protection to concrete is paid attention to when dismounting, is prevented and is pounded, prizes suddenly firmly.Connection bolt is first removed, selling sheet is being removed, is finally removing Template.
Compared with prior art, the utility model has the beneficial effects that the application template is combined using standard component, Yi Taogang Pallet recycles, and improves the number of turnover, saves material;It installs and removes more convenient quick, greatly shorten construction work Phase;Template is steel part, and concrete appearance is ideal after demoulding, reduces cost payout.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model.
Fig. 2 is the structural schematic diagram that the utility model limits stay.
Specific embodiment
In order to make the purpose of the utility model, technical solutions and advantages more clearly understood, below in conjunction with attached drawing and implementation Example, the present invention will be further described in detail.It should be appreciated that specific embodiment described herein is only used to explain The utility model is not used to limit the utility model.
Embodiment 1:
Present embodiments provide a kind of inspection shaft steel combined template, as shown in Figs. 1-2, the internal model including coaxial arrangement 2 and external mold 1, more than two limit stays 3 are provided between the internal model 2 and external mold 1,
The every limit stay 3 is described to take including clinch 31 and the supporting part 32 being arranged in below clinch 31 31 both ends of socket part are separately positioned in internal model 2 and touch outside, and the supporting part 32 is against between internal model 2 and external mold 1.
The clinch 31 and supporting part 32 limited in stay 3 cooperates, and supporting part 32 is used to adjust between inside and outside touch Distance, so that internal model 2 is arranged concentrically with external mold 1;Clinch 31 prevents supporting part 32 from falling between inside and outside touch, and influences inspection shaft The quality of wall.
Embodiment 2:
The present embodiment on the basis of embodiment 1, further defines: the internal model 2 and external mold 1 are including two or more The template of arc is connected by connector between adjacent forms, conveniently stripped.
Embodiment 3:
The present embodiment further defines on the basis of embodiment 2: the connector includes being axially arranged on correspondence Connection sheet on template edge, connection sheet corresponding to adjacent forms is bolted, convenient for disassembly and assembly.
Embodiment 4:
The present embodiment on the basis of embodiment 1, further defines: the clinch 31 at least one end is provided with and supports The vertical gag lever post 33 in support part 32 forms the folder for clamping internal model 2 or external mold 1 between the gag lever post 33 and supporting part 32 Slot, the clip slot are arranged along the vertical direction, and inside and outside touch can be kept to be vertically arranged.
Embodiment 5:
The present embodiment on the basis of embodiment 1, further defines: the branch of Anti-inclining is provided with outside the external mold 1 Frame 4.
Embodiment 6:
The present embodiment further defines on the basis of embodiment 5: the bracket 4 includes head and the tail sequentially connected the One strut 41, the second strut 42 and third strut 43, wherein
First strut 41 is axially fixed on external mold 1 along external mold 1;
Second strut 42 is radially arranged in the bottom of the first strut 41 along external mold 1.
Embodiment 7:
The present embodiment further defines on the basis of embodiment 5: the bracket 4 is symmetricly set on there are two more than 1 bottom of external mold can keep inside and outside touch to be vertically arranged.
Although reference be made herein to the utility model is described in multiple explanatory embodiments of the utility model, still, It should be understood that those skilled in the art can be designed that a lot of other modification and implementations, these modifications and implementations It will fall within scope and spirit disclosed in the present application.More specifically, it discloses in the application, drawings and claims In range, can building block to theme combination layout and/or layout carry out a variety of variations and modifications.In addition to building block And/or outside the modification and improvement of layout progress, to those skilled in the art, other purposes also be will be apparent.

Claims (7)

1. a kind of inspection shaft steel combined template, it is characterised in that: internal model (2) and external mold (1) including coaxial arrangement, it is described More than two limits stay (3) are provided between internal model (2) and external mold (1),
Every limit stay (3) includes the supporting part (32) of clinch (31) and setting below clinch (31), institute It states clinch (31) both ends to be separately positioned on internal model (2) and touch outside, the supporting part (32) is against internal model (2) and external mold (1) between.
2. inspection shaft steel combined template according to claim 1, which is characterized in that the internal model (2) and external mold (1) Include the template of more than two arcs, is connected between adjacent forms by connector.
3. inspection shaft steel combined template according to claim 2, which is characterized in that the connector includes along axial direction Connection sheet on corresponding templates edge is set, and connection sheet corresponding to adjacent forms is bolted.
4. inspection shaft steel combined template according to claim 1, which is characterized in that the clinch (31) at least one End is provided with the gag lever post vertical with supporting part (32) (33), is formed between the gag lever post (33) and supporting part (32) for pressing from both sides The clip slot of internal model (2) or external mold (1) is held, the clip slot is arranged along the vertical direction.
5. inspection shaft steel combined template according to claim 1, which is characterized in that setting outside the external mold (1) There is the bracket (4) of Anti-inclining.
6. inspection shaft steel combined template according to claim 5, which is characterized in that the bracket (4) includes head and the tail Sequentially connected first strut (41), the second strut (42) and third strut (43), wherein
First strut (41) is axially fixed on external mold (1) along external mold (1);
Second strut (42) is radially arranged in the bottom of the first strut (41) along external mold (1).
7. inspection shaft steel combined template according to claim 5, which is characterized in that the bracket (4) there are two with On, it is symmetricly set on external mold (1) bottom.
CN201821561730.9U 2018-09-25 2018-09-25 Inspection shaft steel combined template Active CN208830444U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821561730.9U CN208830444U (en) 2018-09-25 2018-09-25 Inspection shaft steel combined template

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821561730.9U CN208830444U (en) 2018-09-25 2018-09-25 Inspection shaft steel combined template

Publications (1)

Publication Number Publication Date
CN208830444U true CN208830444U (en) 2019-05-07

Family

ID=66317583

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821561730.9U Active CN208830444U (en) 2018-09-25 2018-09-25 Inspection shaft steel combined template

Country Status (1)

Country Link
CN (1) CN208830444U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110863430A (en) * 2019-10-11 2020-03-06 中建八局第一建设有限公司 Anti-seismic pier column construction device and method
CN113843888A (en) * 2021-10-11 2021-12-28 阳谷天马建筑材料有限公司 Prefabricated composite pipe structure mold and using method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110863430A (en) * 2019-10-11 2020-03-06 中建八局第一建设有限公司 Anti-seismic pier column construction device and method
CN113843888A (en) * 2021-10-11 2021-12-28 阳谷天马建筑材料有限公司 Prefabricated composite pipe structure mold and using method thereof

Similar Documents

Publication Publication Date Title
CN107313589A (en) Outer wall of basement one side steel form support system and its construction method
CN100476142C (en) Construction method for combined V-shape steel pipe concrete pile
CN206337819U (en) A kind of bracing means of concrete structure templates for expansion joints
CN208830444U (en) Inspection shaft steel combined template
CN206625428U (en) Floor closed system is poured after a kind of pipe well
CN102518300B (en) Embedded conical bearing joint type steel structural support and construction method thereof
CN105586833A (en) Construction method for integrally forming large cast-in-place thin-wall high pier through stiff skeleton reinforcement cage
CN104153573B (en) V-type cylinder concrete pour mould and construction method
CN206245231U (en) A kind of box culvert internal die support device
CN214614647U (en) Floor hole plugging device
CN109811787A (en) It is a kind of to use the additional elevator structure of pin-connected panel foundation precast elements and its construction method
CN203462754U (en) Free-disassembly suspension template
CN107859058A (en) A kind of cast-in-place concrete retaining wall anti-incline anti-floating large steel moulding plate device and installation method
CN103552911B (en) A kind of movable boom hoisting and the construction installation method of use thereof
CN205617732U (en) Job site pipeline formula floor rubbish clearance system
CN105908752B (en) Formwork supporting and stripping system for pouring concrete on side wall and working process of formwork supporting and stripping system
CN105951599B (en) High column mould bases integrated construction technique
CN207685855U (en) A kind of anti-anti-floating large steel moulding plate device that inclines of cast-in-place concrete retaining wall
CN111827648A (en) Construction device and method for down-supporting type overhanging scaffold
CN209469875U (en) A kind of concrete pump pipe bending place support device
CN105804448A (en) Vertical prefabricating construction method of cooling tower herringbone column
CN210529735U (en) Building steel structure platform base
CN208088827U (en) The detachable earth anchor of iron on floor beam
CN209538013U (en) A kind of end template for the construction of Thin-wall Hollow Pier pier top solid-section
CN208733622U (en) A kind of template of simple type Fast Installation manhole retaining wall

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant