CN208749087U - Entirety is climbed steel platform - Google Patents

Entirety is climbed steel platform Download PDF

Info

Publication number
CN208749087U
CN208749087U CN201820897568.1U CN201820897568U CN208749087U CN 208749087 U CN208749087 U CN 208749087U CN 201820897568 U CN201820897568 U CN 201820897568U CN 208749087 U CN208749087 U CN 208749087U
Authority
CN
China
Prior art keywords
steel
guide rail
connection
climbed
climbing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820897568.1U
Other languages
Chinese (zh)
Inventor
张长明
沈韦霞
周守华
林承浩
高亚松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui New Infrastructure Co ltd
Original Assignee
Anhui Sijian Holding Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Sijian Holding Group Co ltd filed Critical Anhui Sijian Holding Group Co ltd
Priority to CN201820897568.1U priority Critical patent/CN208749087U/en
Application granted granted Critical
Publication of CN208749087U publication Critical patent/CN208749087U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model provides a kind of entirety and climbs steel platform.The utility model includes steel plateform system, connection system for guide rail, support system, climbing system, template system;It is characterized in that: the steel plateform system connects climbing system, the climbing system is connected on concrete structure by support system, the steel plateform system includes steel frame, the steel frame bottom is provided with track, the connection system for guide rail is mounted in the track by the suspension sheave at top, the suspension sheave connects driving wheel by connecting rod, and the driving wheel connects travel driving unit, the connection system for guide rail connection template system.The utility model can expand construction width range, and the scope of application is wider.

Description

Entirety is climbed steel platform
Technical field:
It climbs steel platform the utility model relates to a kind of entirety, belongs to construction equipment technical field.
Background technique:
Steel platform technology of integrally climbing is to form integration using by the totally enclosed type steel platform and scaffold integrally climbed Template scaffold system carry out building the engineering construction of high-altitude steel bar template technology.The technology passes through support system or climbs The load born is passed to concrete structure by system, is driven by power-equipment, replaces branch with climbing system with support system Support carries out template scaffold system and climbs, and realizes form work engineering operation.
Entirety climbs steel plateform system mainly by steel plateform system, connection system for guide rail, support system, climbing system, template System is constituted, and steel plateform system is located at top, usually passes through combination connection by components such as steel frame, steel truss, cover board, surrounding baffles Form overall structure, have the characteristics that large bearing capacity, meet construction material and construction equipment park and bear scaffold with The needs of the components synchronization job load such as support system transmitting, steel plateform system is the transfer heap that ground transports high-altitude material equipment to Put place.Connection system for guide rail provides high-altitude stereo working space for concrete structure construction, is generally connected under steel plateform system Side, support system provides supporting role for whole steel platform of climbing, and the load of receiving is transferred to concrete structure;It is existing Entirety climb steel platform the problem is that: boundary of works area is smaller, is only limitted to its corresponding vertical area, for construct width ratio Biggish engineering, then be not suitable for.
Summary of the invention:
The purpose of this utility model is to provide a kind of entirety in view of the above problems to climb steel platform, can expand and apply Work width range, the scope of application are wider.
Above-mentioned purpose is realized by following technical scheme:
Integrally climb steel platform, including steel plateform system, connection system for guide rail, support system, climbing system, template system; The steel plateform system connects climbing system, and the climbing system is connected on concrete structure by support system, institute The steel plateform system stated includes steel frame, and the steel frame bottom is provided with track, and the connection system for guide rail passes through top Suspension sheave be mounted in the track, the suspension sheave connects driving wheel by connecting rod, and the driving wheel connection is walked Driving device, the connection system for guide rail connection template system.
The entirety is climbed steel platform, and the travel driving unit includes headstock, is set inside the headstock It is equipped with driving motor, the power output shaft of the driving motor driving wheel described by retarder connection.
The entirety is climbed steel platform, and the climbing system includes the guide rail connecting with the steel plateform system, liquid Compressing cylinder, the guide rail are mounted on wall by the support system, the guide rail steel described by anchor ear connection The steel frame side of plateform system, the pedestal of the steel frame bottom installation of the steel plateform system hydraulic cylinder are described The piston rod of hydraulic cylinder be connected on the guide rail.
The entirety is climbed steel platform, and the connection system for guide rail includes cabinet, and the top of the box setting is The suspension sheave stated, the cabinet surrounding are provided with guardrail.
The entirety is climbed steel platform, and the support system includes through-wall bolt.
The utility model has the advantages that
1. the track that the steel frame bottom is arranged in by the suspension sheave at top for the connection system for guide rail of the utility model On, and the suspension sheave connects driving wheel by connecting rod, and the driving wheel connects travel driving unit, so that scaffold system System can move left and right, so that construction width range is greatly expanded, it is applied widely.
Detailed description of the invention:
Fig. 1 is the structural schematic diagram of the utility model.
Fig. 2 is the left view of Fig. 1.
1, template system in figure;2, concrete structure;3, steel frame;4, track;5, suspension sheave;6, connecting rod;7, driving wheel; 8, headstock;9, guide rail;10, hydraulic cylinder;11, cabinet;12, through-wall bolt.
Specific embodiment:
Embodiment 1:
The entirety of the present embodiment is climbed steel platform as shown in Figure 1:, including steel plateform system, connection system for guide rail, support system System, climbing system, template system 1;The steel plateform system connects climbing system, and the climbing system passes through support system It being connected on concrete structure 2, the steel plateform system includes steel frame 3, and the steel frame bottom is provided with track 4, The connection system for guide rail is mounted in the track by the suspension sheave 5 at top, and the suspension sheave is connected by connecting rod 6 Driving wheel 7, the driving wheel connect travel driving unit, the connection system for guide rail connection template system 1.Using upper Scheme is stated, when the utility model is constructed in the range for needing width larger, it is only necessary to it is flat to build entirety steel that climbs Platform drives connection system for guide rail side-to-side movement by driving device, is convenient for expansion construction width range.
Entirety described in the present embodiment is climbed steel platform, and the travel driving unit includes headstock 8, and described is dynamic Driving motor, the power output shaft of the driving motor driving wheel described by retarder connection are provided with inside power case.
Entirety described in the present embodiment is climbed steel platform, and the climbing system includes connecting with the steel plateform system Guide rail 9, hydraulic cylinder 10, the guide rail is mounted on wall by the support system, and the guide rail passes through anchor ear The steel frame side of the connection steel plateform system, the steel frame bottom installation of the steel plateform system hydraulic cylinder Pedestal, the piston rod of the hydraulic cylinder is connected on the guide rail.
Entirety described in the present embodiment is climbed steel platform, and the connection system for guide rail includes cabinet 11, the cabinet Top is provided with the suspension sheave, and the cabinet surrounding is provided with guardrail.
Entirety described in the present embodiment is climbed steel platform, and the support system includes through-wall bolt 12.
Technological means disclosed in the utility model is not limited to the technical means disclosed in the above technical means, also Including the technical solution as composed by the above technical characteristic equivalent replacement.The unaccomplished matter of the utility model belongs to this field skill The common knowledge of art personnel.

Claims (5)

  1. The steel platform 1. a kind of entirety is climbed, including steel plateform system, connection system for guide rail, support system, climbing system, template system System;It is characterized in that: the steel plateform system connects climbing system, the climbing system is connected to coagulation by support system In soil structure, the steel plateform system includes steel frame, and the steel frame bottom is provided with track, the scaffold system System is mounted in the track by the suspension sheave at top, and the suspension sheave connects driving wheel, the driving by connecting rod Wheel connection travel driving unit, the connection system for guide rail connection template system.
  2. The steel platform 2. entirety according to claim 1 is climbed, it is characterized in that: the travel driving unit includes power Case, the headstock the inside are provided with driving motor, and the power output shaft of the driving motor connects institute by retarder The driving wheel stated.
  3. The steel platform 3. entirety according to claim 1 is climbed, it is characterized in that: the climbing system includes flat with the steel Guide rail, the hydraulic cylinder of platform system connection, the guide rail are mounted on wall by the support system, and the guide rail is logical Cross the steel frame side of the anchor ear connection steel plateform system, the steel frame bottom installation of the steel plateform system liquid The pedestal of compressing cylinder, the piston rod of the hydraulic cylinder are connected on the guide rail.
  4. The steel platform 4. entirety according to claim 1 is climbed, it is characterized in that: the connection system for guide rail includes cabinet, institute The top of the box stated is provided with the suspension sheave, and the cabinet surrounding is provided with guardrail.
  5. The steel platform 5. entirety according to claim 1 is climbed, it is characterized in that: the support system includes through-wall bolt.
CN201820897568.1U 2018-06-11 2018-06-11 Entirety is climbed steel platform Active CN208749087U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820897568.1U CN208749087U (en) 2018-06-11 2018-06-11 Entirety is climbed steel platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820897568.1U CN208749087U (en) 2018-06-11 2018-06-11 Entirety is climbed steel platform

Publications (1)

Publication Number Publication Date
CN208749087U true CN208749087U (en) 2019-04-16

Family

ID=66054140

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820897568.1U Active CN208749087U (en) 2018-06-11 2018-06-11 Entirety is climbed steel platform

Country Status (1)

Country Link
CN (1) CN208749087U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114829717A (en) * 2019-08-02 2022-07-29 萨夫路品牌服务有限责任公司 Monorail system and associated scaffolding structure, system and method of use

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114829717A (en) * 2019-08-02 2022-07-29 萨夫路品牌服务有限责任公司 Monorail system and associated scaffolding structure, system and method of use

Similar Documents

Publication Publication Date Title
CN201826525U (en) Climbing shuttering system device for buildings
CN104234723A (en) Self-propelled mobile template support trolley for open trench tunnel with rectangular cross section
CN205314542U (en) Construction liquid die plate device that climbs
CN109184190A (en) It climbs and carries integrated beam type hydraulic climbing platform and its installation method
CN201268569Y (en) Double-acting integral hydraulic automatic jacking platform system
CN208749087U (en) Entirety is climbed steel platform
CN208137458U (en) Construction discharging platform
CN104291222A (en) Rigid protection and crane integration system inside super high-rise building core tube
CN107514145A (en) A kind of removable steel roofing liner installation construction device and method
CN209686254U (en) A kind of folding retractable support leg device
CN217761022U (en) Comprehensive operation trolley for construction of air cushion type surge chamber of hydropower station
CN212766235U (en) Equipment suitable for prefabricated rail top air duct assembly construction of subway station
CN217297219U (en) Special equipment for steel structure installation
CN1020645C (en) Integral elevating system for out-mould scaffold of super-high buildings
CN207177246U (en) A kind of elevated truss Mobile operating platform
CN206319628U (en) One kind building assembled wallboard fitting machine
CN211524104U (en) Novel bridge girder erection machine
CN106812051A (en) A kind of asphalt road construction formation works machinery
CN205276727U (en) Metal roofing inner panel construction and installation platform
CN211621476U (en) Concrete lining machine suitable for channels with different slope ratios
CN207453450U (en) A kind of pedal extension rod
CN103726449A (en) Automatic beam placement platform device and construction method of replacing railway beams thereby
CN209538759U (en) Applied to the jack up high-building construction workshop on climbing frame
CN206873303U (en) A pin-connected panel high position falls boom support
CN203319589U (en) Hoisting machine for installing air hose

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 230000 12 / F, block a, innovation Plaza, 222 Caihong Road, high tech Zone, Hefei City, Anhui Province

Patentee after: Anhui new infrastructure Co.,Ltd.

Address before: 230088 floor 12, block a, innovation Plaza, No. 222, Caihong Road, high tech Zone, Hefei, Anhui Province

Patentee before: ANHUI SIJIAN HOLDING GROUP CO.,LTD.