CN105113803B - High-altitude sliding hoisting device of corridor truss of mountain and implementing method of high-altitude sliding hoisting device - Google Patents
High-altitude sliding hoisting device of corridor truss of mountain and implementing method of high-altitude sliding hoisting device Download PDFInfo
- Publication number
- CN105113803B CN105113803B CN201510517159.5A CN201510517159A CN105113803B CN 105113803 B CN105113803 B CN 105113803B CN 201510517159 A CN201510517159 A CN 201510517159A CN 105113803 B CN105113803 B CN 105113803B
- Authority
- CN
- China
- Prior art keywords
- truss
- sliding
- rope
- gallery
- support
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention discloses a high-altitude sliding hoisting device of a corridor truss of a mountain and an implementing method of the high-altitude sliding hoisting device. The problem that a crane hoisting mode or a climbing pole hoisting mode cannot be used in a cliffy mountain in the prior art is solved. The high-altitude sliding hoisting device of the corridor truss of the mountain comprises supports, a sliding frame, a sliding rope and a traction mechanism; the supports are arranged at two ends of a mounting platform; the sliding frame is arranged on the top of the mounting platform and consists of upright columns; the sliding rope and the traction mechanism are used with the sliding frame; a crossbeam is arranged on tops of each two upright columns at the same end; rib plates with through holes are arranged on each crossbeam and are close to positions where the crossbeam is connected with the corresponding upright columns; the sliding rope penetrates in the rib plates on the tops of two ends of the sliding frame; two tips of the sliding rope are anchored to the support; and the corridor truss is positioned in the sliding frame, is dragged by the traction mechanism, and moves on the sliding rope through a movable pulley mounted on the sliding rope. By the high-altitude sliding hoisting device, technology quality of manufacturing assembly and hoisting of the corridor truss is ensured, construction safety and precision are ensured, construction cost is reduced greatly, and construction period is shortened.
Description
Technical field
The present invention relates to vestibule steel structure truss installs handling field, it is to be related to a kind of mountain area gallery truss specifically
Air translation hanging apparatus and its implementation.
Background technology
Feedstock transportation is one important operation in cement industry production, and most of raw limestone mineries and cement
, due to respective operating condition and the difference of residing region terrain, raw limestone need to be by making somebody a mere figurehead gallery for clinker production line
Induction system is installed by feedstock transportation to material storage yard with tunnel.In prior art, truss installa-tion handling equipment needed thereby structure is huge
Greatly, equipment is complicated, and is not suitable for, in the high-altitude gallery installation of mountain area complexity landform, actually practicing inconvenience, efficiency
It is low, easy schedule delays.
The content of the invention
It is an object of the invention to overcome drawbacks described above, there is provided a kind of simple structure, realize it is convenient, construction can be reduced account for
Ground, minimize transport costs, the mountain area gallery truss air translation hanging apparatus that efficiency of construction is high.
To achieve these goals, the technical solution used in the present invention is as follows:
A kind of mountain area gallery truss air translation hanging apparatus, including the support for being installed on mounting platform two ends, are arranged at
Mounting platform top and the sliding framework being made up of column, the slip rope used cooperatively with the sliding framework, and haulage gear;
Crossbeam is installed at the top of two columns with end, is provided with the junction of the column near it on the crossbeam
Gusset with through hole, the slip rope is through the gusset at the top of the sliding framework two ends and two ends are anchored in the support
On, gallery truss is located in the sliding framework and is drawn by the haulage gear, by the dynamic cunning on the slip rope
Wheel is moved on the slip rope.
Further, the haulage gear includes the hoist engine being disposed therein on a support, and is arranged on another
Fixed pulley on individual support, the hauling rope of the hoist engine is bypassed and is connected to after the fixed pulley on gallery truss.
Further, the fixed pulley is centrally located, so that the center of the hauling rope of the hoist engine and gallery truss
Line is consistent.
Further, the both sides lower edge termination of the gallery truss is provided with hoist cable, the hauling rope of the hoist engine leads to
Cross the hoist cable traction gallery truss movement.
Further, some support posts are additionally provided with the mounting platform bottom.
Further, the support post carries out drawing anchor by cable wind rope.
Further, a railing post is set every three meters on the mounting platform top.
Further, it is additionally provided with for the safety rope in connection construction personnel on the sliding framework.
Further, the gallery truss is connected by jack cucurbit with the movable pulley.
A kind of implementation method of above-mentioned mountain area gallery truss air translation hanging apparatus, comprises the following steps:
(1) the step of the setting support of mounting platform two ends;
(2) the step of sliding framework being built by column at the top of mounting platform;
(3) in the welded top gusset of sliding framework, by slip rope is through gusset and two ends are drawn along glide direction and are anchored on
Step on support;
(4) the step of installing haulage gear on support;
(5) on mounting platform the step of assembled gallery truss;
(6) by gallery truss sections into some truss elements;
(7) the step of truss element being connected with the movable pulley on slip rope with jack cucurbit;
(8) the step of haulage gear truss frame for connecting unit;
(9) hand fit's haulage gear carries out the continuous sliding of truss element, until truss element slides onto installation site
Step;
(10) step (7)~(9) are repeated all truss elements is slid onto into installation site;
(11) carry out docking the complete gallery truss of assembling composition is fixed truss element temporarily after;
(12) gallery truss is aligned, is installed the step of fixation with pre-embedded bolt.
Design principle of the present invention:Principle is installed according to the sliding method in rack installation method, with reference to actual design slip system
Slip rope structure in system, haulage gear, security system.The main supporting member of suspended-cable structure is the suspension cable of tension, in sliding
Cheng Zhong, the deadweight of gallery truss and horizontal drag force are mainly undertaken by suspension cable and sliding framework;Wherein, the main load truss of suspension cable
Deadweight, temporary support door frame mainly resists horizontal drag force.For this purpose, sag of the present invention by reduction suspension cable, strengthens sliding
The rigidity of framework, improves the pulling force of cable wire and the stability of sliding framework.Haulage gear is mainly by hoisting mechanism into by fixed
Pulley changes power direction, draws truss sliding in place.Because gallery truss adopts cases of otherwise standard design, its span, weight are not
It is equal.The uncertain factor of sliding installation process risk is more, and the control of security system adopts field measurement actual quantities, to cunning
Moving installation process carries out deformation monitoring, and is in real time analyzed deformation data with empirical data, and index system is effectively ensured
System, temporary support door frame Deformation control in value range, it is ensured that construction safety.
Compared with prior art, the invention has the advantages that:
(1) the characteristics of present invention is for mountain area induction system gallery steel truss, has been made using existing conveying gallery platform
Into, and using " truss fabrication is installed by Pin propulsions " technical measures Fast Installation steel truss technology, it is possible to reduce construction area, section
About transport the expense of falling.
(2) present invention is for mountain area complexity landform, transport material, component road conditions, project progress situation, science
Classifying rationally construction section, using organizing construction simultaneously is segmented, so as to be effectively shortened the duration.
(3) present invention makes assembling, air translation Hoisting Construction Technology using high-altitude, reduces gallery truss fabrication group
Dress, Hoisting Construction Technology difficulty, solving cannot use an especially big difficult problem for the lifting mode such as crane and pole-climbing in cliffy mountain, really
The assembling of gallery truss fabrication and the technical quality for lifting are protected, it is ensured that construction safety and precision, have significantly reduced and be constructed into
This, shortens the duration.
Description of the drawings
Fig. 1 is the structural representation of the present invention.
Fig. 2 is the sectional schematic diagram of the present invention.
Corresponding reference title is as follows in accompanying drawing:
1- columns, 2- crossbeams, 3- through holes, 4- gussets, 5- supports, 6- slip ropes, 7- hoist engines, 8- fixed pulleys, 9- supports vertical
Post, 10- cable wind ropes, 11- jack cucurbits, 12- gallery truss.
Specific embodiment
With reference to the accompanying drawings and examples the invention will be further described, and embodiments of the present invention are included but is not limited to
The following example.
Embodiment
As shown in Figure 1, 2, a kind of mountain area gallery truss air translation hanging apparatus are present embodiments provided, to solve
Cliffy mountain cannot use a difficult problem for the lifting mode such as crane and pole-climbing.The hanging apparatus mainly include support, sliding framework, cunning
Rope and haulage gear.Support is four column holder posts, is arranged on the two ends of mounting platform.
Sliding framework is made up of column, and its structure is cuboid framework or square framework, in the present embodiment, sliding framework
Constituted with each 2 meters long columns of 219 steel pipe manufacturings of Φ 6, specifically, continuous three at the top of concrete support both sides respectively anchor
Two root posts, column spacing is more than the chord width degree of gallery truss two, and the material that column welded top has crossbeam, crossbeam does not make especially limit
It is fixed, but there should be higher intensity, and crossbeam two ends are welded gusset at column 100mm, offer on gusset and worn for slip rope
The through hole crossed, during installation, slip rope draws along glide direction and is anchored on two through the gusset at the top of sliding framework two ends, slip rope two ends
Hold on adjacent four column holders post, slip rope first fixes one end before fixing, and the other end is tensioned slip rope using jack cucurbit, treats slip rope
With 4 groups of buckles by slip rope fixation after tight, when end frame is the higher single-side stand of height, the anchoring angle of slip rope is preferably not
More than 60 degree, and support 5 need to make of cable wind rope and effectively draw anchor, prevent suspension cable stress rearward end support from capsizing case occurring.
Haulage gear includes hoist engine and fixed pulley two parts in the present embodiment, and the two is separately positioned on the support at two ends
On, and fixed pulley frame is centrally located, and makes hoist engine cable traction line of force try one's best with gallery truss center line consistent, it is ensured that corridor
There is no larger off normal in road truss slipping, cause the problems such as stopping cunning, grab, increase quality safety risk.
The installation of haulage gear is as follows:Install on the column holder of rear four for installing gallery truss and fix a hoist engine,
As the traction power of gallery truss sliding;A fixed pulley, the traction of hoist engine are fixed on the column holder of front four with steel wire rope
When rope and gallery truss connect, first the hoist cable buckle of 4.5m length is fixed on into gallery truss both sides lower edge termination, hauling rope is again
It is connected with the hoist cable centre for fixing, when gallery truss is drawn stress, the string of truss two will be while stress, prevents truss skeleton
Deformed in tension.
Movable pulley is installed, gallery truss is connected by movable pulley with slip rope on slip rope, during construction, gallery truss is being installed
On platform after the completion of assembly, gallery truss is connected with the movable pulley installed on slip rope with jack cucurbit, pulls jack cucurbit, slowly
Slowly by gallery truss integrated hanging 50mm or so, the components such as slip rope system frame, slip rope, jack cucurbit, movable pulley are checked whether
Have deformation, a loosening situation, it is to be checked it is errorless after carry out short distance examination further along and slide, check again for slip rope system frame, slip rope, fall
Whether the components such as chain block, pulley have deformation, loosening situation.After the equal normal work of slip rope system components to be confirmed, manually match somebody with somebody
Close hoist engine and proceed the continuous sliding operation of truss, in slipping when slip rope stress downwarp radian is excessive, use jack calabash
Reed boist truss is to adjust the height of truss, until draw sliding onto steel truss installation site.
Safety devices mainly include railing post, safety rope and cable wind rope in the present embodiment, and its installation is as follows:Make,
Work high above the ground is in sliding, installation process, safety point danger is very big, for the execution conditions of each job step, takes targetedly
Safety measure.Restricted and be easy to the movement of trussmember, turned to by berm width when platform makes, using flexible anti-
Shield, i.e., be welded and fixed railing post on platform every 3m, and flexible protective railing is formed on railing post with manila rope colligation;
Before sliding construction, the single-side stand higher to height carries out drawing anchor using 2 road cable wind ropes to support, prevents single-side stand from receiving side force
Topple;When sliding, installation, a safety rope is set up on sliding framework, sliding operating personnel be hung on safety belt
Thereon.
In the present embodiment, using segmentation while organizing construction, holds the same examination of truss and hang, try under monolithic truss is adopted
It is sliding, after inspection is errorless, will segmentation monolithic truss sliding in place.According to the position of truss center line on support and sliding framework, adjust
The position of whole each section of monolithic truss, after being adjusted in place, interim fixation is done by truss at two ends.Four sections of monolithic steel truss are from far near
Successively sliding in place, fix temporarily after monolithic docking is carried out, then carries out upper and lower string support member installation from centre to two ends.
Fixed and landing slab is installed to mat formation:Truss is slid onto after support position, away from post datum level 100mm when the loosening that blows slowly fall
Chain block, manually prizes gallery truss, makes gallery truss support bolt hole be directed at capital pre-embedded bolt, the slow off the hook of jack cucurbit
It is in place.Suspension column surrounding is held out against using wedge (carving son), and gallery truss is corrected, and makes horizontal displacement and perpendicularity deviation in rule
Break off relations after being welded and fixed after within model and design allowed band.Can carry out follow-up steel platform and mat formation after the completion of this work to apply
Work.
According to above-described embodiment, the present invention just can be well realized.What deserves to be explained is, before above-mentioned design principle
Put, be to solve same technical problem, even if some made on architecture basics disclosed in this invention are without substantial
Change or polish, the essence of the technical scheme for being adopted is still as the present invention, therefore it should also be as the protection model in the present invention
In enclosing.
Claims (8)
1. a kind of mountain area gallery truss air translation hanging apparatus, it is characterised in that including be installed on mounting platform two ends
Frame(5), it is arranged at mounting platform top and by column(1)The sliding framework of composition, the cunning used cooperatively with the sliding framework
Rope(6), and haulage gear;Crossbeam is installed at the top of two columns with end(2), in the crossbeam(2)It is upper close
It is provided with through hole with the junction of the column(3)Gusset(4), the slip rope(6)Through the sliding framework two
Gusset at the top of end(4)And two ends are anchored in the support(5)On, gallery truss is located in the sliding framework and by described
Haulage gear draws, by installed in the slip rope(6)On movable pulley in the slip rope(6)Upper movement;In the sliding frame
It is additionally provided with frame for the safety rope in connection construction personnel;The gallery truss passes through jack cucurbit(11)With the dynamic cunning
Wheel connection.
2. a kind of mountain area gallery truss air translation hanging apparatus according to claim 1, it is characterised in that the traction
Mechanism includes being disposed therein a support(5)On hoist engine(7), and it is arranged on another support(5)On fixed pulley
(8), the hoist engine(7)Hauling rope bypass the fixed pulley(8)After be connected on gallery truss.
3. a kind of mountain area gallery truss air translation hanging apparatus according to claim 2, it is characterised in that described to determine cunning
Wheel(8)It is centrally located, so that the hauling rope of the hoist engine is consistent with the center line of gallery truss.
4. a kind of mountain area gallery truss air translation hanging apparatus according to claim 3, it is characterised in that in the corridor
The both sides lower edge termination of road truss is provided with hoist cable, and the hauling rope of the hoist engine draws gallery truss and moves by the hoist cable
It is dynamic.
5. a kind of mountain area gallery truss air translation hanging apparatus according to any one of Claims 1-4, its feature exists
In being additionally provided with some support posts in the mounting platform bottom(9).
6. a kind of mountain area gallery truss air translation hanging apparatus according to claim 5, it is characterised in that the support
Column(9)By cable wind rope(10)Carry out drawing anchor.
7. a kind of mountain area gallery truss air translation hanging apparatus according to claim 1, it is characterised in that in the peace
Assembling platform top arranges a railing post every three meters.
8. the implementation method of a kind of mountain area gallery truss air translation hanging apparatus as described in any one of claim 1-7, its
It is characterised by, comprises the following steps:
(1)At mounting platform two ends the step of setting support;
(2)The step of sliding framework is built by column at the top of mounting platform;
(3)In the welded top gusset of sliding framework, by slip rope is through gusset and two ends are drawn along glide direction and are anchored on support
On step;
(4)The step of haulage gear being installed on support;
(5)On mounting platform the step of assembled gallery truss;
(6)By gallery truss sections into some truss elements;
(7)Truss element is connected with the movable pulley on slip rope with jack cucurbit the step of;
(8)The step of haulage gear truss frame for connecting unit;
(9)Hand fit's haulage gear carries out the continuous sliding of truss element, until the step of truss element slides onto installation site;
(10)Repeat step(7)~(9)All truss elements are slid onto into installation site;
(11)Carry out docking assembling composition complete gallery truss truss element is fixed temporarily after;
(12)Gallery truss is aligned, is installed the step of fixation with pre-embedded bolt.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510517159.5A CN105113803B (en) | 2015-08-21 | 2015-08-21 | High-altitude sliding hoisting device of corridor truss of mountain and implementing method of high-altitude sliding hoisting device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510517159.5A CN105113803B (en) | 2015-08-21 | 2015-08-21 | High-altitude sliding hoisting device of corridor truss of mountain and implementing method of high-altitude sliding hoisting device |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105113803A CN105113803A (en) | 2015-12-02 |
CN105113803B true CN105113803B (en) | 2017-05-10 |
Family
ID=54661894
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510517159.5A Active CN105113803B (en) | 2015-08-21 | 2015-08-21 | High-altitude sliding hoisting device of corridor truss of mountain and implementing method of high-altitude sliding hoisting device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105113803B (en) |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108265987B (en) * | 2018-01-29 | 2019-12-20 | 江苏江中集团有限公司 | Installation method of large-span space truss |
CN109098452B (en) * | 2018-08-09 | 2020-11-27 | 上海宝冶建筑装饰有限公司 | Scenic spot complex terrain steel structure installation method |
CN115405106A (en) * | 2021-05-28 | 2022-11-29 | 中国核工业二三建设有限公司 | Method for fixing first framework of nuclear power drum filter screen |
CN113982100B (en) * | 2021-11-11 | 2023-03-28 | 防城港中一重工有限公司 | Overall sliding installation method for steel gallery in complex environment |
CN114362034B (en) * | 2021-11-26 | 2023-12-08 | 宁波送变电建设有限公司 | Method for replacing overhead ground wire by corridor wiring |
CN114197530A (en) * | 2022-01-12 | 2022-03-18 | 中国建筑土木建设有限公司 | Accurate positioning and mounting equipment for oversized-diameter pipeline in pipe gallery and construction method thereof |
CN118495368B (en) * | 2024-07-22 | 2024-10-18 | 中建四局安装工程有限公司 | Large-span pipe rack sliding and lifting device, control method thereof and related products |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH07279434A (en) * | 1994-04-13 | 1995-10-27 | Shimizu Corp | Erection method of structure and erection device used |
CN201158944Y (en) * | 2007-12-28 | 2008-12-03 | 浙江东南网架股份有限公司 | Support ball node slipping device of arched network frame accumulation slippage method |
CN101343949A (en) * | 2008-08-19 | 2009-01-14 | 河北建工集团有限责任公司 | Dislocation assembly network frame hoisting construction method and its hoisting system |
CN204510844U (en) * | 2015-03-23 | 2015-07-29 | 中建八局第三建设有限公司 | A kind of large-span steel girder high-altitude mounting slip device |
CN204983693U (en) * | 2015-08-21 | 2016-01-20 | 中国五冶集团有限公司 | Hoist device slides in mountain area corridor truss high altitude |
-
2015
- 2015-08-21 CN CN201510517159.5A patent/CN105113803B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH07279434A (en) * | 1994-04-13 | 1995-10-27 | Shimizu Corp | Erection method of structure and erection device used |
CN201158944Y (en) * | 2007-12-28 | 2008-12-03 | 浙江东南网架股份有限公司 | Support ball node slipping device of arched network frame accumulation slippage method |
CN101343949A (en) * | 2008-08-19 | 2009-01-14 | 河北建工集团有限责任公司 | Dislocation assembly network frame hoisting construction method and its hoisting system |
CN204510844U (en) * | 2015-03-23 | 2015-07-29 | 中建八局第三建设有限公司 | A kind of large-span steel girder high-altitude mounting slip device |
CN204983693U (en) * | 2015-08-21 | 2016-01-20 | 中国五冶集团有限公司 | Hoist device slides in mountain area corridor truss high altitude |
Also Published As
Publication number | Publication date |
---|---|
CN105113803A (en) | 2015-12-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105113803B (en) | High-altitude sliding hoisting device of corridor truss of mountain and implementing method of high-altitude sliding hoisting device | |
CN101476293B (en) | Non-stand construction method for large bridge arch rib | |
CN202090286U (en) | Traction system suitable for self-anchored type double cable plane suspension bridge | |
CN106193618B (en) | A kind of aerial steel structure truss construction of Long span | |
CN104695752B (en) | Rapid rush-repair Tower System and its erection method | |
CN107201721A (en) | Stay cable installation construction method | |
CN109911770B (en) | Construction method for hoisting gantry crane | |
CN103883129B (en) | A kind of steel structural roof beam installation method | |
CN109488038A (en) | Across the mounting structure and installation method of the beam string flexible cable of existing building | |
CN201376848Y (en) | Large-scale double-tower automatic-elevation hoisting equipment | |
CN106245527A (en) | A kind of dicyclic suspender and the erection method of Long span cat road track cable | |
CN105092395B (en) | A kind of device for increasing the load of horizontal impact testing stand | |
CN208088097U (en) | A kind of three-tower suspension bridge erection of main beam constructing structure | |
CN108221694B (en) | The method for installing long-span arch bridge tie-rod | |
CN105586832A (en) | Suspension type catwalk surface net mounting system | |
CN204983693U (en) | Hoist device slides in mountain area corridor truss high altitude | |
CN105018115B (en) | Dry quenching primary deduster fragment hoisting method | |
CN103288002A (en) | Simple combination portal upper-air heavy-article hoisting device | |
CN203284126U (en) | Simple composite gantry high-altitude weight hoisting device | |
CN106144929A (en) | Group hoist device and construction method | |
CN110820555B (en) | Bridge maintenance vehicle and method for avoiding bridge pier by maintenance platform | |
CN105040592B (en) | Horizontal pull rope bridge and erection method thereof | |
CN108675116B (en) | Construction method of PC (polycarbonate) component | |
CN110886214B (en) | Mounting and dismounting method of maintenance platform for bridge maintenance vehicle | |
CN205591115U (en) | Suspension type catwalk veil installing the system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |