CN208586801U - A kind of integrated smallpox light trough construction of lightgage steel joist frame - Google Patents

A kind of integrated smallpox light trough construction of lightgage steel joist frame Download PDF

Info

Publication number
CN208586801U
CN208586801U CN201821019664.2U CN201821019664U CN208586801U CN 208586801 U CN208586801 U CN 208586801U CN 201821019664 U CN201821019664 U CN 201821019664U CN 208586801 U CN208586801 U CN 208586801U
Authority
CN
China
Prior art keywords
frame body
setting
frame
light trough
integrated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821019664.2U
Other languages
Chinese (zh)
Inventor
汤平
蒋应德
张德玉
张德富
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Jufengyuan Design And Decoration Engineering Co Ltd
Original Assignee
Shenzhen Jufengyuan Design And Decoration Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Jufengyuan Design And Decoration Engineering Co Ltd filed Critical Shenzhen Jufengyuan Design And Decoration Engineering Co Ltd
Priority to CN201821019664.2U priority Critical patent/CN208586801U/en
Application granted granted Critical
Publication of CN208586801U publication Critical patent/CN208586801U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model provides a kind of integrated smallpox light trough construction of lightgage steel joist frame, it is related to furred ceiling technical field, aim to solve the problem that lightgage steel joist frame constitutes the problem of staged smallpox light trough fashionable dress connects low efficiency in the prior art, it includes the first frame body in rectangular-ambulatory-plane setting, the second frame body in rectangular-ambulatory-plane setting is equipped in first frame body, third frame body is equipped in second frame body, several U-shaped steels being vertically arranged are equipped with around the first frame body and the second frame body inner circumferential array, second frame body and third frame body periphery are correspondingly provided with the adjustment sheet that sliding is plugged in U-shaped steel, second frame body and third frame body are connected to wall top by postposition sunpender and are arranged.The utility model cooperates postposition sunpender by the first frame body, the second frame body and third frame body of integrated setting, and the rapid shaping of smallpox light trough construction is realized using the sliding grafting of U-shaped steel and adjustment sheet, to improve construction efficiency, and its in-site installation is generated without waste wood, meets the requirement of environmental protection finishing.

Description

A kind of integrated smallpox light trough construction of lightgage steel joist frame
Technical field
The utility model relates to furred ceiling technical field, in particular to the integrated smallpox light trough of a kind of lightgage steel joist frame Construction.
Background technique
It is miscellaneous with the development of national economy, social progress, the promotion of design level and the demand in market Interior Design Style trend continues to introduce new, and the miscellaneous smallpox moulding of cooperation interior decoration aesthetic feeling is also increasingly to have Intention, especially smallpox light trough are seen everywhere in designing indoors, are widely used.But in the prior art, wood is generallyd use Matter wood-based plate makes smallpox light trough.Have many defects using wood-base fibre and particle panel material production smallpox light trough: 1, wood-base fibre and particle panel material burns Performance rate does not meet the requirement of " code for fire prevention design of interior decoration of buildings ";2, heavy workload, cumbersome are made not Specification does not meet the development trend that building decoration gradually changes to batch production centralized production;3, wood-base fibre and particle panel material material cost is high; 4, the social desirability for recycling, saving material, environmental protection and energy saving low-carbon is not met.
Therefore, notification number is that the Chinese utility model patent of CN202370147U discloses a kind of day of lightgage steel joist skeleton Festive lantern slot construction, comprising: ceiling fixed to the top lightgage steel joist frame on the ceiling and is mounted on by the first sunpender pendency Side lightgage steel joist frame at least one end of the left and right directions of the top lightgage steel joist frame.In the utility model, The fire protecting performance of smallpox light trough is effectively improved as smallpox light trough substrate due to using lightgage steel joist, and is made The manufacture craft for obtaining smallpox light trough is simplified, while greatly reducing product cost, and product meets environmental requirement.
But in the smallpox light trough of this lightgage steel joist skeleton construction, does not design level-one Ceiling light slot structure and need separately Outer attaching side lightgage steel joist frame, and the smallpox light trough of multi-stage stepwise is constructed, it needs to overlap side lightgage steel joist repeatedly Frame and its connecting component, thus using this structure assembly trouble, efficiency is lower.
Utility model content
The purpose of the utility model is to provide a kind of integrated smallpox light trough of lightgage steel joist frame constructions, have integration Setting, convenient formation, the higher advantage of efficiency.
The above-mentioned technical purpose of the utility model has the technical scheme that a kind of lightgage steel joist frame Integrated smallpox light trough construction is connected between first frame body and wall top including the first frame body in rectangular-ambulatory-plane setting First sunpender is equipped with the second frame body in rectangular-ambulatory-plane setting in first frame body, is additionally provided with third frame in second frame body Body is equipped with several U-shaped steels being vertically arranged around first frame body and the second frame body inner circumferential array, second frame body and the Triframe body periphery is correspondingly provided with the adjustment sheet that sliding is plugged in U-shaped steel, and second frame body and third frame body are hung by postposition Bar is connected to wall top setting, and the positioning device for secured adjusted piece position is equipped at the U-shaped steel.
By using above-mentioned technical proposal, according to required ceiling structure and the good lightgage steel joist frame of Ceiling light groove structure design Structure, and it includes the first frame body, the second frame body and third frame body being wholely set, wherein the first frame body and the second frame body are in Rectangular-ambulatory-plane setting, so that multilayered structure is formed, to push up the second frame body and third frame body after entirety is hung and connect, and Postposition length of boom is selected at a distance from wall top according to the second frame body, to fix the second frame body position, then pushes third frame body It continues up, forms stepped Ceiling light slot structure, and according to third frame body postposition sunpender corresponding with wall top distance selection Length, to fix third frame body position;Wherein, the setting of U-shaped steel can not only cooperate adjustment sheet be oriented to the second frame body and The sliding of third frame body, moreover it is possible to cooperate positioning device to pre-fix the position after the second frame body and the jacking of third frame body, thus side Just staff is fixed using postposition sunpender, and then facilitates installation, improves decoration efficiency.
Further, the U-shaped steel bottom end closure is equipped with baffle, when the adjustment sheet is connected to baffle top surface, described the During one frame body, the second frame body and third frame body are generally aligned in the same plane.
By using above-mentioned technical proposal, U-shaped steel bottom is provided with baffle, to avoid adjustment sheet from U-shaped steel bottom It is detached from, and then avoids the first frame body, the second frame body and the separation of third frame body;Meanwhile the setting of adjustment sheet can also pass through first Body holds the second frame body and third frame body, and construction personnel is facilitated integrally to promote installation.
Further, U-shaped steel opening two sides are provided inwardly with flange, the adjustment sheet two sides be connected in respectively flange with Angle setting between U-shaped steel side plate.
By using above-mentioned technical proposal, upper overturning is set in the two sides of U-shaped steel, and adjustment sheet two sides are connected to flange Between the side plate of U-shaped steel, to block adjustment sheet, avoids adjustment sheet from being laterally detached from U-shaped steel and influence the first frame body and the Two frame bodies, the second frame body are docked with third frame body.
Further, the positioning device includes the butt hole group that the U-shaped steel is arranged close to the first frame body side, described Butt hole group includes two spaced butt holes, and grafting is equipped with the docking block for the setting that is in U-shape in the butt hole group, described Adjustment sheet is plugged in docking block setting.
By using above-mentioned technical proposal, after mobile adjustment sheet to predeterminated position, the grafting at corresponding butt hole group Upper docking block, and it is plugged on adjustment sheet in docking block, it is adjusted to be driven using the gravity of the second frame body or third frame body itself Nodal plate pushes down corresponding docking block, fixes docking block position, and then provide support platform using docking block for adjustment sheet, convenient Postposition sunpender is arranged in construction personnel.
Further, the butt hole group is set as multiple groups along the vertical direction.
By using above-mentioned technical proposal, butt hole group is set as multiple groups, to facilitate construction personnel to be selected according to actual condition Select the butt hole group secured adjusted piece of a height.
Further, the postposition sunpender includes the expansion bolt for being fixed in wall top, and wall is stretched out in the expansion bolt bottom Body setting, and its bottom is connected with adjusting rod, the adjusting rod bottom end is fixed in the main joist of the second frame body and third frame body Setting.
By using above-mentioned technical proposal, since the distance between the second frame body, third frame body and wall top are indefinite, Realize that the drawing of hanging of postposition sunpender acts on the connection cooperation adjusting rod of adjusting rod with docking for main joist by expansion bolt, and can The adjusting rod of dismantling connection can facilitate construction personnel to be closed according to the second frame body or the selection of the distance between third frame body and wall top Suitable adjusting pole length.
Further, the adjusting rod top is provided with screw hole, and the expansion bolt bottom thread is connected in screw hole.
By using above-mentioned technical proposal, expansion bolt is realized by the cooperation of expansion bolt and the screw hole for adjusting boom end With being connected and fixed for adjusting rod, to facilitate the affixed postposition sunpender of construction personnel.
Further, the bottom surface of the main joist of second frame body and third frame body is provided with link slot, the link slot slot Bottom penetrates through main joist and is equipped with connecting hole, and the adjusting rod is plugged in connecting hole, and protrudes into link slot setting, the adjusting rod bottom End is threaded with the T-piece being connected in link slot.
By using above-mentioned technical proposal, link slot is protruded into connecting rod bottom, and be threadedly coupled T shape in connecting rod bottom end Part holds the main joist of the second frame body or third frame body by the clamping effect of T-piece and link slot.
In conclusion the utility model has the effect that through the first frame body of integrated setting, the second frame body and Triframe body cooperates postposition sunpender, and the rapid shaping of smallpox light trough construction is realized using the sliding grafting of U-shaped steel and adjustment sheet, from And improve construction efficiency.
Detailed description of the invention
Fig. 1 is a kind of overall structure diagram of the integrated smallpox light trough construction of lightgage steel joist frame of the utility model;
Fig. 2 is the enlarged drawing of part A in Fig. 1;
Fig. 3 is the explosive view of U-shaped steel and adjustment sheet part;
Fig. 4 is the enlarged drawing of part B in Fig. 1;
Fig. 5 is the explosive view of adjusting rod and link slot part.
In figure, the 1, first frame body;11, the first sunpender;12, the second frame body;13, third frame body;2, U-shaped steel;21, flange; 22, butt hole group;221, butt hole;23, block is docked;24, fixing bolt;25, baffle;3, adjustment sheet;31, grab;4, postposition Sunpender;41, expansion bolt;42, adjusting rod;421, screw hole;43, link slot;431, connecting hole;432, card slot;44, T-piece;5, Positioning device.
Specific embodiment
The utility model is described in further detail below in conjunction with attached drawing.
Embodiment: a kind of integrated smallpox light trough construction of lightgage steel joist frame, as shown in Figure 1, including being arranged in rectangular-ambulatory-plane The first frame body 1, the first sunpender 11 is connected between first frame body 1 and wall top, attaching has in Back Word in the first frame body 1 Second frame body 12 of shape setting, and also attaching has third frame body 13 in the second frame body 12, here, the first frame body 1, the second frame body 12 and third frame body 13 be all lightgage steel joist skeleton structure, formed by main joist and secondary joist attaching;Around the first frame body 1 and second 12 inner circumferential array of frame body is provided with several U-shaped steels 2 being vertically arranged, as shown in Fig. 2, and in the second frame body 12 and third frame body 13 peripheries are correspondingly arranged on the adjustment sheet 3 that sliding is plugged in U-shaped steel 2, and the second frame body 12 and third frame body 13 pass through postposition Sunpender 4 is connected to wall top setting, and the positioning device 5 for 3 position of secured adjusted piece is provided at U-shaped steel 2.
In the prior art, it in order to form stair-stepping smallpox light trough construction, needs to be layered one by one to hang and connects each light steel dragon Skeleton, attaching trouble, construction efficiency are lower;Therefore, by 13 integrated setting of the first frame body 1, the second frame body 12 and third frame body, After hanging entire lightgage steel joist frame and being connected to wall top, the first frame body 1 is fixed in wall top by the first sunpender 11, and utilizes first The second frame body 12 and third frame body 13 are held in the connection of body 1 and the second frame body 12, third frame body 13, and subsequent installation is facilitated to make Industry;And after the affixed molding of the first frame body 1, the second frame body 12, are gradually pushed up by the cooperation of U-shaped steel 2 and adjustment sheet 3 Triframe body 13 forms staged smallpox light trough construction, further according to the second frame body 12 and third frame body 13 and wall top to preset height Distance select suitable postposition sunpender 4, by its it is stable be fixed in wall top, to realize the fast of multi-stage stepwise smallpox light trough Rapid-result type improves construction efficiency;In addition, in practical applications, it is not limited only to two-stage ladder, it can be according to the actual situation by third frame Body 13 is made as rectangular-ambulatory-plane in advance and adds remaining lightgage steel joist frame structure, improves its applicability.
In order to realize the integration of the first frame body 1, the second frame body 12 and third frame body 13, the second frame body 12 and third are avoided Frame body 13 is detached from termination process in hanging for the first frame body 1 and influences construction progress, therefore, as shown in Fig. 2, U-shaped steel 2 is set to The top of 12 inner circumferential frame of first frame body 1 and the second frame body, and its opening is respectively facing 12 periphery of the second frame body and third frame body The setting of 13 peripheries, here, the closing of 2 bottom of U-shaped steel are provided with baffle 25, top opening setting, and adjustment sheet 3 is set to the second frame The top of 13 peripheral frame of body 12 and third frame body is arranged;Meanwhile the frame of first frame body 1, the second frame body 12 and third frame body 13 When frame structure is in same plane, adjustment sheet 3 is overlapped in the setting of 25 top surface of baffle in U-shaped steel 2.In this way, passing through adjustment sheet 3 With the overlap joint of 2 bottom baffle 25 of U-shaped steel be that the second frame body 12 with third frame body 13 provides support platform, and realize the first frame body 1, The integrated structure of second frame body 12 and third frame body 13.
In addition, as shown in figure 3, have a flange 21 in the inside convolution in 2 two sides of U-shaped steel, and 3 two sides of adjustment sheet cooperation grab 31 exists In angle between flange 21 and the side plate of U-shaped steel 2.In this way, blocking adjustment sheet 3 by the setting of flange 21, adjustment sheet 3 is prevented Movement in the horizontal direction improves the stabilization shape of connection structure.
After hanging and connecing and finish the first frame body 1, the second frame body 12 and third frame body 13 are gradually pushed up, and by the second frame After body 12 and third frame are pushed to predeterminated position, in order to be positioned to the second frame body 12 and third frame body 13, as shown in figure 3, Positioning device 5 includes the butt hole group 22 that U-shaped steel 2 is arranged close to 1 side outer wall of the first frame body, and here, butt hole group 22 includes Two spaced butt holes 221, and the docking block 23 for the setting that is in U-shape in grafting in butt hole 221 docks block here 23 both side plate distinguishes grafting into corresponding butt hole 221, meanwhile, adjustment sheet 3 is plugged in docking block 23, and in butt hole Run through the fixing bolt 24 of adjustment sheet 3 in 221 screw top grafting.In this way, passing through the setting of butt hole 221, adjustment sheet 3 is consolidated It is scheduled at the butt hole group 22 opened up in U-shaped steel 2, positioning of the realization to the second frame body 12 or third frame body 13, and adjustment sheet 3 Adjustment sheet 3 is fixed with the fixing bolt 24 being arranged on the mating docking block 23 for docking block 23, to pre-fix the second frame The connection of body 12 and the first frame body 1, the connection of third frame body 13 and the second frame body 12.
In addition, as shown in figure 3, butt hole group 22 is set as multiple groups along the vertical direction, to facilitate construction personnel according to reality Border operating condition selects suitable butt hole group 22 to be positioned.
And after the second frame body 12 and third frame body 13 are pre-fixed, in order to facilitate construction personnel be arranged postposition sunpender 4, one Aspect, as shown in figure 5, it is prefabricated with expansion bolt 41 in wall top, and the screw portion of 41 bottom of expansion bolt stretches out wall top setting, 41 bottom of expansion bolt is provided with adjusting rod 42, screw hole 421 is provided at the top of adjusting rod 42, expansion bolt 41 is threaded in spiral shell In hole 421;On the other hand, as shown in figure 4, corresponding to adjusting rod 42 on the ground of the second frame body 12 and the main joist of third frame body 13 Position is provided with link slot 43, and here, main joist is rectangular channel steel, and connecting hole 431 is provided at the top of it, and connecting hole 431 penetrates through It is arranged to link slot 43, and adjusting rod 42 is connected in connecting hole 431, and is threaded with T-piece 44 in 42 bottom end of adjusting rod, Here, T-piece 44 is set in link slot 43, and it is being arranged perpendicular to the width on main joist direction greater than main joist.In this way, Main joist is held by the clamping of T-piece 44 and main joist, so that the second frame body 12 and third frame body 13 are hung on wall top.
And hang connect for convenience, as shown in figure 5, connecting hole 431 is arranged in kidney-shaped, and the main joist in 43 two sides of link slot Card slot 432 is provided on side plate upwards, here, card slot 432 be provided with along main joist length direction it is multiple, and 44 two sides of T-piece insert It is connected in card slot 432.In this way, the cooperation for the connecting hole 431 and card slot 432 being arranged by kidney-shaped can facilitate construction personnel to the Two frame bodies 12 and 13 position of third frame body are finely adjusted, and eliminating processing and construction error leads to 4 position of postposition sunpender and connecting hole The inconvenience of the not corresponding band in 431 positions.
The above is only the preferred embodiment of the utility model, and the protection scope of the utility model is not limited merely to Above-described embodiment, technical solution belonging to the idea of the present invention belong to the protection scope of the utility model.It should refer to Out, for those skilled in the art, it is without departing from the principle of the utility model it is several improvement and Retouching, these improvements and modifications also should be regarded as the protection scope of the utility model.

Claims (8)

1. a kind of integrated smallpox light trough of lightgage steel joist frame constructs, including the first frame body (1) in rectangular-ambulatory-plane setting, described the The first sunpender (11) are connected between one frame body (1) and wall top, it is characterised in that: be equipped with and be in back in first frame body (1) The second frame body (12) of font setting, is additionally provided with third frame body (13) in second frame body (12), around first frame body (1) Several U-shaped steels (2) being vertically arranged, second frame body (12) and third frame body are equipped with the second frame body (12) inner circumferential array (13) periphery is correspondingly provided with the adjustment sheet (3) that sliding is plugged in U-shaped steel (2), second frame body (12) and third frame body (13) it is connected to wall top setting by postposition sunpender (4), is equipped at the U-shaped steel (2) and determines for secured adjusted piece (3) position Position device (5).
2. a kind of integrated smallpox light trough of lightgage steel joist frame according to claim 1 constructs, it is characterised in that: the U Fashioned iron (2) bottom end closure is equipped with baffle (25), when the adjustment sheet (3) is connected to baffle (25) top surface, first frame body (1), during the second frame body (12) and third frame body (13) are generally aligned in the same plane.
3. a kind of integrated smallpox light trough of lightgage steel joist frame according to claim 1 constructs, it is characterised in that: the U Fashioned iron (2) opening two sides are provided inwardly with flange (21), and adjustment sheet (3) two sides are connected in flange (21) and U-shaped steel (2) respectively Angle setting between side plate.
4. a kind of integrated smallpox light trough of lightgage steel joist frame according to claim 3 constructs, it is characterised in that: described fixed Position device (5) includes the butt hole group (22) of the U-shaped steel (2) close to the setting of the first frame body (1) side, the butt hole group It (22) include two spaced butt holes (221), grafting is equipped with the docking block for the setting that is in U-shape in the butt hole group (22) (23), the adjustment sheet (3) is plugged in docking block (23) setting.
5. a kind of integrated smallpox light trough of lightgage steel joist frame according to claim 4 constructs, it is characterised in that: described right It connects hole group (22) and is set as multiple groups along the vertical direction.
6. a kind of integrated smallpox light trough of lightgage steel joist frame according to claim 1 constructs, it is characterised in that: after described Setting sunpender (4) includes the expansion bolt (41) for being fixed in wall top, and wall setting, and its bottom are stretched out in expansion bolt (41) bottom Portion is connected with adjusting rod (42), and adjusting rod (42) bottom end is fixed in the main dragon of the second frame body (12) and third frame body (13) Bone setting.
7. a kind of integrated smallpox light trough of lightgage steel joist frame according to claim 6 constructs, it is characterised in that: the tune Pole (42) top is provided with screw hole (421), and expansion bolt (41) bottom thread is connected in screw hole (421).
8. a kind of integrated smallpox light trough of lightgage steel joist frame according to claim 7 constructs, it is characterised in that: described The bottom surface of the main joist of two frame bodies (12) and third frame body (13) is provided with link slot (43), link slot (43) the slot bottom perforation master Keel are equipped with connecting hole (431), and the adjusting rod (42) is plugged in connecting hole (431), and protrude into link slot (43) setting, institute It states adjusting rod (42) bottom end and is threaded with the T-piece (44) being connected in link slot (43).
CN201821019664.2U 2018-06-28 2018-06-28 A kind of integrated smallpox light trough construction of lightgage steel joist frame Expired - Fee Related CN208586801U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821019664.2U CN208586801U (en) 2018-06-28 2018-06-28 A kind of integrated smallpox light trough construction of lightgage steel joist frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821019664.2U CN208586801U (en) 2018-06-28 2018-06-28 A kind of integrated smallpox light trough construction of lightgage steel joist frame

Publications (1)

Publication Number Publication Date
CN208586801U true CN208586801U (en) 2019-03-08

Family

ID=65539209

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821019664.2U Expired - Fee Related CN208586801U (en) 2018-06-28 2018-06-28 A kind of integrated smallpox light trough construction of lightgage steel joist frame

Country Status (1)

Country Link
CN (1) CN208586801U (en)

Similar Documents

Publication Publication Date Title
CN208586801U (en) A kind of integrated smallpox light trough construction of lightgage steel joist frame
CN208235767U (en) Half frame concealed curtain wall of bright frame effect is formed using hidden frame column
CN102418707A (en) Multifunctional electric fan
CN105275123A (en) Pitched roof type integrated ceiling
CN208309791U (en) Herringbone top glass sunlight house
CN204940649U (en) A kind of module unit type dome assembly
CN211923182U (en) Suspended ceiling
CN105179918B (en) A kind of profile piece for sheet material assembling
CN109057007B (en) Two-stage roof Chinese-style structure frame house prepared from aluminum profiles
CN206985492U (en) A kind of door of elevator
CN208981506U (en) A kind of twin-stage top structure of Chinese style frame room of aluminum profile preparation
CN208803605U (en) Building curtain wall
CN209227881U (en) A kind of assembled ceiling structure
CN102776991B (en) Steel structure canopy and construction method
CN112160483A (en) Assembled furred ceiling with steel framed aerial layer locking structure
CN207761200U (en) A kind of modularization steel canopy convenient for assembly
CN202382194U (en) Light trough for a multifunction device zone
CN205296905U (en) Frame construction rainshelter
CN206034952U (en) Modular steel construction
CN204826778U (en) Pin -connected panel frameless computer lab of communicating by letter
CN206090811U (en) Thermal -insulated sunshine room
CN205475952U (en) Light groove furred ceiling is used again in interior decoration decoration
CN109184087A (en) A kind of spliced wall or roof
CN205035957U (en) Staggered floor roof beam
CN220814271U (en) Assembled mobile house

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190308