CN208701685U - A kind of Superfluid state concrete pile grouting device - Google Patents

A kind of Superfluid state concrete pile grouting device Download PDF

Info

Publication number
CN208701685U
CN208701685U CN201821065607.8U CN201821065607U CN208701685U CN 208701685 U CN208701685 U CN 208701685U CN 201821065607 U CN201821065607 U CN 201821065607U CN 208701685 U CN208701685 U CN 208701685U
Authority
CN
China
Prior art keywords
grouting pipe
collar tie
tie beam
stringer
grouting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821065607.8U
Other languages
Chinese (zh)
Inventor
林国友
宋蕾
尹金香
高同玉
钟光强
董艳君
梁若东
白皓
杨威
李凤飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Liaoning Municipal Engineering Design And Research Institute Co Ltd
Original Assignee
Liaoning Municipal Engineering Design And Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Liaoning Municipal Engineering Design And Research Institute Co Ltd filed Critical Liaoning Municipal Engineering Design And Research Institute Co Ltd
Priority to CN201821065607.8U priority Critical patent/CN208701685U/en
Application granted granted Critical
Publication of CN208701685U publication Critical patent/CN208701685U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a kind of Superfluid state concrete pile grouting device, and including the steel reinforcement cage being made of multiple groups collar tie beam and stringer, the stringer is fixed on collar tie beam, and Grouting Pipe is parallel with stringer and is fixed on collar tie beam;The lower section length of Grouting Pipe is more than lower end 200-300 millimeters of collar tie beam;Conus portion is arranged in the lower section of Grouting Pipe, and the maximum gauge of conus portion is greater than the outer diameter of Grouting Pipe;Multiple outfluxes are set to the tube wall of the Grouting Pipe between collar tie beam above conus portion;The support tube of oblique top is arranged in Grouting Pipe and lower part collar tie beam bearing, and the both ends of the support tube are fixed on collar tie beam.The utility model has the advantages that: since lower end is provided with Grouting Pipe, water is injected to the Soft Soil Layer of pile foundation bottom by Grouting Pipe and cement proportion is 1;The cement slurry of 1-2 solidifies pile foundation bottom, avoids sinking for pile foundation.

Description

A kind of Superfluid state concrete pile grouting device
Technical field
The utility model relates to building field, specifically a kind of grouting device.
Background technique
In construction, pile foundation generally uses long screw drill rod to tunnel to underground to projected depth back to lift drilling rod, While drilling rod again hammers steel reinforcement cage in the pile foundation into shape after proposing by pouring channel poured concrete among drilling rod.Due to drilling rod Bottom be an incomplete helical blade, therefore, the lowermost soil of pile foundation can not but have blade after being blended by blade Output forms one 20-30 centimetres of Soft Soil Layer in the bottom of pile foundation, the axial bearing capacity of the presence of the Soft Soil Layer to pile foundation It makes a big impact, pile foundation is be easy to cause to sink.
Utility model content
In order to solve the above-mentioned technical problem, the purpose of the utility model is to provide a kind of solution pile foundation the lowermost Soft Soil Layers The sagging structure of caused pile foundation, specific technical solution are as follows:
A kind of Superfluid state concrete pile grouting device, it is described vertical including the steel reinforcement cage being made of multiple groups collar tie beam and stringer Beam is fixed on collar tie beam, and Grouting Pipe is parallel with stringer and is fixed on collar tie beam;The lower section length of Grouting Pipe is more than the lower end of collar tie beam 200-300 millimeters;Conus portion is arranged in the lower section of Grouting Pipe, and the maximum gauge of conus portion is greater than the outer diameter of Grouting Pipe;On conus portion Multiple outfluxes are arranged in the tube wall of side to the Grouting Pipe between collar tie beam;The branch of oblique top is arranged in Grouting Pipe and lower part collar tie beam bearing The both ends of stay tube, the support tube are fixed on collar tie beam.
The Grouting Pipe is 2-6 root, and is distributed along collar tie beam even circumferential.
The cone angle of conus portion is 45-60 degree.
To save cost, Grouting Pipe replaces the stringer of position.
The utility model has the advantages that: since lower end is provided with Grouting Pipe, by Grouting Pipe to the Soft Soil Layer of pile foundation bottom It injects water and cement proportion is 1;The cement slurry of 1-2 solidifies pile foundation bottom, avoids sinking for pile foundation.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model;
Fig. 2 is the top view of Fig. 1.
Specific embodiment
The utility model is illustrated with reference to the accompanying drawing, as shown, the utility model includes by multiple groups collar tie beam 1 and indulging The steel reinforcement cage that beam 2 forms, the stringer 2 are fixed on collar tie beam 1, and Grouting Pipe 3 is parallel with stringer 2 and is fixed on collar tie beam 1;Slip casting The lower section of pipe is more than that the length of collar tie beam part 4 is 200-300 millimeters;Conus portion 6 is arranged in the bottom of Grouting Pipe, and conus portion is most Major diameter is greater than the outer diameter of Grouting Pipe, in this way, can be more than collar tie beam part 4 in the lower section of Grouting Pipe in Grouting Pipe folding process Around formed a space 8, on the one hand the presence in the space 8 avoids blocking of the weak soil to Grouting Pipe tube wall outlet, another Aspect, the space are convenient for the aggregation of cement slurry, form the cement stock tank an of entirety, preferably permeate around;
Multiple outfluxes 5 are arranged in the tube wall of conus portion 6 top to the Grouting Pipe between collar tie beam;
Biggish resistance is born other than the collar tie beam of lower part since the lower end of Grouting Pipe is prominent, which can be transferred to collar tie beam, The deformation of collar tie beam is caused, to solve this problem, the support tube 7 of oblique top is arranged with lower part collar tie beam bearing for Grouting Pipe, described The both ends of support tube 7 are fixed on collar tie beam by welding.
The Grouting Pipe is 2-6 root, and is distributed along collar tie beam even circumferential.
The cone angle of conus portion is 45-60 degree.
Grouting Pipe can also replace the stringer of position.

Claims (4)

1. a kind of Superfluid state concrete pile grouting device, it is characterised in that: including the reinforcing bar being made of multiple groups collar tie beam and stringer Cage, the stringer are fixed on collar tie beam, and Grouting Pipe is parallel with stringer and is fixed on collar tie beam;The lower section length of Grouting Pipe is more than circle Lower end 200-300 millimeters of beam;Conus portion is arranged in the lower section of Grouting Pipe, and the maximum gauge of conus portion is greater than the outer diameter of Grouting Pipe; Multiple outfluxes are set to the tube wall of the Grouting Pipe between collar tie beam above conus portion;Grouting Pipe is arranged oblique with lower part collar tie beam bearing The both ends of the support tube of top, the support tube are fixed on collar tie beam.
2. Superfluid state concrete pile grouting device according to claim 1, it is characterised in that: the Grouting Pipe is 2-6 Root, and be distributed along collar tie beam even circumferential.
3. Superfluid state concrete pile grouting device according to claim 1, it is characterised in that: the cone angle of conus portion is 45-60 degree.
4. Superfluid state concrete pile grouting device according to claim 1, it is characterised in that: Grouting Pipe replaces institute in place The stringer set.
CN201821065607.8U 2018-07-06 2018-07-06 A kind of Superfluid state concrete pile grouting device Expired - Fee Related CN208701685U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821065607.8U CN208701685U (en) 2018-07-06 2018-07-06 A kind of Superfluid state concrete pile grouting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821065607.8U CN208701685U (en) 2018-07-06 2018-07-06 A kind of Superfluid state concrete pile grouting device

Publications (1)

Publication Number Publication Date
CN208701685U true CN208701685U (en) 2019-04-05

Family

ID=65937880

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821065607.8U Expired - Fee Related CN208701685U (en) 2018-07-06 2018-07-06 A kind of Superfluid state concrete pile grouting device

Country Status (1)

Country Link
CN (1) CN208701685U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110835913A (en) * 2019-11-07 2020-02-25 盐城工学院 Preparation method and preparation structure of fluid mud solidified pile with coupling effect of pre-consolidation, pre-stress and reinforcement

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110835913A (en) * 2019-11-07 2020-02-25 盐城工学院 Preparation method and preparation structure of fluid mud solidified pile with coupling effect of pre-consolidation, pre-stress and reinforcement
CN110835913B (en) * 2019-11-07 2021-10-15 盐城工学院 Preparation method and preparation structure of fluid mud solidified pile with coupling effect of pre-consolidation, pre-stress and reinforcement

Similar Documents

Publication Publication Date Title
CN202073110U (en) Concrete pile and bearing platform connecting structure
CN203756203U (en) Self-drilling type full-thread bolt grouting anchor rod
CN104847014A (en) Vertical connection structure for precast concrete shear walls and construction method
CN107604902B (en) Grouting behind shaft or drift lining bored concrete pile and its construction technology
CN210562157U (en) Post-grouting composite pile
CN109024651A (en) A kind of concrete filled steel tube mixing pile foundation and construction method
US10161096B2 (en) Ground reinforcing device
CN102605773A (en) Construction method of slip-casting expanded-base cast-in-situ bored pile and extruding-extending device thereof
CN208701685U (en) A kind of Superfluid state concrete pile grouting device
CN202644519U (en) Special fixing clamp for preventing reinforcement cage of cast-in-situ bored pile from floating upward
CN104563147A (en) Composite structure pile foundation applied to karst area and construction method of composite structure pile foundation
CN103410144B (en) Prestressed reinforcement piles set into rock and construction method
CN207998838U (en) A kind of compound pile pile of resistance to plucking
CN104594343B (en) A kind of assembled stake and its construction method
CN107299644A (en) A kind of pile anchor rod basis available for soft clay area
CN204491620U (en) Drilled pile is super fills with controller
CN103911986B (en) A kind of construction method combining strike-on steel pipe pile
CN103882859B (en) A kind of original state of Shi Hanzhang fetches earth cast-with-pressure concrete pile and construction method thereof
CN101979777A (en) Cast-in-place hollow square pile and combined underground continuous wallboard and construction method thereof
CN104452748B (en) Filling type reinforcing self tapping stake and preparation method thereof
CN107190737A (en) A kind of construction technology of high intensity mould bag stake
CN207193966U (en) A kind of prestressed concrete pipe pile
CN209585028U (en) A kind of open caisson applies broken pile
CN208251078U (en) A kind of bottom-expanding sinking-pipe pilework
CN103205974B (en) The supporting construction that pregroove stake is combined with mixing pile

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190405

Termination date: 20190706