CN208734075U - A kind of steel structure concrete platform template installs structure - Google Patents

A kind of steel structure concrete platform template installs structure Download PDF

Info

Publication number
CN208734075U
CN208734075U CN201821177527.1U CN201821177527U CN208734075U CN 208734075 U CN208734075 U CN 208734075U CN 201821177527 U CN201821177527 U CN 201821177527U CN 208734075 U CN208734075 U CN 208734075U
Authority
CN
China
Prior art keywords
steel
template
hanging ring
flitch
steel pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821177527.1U
Other languages
Chinese (zh)
Inventor
王继良
贾久平
孟凡勇
杜保
陈兴昆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Shougang Construction Group Co Ltd
Original Assignee
Beijing Shougang Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Shougang Construction Group Co Ltd filed Critical Beijing Shougang Construction Group Co Ltd
Priority to CN201821177527.1U priority Critical patent/CN208734075U/en
Application granted granted Critical
Publication of CN208734075U publication Critical patent/CN208734075U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

A kind of steel structure concrete platform template installs structure, belongs to construction engineering technical field.Including hanging ring (1), steel pipe (2), flitch (3), template (4);The edge of a wing plate surface two-sided welding of hanging ring (1) and girder steel, steel pipe (2) is laid on hanging ring (1) stupefied as master, flitch (3) is laid on steel pipe (2) as time stupefied, and template (4) is placed on flitch (3) with steel nail fixation.Advantage is: structure fabrication is simple, and installation is convenient, can have enough to meet the need, reuse, and reduces common platform shuttering supporting occupied ground, it is convenient with each professional crossed construction, accelerate construction progress, reduction construction cost.

Description

A kind of steel structure concrete platform template installs structure
Technical field
The utility model belongs to construction engineering technical field, in particular, provides a kind of steel structure concrete platform template branch If structure.
Background technique
Steel structure concrete platform template installs structure and generally uses fastener type all round victory scaffold in building engineering construction The molding of flitch formwork reinforcement, this method is uneven for construction site, steel structure concrete platform lower has fragmentary steel knot Structure and the construction environment constructional difficulties of equipment installation cross-operation, therefore under the premise of guaranteeing the engineering entirety duration, quality, safety Structure platform formwork erection uses and hangs equipment, method.
Summary of the invention
The purpose of this utility model is to provide a kind of steel structure concrete platform template structures, solve steel construction coagulation Native platform template is installed because construction site is uneven, there are also fragmentary steel constructions and equipment to install for steel structure concrete platform lower The constructional difficulties problem such as cross-operation.It improves efficiency, reduces the construction time, reduce construction cost, guarantee concrete structure member Forming Quality.
The utility model includes hanging ring 1, steel pipe 2, flitch 3, template 4.Hanging ring 1 and steel beam flange plate surface two-sided welding, Steel pipe 2 is laid on hanging ring 1 stupefied as master, and flitch 3 is laid on steel pipe 2 as time stupefied, and template 4 is placed on flitch 3 and uses steel Fixation is followed closely, the edge joint position between template 4 is obturaged with adhesive tape.Hanging ring 1 is several fonts.
The making step of the utility model is as follows:
1,1 processing and fabricating of "Ji" type hanging ring is determined according to the size of live material steel pipe 2, flitch 3 and template 4 first Size, hanging ring and steel beam flange plate surface two-sided welding, fusion length 80mm, Size of welds hf=0.6dmm, weld bead height hf =0.6dmm;
2, hanging ring 1 be installed and acceptance(check) after be laid with that steel pipe 2 is stupefied as master, and main stupefied construction is completed and examination on it Flitch 3 is laid with after qualification as time stupefied, it is secondary it is stupefied be installed and acceptance(check) after be laid with template 4, and with level measurement template 4 Absolute altitude is corrected;4 flatness of template is checked with horizontal detection ruler simultaneously, consolidates template 4 and 3 stickfast of flitch after passed examination, Edge joint position is obturaged with adhesive tape, prevents spillage.Template 4 will be cleared up sufficiently before laying is set, brush release agent, it is ensured that structure platform Surface Quality of Concrete;
3, reinforcement construction finishes, and by inspecting for acceptance;
4, pump concrete of inspecting for acceptance pours;
5, completion is poured, concrete strength, which reaches layout design and code requirement, to be removed, must be flat when form removal Simple scaffold is arranged in platform lower part, and should have a Φ 48*3.5 steel pipe of enough strength and stiffness, upright bar spacing 1.5m, between cross bar Away from 1.8m, operating surface should be advisable away from bottom plate 2m, and operating position completely spreads scaffold board.When form removal, concrete platform and ± Necessary special messenger's nurse on the ground 0.000m, form removal region surrounding is posted a cordon and striking caution board, and non-operator must not enter It is interior, when form removal not handy sledgehammer, crowbar pound violent sled firmly, in order to avoid influence the presentation quality of concrete.
The present invention has the advantages that structure fabrication is simple, installation is convenient, can have enough to meet the need, reuse, improve efficiency, It accelerates construction progress, reduces construction cost.
Detailed description of the invention
Fig. 1 is steel structure concrete platform template support construction transverse direction schematic diagram.
Fig. 2 is steel structure concrete platform template support construction longitudinal direction schematic diagram.
Fig. 3 is hanging ring scheme of installation.
Fig. 4 is hanging ring shop detail drawing.
In figure, hanging ring 1, steel pipe 2, flitch 3, template 4.
Specific embodiment
1,1 processing and fabricating of "Ji" type hanging ring is determined according to the size of live material steel pipe 2, flitch 3 and template 4 first Size, hanging ring and steel beam flange plate surface two-sided welding, fusion length 80mm, Size of welds hf=0.6dmm, weld bead height hf =0.6dmm;
2, hanging ring 1 be installed and acceptance(check) after be laid with that steel pipe 2 is stupefied as master, and main stupefied construction is completed and examination on it Flitch 3 is laid with after qualification as time stupefied, it is secondary it is stupefied be installed and acceptance(check) after be laid with template 4, and with level measurement template 4 Absolute altitude is corrected;4 flatness of template is checked with horizontal detection ruler simultaneously, consolidates template 4 and 3 stickfast of flitch after passed examination, Edge joint position is obturaged with adhesive tape, prevents spillage.Template 4 will be cleared up sufficiently before laying is set, brush release agent, it is ensured that structure platform Surface Quality of Concrete;
3, reinforcement construction finishes, and by inspecting for acceptance;
4, pump concrete of inspecting for acceptance pours;
5, completion is poured, concrete strength, which reaches layout design and code requirement, to be removed, must be flat when form removal Simple scaffold is arranged in platform lower part, and should have a Φ 48*3.5 steel pipe of enough strength and stiffness, upright bar spacing 1.5m, between cross bar Away from 1.8m, operating surface should be advisable away from bottom plate 2m, and operating position completely spreads scaffold board.When form removal, concrete platform and ± Necessary special messenger's nurse on the ground 0.000m, form removal region surrounding is posted a cordon and striking caution board, and non-operator must not enter It is interior, when form removal not handy sledgehammer, crowbar pound violent sled firmly, in order to avoid influence the presentation quality of concrete.

Claims (4)

1. a kind of steel structure concrete platform template installs structure, it is characterised in that: including hanging ring (1), steel pipe (2), flitch (3), template (4);The edge of a wing plate surface two-sided welding of hanging ring (1) and girder steel, steel pipe (2), which is laid on hanging ring (1), is used as master stupefied, Flitch (3) is laid on steel pipe (2) as time stupefied, and template (4) is placed on flitch (3) with steel nail fixation.
2. steel structure concrete platform template according to claim 1 installs structure, it is characterised in that: hanging ring (1) is several Font.
3. steel structure concrete platform template according to claim 1 installs structure, it is characterised in that: between template (4) Edge joint position obturaged with adhesive tape.
4. steel structure concrete platform template according to claim 1 installs structure, it is characterised in that: hanging ring (1) and steel The fusion length 80mm, Size of welds hf=0.6dmm, weld bead height hf=0.6dmm of the edge of a wing plate surface two-sided welding of beam.
CN201821177527.1U 2018-07-24 2018-07-24 A kind of steel structure concrete platform template installs structure Active CN208734075U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821177527.1U CN208734075U (en) 2018-07-24 2018-07-24 A kind of steel structure concrete platform template installs structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821177527.1U CN208734075U (en) 2018-07-24 2018-07-24 A kind of steel structure concrete platform template installs structure

Publications (1)

Publication Number Publication Date
CN208734075U true CN208734075U (en) 2019-04-12

Family

ID=66028311

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821177527.1U Active CN208734075U (en) 2018-07-24 2018-07-24 A kind of steel structure concrete platform template installs structure

Country Status (1)

Country Link
CN (1) CN208734075U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110777665A (en) * 2019-11-08 2020-02-11 广州市第三市政工程有限公司 Construction method of cast-in-situ box girder skylight supporting template
CN117627342A (en) * 2024-01-26 2024-03-01 山西一建集团有限公司 Chimney lining construction mold turning inner formwork construction platform and construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110777665A (en) * 2019-11-08 2020-02-11 广州市第三市政工程有限公司 Construction method of cast-in-situ box girder skylight supporting template
CN117627342A (en) * 2024-01-26 2024-03-01 山西一建集团有限公司 Chimney lining construction mold turning inner formwork construction platform and construction method
CN117627342B (en) * 2024-01-26 2024-04-19 山西一建集团有限公司 Chimney lining construction mold turning inner formwork construction platform and construction method

Similar Documents

Publication Publication Date Title
CN103161126A (en) Road bridge variable section hollow high pier slip-form construction method
CN104947926B (en) A kind of Core Walls Structure inner core top formwork system hard protection device and its construction method
CN105714684A (en) Prestressed concrete variable cross-section fish-bellied type continuous box girder construction method
CN105804395B (en) Stair continuously poured in one molding construction method based on monoblock type typified form
CN208734075U (en) A kind of steel structure concrete platform template installs structure
CN105952133A (en) Suspended large-span reinforced concrete structure construction steel platform and construction method
CN103882813A (en) Corbel bracket platform for bridge pier and transverse straining beam synchronous construction and construction method of corbel bracket platform
CN103556823A (en) Construction method with silo sliding formwork operating platform as top cover plate formwork supporting system
CN103790423A (en) Construction method of large concrete granary
CN103758348A (en) Profile steel framework structure concrete floor slab suspension mould pouring construction method
CN108755421A (en) Capping beam construction device and construction method
CN103952979B (en) A kind of steel concrete superposed beam top board erection without scaffolding device and construction method
CN106032704A (en) Construction method for using concrete columns to support structures on both sides of post-pouring strip
CN101614039B (en) Inverted construction method for template engineering of cast-in-place shear wall structure system
CN109869153A (en) The whole of rapid construction vertical shaft lining cutting promotes cantilever form device and construction method
CN104499706B (en) Hoistway formwork platform and construction method thereof
CN210061545U (en) Prefabricated T roof beam concrete placement platform truck
CN204876516U (en) Hard protector of core section of thick bamboo inner tube upper portion die carrier system
CN106284981A (en) The mold method of two side templates in a kind of shear force wall deformation slit
CN210025768U (en) A operation platform system for caisson template installation
CN208267342U (en) High-altitude overhanging concrete structure formwork scaffold
CN111648411A (en) Downward-turning type post-cast strip support replacing structure, construction method and post-cast strip construction method
CN204386608U (en) A kind of tunnel invert construction tool
CN105275198B (en) A kind of shear-wall strengthening formwork structure and its construction method
CN102605945B (en) Manufacturing method of big wood formwork

Legal Events