Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821145481.5U
Other languages
Chinese (zh)
Inventor
柳俊
雷金波
张振礼
佘清雅
万梦华
赵正元
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 2 Group Co Ltd
Original Assignee
Shanghai Construction No 2 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction No 2 Group Co Ltd filed Critical Shanghai Construction No 2 Group Co Ltd
Priority to CN201821145481.5U priority Critical patent/CN208792356U/en
Application granted granted Critical
Publication of CN208792356U publication Critical patent/CN208792356U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

Multi-column pier foundation provided by the utility model with starlike through-hole, by being equipped with several sets of vias along the longitudinal gap of tube wall on the tube wall of the tubular pole, each sets of vias includes first through hole, second through-hole and third through-hole, first through hole in same sets of vias, second through-hole and third through-hole are located in the same horizontal position and are uniformly distributed on the tube wall of the tubular pole, it can be being formed between the soil body outside tubular pole and stake by the channel in three directions that the soil body is conducted outside tubular pole inner cavity and stake, it can make in clump of piles pile driving process, the intracorporal Free water of soil around pile and mud are out of, three directions flow freely into tubular pole lumen, in work progress or the construction intermittent phase can use water pump and persistently extract out, the maximum value of the intracorporal excess pore water pressure of soil around pile can be effectively reduced, accelerate the dissipation of excess pore water pressure, reaching faster reduces super hole The purpose of water pressure, reduces the generation of pile sinking accident, and the shearing strength of pile peripheral earth is improved, foundation bearing capacity enhancing.

Description

A kind of multi-column pier foundation with starlike through-hole
Technical field
The utility model relates to the realm of building construction more particularly to a kind of multi-column pier foundations with starlike through-hole.
Background technique
With the development of construction industry and national economy, construction land is more nervous, and people is caused to have in limited soil High-rise even Super High, the utilization rate in the soil Lai Tigao are built on the ground.In order to make basis be able to satisfy upper load requirement, usually need Consolidation process is carried out to the soil body, pile foundation is exactly one of the most common type base form.
In numerous pile foundations, tubular pole because of its bearing capacity of single pile height, bending resistance and extraction-resistant behavior relative to traditional pile-type have compared with Big advantage, static pressure pile-sinking have low pollution in work progress, do not disturb residents, and it is excellent can to efficiently control uneven settlement of foundation etc. Point, therefore be widely used.However usual single stake is the load of unbearable superstructure in engineering, when single pile bearing capacity without When method is met the requirements, for actual needs using two or two or more more piles come shared upper load, each stake passes through stake The cushion cap on top is linked together, and forms clump of piles pipe pile foundation.But clump of piles tubular pole inevitably generates soil compaction during the pile driving process Effect steeply rises pile peripheral earth excess pore water pressure in a short time, so that a series of pile sinking thing can be caused to engineering Therefore.
Therefore, how to accelerate the dissipation of excess pore water pressure in clump of piles pile driving process or reduce clump of piles Super-void Water Pressure The maximum value of power, effectively reduces effect of driving pile, reduces the generation of pile sinking accident, is this field technology urgently to be resolved Problem.
Utility model content
The purpose of this utility model is to provide a kind of multi-column pier foundations with starlike through-hole, open up on the tube wall of tubular pole First through hole, the second through-hole and the third through-hole being evenly arranged, can make the excess pore water generated in pile driving process from three A direction equilibrium flows freely into the lumen of tubular pole, accelerates the dissipation of excess pore water pressure or reduces clump of piles excess pore water pressure Maximum value, effectively reduce effect of driving pile, reduce the generation of pile sinking accident.
In order to solve the above technical problems, the utility model provides the following technical solutions:
A kind of multi-column pier foundation with starlike through-hole is set in the soil body for soil mass consolidation, including cushion cap and setting Several tubular poles below cushion cap are equipped with several sets of vias, Mei Yitong along the longitudinal gap of tube wall on the tube wall of the tubular pole Hole group includes first through hole, the second through-hole and third through-hole, and the first through hole, the second through-hole and third in each sets of vias are logical Hole is correspondingly arranged up and down respectively, and the first through hole, the second through-hole and third through-hole in same sets of vias are located at same level position It sets and is uniformly distributed on the tube wall of the tubular pole.
Preferably, in the above-mentioned multi-column pier foundation with starlike through-hole, the quantity of the tubular pole is four, four tubular poles Top be fixedly connected with cushion cap, be distributed at the top of four tubular poles on square four vertex, the cushion cap is positive Rectangular, the square and the four edges of the square where cushion cap where the top of four tubular poles are corresponding parallel and described Square where the top of four tubular poles is with the square line of centres where cushion cap perpendicular to the upper surface of cushion cap.
Preferably, in the above-mentioned multi-column pier foundation with starlike through-hole, the distance between adjacent first through hole is pipe The stake of stake long 1/N, N are the sum of the quantity of first through hole.
Preferably, in the above-mentioned multi-column pier foundation with starlike through-hole, the first through hole and the second through-hole are circle Hole.
Preferably, in the above-mentioned multi-column pier foundation with starlike through-hole, the aperture of the first through hole and the second through-hole It is the 1/15~2/15 of the stake diameter of tubular pole.
Preferably, in the above-mentioned multi-column pier foundation with starlike through-hole, the wall thickness of the tubular pole is the 1/10 of stake diameter ~1/12.
Preferably, in the above-mentioned multi-column pier foundation with starlike through-hole, the stake diameter of the tubular pole is that the stake of tubular pole is long 1/14~1/15.
Preferably, in the above-mentioned multi-column pier foundation with starlike through-hole, the spacing of adjacent tubular pole is the 5~10 of stake diameter Times.
Preferably, in the above-mentioned multi-column pier foundation with starlike through-hole, several sets of vias along tubular pole longitudinal direction Spaced set.
Preferably, in the above-mentioned multi-column pier foundation with starlike through-hole, the first through hole, the second through-hole and third The shapes and sizes of through-hole are consistent.
By techniques disclosed above scheme it is found that the beneficial effects of the utility model are as follows:
Multi-column pier foundation provided by the utility model with starlike through-hole, by the tube wall of the tubular pole along tube wall Longitudinal gap be equipped with several groups through-hole, each sets of vias includes first through hole, the second through-hole and third through-hole, and first is logical Hole, the second through-hole and third through-hole are located in the same horizontal position and are uniformly distributed on the tube wall of the tubular pole, Ke Yi It is formed between tubular pole and the outer soil body of stake by the channel in three directions that the soil body is conducted outside tubular pole inner cavity and stake, clump of piles pile sinking can be made In the process, the intracorporal Free water of soil around pile and mud in work progress or are applied out of three directions flow freely into tubular pole lumen The work intermittent phase can use water pump and persistently extract out, and the maximum value of the intracorporal excess pore water pressure of soil around pile can be effectively reduced, accelerate The dissipation of excess pore water pressure achievees the purpose that faster to reduce excess pore water pressure, effectively reduces effect of driving pile, and it is heavy to reduce The generation of stake accident, and the shearing strength of pile peripheral earth is improved, foundation bearing capacity enhancing.Also, it is tried by model It tests and is obtained with numerical simulation analysis: compared to unidirectional aperture and two-way aperture, starlike aperture not only excess pore water pressure maximum value Minimum, and the stress concentration effect generated in tapping influences minimum, is optimal aperture mode.
Detailed description of the invention
Fig. 1 is the schematic perspective view of the multi-column pier foundation with starlike through-hole of the utility model embodiment one.
Fig. 2 is the schematic view of facade structure of the multi-column pier foundation with starlike through-hole of the utility model embodiment one.
Fig. 3 is the A-A diagrammatic cross-section of Fig. 2.
Fig. 4 is the B-B diagrammatic cross-section of Fig. 2.
In figure: 1- cushion cap, 2- tubular pole, 3- lumen, 4- first through hole, the second through-hole of 5-, 6- third through-hole.
Specific embodiment
The utility model is described in further detail below in conjunction with the drawings and specific embodiments.According to following explanation and The advantages of claims, the utility model and feature will become apparent from.It below will be by cited embodiment combination attached drawing, in detail Illustrate the technology contents and feature of the utility model.Need in addition it illustrate, attached drawing is all made of very simplified form and makes With non-accurate ratio, the purpose of the utility model embodiment is only aided in illustrating to convenience, lucidly.For sake of convenience, under "upper" described in the text, "lower" are consistent with the upper and lower direction of attached drawing, but this can't be the limit of technical solutions of the utility model System.
Referring to FIG. 1 to FIG. 4, present embodiment discloses a kind of multi-column pier foundation with starlike through-hole, it is set in the soil body For soil mass consolidation, including cushion cap 1 and several tubular poles being set to below cushion cap 1, the tubular pole 2 is round tubular pole, is had One lumen 3 is equidistantly equipped at intervals with several groups through-hole, each through-hole along the longitudinal of tube wall on the tube wall of the tubular pole 2 Group includes first through hole 4, the second through-hole 5 and third through-hole 6, first through hole 4, the second through-hole 5 in each sets of vias and the Three through-holes 6 respectively up and down is correspondingly arranged, first through hole 4, the second through-hole 5 and third through-hole 6 be located in the same horizontal position and Be uniformly distributed on the tube wall of the tubular pole 2, the first through hole 4, the shape of second through-hole 5 and third through-hole 6 and It is in the same size.
Multi-column pier foundation provided by the utility model with starlike through-hole, by the tube wall of the tubular pole 2 along pipe The longitudinal gap of wall is equipped with several groups through-hole, and each sets of vias includes first through hole 4, the second through-hole 5 and third through-hole 6, and one Through-hole 4, the second through-hole 5 and third through-hole 6 are located in the same horizontal position and are uniformly distributed on the tube wall of the tubular pole 2, Can make in clump of piles pile driving process, the intracorporal Free water of soil around pile and mud out of, three directions flow freely into tubular pole 2 lumen 3, In work progress or the construction intermittent phase can use water pump and persistently extract out, and the intracorporal excess pore water pressure of soil around pile can be effectively reduced Maximum value, accelerate excess pore water pressure dissipation, achieve the purpose that faster reduce excess pore water pressure, effectively reduce pile sinking squeeze Native effect, reduces the generation of pile sinking accident, and the shearing strength of pile peripheral earth is improved, foundation bearing capacity enhancing.This Outside, it is obtained by model test and numerical simulation analysis: compared to unidirectional aperture and two-way aperture, starlike aperture not only super hole Water pressure maximum value is minimum, and the stress concentration effect generated in tapping influences minimum, is optimal aperture mode.
In order to enable the multi-column pier foundation with starlike through-hole is whole more stable, increases it with the periphery soil body and bear top The ability of load, it is preferred that in the above-mentioned multi-column pier foundation with starlike through-hole, the quantity of the tubular pole 2 is four, four The top of tubular pole 2 is fixedly connected with cushion cap 1, and the top of four tubular poles 2 is distributed on square four vertex, described to hold Platform 1 is square, and the square where the top of four tubular poles 2 is corresponding with the four edges of square where cushion cap 1 flat Row, and the line of centres of the square where the square and cushion cap 1 where the top of four tubular poles 2 is perpendicular to cushion cap 1 Upper surface.
Preferably, in the above-mentioned multi-column pier foundation with starlike through-hole, the distance between adjacent first through hole 4 is pipe The stake of stake 2 long 1/N, N are the sum of the quantity of first through hole 4.
Preferably, in the above-mentioned multi-column pier foundation with starlike through-hole, the first through hole 4 is with the second through-hole 5 Circular hole, circular hole pore-forming is more convenient, and in the case that first through hole 4 is equal with 5 perimeter of the second through-hole, the maximum figure of area is circle Shape, accelerates the dissipation of excess pore water pressure, and reduces the maximum value of clump of piles excess pore water pressure.
In order to enable tubular pole 2 has enough strength and stiffness, it is preferred that in the above-mentioned clump of piles base with starlike through-hole In plinth, the aperture of the first through hole 4 and the second through-hole 5 is the 1/15~2/15 of the stake diameter of tubular pole 2, the wall of the tubular pole 2 Thickness is the 1/10~1/12 of stake diameter, and the stake diameter of the tubular pole 2 is long 1/14~1/15 of the stake of tubular pole 2, the first through hole 4, The open pore size of second through-hole 5 and third through-hole 6 is the 1/15~2/15 of a diameter, and the tubular pole interval S takes 5~10 times Stake diameter.
Preferably, in the above-mentioned multi-column pier foundation with starlike through-hole, the spacing of adjacent tubular pole 2 is the 5~10 of stake diameter Times, to improve the entire stability and intensity with the multi-column pier foundation of starlike through-hole, increases it with the periphery soil body and bear top The ability of load.
In conclusion the multi-column pier foundation provided by the utility model with starlike through-hole, enables to soil around pile intracorporal Free water and mud are out of, three directions flow freely into tubular pole lumen, and in work progress or the construction intermittent phase can use water pump Lasting extraction can be effectively reduced the maximum value of the intracorporal excess pore water pressure of soil around pile, accelerate the dissipation of excess pore water pressure, reach To the purpose for faster reducing excess pore water pressure, effect of driving pile is effectively reduced, the generation of pile sinking accident is reduced, and makes stake The shearing strength of Zhou Tuti is improved, foundation bearing capacity enhancing.
Foregoing description is only the description to the utility model preferred embodiment, not to any limit of the scope of the utility model Fixed, any change, the modification that the those of ordinary skill in the utility model field does according to the disclosure above content belong to right and want Seek the protection scope of book.

Claims (10)

1. a kind of multi-column pier foundation with starlike through-hole is set in the soil body for soil mass consolidation, which is characterized in that including cushion cap And several tubular poles below cushion cap are set to, several through-holes are equipped with along the longitudinal gap of tube wall on the tube wall of the tubular pole Group, each sets of vias include first through hole, the second through-hole and third through-hole, first through hole, the second through-hole in each sets of vias And third through-hole is correspondingly arranged up and down respectively, the first through hole, the second through-hole and third through-hole in same sets of vias are located at In the same horizontal position and it is uniformly distributed on the tube wall of the tubular pole.
2. as described in claim 1 with the multi-column pier foundation of starlike through-hole, which is characterized in that the quantity of the tubular pole is four A, the top of four tubular poles is fixedly connected with cushion cap, is distributed on square four vertex at the top of four tubular poles, institute It states cushion cap to be square, the square where the top of four tubular poles is corresponding with the four edges of square where cushion cap flat Row, and the line of centres of the square and square where cushion cap where the top of four tubular poles is perpendicular to the upper of cushion cap Surface.
3. as described in claim 1 with the multi-column pier foundation of starlike through-hole, which is characterized in that between adjacent first through hole Distance is the long 1/N of the stake of tubular pole, and N is the sum of the quantity of first through hole.
4. as described in claim 1 with the multi-column pier foundation of starlike through-hole, which is characterized in that the through-hole is circular hole.
5. as described in claim 1 with the multi-column pier foundation of starlike through-hole, which is characterized in that the first through hole is logical with second The aperture in hole is the 1/15~2/15 of the stake diameter of tubular pole.
6. as described in claim 1 with the multi-column pier foundation of starlike through-hole, which is characterized in that the wall thickness of the tubular pole is stake The 1/10~1/12 of diameter.
7. as described in claim 1 with the multi-column pier foundation of starlike through-hole, which is characterized in that the stake diameter of the tubular pole is tubular pole Stake it is long 1/14~1/15.
8. as described in claim 1 with the multi-column pier foundation of starlike through-hole, which is characterized in that the spacing of adjacent tubular pole is stake diameter 5~10 times.
9. as described in claim 1 with the multi-column pier foundation of starlike through-hole, which is characterized in that several sets of vias are along pipe Longitudinal spaced set of stake.
10. as described in claim 1 with the multi-column pier foundation of starlike through-hole, which is characterized in that the first through hole, second are led to The shapes and sizes of hole and third through-hole are consistent.
CN201821145481.5U 2018-07-19 2018-07-19 A kind of multi-column pier foundation with starlike through-hole Active CN208792356U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821145481.5U CN208792356U (en) 2018-07-19 2018-07-19 A kind of multi-column pier foundation with starlike through-hole

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821145481.5U CN208792356U (en) 2018-07-19 2018-07-19 A kind of multi-column pier foundation with starlike through-hole

Publications (1)

Publication Number Publication Date
CN208792356U true CN208792356U (en) 2019-04-26

Family

ID=66202770

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821145481.5U Active CN208792356U (en) 2018-07-19 2018-07-19 A kind of multi-column pier foundation with starlike through-hole

Country Status (1)

Country Link
CN (1) CN208792356U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110397021A (en) * 2019-08-12 2019-11-01 上海建工二建集团有限公司 A kind of prefabricated variable diameters hole tube pile structure and its construction method for treatment of soft foundation

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110397021A (en) * 2019-08-12 2019-11-01 上海建工二建集团有限公司 A kind of prefabricated variable diameters hole tube pile structure and its construction method for treatment of soft foundation

Similar Documents

Publication Publication Date Title
CN202989937U (en) Grille-type double-row pile supporting structure
CN205134327U (en) Concrete diclinic props row -pile support system
CN209179042U (en) A kind of multi-column pier foundation with helical form through-hole
CN208792356U (en) A kind of multi-column pier foundation with starlike through-hole
CN105862906A (en) Offshore wind power plant draught fan single pile foundation and construction method
CN207498959U (en) Double pile-anchor system
CN206418464U (en) A kind of Bailey bracket support system
CN218597181U (en) Permanent foundation pit supporting pit-in-pit structure in historic site area
CN205116207U (en) Offshore wind farm fan combined type embedded rock pile basis
CN204703175U (en) Combine double sheet pile support system
CN208701730U (en) A kind of multi-column pier foundation with two-way through-hole
CN204940304U (en) A kind of odd-shaped cross section foundation pit supporting pile
CN208792355U (en) A kind of multi-column pier foundation
CN207959245U (en) A kind of load-bearing pile foundation structure
CN204125931U (en) Foundation pile structure
CN203684267U (en) Novel offshore wind power basic structure
CN201169781Y (en) Cap digging pit structure
CN212077954U (en) Portable assembled deep basal pit steel sheet case supporting construction that can have enough to meet need
CN202440824U (en) Three-line-pile super-deep foundation-pit support structure
CN103726505B (en) Offshore wind plant wind turbine foundation
CN208152054U (en) A kind of triangle engineering method deep footing groove enclosing structure
CN203080540U (en) Iron tower foundation of power transmission line
CN204645056U (en) A kind of combined type double-row pile foundation pit support structure
CN203782729U (en) Diamond-shape arranged low pile caps provided with reinforcing ribs
CN213682250U (en) Pile foundation subsides and consolidates jacking leveling structure