CN208650050U - Uplift pile - Google Patents

Uplift pile Download PDF

Info

Publication number
CN208650050U
CN208650050U CN201820932397.1U CN201820932397U CN208650050U CN 208650050 U CN208650050 U CN 208650050U CN 201820932397 U CN201820932397 U CN 201820932397U CN 208650050 U CN208650050 U CN 208650050U
Authority
CN
China
Prior art keywords
pile body
pile
sub
uplift
cement slurry
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820932397.1U
Other languages
Chinese (zh)
Inventor
左熹
倪红
周桂云
顾荣蓉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jinling Institute of Technology
Original Assignee
Jinling Institute of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jinling Institute of Technology filed Critical Jinling Institute of Technology
Priority to CN201820932397.1U priority Critical patent/CN208650050U/en
Application granted granted Critical
Publication of CN208650050U publication Critical patent/CN208650050U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a kind of uplift pile, belongs to technical field of building construction, solves the not high technical problem of the breakout capacity of uplift pile in the prior art, and the utility model provides the technical solution of two kinds of solutions;It is all the structure by the way that a pile body and multiple pile bodies is arranged in first and second technical solution, occlusion portion/barb that the junction between pile body and pile body protrudes outward composition can be used in being mutually twisted with building soil layer, improve its breakout capacity;The first technical solution reinforces the intensity of entire pile body by the cement slurry runner of one perforation of setting;Second of technical solution, the structure for being combined into combination pile body by the way that multiple sub- pile bodies are arranged, so that the length of pile body can be realized by increasing or decreasing sub- pile body, it being capable of adaptation to local conditions, by the way that the up big and down small cement slurry runner of diameter is arranged in each sub- pile body, so that the pile body after combination is capable of forming an entirety, reinforce the intensity connected between sub- pile body and sub- pile body.

Description

Uplift pile
Technical field
The utility model relates to technical field of building construction, in particular to a kind of uplift pile.
Background technique
The Chinese utility model patent application of Publication No. CN102363956A discloses a kind of uplift pile, for uplift pile Because using welding between the buoyancy and pile body by underground water due to the not high technical problem for causing its breakout capacity weak of intensity, Following technical solution is disclosed in its specification;Its by increasing pile body entire surface to the frictional force of sub-surface, increase stake with Stake between bonding strength and improve pile body to the drag of the buoyancy of underground water, using the stake of solid construction, between stake and stake It is fastenedly connected by fasteners such as connecting plate and bolts, and the overlapping between plate welds setting.Since pile body is long-term It is embedded in subsurface, the metal fastenings such as commissure or bolt are likely to encounter aqueous vapor and corrode, and destroy the connection between stake and stake Intensity, to reduce the breakout capacity of uplift pile.
The Chinese utility model patent of Publication No. CN100585092C discloses the pile making method of pressing-resistant plucking-resistant, needle To straight columnar bored concrete pile, bearing capacity and the limited technical problem of resistance to compression breakout capacity, disclosed in its specification as Lower technical solution;The pile foundation main body constituted using reinforcing bar and concrete, reinforcing bar is expanded outwardly in the bottom of pile foundation main body, in pile foundation The chassis that radial dimension is greater than the big head of pile foundation main part is formed on the bottom of main body, but the pile foundation of this spline structure needs Additional processing goes out multiple for being put into the through-hole of reinforcing bar on the tube wall of steel pipe mould, and when squeezing into steel pipe mould in ground, needs Two-hit reinforcing bar is wanted, so that reinforcing bar exposes steel pipe film, construction technology is relatively complicated.
The Chinese utility model patent application of Publication No. 105133599A discloses a kind of uplift pile, for pile body and week Enclose soil property frictional force be only pile body outer wall provide, the not high technical problem of breakout capacity, disclosed in its specification as Lower technical solution;By the way that multiple stage portions are arranged on pile body, so that pile body can obtain good resistance to plucking in each soil layer Power, but pile body is solid construction, the connection between two neighboring pile body is by opening up connection on the length direction of pile body The pile body manufacture difficulty in hole, this spline structure is larger, and if the method for filling in conjunction with disclosed in publication number CN100585092C Words, it will there is the bonding strength problem between pile body, the withdrawal resistance of pile body can be much smaller than due to the bonding strength between pile body, It is easy to appear the defect that the junction being opened between even pile body between pile body is pulled off.
Utility model content
In order to solve the above-mentioned technical problem, the purpose of the utility model is to provide a kind of stronger uplift piles of breakout capacity.
In order to realize the purpose of above-mentioned utility model, the utility model is using the first following technical solution:
A kind of uplift pile, it is characterised in that: including pile body, form multiple pile bodies of the pile body and run through the pile body Cement slurry runner, multiple pile bodies are successively fixedly installed, and each pile body has first end and the second end, The transverse width of the first end is greater than the transverse width of the second end, in the two neighboring pile body described in one The first end of the second end of pile body and another pile body is fixedly installed, and the junction of first and second end is outside It is prominent to constitute the uplift pile and build occlusion portion/barb that soil layer is mutually twisted.
In above-mentioned technical proposal, it is preferred that be provided at least one and the cement slurry runner on each pile body The through-hole communicated.
In above-mentioned technical proposal, it is preferred that each pile body has the outer diameter being gradually reduced from top to bottom.
In above-mentioned technical proposal, it is preferred that multiple pile bodies are integrally formed the pile body.
In above-mentioned technical proposal, it is preferred that each pile body is in a circular table shape, and first and second end is rounded.
In order to realize the purpose of above-mentioned utility model, the utility model uses following second of technical solution:
A kind of uplift pile characterized by comprising combination pile body, the combination pile body include multiple being mutually arranged Sub- pile body, each sub- pile body is a global facility, and each sub- pile body has the first open end and second Open end and the cement slurry runner between first and second open end, the diameter of first open end are greater than described The diameter of second open end, the second open end of a sub- pile body is set in another in the two neighboring sub- pile body In first open end of the sub- pile body, the junction that is arranged of first and second open end protrudes outward the composition uplift pile Occlusion portion/the crook being mutually twisted with building soil layer, multiple cement slurry runners are successively connected, each water Mud stream road has the internal diameter being gradually reduced from top to bottom.
In above-mentioned technical proposal, it is preferred that be provided on each sub- pile body at least one to it is each it is corresponding described in The through-hole that cement slurry runner communicates.
In above-mentioned technical proposal, it is preferred that each sub- pile body is in a circular table shape, each sub- pile body first, Two open ends are rounded.
In above-mentioned technical proposal, it is preferred that each sub- pile body has the outer diameter being gradually reduced from top to bottom.
The utility model obtains following the utility model has the advantages that the first and second technical solution, is all to pass through setting compared with prior art The structure of one pile body and multiple pile bodies, the junction between pile body and pile body protrude outward occlusion portion/barb energy of composition It is enough in and is mutually twisted with building soil layer, improve its breakout capacity;The first technical solution passes through the cement of one perforation of setting Runner is starched, the intensity of entire pile body is reinforced;Second of technical solution, the knot for being combined into combination pile body by the way that multiple sub- pile bodies are arranged Structure so that the length of pile body can be realized by increasing or decreasing sub- pile body, can adaptation to local conditions, by each sub- pile body The up big and down small cement slurry runner of diameter is set, so that the pile body after combination is capable of forming an entirety, reinforces sub- pile body and son The intensity connected between pile body;Construction method processing step is simple, convenient for operation.
Detailed description of the invention
Attached drawing 1 is the schematic front view of the uplift pile of the utility model first embodiment;
Attached drawing 2 is the stereoscopic schematic diagram of the uplift pile of the utility model second embodiment;
Attached drawing 3 is the stereoscopic schematic diagram of the sub- pile body of the utility model second embodiment;
Attached drawing 4 is the schematic front view of the sub- pile body of the utility model second embodiment;
Attached drawing 5 is the main view cut-away illustration of the sub- pile body of the utility model second embodiment;
Attached drawing 6 is the construction effect schematic diagram of the uplift pile of the utility model second embodiment;
Wherein: 100, uplift pile;1, pile body;11, pile body;111, first end;112, the second end;113, through-hole;12, Cement slurry runner;13, occlusion portion/barb;200, uplift pile;2, pile body is combined;21, occlusion portion/crook;3, sub- pile body; 31, the first open end;32, the second open end;33, cement slurry runner;34, through-hole.
Specific embodiment
By the technology contents of utility model are described in detail, construction feature, are reached purpose and efficacy, below in conjunction with implementation Example simultaneously cooperates attached drawing to be described in detail.
First embodiment: with reference to the accompanying drawings shown in 1, uplift pile 100 include one vertically extend pile body 1, formed stake Multiple pile bodies 11 of body 1 and cement slurry runner 12 through pile body 1.Wherein, multiple pile bodies 11 are successively fixedly installed.In this example In, each pile body 11 has superposed first end 111 and the second end 112 positioned at lower part, and first end 111 Transverse width be greater than the transverse width of the second end 112, in two neighboring pile body 11 the second end 112 of a pile body 11 with The first end 111 of another pile body 11 is fixedly installed.The junction of first and second end protrude outward constitute uplift pile 100 with Occlusion portion/barb 13 that building soil layer is mutually twisted.In other embodiments, multiple pile bodies 11 are integrally formed pile body 1;It can also Can being fastenedly connected by external fastener or connector between two neighboring pile body 11, for example, stiffening plate or dowel. Wherein, positional relationship is corresponding with the positional relationship of uplift pile 100 shown in attached drawing 1 up and down described in this example, institute The transverse direction stated is the direction that the left and right of uplift pile 100 shown in attached drawing 1 extends.
In order to further strengthen the breakout capacity of uplift pile 100, multiple and cement slurry runner is provided on each pile body 11 12 through-holes 113 communicated.In this example, 8 through-holes 113 are offered on each pile body 11, so, uplift pile 100 is embedded in When building soil layer or less, it will be flowed out from through-hole 113 by the cement slurry that cement slurry runner 12 injects, to cement slurry sets Afterwards, the cement slurry flowed out by this through-hole 113 will form the engaging portion of the tree root shape in conjunction with building soil layer.
In order to further strengthen occlusion portion/barb 13 and build the keying strength between soil layer, each pile body 11 has The outer diameter being gradually reduced from top to bottom.Each pile body 11 is in a circular table shape, and the first and second end is rounded.
Second embodiment: with reference to the accompanying drawings shown in 2~attached drawing 5, uplift pile 200 includes a combination pile body 2, the combination pile body 2 It is composed of multiple sub- pile bodies 3 being mutually arranged.Each sub- pile body 3 is a global facility, and each sub- pile body 3 is in rotary table Shape, each sub- pile body 3 have the first open end 31 and the second open end 32 and the cement slurry between the first and second open end Runner 33, the diameter of the first open end 31 are greater than the diameter of the second open end 32, a sub- pile body 3 in two neighboring sub- pile body 3 The second open end 32 be set in the first open end 31 of another sub- pile body 3, the first and second open end be arranged junction to It is outer it is prominent constitute uplift pile 200 and build occlusion portion/crook 21 that soil layer is mutually twisted, multiple cement slurry runners 33 successively phase It connects, each cement slurry runner 33 has the internal diameter being gradually reduced from top to bottom.
In order to further strengthen the breakout capacity of uplift pile 200, it is provided on each sub- pile body 3 multiple to each corresponding water The through-hole 34 that mud runner 33 communicates.In this example, 8 through-holes 113, so, uplift pile are offered on each sub- pile body 3 200 be embedded in building soil layer below when, by cement slurry runner 33 inject cement slurry will be flowed out from through-hole 34, to cement After slurry solidification, the cement slurry flowed out by this through-hole 34 will form the engaging portion of the tree root shape in conjunction with building soil layer.
In order to further strengthen occlusion portion/crook 21 and build the keying strength between soil layer, each sub- pile body 3 has The outer diameter being gradually reduced from top to bottom.
The construction method of uplift pile 200 shown in 6 with reference to the accompanying drawings, including following construction procedure:
1. drill out drilling in advance on building soil layer, the sum of diameter of the diameter of drilling and first and second open end Average value is roughly equal;
2. multiple sub- pile bodies to be successively arranged to and are combined into the combination pile body, the length of the combination pile body It spends roughly equal with the depth of the drilling;
3. injecting cement slurry from the bottom of combination pile body by high-pressure slip-casting pipe, cement slurry is injected on one side, on one side by high pressure Grouting Pipe is lifted up, so that being full of cement slurry in the cement slurry runner of each sub- pile body, and cement slurry is led to from described Hole outflow;
4. after cement slurry sets, the cement slurry inside built pile body forms the company for connecting two neighboring sub- pile body Column is connect, the cement slurry flowed out from the through-hole forms the engaging portion of the tree root shape in conjunction with building soil layer, is finally completed uplift pile Construction operation.
The above embodiments are only for explaining the technical ideas and features of the present invention, and its object is to allow be familiar with technique Personage can understand the content of the utility model and implement accordingly, do not limit the protection scope of the present invention. All equivalent changes or modifications made according to the spirit of the present invention should be covered within the scope of the utility model.

Claims (9)

1. a kind of uplift pile, it is characterised in that: including pile body (1), form multiple pile bodies (11) of the pile body (1) and run through The cement slurry runner (12) of the pile body (1), multiple pile bodies (11) are successively fixedly installed, each pile body (11) With first end (111) and the second end (112), the transverse width of the first end (111) is greater than the second end (112) transverse width, in the two neighboring pile body (11) the second end (112) of a pile body (11) with it is another The first end (111) of a pile body (11) is fixedly installed, and the junction of first and second end protrudes outward described in composition Occlusion portion/barb (13) that uplift pile and building soil layer are mutually twisted.
2. uplift pile according to claim 1, it is characterised in that: be provided at least one on each pile body (11) The through-hole (113) communicated with the cement slurry runner (12).
3. uplift pile according to claim 1, it is characterised in that: each pile body (11) has from top to bottom gradually Reduced outer diameter.
4. uplift pile according to claim 1, it is characterised in that: multiple pile bodies (11) are integrally formed the stake Body (1).
5. uplift pile according to claim 1, it is characterised in that: each pile body (11) in hollow round table-like, First and second end is rounded.
6. a kind of uplift pile characterized by comprising combination pile body (2), the combination pile body (2) includes multiple mutual sets If sub- pile body (3), each sub- pile body (3) is a global facility, and each sub- pile body (3) has first Open end (31) and the second open end (32) and the cement slurry runner (33) between first and second open end, it is described The diameter of first open end (31) is greater than the diameter of second open end (32), one in the two neighboring sub- pile body (3) The second open end (32) of a sub- pile body (3) is set in the first open end (31) of another sub- pile body (3), institute State the first and second open end be arranged junction protrude outward constitute the uplift pile and occlusion portion that building soil layer is mutually twisted/ Crook (21), multiple cement slurry runners (33) are successively connected, and each cement slurry runner (33) has certainly The internal diameter being gradually reduced under.
7. uplift pile according to claim 6, it is characterised in that: be provided at least one on each sub- pile body (3) A through-hole (34) communicated to each corresponding cement slurry runner (33).
8. uplift pile according to claim 6, it is characterised in that: each sub- pile body (3) is in a circular table shape, Ge Gesuo The first and second open end for stating sub- pile body (3) is rounded.
9. uplift pile according to claim 6, it is characterised in that: each sub- pile body (3) have from top to bottom by Decrescence small outer diameter.
CN201820932397.1U 2018-06-15 2018-06-15 Uplift pile Active CN208650050U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820932397.1U CN208650050U (en) 2018-06-15 2018-06-15 Uplift pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820932397.1U CN208650050U (en) 2018-06-15 2018-06-15 Uplift pile

Publications (1)

Publication Number Publication Date
CN208650050U true CN208650050U (en) 2019-03-26

Family

ID=65780531

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820932397.1U Active CN208650050U (en) 2018-06-15 2018-06-15 Uplift pile

Country Status (1)

Country Link
CN (1) CN208650050U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108677934A (en) * 2018-06-15 2018-10-19 金陵科技学院 The construction method of uplift pile and uplift pile

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108677934A (en) * 2018-06-15 2018-10-19 金陵科技学院 The construction method of uplift pile and uplift pile
CN108677934B (en) * 2018-06-15 2024-01-19 金陵科技学院 Anti-pulling pile anti-cancer agent pile pulling construction method

Similar Documents

Publication Publication Date Title
US11299864B2 (en) Jetting, expansion and extrusion combined pile, construction method thereof and spiral jetting, expansion and extrusion drilling rig used in method
CN209854705U (en) Cement soil inserted PHC tubular pile bag grouting expanding pile
CN102691296A (en) Pipe pile foundation for static-pressure grouting on pile side and rotary jet grouting at pile bottom and construction method thereof
CN206784372U (en) Injection forming club-footed pile
CN208472708U (en) A kind of grouting behind shaft or drift lining filling pile structure
CN108677934A (en) The construction method of uplift pile and uplift pile
CN106759295B (en) The quiet combined pile and its construction method for boring extruding-enlarging branch tray and tubular pole
CN208650050U (en) Uplift pile
CN104196013B (en) A kind of composite Y shape stake and construction method thereof
CN207582459U (en) A kind of prefabricated steel-pipe pile of variable cross-section
CN202787275U (en) Tubular soil nailing wall of novel pneumatic impact anchor
CN101024958A (en) Drilling poured-pile hole-bottom slurry-injection pile-forming method
CN206279525U (en) A kind of band edge of a wing variable cross-section prefabricated pile
CN209293051U (en) A kind of open caisson reserved opening plugging structure
CN202099803U (en) Post grouting device of enlarged head of prestressed concrete tube pile
CN205975582U (en) Improve device of hollow pile bearing capacity
CN209178989U (en) A kind of PHC tubular pole anti-freeze expansion processing unit
CN209260899U (en) A kind of steel pipe connecting node of assembly concrete column
CN208039240U (en) A kind of built pile
CN202124857U (en) Splitting pile
CN102127910B (en) Method for constructing soil-cement composite foundation pile as core tubular pile
CN206887953U (en) Soil nailing port closing device and soil nailing wall structure
CN204098023U (en) The stake of a kind of composite Y shape
CN204849735U (en) Weak crowded native precast pile of opening type
CN203256736U (en) Composite pile with strongly-stirred soil implanted with rigid body and embedded with hard bearing layer

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant