CN208586515U - Moveable Roadway Construction hanging basket - Google Patents

Moveable Roadway Construction hanging basket Download PDF

Info

Publication number
CN208586515U
CN208586515U CN201820918073.2U CN201820918073U CN208586515U CN 208586515 U CN208586515 U CN 208586515U CN 201820918073 U CN201820918073 U CN 201820918073U CN 208586515 U CN208586515 U CN 208586515U
Authority
CN
China
Prior art keywords
counterweight
construction
bridge
hanging
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820918073.2U
Other languages
Chinese (zh)
Inventor
黄增财
殷胜光
邵文泽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Road and Bridge International Co Ltd
China Communication North Road and Bridge Co Ltd
Original Assignee
Road and Bridge International Co Ltd
China Communication North Road and Bridge Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Road and Bridge International Co Ltd, China Communication North Road and Bridge Co Ltd filed Critical Road and Bridge International Co Ltd
Priority to CN201820918073.2U priority Critical patent/CN208586515U/en
Application granted granted Critical
Publication of CN208586515U publication Critical patent/CN208586515U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model provides a kind of moveable Roadway Construction hanging basket, including operation platform, hanging structure, the bridge fixed structure fixed with the hanging structure, wherein, the bridge fixed structure includes hanging structure counterweight and the counterweight support base for supporting the hanging structure counterweight;Wherein, the operation platform is arranged in bridge bottom, is provided with ladder between the operation platform and the hanging structure, the side of the operation platform is provided with concrete conveying pipe;The counterweight support base is fixed on the surface of bridge, and the hanging structure counterweight is fixed between the hanging structure and the counterweight support base in ramp type, wherein the exit passageway passed through for construction personnel is provided in the hanging structure counterweight;The four corners position of the counterweight support base is provided with pulley.Using the utility model, it is able to solve the problems such as barrel structure is dangerous and mobile inconvenient.

Description

Movable hanging basket for bridge deck construction
Technical Field
The utility model relates to a construction technical field, more specifically relates to a mobilizable bridge floor construction hanging flower basket.
Background
In the modern society, the hanging basket is used as basic construction equipment and plays an important role in high-altitude operation such as external wall construction, building high-altitude transportation, bridge deck construction and the like; the hanging basket in the prior art has an imperfect structure and still has a series of problems in use, firstly, the personnel in the hanging basket are not protected enough, and safety accidents are caused; meanwhile, the transportation of concrete and the movement of the hanging basket are inconvenient in the construction process.
In order to solve the problem, the utility model provides a mobilizable bridge floor construction hanging flower basket.
SUMMERY OF THE UTILITY MODEL
In view of the above problems, the present invention is to provide a movable hanging basket for bridge deck construction, which solves the problems of unsafe structure and inconvenient movement of the hanging basket.
The utility model provides a movable hanging basket for bridge deck construction, which comprises a construction platform, a suspension structure and a bridge body fixing structure fixed with the suspension structure, wherein the bridge body fixing structure comprises a suspension structure counterweight and a counterweight supporting seat for supporting the suspension structure counterweight; wherein,
the construction platform is arranged at the bottom of the bridge, a ladder stand is arranged between the construction platform and the suspended structure, and a concrete conveying pipeline is arranged on the side surface of the construction platform;
the counterweight supporting seat is fixed on the surface of the bridge body, the counterweight of the suspended structure is fixed between the suspended structure and the counterweight supporting seat in a slope manner, and a safety channel for construction personnel to pass through is arranged on the counterweight of the suspended structure;
pulleys are arranged at four corners of the counterweight supporting seat.
In addition, the preferred structure is that the suspended structure is formed by combining 20cm of I-steel or channel steel through bolting and welding, wherein the width of the suspended structure is 80 cm.
In addition, it is preferable that a safety device for protecting a worker is provided on the ladder.
In addition, the preferable structure is that the safety channel is communicated with the suspension structure, and the suspension structure is communicated with the ladder stand.
Further, it is preferable that the end of the concrete feed pipe has a funnel shape.
In addition, it is preferable that an end portion of the concrete delivery pipe is provided on the ladder stand, and a bottom portion of the concrete delivery pipe is provided on the construction platform.
According to the technical scheme, the utility model provides a mobilizable bridge floor construction hanging flower basket, this device is used for the repair of bridge face roof beam bottom quality defect to use, and this device superstructure (unsettled structure counter weight) will have sufficient resistance to topple the counter weight, guarantees the safety of structure, installs the concrete conveying pipe in the outside of construction platform and cat ladder simultaneously, is convenient for the transportation of the bottom of the beam repair use concrete; the pulley is installed, so that the hanging basket can be conveniently moved.
Drawings
Other objects and results of the present invention will become more apparent and more readily appreciated as the same becomes better understood by reference to the following description and appended claims, taken in conjunction with the accompanying drawings. In the drawings:
figure 1 is according to the utility model discloses mobilizable bridge floor construction hanging flower basket structure sketch map.
Wherein the reference numerals include: 1. suspended structure, 2, cat ladder, 3, concrete conveying pipe, 4, suspended structure counter weight, 5, counter weight supporting seat, 6, pulley, 7, bridge body, 8, construction platform.
The same reference numbers in all figures indicate similar or corresponding features or functions.
Detailed Description
To the current hanging flower basket structure that aforementioned proposed unsafe and remove inconvenient scheduling problem, the utility model provides a mobilizable bridge floor construction hanging flower basket to solve above-mentioned problem.
Specific embodiments of the present invention will be described in detail below with reference to the accompanying drawings.
To illustrate the structure of the movable hanging basket for bridge deck construction provided by the present invention, fig. 1 shows a movable hanging basket structure for bridge deck construction according to an embodiment of the present invention.
As shown in fig. 1, the utility model provides a mobilizable bridge floor construction hanging flower basket, including construction platform 8, suspended structure 1, with the fixed bridge fixed knot of suspended structure 1 constructs, bridge fixed knot constructs including suspended structure counter weight 4 and the counter weight supporting seat 5 that supports suspended structure counter weight 4.
Wherein, construction platform 8 sets up in the bridge bottom, is provided with cat ladder 2 between construction platform 8 and unsettled structure 1, is provided with concrete conveying pipe 3 in construction platform 8's side.
The counterweight support seat 5 is fixed on the surface of the bridge body 7, the suspended structure counterweight 4 is fixed between the suspended structure 1 and the counterweight support seat 5 in a slope manner, wherein a safety channel for construction personnel to pass through is arranged on the suspended structure counterweight 4; pulleys 6 are arranged at four corners of the counterweight supporting seat 5.
Wherein, in the embodiment of the present invention, the suspension structure weight 4 has enough resistance to overturn. The safety channel is communicated with the suspension structure 1, and the suspension structure 1 is communicated with the ladder stand 2.
Wherein, the operating personnel on the surface of the bridge body 7 reaches the position of the suspended structure 1 through the safety channel on the suspended structure balance weight 4, enters the construction platform 8 from the position of the suspended structure 1 through the crawling ladder 2 to start operation and construction, and the crawling ladder is provided with safety equipment for protecting the operating personnel.
That is to say, constructor needs the safety device to contain constructor's safety when passing through cat ladder 2, thinks about for constructor's safety, has set up safety device such as safety rope on cat ladder 2, and the one end of safety rope is fixed and is being close to the position of unsettled structure 1 at cat ladder 2, and the other end is fixed on constructor's one's body, and this kind can the personal safety of safety protection constructor.
Furthermore, in the embodiment of the present invention, the suspended structure 1 is formed by 20cm of steel or channel steel through bolting and welding, wherein the width of the suspended structure 1 is 80cm, and the suspended structure is combined with the suspended structure counterweight to ensure the safety of the structure.
Wherein, in the embodiment of the present invention, the end of the concrete conveying pipe 3 is funnel-shaped. The tip setting of concrete conveying pipe 3 is in on the cat ladder, the bottom setting of concrete conveying pipe 3 is on construction platform 8, and the transportation of using the concrete is repaired to the bottom of the beam of being convenient for.
Wherein, in the embodiment of the utility model, be provided with pulley 6 at four angular points positions of counter weight supporting seat 5, installation pulley 6 makes things convenient for the removal of hanging flower basket, wherein, it is explainable, the embodiment of the utility model, pulley 6 has automatic pinning and automatic opening function, in practical application, pins automatically according to specific need, prevents that the hanging flower basket from removing at will for the stable fixing of hanging flower basket is in required position, finishes when repairing in the bridge bottom, starts pulley 6, removes the hanging flower basket to required position, and is thus visible, uses pulley 6 to make things convenient for the removal of hanging flower basket.
According to the above embodiment, the utility model provides a mobilizable bridge floor construction hanging flower basket, this device are used for repairing of bridge face bottom of the girder portion quality defect to use, and this device superstructure suspended structure is joined in marriage important have sufficient resistance counter weight that topples, guarantees the safety of structure, installs the concrete conveying pipe in the outside of construction platform and cat ladder simultaneously, and the bottom of the beam portion of being convenient for is repaired the transportation of using the concrete, installs the pulley, makes things convenient for the removal of hanging flower basket.
The movable bridge deck construction basket according to the present invention has been described above by way of example with reference to the accompanying drawings. However, it will be appreciated by those skilled in the art that various modifications may be made to the removable deck construction basket set forth above without departing from the scope of the invention. Therefore, the scope of the present invention should be determined by the content of the appended claims.

Claims (6)

1. A movable hanging basket for bridge deck construction is characterized by comprising a construction platform, a suspension structure and a bridge body fixing structure fixed with the suspension structure, wherein the bridge body fixing structure comprises a suspension structure counterweight and a counterweight supporting seat for supporting the suspension structure counterweight; wherein,
the construction platform is arranged at the bottom of the bridge, a ladder stand is arranged between the construction platform and the suspended structure, and a concrete conveying pipeline is arranged on the side surface of the construction platform;
the counterweight supporting seat is fixed on the surface of the bridge body, the counterweight of the suspended structure is fixed between the suspended structure and the counterweight supporting seat in a slope manner, and a safety channel for construction personnel to pass through is arranged on the counterweight of the suspended structure;
pulleys are arranged at four corners of the counterweight supporting seat.
2. A movable deck construction basket according to claim 1,
the hanging structure is formed by combining 20cm of I-steel or channel steel through bolting and welding, wherein the width of the hanging structure is 80 cm.
3. A movable deck construction basket according to claim 1,
and safety equipment for protecting constructors is arranged on the ladder stand.
4. A movable deck construction basket according to claim 1,
the safety channel is communicated with the suspension structure, and the suspension structure is communicated with the ladder stand.
5. A movable deck construction basket according to claim 1,
the end part of the concrete conveying pipe is in a funnel shape.
6. A movable deck construction basket according to claim 5,
the end part of the conveying pipeline is arranged on the ladder stand, and the bottom of the conveying pipeline is arranged on the construction platform.
CN201820918073.2U 2018-06-13 2018-06-13 Moveable Roadway Construction hanging basket Active CN208586515U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820918073.2U CN208586515U (en) 2018-06-13 2018-06-13 Moveable Roadway Construction hanging basket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820918073.2U CN208586515U (en) 2018-06-13 2018-06-13 Moveable Roadway Construction hanging basket

Publications (1)

Publication Number Publication Date
CN208586515U true CN208586515U (en) 2019-03-08

Family

ID=65536469

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820918073.2U Active CN208586515U (en) 2018-06-13 2018-06-13 Moveable Roadway Construction hanging basket

Country Status (1)

Country Link
CN (1) CN208586515U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110847031A (en) * 2019-11-28 2020-02-28 北京市政路桥股份有限公司 Movable hanging basket for bridge construction

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110847031A (en) * 2019-11-28 2020-02-28 北京市政路桥股份有限公司 Movable hanging basket for bridge construction

Similar Documents

Publication Publication Date Title
CN205591111U (en) Portable type bridge of cantilever type bottom is repaired and is used platform device
US20090020363A1 (en) Scaffolding fall protection system
CN208586515U (en) Moveable Roadway Construction hanging basket
CN105113803B (en) High-altitude sliding hoisting device of corridor truss of mountain and implementing method of high-altitude sliding hoisting device
CN205348733U (en) Furred ceiling operation platform
US7000733B2 (en) Work platform
KR101028631B1 (en) Movable bridge inspection equipment
CN210598089U (en) Attached lifting scaffold in high-rise building
KR20190056097A (en) Apparatus of life rope
CA2482342A1 (en) Work platform
JP2005299280A (en) Mobile scaffold system
JP2020153208A (en) Suspended scaffold and erection method therefor
CN212249126U (en) Sliding platform for large-size cornice aluminum plate construction
CN205777613U (en) Horizontal protective device
CN105735662B (en) A kind of prefabrication is collapsible to throw net and installation method
CN211850731U (en) 7-shaped large-angle inner-inclined high-altitude sliding operation platform
JP6688414B1 (en) A fall prevention device from a lorry carrier
CN203716835U (en) Platform device for getting on or off truck
JP4841171B2 (en) Rise-up elevator installation method
RU2598704C1 (en) Method of replacing lifting crane cable
CN110905181A (en) 7-shaped large-angle inner-inclined high-altitude sliding operation platform and construction method thereof
JP2004263498A (en) Guard fence installation method and guard fence installation device
CN205276895U (en) Interior wall body lifts by crane assembly auxiliary assembly
JP2019027145A (en) Installation method for falling object protective device
CN106049848A (en) Adjustable anti-shaking moving platform and mounting method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant