CN211923182U - Suspended ceiling - Google Patents

Suspended ceiling Download PDF

Info

Publication number
CN211923182U
CN211923182U CN202020421794.XU CN202020421794U CN211923182U CN 211923182 U CN211923182 U CN 211923182U CN 202020421794 U CN202020421794 U CN 202020421794U CN 211923182 U CN211923182 U CN 211923182U
Authority
CN
China
Prior art keywords
type
sets
suspended ceiling
shaped
longitudinal section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020421794.XU
Other languages
Chinese (zh)
Inventor
熊晓莉
韩森
冯实
乔顺利
咸庆军
李涛
史凝哲
高萌
李江华
陈鹏
李战毫
唐雷振
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fifth Engineering Co Ltd of China Railway Seventh Group Co Ltd
Original Assignee
Henan University of Technology
Fifth Engineering Co Ltd of China Railway Seventh Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan University of Technology, Fifth Engineering Co Ltd of China Railway Seventh Group Co Ltd filed Critical Henan University of Technology
Priority to CN202020421794.XU priority Critical patent/CN211923182U/en
Application granted granted Critical
Publication of CN211923182U publication Critical patent/CN211923182U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a suspended ceiling, including setting up in the conversion layer mechanism on roof, the bottom of conversion layer mechanism evenly sets up a plurality of jibs, the bottom of jib sets up the fretwork board, is located fretwork board special fossil fragments all around, fretwork board top sets up lamps and lanterns, the bottom of special fossil fragments sets up the compoboard, the compoboard includes a plurality of mainboards that even interval set up, sets up a plurality of auxiliary plates between two adjacent mainboards, the mainboard include the longitudinal section be the U type slat of U type, set up in the flanging at U type slat both ends top, auxiliary plates include the longitudinal section be the U type lacing film of U type, set up in the both ends top of U type lacing film and with flanging matched with in-turned edge, the utility model discloses the dismouting is convenient, handsome in appearance.

Description

Suspended ceiling
Technical Field
The utility model relates to a building decoration technical field especially relates to a furred ceiling.
Background
The suspended ceiling refers to the top decoration of the ceiling in a house, and besides the top decoration function, the suspended ceiling is generally endowed with the functions of heat preservation, heat insulation, sound insulation and the like, and is also generally used as a hidden layer for the projects of electric, ventilation and air conditioning, communication, fire prevention and the like. With the rapid development of high-speed railway construction in China, high-speed railway station house projects are more and more, and the requirements of high-speed railway station house specifications and decoration are higher and higher. The requirement design of the China national railway group for the construction of high-speed rail station houses is suitable for urban characteristics and regional planning. In recent years, with the continuous and deep development of high-speed rail construction in China, the development of high-speed rail station building with regional culture characteristics based on regional characteristics of the local area has become a hot point of engineering practice. The suspended ceiling of the public building such as the high-speed rail station house has large span and high height, and has high requirements on the building type. The existing common suspended ceiling building of the high-speed rail station house is simple in modeling, the patterns are mostly planar design patterns, and the suspended ceiling building looks like having no layering sense and is not vivid and attractive.
Disclosure of Invention
An object of the utility model is to overcome not enough among the prior art, provide a convenient, the handsome in appearance furred ceiling of dismouting.
The utility model discloses a realize through following technical scheme:
the utility model provides a suspended ceiling, is including setting up in the conversion layer mechanism on roof, the bottom of conversion layer mechanism evenly sets up a plurality of jibs, the bottom of jib sets up the fretwork board, is located fretwork board special fossil fragments all around, the fretwork board top sets up lamps and lanterns, the bottom of special fossil fragments sets up the compoboard, the compoboard includes a plurality of mainboards that even interval set up, sets up a plurality of auxiliary plates between two adjacent mainboards, the mainboard include the longitudinal section be the U type slat of U type, set up in the flanging at U type slat both ends top, auxiliary plates include the longitudinal section be the U type lacing film of U type, set up in the both ends top of U type lacing film and with flanging matched with in-flanges.
Preferably, the conversion layer mechanism comprises a plurality of vertical angle steels arranged on the roof along the vertical direction and a horizontal steel skeleton connected with the bottoms of the vertical angle steels and arranged along the horizontal direction.
Preferably, a reinforcing rib is arranged between the vertical angle steel and the horizontal steel framework.
Preferably, a connecting plate is arranged between the hollow plate and the suspension rod, and the longitudinal section of the connecting plate is Z-shaped.
Preferably, the width of the U-shaped strip is 140-160mm, the height of the U-shaped strip is 22-28mm, and the width of the outward flange is 8-12 mm.
Preferably, the width of the U-shaped hanging piece is 55-65mm, the height of the U-shaped strip plate is 18-22mm, and the width of the inward flange is 8-12 mm.
The beneficial effects of the utility model reside in that: the utility model is provided with the composition board which comprises a plurality of main boards arranged at even intervals and a plurality of auxiliary boards arranged between two adjacent main boards, wherein the auxiliary boards can have various colors and are combined into patterns with three-dimensional stereovision, so that the composition board is more natural and vivid and has beautiful appearance; the mainboard includes that the longitudinal section is the U type slat of U type, sets up in the flanging at U type slat both ends top, assists the board including the longitudinal section for the U type lacing film of U type, set up in the both ends top of U type lacing film and with flanging matched with inside flanging, can be connected with the mainboard with assisting the board through the mode of inside flanging and flanging buckle, the dismouting is convenient.
Drawings
Fig. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic structural view of the main board of the present invention;
FIG. 3 is a schematic structural view of the auxiliary plate of the present invention;
wherein: the steel angle lamp comprises vertical angle steel 1, a horizontal steel framework 2, reinforcing ribs 3, a hanging rod 4, a connecting plate 5, a hollowed-out plate 6, a lamp 7, a special keel 8, a main plate 9, an auxiliary plate 10, a U-shaped strip plate 11, an outward turned edge 12, a U-shaped hanging piece 13 and an inward turned edge 14.
Detailed Description
In the description of the present invention, it should also be noted that, unless otherwise explicitly specified or limited, the terms "disposed," "mounted," "connected," and "connected" are to be construed broadly, e.g., as meaning either a fixed connection, a removable connection, or an integral connection; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Example 1
As shown in fig. 1-3, a suspended ceiling comprises a plurality of vertical angle steels 1 installed on a roof along the vertical direction, horizontal steel frames 2 installed along the horizontal direction are connected to the bottoms of the vertical angle steels 1, and reinforcing ribs 3 are connected between the vertical angle steels 1 and the horizontal steel frames 2 to play a role in reinforcing. Many jibs 4 of horizontal steel skeleton 2's bottom evenly mounted, jib 4 is installed along vertical direction, the special fossil fragments 8 around the bottom installation fretwork board 6 of jib 4 and being located fretwork board 6, the external screw thread has all been seted up to jib 4's top and bottom, the trompil has been seted up on horizontal steel skeleton 2, the trompil is run through at jib 4's top and just is located two nuts of horizontal steel skeleton 2 upper and lower both sides respectively and connect through two threaded connection. The connection plate 5 is installed between the hollow plate 6 and the hanging rod 4, the longitudinal section of the connection plate 5 is Z-shaped, a hole for the bottom of the hanging rod 4 to penetrate through is formed in the connection plate 5, and the connection is carried out through two nuts. The connecting plate 5 and the hollow plate 6 are correspondingly provided with holes, and the connecting plate and the hollow plate are connected through bolts. And a lamp 7 is arranged above the hollow plate 6. The bottom installation compoboard of special fossil fragments 8, compoboard include a plurality of mainboards 9 of even interval installation, install a plurality of auxiliary boards 10 between two adjacent mainboards 9, and auxiliary board 10 can have multiple colour, makes up the pattern that has three-dimensional stereovision jointly, and is more natural, lively, handsome in appearance. The main board 9 comprises a U-shaped slat 11 with a U-shaped longitudinal section and an outer flanging 12 connected to the tops of two ends of the U-shaped slat 11, and the auxiliary board 10 comprises a U-shaped hanging piece 13 with a U-shaped longitudinal section and an inner flanging 14 connected to the tops of two ends of the U-shaped hanging piece 13 and matched with the outer flanging 12. The width of the U-shaped strip 11 is 150mm, the height of the U-shaped strip 11 is 25mm, and the width of the outward flange 12 is 10 mm. The width of the U-shaped hanging piece 13 is 60mm, the height of the U-shaped strip plate 11 is 20mm, and the width of the inward flange 14 is 10 mm. Can be connected supplementary board 10 and mainboard 9 through the mode of inside flanging 14 and the 12 buckles of flanging, the dismouting is convenient.
Example 2
As shown in fig. 1-3, a suspended ceiling comprises a plurality of vertical angle steels 1 installed on a roof along the vertical direction, horizontal steel frames 2 installed along the horizontal direction are connected to the bottoms of the vertical angle steels 1, and reinforcing ribs 3 are connected between the vertical angle steels 1 and the horizontal steel frames 2 to play a role in reinforcing. Many jibs 4 of horizontal steel skeleton 2's bottom evenly mounted, jib 4 is installed along vertical direction, the special fossil fragments 8 around the bottom installation fretwork board 6 of jib 4 and being located fretwork board 6, the external screw thread has all been seted up to jib 4's top and bottom, the trompil has been seted up on horizontal steel skeleton 2, the trompil is run through at jib 4's top and just is located two nuts of horizontal steel skeleton 2 upper and lower both sides respectively and connect through two threaded connection. The connection plate 5 is installed between the hollow plate 6 and the hanging rod 4, the longitudinal section of the connection plate 5 is Z-shaped, a hole for the bottom of the hanging rod 4 to penetrate through is formed in the connection plate 5, and the connection is carried out through two nuts. The connecting plate 5 and the hollow plate 6 are correspondingly provided with holes, and the connecting plate and the hollow plate are connected through bolts. And a lamp 7 is arranged above the hollow plate 6. The bottom installation compoboard of special fossil fragments 8, compoboard include a plurality of mainboards 9 of even interval installation, install a plurality of auxiliary boards 10 between two adjacent mainboards 9, and auxiliary board 10 can have multiple colour, makes up the pattern that has three-dimensional stereovision jointly, and is more natural, lively, handsome in appearance. The main board 9 comprises a U-shaped slat 11 with a U-shaped longitudinal section and an outer flanging 12 connected to the tops of two ends of the U-shaped slat 11, and the auxiliary board 10 comprises a U-shaped hanging piece 13 with a U-shaped longitudinal section and an inner flanging 14 connected to the tops of two ends of the U-shaped hanging piece 13 and matched with the outer flanging 12. The width of the U-shaped batten 11 is 140mm, the height of the U-shaped batten 11 is 22mm, and the width of the outward flange 12 is 8 mm. The width of the U-shaped hanging piece 13 is 55mm, the height of the U-shaped strip plate 11 is 18mm, and the width of the inward flange 14 is 8 mm. Can be connected supplementary board 10 and mainboard 9 through the mode of inside flanging 14 and the 12 buckles of flanging, the dismouting is convenient.
Example 3
As shown in fig. 1-3, a suspended ceiling comprises a plurality of vertical angle steels 1 installed on a roof along the vertical direction, horizontal steel frames 2 installed along the horizontal direction are connected to the bottoms of the vertical angle steels 1, and reinforcing ribs 3 are connected between the vertical angle steels 1 and the horizontal steel frames 2 to play a role in reinforcing. Many jibs 4 of horizontal steel skeleton 2's bottom evenly mounted, jib 4 is installed along vertical direction, the special fossil fragments 8 around the bottom installation fretwork board 6 of jib 4 and being located fretwork board 6, the external screw thread has all been seted up to jib 4's top and bottom, the trompil has been seted up on horizontal steel skeleton 2, the trompil is run through at jib 4's top and just is located two nuts of horizontal steel skeleton 2 upper and lower both sides respectively and connect through two threaded connection. The connection plate 5 is installed between the hollow plate 6 and the hanging rod 4, the longitudinal section of the connection plate 5 is Z-shaped, a hole for the bottom of the hanging rod 4 to penetrate through is formed in the connection plate 5, and the connection is carried out through two nuts. The connecting plate 5 and the hollow plate 6 are correspondingly provided with holes, and the connecting plate and the hollow plate are connected through bolts. And a lamp 7 is arranged above the hollow plate 6. The bottom installation compoboard of special fossil fragments 8, compoboard include a plurality of mainboards 9 of even interval installation, install a plurality of auxiliary boards 10 between two adjacent mainboards 9, and auxiliary board 10 can have multiple colour, makes up the pattern that has three-dimensional stereovision jointly, and is more natural, lively, handsome in appearance. The main board 9 comprises a U-shaped slat 11 with a U-shaped longitudinal section and an outer flanging 12 connected to the tops of two ends of the U-shaped slat 11, and the auxiliary board 10 comprises a U-shaped hanging piece 13 with a U-shaped longitudinal section and an inner flanging 14 connected to the tops of two ends of the U-shaped hanging piece 13 and matched with the outer flanging 12. The width of the U-shaped strip 11 is 160mm, the height of the U-shaped strip 11 is 28mm, and the width of the outward flange 12 is 12 mm. The width of the U-shaped hanging piece 13 is 65mm, the height of the U-shaped strip plate 11 is 22mm, and the width of the inward flange 14 is 12 mm. Can be connected supplementary board 10 and mainboard 9 through the mode of inside flanging 14 and the 12 buckles of flanging, the dismouting is convenient.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications and variations can be made in the embodiments or in part of the technical features of the embodiments without departing from the spirit and the scope of the invention.

Claims (6)

1. A suspended ceiling, its characterized in that: including setting up in the conversion layer mechanism on roof, the bottom of conversion layer mechanism evenly sets up a plurality of jibs, the bottom of jib sets up the fretwork board, is located fretwork board special fossil fragments all around, the fretwork board top sets up lamps and lanterns, the bottom of special fossil fragments sets up the compoboard, the compoboard includes a plurality of mainboards that even interval set up, sets up a plurality of auxiliary boards between two adjacent mainboards, the mainboard include the longitudinal section be the U type slat of U type, set up in the flanging at U type slat both ends top, auxiliary board include the longitudinal section be the U type lacing film of U type, set up in the both ends top of U type lacing film and with flanging matched with in-turned over edge.
2. A suspended ceiling as claimed in claim 1, wherein: the conversion layer mechanism comprises a plurality of vertical angle steels arranged on the roof along the vertical direction and a horizontal steel skeleton connected with the bottoms of the vertical angle steels and arranged along the horizontal direction.
3. A suspended ceiling as claimed in claim 2, wherein: and reinforcing ribs are arranged between the vertical angle steel and the horizontal steel framework.
4. A suspended ceiling as claimed in claim 1, wherein: a connecting plate is arranged between the hollow plate and the hanging rod, and the longitudinal section of the connecting plate is Z-shaped.
5. A suspended ceiling as claimed in claim 1, wherein: the width of the U-shaped strip is 140-160mm, the height of the U-shaped strip is 22-28mm, and the width of the outward flange is 8-12 mm.
6. A suspended ceiling as claimed in claim 1, wherein: the width of the U-shaped hanging piece is 55-65mm, the height of the U-shaped strip plate is 18-22mm, and the width of the inward flange is 8-12 mm.
CN202020421794.XU 2020-03-28 2020-03-28 Suspended ceiling Active CN211923182U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020421794.XU CN211923182U (en) 2020-03-28 2020-03-28 Suspended ceiling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020421794.XU CN211923182U (en) 2020-03-28 2020-03-28 Suspended ceiling

Publications (1)

Publication Number Publication Date
CN211923182U true CN211923182U (en) 2020-11-13

Family

ID=73348706

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020421794.XU Active CN211923182U (en) 2020-03-28 2020-03-28 Suspended ceiling

Country Status (1)

Country Link
CN (1) CN211923182U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113605593A (en) * 2021-08-19 2021-11-05 中建二局装饰工程有限公司 Large-area hyperbolic aluminum plate and lamp ceiling mounting structure and construction method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113605593A (en) * 2021-08-19 2021-11-05 中建二局装饰工程有限公司 Large-area hyperbolic aluminum plate and lamp ceiling mounting structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN102041864A (en) Support keel of integrated ceiling, unit buckle, electrical appliance module and installation method thereof
CN211923182U (en) Suspended ceiling
CN206829468U (en) A kind of new double light trough two level aluminium beam bar ceilings
CN207538287U (en) Combined type suspended ceiling
CN203284930U (en) Suspended ceiling structure with decorative light bar
CN203821680U (en) Fully invisible frame system structure
CN208251423U (en) More sunk panel ceiling structures
CN201891220U (en) Transverse skylight for building
CN203755506U (en) Ribbon curtain wall structure
CN206625355U (en) Aluminium alloy structure house
CN205242628U (en) Plug -in type activity board house
CN210562843U (en) Connection structure of aluminum plate curtain wall of choosing outward
CN109629689B (en) Green dome for building
CN209339306U (en) A kind of prefabricated buildings heat preservation decoration integrative roofing board
CN209163292U (en) Environment-friendly type ceiling
CN208088598U (en) Solar energy curtain wall system
CN206784699U (en) A kind of super bath ceiling board of hiding ventilation
CN202745289U (en) Steel structure canopy
CN205954980U (en) Ceiling furred ceiling device convenient to dismouting
CN220451212U (en) Triangle joint assembled furred ceiling subassembly
CN210947372U (en) Ceiling system adopting H-shaped keel
CN206418650U (en) A kind of two grades of aluminium beam bar ceilings
CN219952408U (en) Suspended ceiling keel and suspended ceiling structure thereof
CN216346842U (en) Decorative fresh air deodorizing air pipe
CN204691098U (en) A kind of rectangular skylight structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20210702

Address after: No. 1225, hanghai East Road, Zhengzhou Economic and Technological Development Zone, Henan 450000

Patentee after: THE FIFTH ENGINEERING CO., LTD. OF CHINA RAILWAY SEVENTH GROUP Co.,Ltd.

Address before: No. 1225, hanghai East Road, Zhengzhou Economic and Technological Development Zone, Henan 450000

Patentee before: THE FIFTH ENGINEERING CO., LTD. OF CHINA RAILWAY SEVENTH GROUP Co.,Ltd.

Patentee before: HENAN University OF TECHNOLOGY

TR01 Transfer of patent right