CN105113803B - A high-altitude sliding hoisting device and its implementation method for a mountain corridor truss - Google Patents

A high-altitude sliding hoisting device and its implementation method for a mountain corridor truss Download PDF

Info

Publication number
CN105113803B
CN105113803B CN201510517159.5A CN201510517159A CN105113803B CN 105113803 B CN105113803 B CN 105113803B CN 201510517159 A CN201510517159 A CN 201510517159A CN 105113803 B CN105113803 B CN 105113803B
Authority
CN
China
Prior art keywords
truss
sliding
corridor
hoisting device
altitude
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510517159.5A
Other languages
Chinese (zh)
Other versions
CN105113803A (en
Inventor
陈磊
弋富国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC5 Group Corp Ltd
Original Assignee
China MCC5 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC5 Group Corp Ltd filed Critical China MCC5 Group Corp Ltd
Priority to CN201510517159.5A priority Critical patent/CN105113803B/en
Publication of CN105113803A publication Critical patent/CN105113803A/en
Application granted granted Critical
Publication of CN105113803B publication Critical patent/CN105113803B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a high-altitude sliding hoisting device of a corridor truss of a mountain and an implementing method of the high-altitude sliding hoisting device. The problem that a crane hoisting mode or a climbing pole hoisting mode cannot be used in a cliffy mountain in the prior art is solved. The high-altitude sliding hoisting device of the corridor truss of the mountain comprises supports, a sliding frame, a sliding rope and a traction mechanism; the supports are arranged at two ends of a mounting platform; the sliding frame is arranged on the top of the mounting platform and consists of upright columns; the sliding rope and the traction mechanism are used with the sliding frame; a crossbeam is arranged on tops of each two upright columns at the same end; rib plates with through holes are arranged on each crossbeam and are close to positions where the crossbeam is connected with the corresponding upright columns; the sliding rope penetrates in the rib plates on the tops of two ends of the sliding frame; two tips of the sliding rope are anchored to the support; and the corridor truss is positioned in the sliding frame, is dragged by the traction mechanism, and moves on the sliding rope through a movable pulley mounted on the sliding rope. By the high-altitude sliding hoisting device, technology quality of manufacturing assembly and hoisting of the corridor truss is ensured, construction safety and precision are ensured, construction cost is reduced greatly, and construction period is shortened.

Description

一种山区廊道桁架高空滑移吊装装置及其实现方法A high-altitude sliding hoisting device and its implementation method for a mountain corridor truss

技术领域technical field

本发明涉及通廊钢结构桁架安装吊运领域,具体的说,是涉及一种山区廊道桁架高空滑移吊装装置及其实现方法。The invention relates to the field of installation and lifting of steel structure trusses in corridors, in particular to a high-altitude sliding lifting device for corridor trusses in mountainous areas and a realization method thereof.

背景技术Background technique

水泥工业生产中原料输送是一道重要的工序,而大多数石灰石原料采矿区和水泥熟料生产线由于各自作业条件和所处的地域地形地势的不同,石灰石原料需通过架空廊道和遂道安装输送系统将原料输送至原料堆场。现有技术中,桁架安装吊运所需设备结构庞大、设备复杂,且不适宜在山区复杂地形的高空廊道安装施工,实际实施应用不方便,效率低,易延误工期。Raw material transportation is an important process in cement industry production, and most limestone raw material mining areas and cement clinker production lines are different due to their respective operating conditions and geographical topography, limestone raw materials need to be installed and transported through overhead corridors and tunnels The system transports the raw materials to the raw material storage yard. In the prior art, the equipment required for the installation and lifting of the truss has a large structure and complex equipment, and is not suitable for installation and construction in high-altitude corridors with complex terrain in mountainous areas. The actual implementation and application are inconvenient, low in efficiency, and easy to delay the construction period.

发明内容Contents of the invention

本发明的目的在于克服上述缺陷,提供一种结构简单、实现方便、可以减少施工占地、节约运输费用、施工效率高的山区廊道桁架高空滑移吊装装置。The purpose of the present invention is to overcome the above-mentioned defects, and provide a high-altitude sliding hoisting device for mountain corridor trusses with simple structure, convenient implementation, reduced construction area, saving transportation costs, and high construction efficiency.

为了实现上述目的,本发明采用的技术方案如下:In order to achieve the above object, the technical scheme adopted in the present invention is as follows:

一种山区廊道桁架高空滑移吊装装置,包括安装于安装平台两端的支架,设置于安装平台顶部且由立柱构成的滑移框架,与所述滑移框架配合使用的滑索,以及牵引机构;在两根同端的所述立柱顶部安装有横梁,在所述横梁上靠近其与所述立柱的连接处设置有具有通孔的筋板,所述滑索穿过所述滑移框架两端顶部的筋板且两端头锚固于所述支架上,廊道桁架位于所述滑移框架内并由所述牵引机构牵引,通过安装在所述滑索上的动滑轮在所述滑索上移动。A high-altitude sliding hoisting device for a mountain corridor truss, including brackets installed at both ends of the installation platform, a sliding frame arranged on the top of the installation platform and composed of columns, a sliding cable used in conjunction with the sliding frame, and a traction mechanism A crossbeam is installed on the top of the two columns at the same end, and a rib plate with a through hole is arranged on the crossbeam near its connection with the column, and the slide cable passes through the two ends of the sliding frame The ribs on the top and both ends are anchored on the bracket, the corridor truss is located in the sliding frame and is pulled by the traction mechanism, and moves on the sliding cable through the movable pulley installed on the sliding cable .

进一步的,所述牵引机构包括设置在其中一个支架上的卷扬机,以及设置在另一个支架上的定滑轮,所述卷扬机的牵引索绕过所述定滑轮后连接在廊道桁架上。Further, the traction mechanism includes a hoist arranged on one of the brackets, and a fixed pulley arranged on the other bracket, and the traction rope of the hoist is connected to the gallery truss after bypassing the fixed pulley.

进一步的,所述定滑轮居中设置,以使得所述卷扬机的牵引索与廊道桁架的中心线一致。Further, the fixed pulley is arranged in the center, so that the traction rope of the hoist coincides with the center line of the gallery truss.

进一步的,在所述廊道桁架的两侧下弦端头设置有吊索,所述卷扬机的牵引索通过所述吊索牵引廊道桁架移动。Further, slings are provided at the ends of the lower chords on both sides of the corridor truss, and the traction cables of the hoist move the corridor truss through the slings.

进一步的,在所述安装平台下部还设置有若干支撑立柱。Further, a number of support columns are also provided at the lower part of the installation platform.

进一步的,所述支撑立柱通过缆风绳进行拉锚。Further, the support column is anchored by a cable wind rope.

进一步的,在所述安装平台上部每隔三米设置一根栏杆立柱。Further, a railing post is set every three meters on the upper part of the installation platform.

进一步的,在所述滑移框架上还设置有用于连接施工人员内的安全绳。Further, the sliding frame is also provided with safety ropes for connecting construction workers.

进一步的,所述廊道桁架通过倒链葫芦与所述动滑轮连接。Further, the corridor truss is connected to the movable pulley through an inverted chain hoist.

上述一种山区廊道桁架高空滑移吊装装置的实现方法,包括以下步骤:The above-mentioned method for realizing the high-altitude sliding hoisting device of a truss in a corridor in a mountainous area comprises the following steps:

(1)在安装平台两端搭建支架的步骤;(1) The steps of building brackets at both ends of the installation platform;

(2)在安装平台顶部通过立柱搭建滑移框架的步骤;(2) The step of building a sliding frame through columns on the top of the installation platform;

(3)在滑移框架的顶部焊接筋板,将滑索穿过筋板且两端沿滑移方向拉锚固定在支架上的步骤;(3) Weld the rib plate on the top of the sliding frame, pass the slide cable through the rib plate and anchor the two ends along the sliding direction to fix it on the bracket;

(4)在支架上安装牵引机构的步骤;(4) The step of installing the traction mechanism on the bracket;

(5)在安装平台上拼装廊道桁架的步骤;(5) Steps for assembling corridor trusses on the installation platform;

(6)将廊道桁架分段成若干桁架单元;(6) Segment the corridor truss into several truss units;

(7)用倒链葫芦将桁架单元与滑索上的动滑轮连接的步骤;(7) The step of connecting the truss unit with the movable pulley on the slide cable with an inverted chain hoist;

(8)牵引机构连接桁架单元的步骤;(8) The step of connecting the truss unit by the traction mechanism;

(9)人工配合牵引机构进行桁架单元连续滑移,直至桁架单元滑移至安装位置的步骤;(9) Manually cooperate with the traction mechanism to continuously slide the truss unit until the truss unit slides to the installation position;

(10)重复执行步骤(7)~(9)将所有桁架单元滑移至安装位置;(10) Repeat steps (7) to (9) to slide all truss units to the installation position;

(11)将桁架单元临时固定后进行对接组装构成完整的廊道桁架;(11) After the truss units are temporarily fixed, they are docked and assembled to form a complete corridor truss;

(12)将廊道桁架与预埋螺栓对准、安装固定的步骤。(12) The steps of aligning the corridor truss with the embedded bolts, installing and fixing them.

本发明设计原理:依据网架安装方法中的滑移法安装原理,结合实际设计滑移系统中的滑索结构、牵引机构、安全系统。悬索结构的主要承重构件是受拉的悬索,在滑移过程中,廊道桁架的自重和水平牵引力主要由悬索和滑移框架承担;其中,悬索主要承载桁架的自重,临时支承门架主要抵御水平牵引力。为此,本发明通过减小悬索的垂度,增强滑移框架的刚度,提高钢索的拉力和滑移框架的稳定性。牵引机构主要是由卷扬机构成,通过定滑轮改变动力方向,牵引桁架滑移就位。由于廊道桁架采用非标准设计,其跨度、重量均不相等。滑移安装过程中风险的不确定性因素较多,安全系统的控制采用现场实测实量,对滑移安装过程进行变形监测,并实时将变形数据与经验数据进行对比分析,有效保证索引系统、临时支承门架的变形控制在范围值内,确保施工安全。The design principle of the present invention is: according to the installation principle of the sliding method in the grid installation method, combined with the actual design of the sliding cable structure, traction mechanism and safety system in the sliding system. The main load-bearing member of the suspension cable structure is the tensioned suspension cable. During the sliding process, the self-weight and horizontal traction force of the corridor truss are mainly borne by the suspension cable and the sliding frame; among them, the suspension cable mainly bears the self-weight of the truss, and the temporary support The mast primarily resists horizontal traction. For this reason, the present invention increases the rigidity of the sliding frame by reducing the sag of the suspension cables, thereby improving the tension of the steel cables and the stability of the sliding frame. The traction mechanism is mainly composed of a winch, the power direction is changed through the fixed pulley, and the traction truss slides into place. Since the corridor truss adopts non-standard design, its span and weight are not equal. There are many uncertain factors of risk in the sliding installation process. The control of the safety system adopts on-site measurement and actual measurement to monitor the deformation during the sliding installation process, and compare and analyze the deformation data and empirical data in real time to effectively ensure the index system, The deformation of the temporary support mast is controlled within the range to ensure construction safety.

与现有技术相比,本发明具有以下有益效果:Compared with the prior art, the present invention has the following beneficial effects:

(1)本发明针对山区输送系统廊道钢桁架的特点,利用现有输送廊道平台制作完成,并采用“桁架制作安装逐榀推进”技术措施快速安装钢桁架技术,可以减少施工占地,节约运输倒费用。(1) The present invention is aimed at the characteristics of the steel truss in the corridor of the mountainous area conveying system. It utilizes the existing conveying corridor platform to complete the manufacture, and adopts the technical measures of "truss production and installation step by step" to quickly install the steel truss technology, which can reduce the construction area. Save on transportation costs.

(2)本发明针对山区复杂地形、运输材料、构件道路情况、工程工期进度情况,科学合理划分施工段,采用分段同时组织施工,从而有效地缩短了工期。(2) The present invention scientifically and rationally divides the construction sections in view of the complex terrain in mountainous areas, transportation materials, component road conditions, and construction period progress, and organizes construction in sections at the same time, thereby effectively shortening the construction period.

(3)本发明采用高空制作组装、高空滑移吊装施工技术,降低了廊道桁架制作组装、吊装施工技术难度,解决了在陡峭山区无法使用吊车及爬杆等吊装方式的特大难题,确保了廊道桁架制作组装及吊装的技术质量,确保了施工安全和精度,极大地降低了施工成本,缩短了工期。(3) The present invention adopts high-altitude fabrication and assembly and high-altitude sliding hoisting construction technology, which reduces the technical difficulty of corridor truss fabrication, assembly, and hoisting construction, and solves the extremely difficult problem that hoisting methods such as cranes and climbing poles cannot be used in steep mountainous areas. The technical quality of corridor truss production, assembly and hoisting ensures construction safety and precision, greatly reduces construction cost and shortens construction period.

附图说明Description of drawings

图1为本发明的结构示意图。Fig. 1 is a structural schematic diagram of the present invention.

图2为本发明的断面示意图。Fig. 2 is a schematic cross-sectional view of the present invention.

附图中对应的附图标记名称如下:The names of the corresponding reference signs in the accompanying drawings are as follows:

1-立柱,2-横梁,3-通孔,4-筋板,5-支架,6-滑索,7-卷扬机,8-定滑轮,9-支撑立柱,10-缆风绳,11-倒链葫芦,12-廊道桁架。1-column, 2-beam, 3-through hole, 4-rib plate, 5-bracket, 6-slip line, 7-hoist, 8-fixed pulley, 9-supporting column, 10-cable wind rope, 11-inversion Chain Hoist, 12-Gallery Truss.

具体实施方式detailed description

下面结合附图和实施例对本发明作进一步说明,本发明的实施方式包括但不限于下列实施例。The present invention will be further described below with reference to the accompanying drawings and examples, and the embodiments of the present invention include but not limited to the following examples.

实施例Example

如图1、2所示,本实施例提供了一种山区廊道桁架高空滑移吊装装置,用以解决在陡峭山区无法使用吊车及爬杆等吊装方式的难题。该吊装装置主要包括支架、滑移框架、滑索和牵引机构。支架为四柱支架柱,设置在安装平台的两端。As shown in Figures 1 and 2, this embodiment provides a high-altitude sliding hoisting device for a mountain corridor truss, which is used to solve the problem that hoisting methods such as cranes and climbing poles cannot be used in steep mountainous areas. The hoisting device mainly includes a bracket, a sliding frame, a sliding cable and a traction mechanism. The support is a four-column support column, which is arranged at both ends of the installation platform.

滑移框架由立柱构成,其结构为长方体框架或正方体框架,本实施例中,滑移框架用Φ219钢管制作6根各2米长立柱构成,具体的说,在连续三跨混凝土支架顶部两侧各锚固两根立柱,立柱间距大于廊道桁架两弦宽度,立柱顶部焊接有横梁,横梁的材质不作特别限定,但是应当具有较高的强度,横梁两端距立柱100mm处焊接筋板,筋板上开设有供滑索穿过的通孔,安装时,滑索穿过滑移框架两端顶部的筋板,滑索两端沿滑移方向拉锚固定在两端相邻四柱支架柱上,滑索固定前先固定一端,另一端采用倒链葫芦将滑索张紧,待滑索张紧后用4组卡扣将滑索固定牢固,当端部支架为高度较高的单支架时,滑索的锚固角度宜不大于60度,且支架5需用缆风绳做有效的拉锚,防止悬索受力后端部支架发生倾覆事故。The sliding frame is composed of upright columns, and its structure is a rectangular parallelepiped frame or a cube frame. In this embodiment, the sliding frame is made of Φ219 steel pipes to make six upright columns each 2 meters long. Specifically, on both sides of the top of the continuous three-span concrete support Two columns are anchored each, the distance between the columns is greater than the width of the two chords of the corridor truss, and the top of the columns is welded with a beam. There is a through hole for the slide cable to pass through. When installing, the slide cable passes through the ribs at the top of both ends of the sliding frame, and the two ends of the slide cable are anchored to the adjacent four-column support columns at both ends along the sliding direction. Fix one end of the zipline before fixing it, and use an inverted chain hoist to tension the zipline at the other end. After the zipline is tensioned, use 4 sets of buckles to fix the zipline firmly. When the end bracket is a single bracket with a higher height, The anchorage angle of slide cable should be no more than 60 degrees, and support 5 needs to do effective pull anchor with cable wind rope, prevents that overturning accident takes place in the back end support of suspension cable stress.

本实施例中牵引机构包括有卷扬机和定滑轮两部分,二者分别设置在两端的支架上,且定滑轮架居中设置,使卷扬机钢索牵引力作用线与廊道桁架中心线尽量一致,确保廊道桁架滑移过程中不发生较大偏位,致使发生停滑、卡钩等问题,增加质量安全风险。The traction mechanism in this embodiment includes two parts: hoist and fixed pulley. During the sliding process of the road truss, there will be no large deviation, resulting in problems such as stop slipping and hooking, which will increase the quality and safety risks.

牵引机构的安装如下:在安装廊道桁架的后方四柱支架上安装固定一台卷扬机,作为廊道桁架滑移的牵引动力;在前方四柱支架上用钢丝绳固定一定滑轮,卷扬机的牵引索和廊道桁架连接时,先将4.5m长的吊索用卡扣固定于廊道桁架两侧下弦端头,牵引索再与固定好的吊索中间连接,当廊道桁架被牵引受力时,桁架两弦将同时受力,防止桁架骨架受拉变形。The installation of the traction mechanism is as follows: install and fix a winch on the rear four-column support of the gallery truss as the traction force for the sliding of the gallery truss; fix a certain pulley on the front four-column support with a wire rope, and the traction rope of the hoist and the gallery When connecting the trusses, first fix the 4.5m-long slings to the ends of the lower chords on both sides of the corridor trusses with buckles, and then connect the traction cables to the middle of the fixed slings. When the corridor trusses are pulled and stressed, the two The strings will be stressed at the same time, preventing the truss frame from being deformed in tension.

滑索上安装有动滑轮,廊道桁架通过动滑轮与滑索连接,施工时,廊道桁架在安装平台上拼装完成后,用倒链葫芦将廊道桁架与滑索上安装的动滑轮连接,拉动倒链葫芦,慢慢将廊道桁架整体悬空50mm左右,检查滑索系统支架、滑索、倒链葫芦、动滑轮等构件是否有变形、松动情况,待检查无误后再向前进行短距离试滑,再次检查滑索系统支架、滑索、倒链葫芦、滑轮等构件是否有变形、松动情况。待确认滑索系统各构件均正常工作后,人工配合卷扬机继续进行桁架连续滑移作业,滑移过程中当滑索受力下挠弧度过大时,用倒链葫芦提升桁架以调整桁架的高度,直至牵引滑移至钢桁架安装位置。A moving pulley is installed on the sliding cable, and the corridor truss is connected with the sliding cable through the moving pulley. During construction, after the corridor truss is assembled on the installation platform, the corridor truss is connected with the moving pulley installed on the sliding cable with an upside-down chain hoist. For the chain hoist, slowly suspend the whole corridor truss about 50mm in the air, check whether there is any deformation or looseness of the zipline system bracket, zipline, upside-down chain hoist, movable pulley, etc. Check again whether there is any deformation or looseness of the sliding cable system bracket, sliding cable, chain hoist, pulley and other components. After confirming that all components of the zipline system are working normally, manually cooperate with the winch to continue the continuous sliding operation of the truss. During the sliding process, when the deflection arc is too large under the force of the zipline, use the inverted chain hoist to lift the truss to adjust the height of the truss , until the traction slides to the installation position of the steel truss.

本实施例中安全设施主要包括栏杆立柱、安全绳和缆风绳,其安装如下:在制作、滑移、安装过程中均为高空作业,安全分险很大,针对各作业段的施工条件,采取有针对性的安全措施。平台制作时受平台宽度的制约和便于桁架构件的移动、转向,均采用柔性防护,即在平台上每隔3m焊接固定栏杆立柱,用粗麻绳绑扎在栏杆立柱上形成柔性防护栏杆;滑移施工前,对高度较高的单支架,采用2道缆风绳对支架进行拉锚,防止单支架受侧向力发生倾覆;滑移、安装施工时,在滑移框架上单设一根安全绳,滑移作业人员将安全带挂于其上。The safety facilities in this embodiment mainly include railing posts, safety ropes and cable wind ropes, which are installed as follows: in the process of making, sliding and installing, they are all high-altitude operations, and the safety risk is very large. According to the construction conditions of each operation section, Take targeted security measures. When the platform is made, it is restricted by the width of the platform and it is convenient for the movement and turning of the truss members. Flexible protection is used, that is, the railing columns are welded and fixed every 3m on the platform, and they are tied to the railing columns with thick hemp ropes to form flexible protective railings; Before construction, for a single support with a high height, use 2 cable wind ropes to anchor the support to prevent the single support from overturning due to lateral force; rope on which the skid steer operator hangs the safety belt.

本实施例中,采用分段同时组织施工,将单片桁架采用下承桁架同样的试吊、试滑,检查无误后,将分段单片桁架滑移就位。根据支架和滑移框架上桁架中心线的位置,调整各段单片桁架的位置,调整到位后,将桁架在两端做临时固定。四段单片钢桁架由远至近依次滑移就位,临时固定后进行单片对接,再由中间向两端进行上、下弦支撑件安装施工。In this embodiment, the construction is organized in sections at the same time, and the single-piece truss is tested for lifting and sliding in the same way as the bottom-bearing truss. After the inspection is correct, the sectioned single-piece truss is slid into place. According to the position of the center line of the truss on the bracket and the sliding frame, adjust the position of each single-piece truss. After the adjustment is in place, temporarily fix the truss at both ends. The four-segment single-piece steel trusses are slid into place in sequence from far to near, temporarily fixed and single-piece butt jointed, and then the upper and lower chord supports are installed from the middle to both ends.

安装固定及平台板铺装:桁架滑移至支座位置后,距柱基准面100mm时徐徐松动倒链葫芦,人工撬动廊道桁架,使廊道桁架支座螺栓孔对准柱顶预埋螺栓,倒链葫芦缓慢落钩就位。柱脚四周采用斜铁(锲子)顶紧,对廊道桁架进行校正,使水平位移和垂直度偏差在规范及设计允许范围之内后焊接固定后脱钩。此项工作完成后即可进行后续钢平台铺装施工。Installation and fixation and platform slab paving: After the truss slides to the support position, slowly loosen the chain hoist at a distance of 100mm from the column datum level, and manually pry the corridor truss so that the bolt holes of the corridor truss support are aligned with the pre-embedded column top Bolt, the inverted chain hoist slowly lowers the hook into place. The pillars are tightened with inclined irons (wedges) around the columns, and the corridor trusses are corrected so that the horizontal displacement and verticality deviation are within the allowable range of the specification and design, then welded and fixed, and then unhooked. After this work is completed, the subsequent steel platform pavement construction can be carried out.

按照上述实施例,便可很好地实现本发明。值得说明的是,基于上述设计原理的前提下,为解决同样的技术问题,即使在本发明所公开的结构基础上做出的一些无实质性的改动或润色,所采用的技术方案的实质仍然与本发明一样,故其也应当在本发明的保护范围内。According to the above-mentioned embodiments, the present invention can be well realized. It is worth noting that, based on the premise of the above-mentioned design principle, in order to solve the same technical problem, even if some insubstantial changes or modifications are made on the basis of the structure disclosed in the present invention, the essence of the adopted technical solution is still Like the present invention, it should also be within the protection scope of the present invention.

Claims (8)

1.一种山区廊道桁架高空滑移吊装装置,其特征在于,包括安装于安装平台两端的支架(5),设置于安装平台顶部且由立柱(1)构成的滑移框架,与所述滑移框架配合使用的滑索(6),以及牵引机构;在两根同端的所述立柱顶部安装有横梁(2),在所述横梁(2)上靠近其与所述立柱的连接处设置有具有通孔(3)的筋板(4),所述滑索(6)穿过所述滑移框架两端顶部的筋板(4)且两端头锚固于所述支架(5)上,廊道桁架位于所述滑移框架内并由所述牵引机构牵引,通过安装在所述滑索(6)上的动滑轮在所述滑索(6)上移动;在所述滑移框架上还设置有用于连接施工人员内的安全绳;所述廊道桁架通过倒链葫芦(11)与所述动滑轮连接。1. A high-altitude sliding hoisting device for a mountain corridor truss, characterized in that it includes brackets (5) installed at both ends of the installation platform, a sliding frame set on the top of the installation platform and composed of columns (1), and the The sliding cable (6) used in conjunction with the sliding frame, and the traction mechanism; a crossbeam (2) is installed on the top of the two columns at the same end, and is set on the crossbeam (2) near its connection with the column There is a rib plate (4) with a through hole (3), the slide cable (6) passes through the rib plate (4) at the top of both ends of the sliding frame and the two ends are anchored on the bracket (5) , the corridor truss is located in the sliding frame and is pulled by the traction mechanism, and moves on the sliding cable (6) through the movable pulley installed on the sliding cable (6); on the sliding frame Safety ropes for connecting construction personnel are also provided; the corridor truss is connected to the movable pulley through an inverted chain hoist (11). 2.根据权利要求1所述的一种山区廊道桁架高空滑移吊装装置,其特征在于,所述牵引机构包括设置在其中一个支架(5)上的卷扬机(7),以及设置在另一个支架(5)上的定滑轮(8),所述卷扬机(7)的牵引索绕过所述定滑轮(8)后连接在廊道桁架上。2. A high-altitude sliding hoisting device for mountain corridor trusses according to claim 1, characterized in that the traction mechanism includes a winch (7) set on one of the supports (5), and a hoist (7) set on the other The fixed pulley (8) on the bracket (5), the traction cable of the hoist (7) is connected to the corridor truss after bypassing the fixed pulley (8). 3.根据权利要求2所述的一种山区廊道桁架高空滑移吊装装置,其特征在于,所述定滑轮(8)居中设置,以使得所述卷扬机的牵引索与廊道桁架的中心线一致。3. The high-altitude sliding hoisting device for trusses in corridors in mountainous areas according to claim 2, characterized in that the fixed pulley (8) is set in the center so that the traction cables of the hoist are aligned with the centerline of the corridor trusses unanimous. 4.根据权利要求3所述的一种山区廊道桁架高空滑移吊装装置,其特征在于,在所述廊道桁架的两侧下弦端头设置有吊索,所述卷扬机的牵引索通过所述吊索牵引廊道桁架移动。4. The high-altitude sliding hoisting device for a mountain corridor truss according to claim 3, characterized in that slings are arranged at the ends of the lower chords on both sides of the corridor truss, and the traction rope of the hoist passes through the Said sling pulls the gallery truss to move. 5.根据权利要求1至4任一项所述的一种山区廊道桁架高空滑移吊装装置,其特征在于,在所述安装平台下部还设置有若干支撑立柱(9)。5. The high-altitude sliding hoisting device for mountain corridor trusses according to any one of claims 1 to 4, characterized in that, a number of support columns (9) are also arranged at the lower part of the installation platform. 6.根据权利要求5所述的一种山区廊道桁架高空滑移吊装装置,其特征在于,所述支撑立柱(9)通过缆风绳(10)进行拉锚。6. The high-altitude sliding hoisting device for truss trusses in corridors in mountainous areas according to claim 5, characterized in that, the support columns (9) are anchored by cable wind ropes (10). 7.根据权利要求1所述的一种山区廊道桁架高空滑移吊装装置,其特征在于,在所述安装平台上部每隔三米设置一根栏杆立柱。7. The high-altitude sliding hoisting device for truss trusses in corridors in mountainous areas according to claim 1, characterized in that a railing post is arranged every three meters on the upper part of the installation platform. 8.如权利要求1-7任一项所述的一种山区廊道桁架高空滑移吊装装置的实现方法,其特征在于,包括以下步骤:8. The implementation method of a mountain corridor truss high-altitude sliding hoisting device according to any one of claims 1-7, characterized in that it comprises the following steps: (1)在安装平台两端搭建支架的步骤;(1) The steps of building brackets at both ends of the installation platform; (2)在安装平台顶部通过立柱搭建滑移框架的步骤;(2) The steps of building a sliding frame through columns on the top of the installation platform; (3)在滑移框架的顶部焊接筋板,将滑索穿过筋板且两端沿滑移方向拉锚固定在支架上的步骤;(3) Weld the rib plate on the top of the sliding frame, pass the slide cable through the rib plate and pull the anchors at both ends along the sliding direction to fix it on the bracket; (4)在支架上安装牵引机构的步骤;(4) The steps of installing the traction mechanism on the bracket; (5)在安装平台上拼装廊道桁架的步骤;(5) Steps for assembling corridor trusses on the installation platform; (6)将廊道桁架分段成若干桁架单元;(6) Segment the corridor truss into several truss units; (7)用倒链葫芦将桁架单元与滑索上的动滑轮连接的步骤;(7) The step of connecting the truss unit with the movable pulley on the cable by using an inverted chain hoist; (8)牵引机构连接桁架单元的步骤;(8) The steps of connecting the traction mechanism to the truss unit; (9)人工配合牵引机构进行桁架单元连续滑移,直至桁架单元滑移至安装位置的步骤;(9) Manually cooperate with the traction mechanism to continuously slide the truss unit until the truss unit slides to the installation position; (10)重复执行步骤(7)~(9)将所有桁架单元滑移至安装位置;(10) Repeat steps (7)~(9) to slide all truss units to the installation position; (11)将桁架单元临时固定后进行对接组装构成完整的廊道桁架;(11) After the truss units are temporarily fixed, they are docked and assembled to form a complete corridor truss; (12)将廊道桁架与预埋螺栓对准、安装固定的步骤。(12) Steps for aligning the corridor truss with the embedded bolts, and installing and fixing them.
CN201510517159.5A 2015-08-21 2015-08-21 A high-altitude sliding hoisting device and its implementation method for a mountain corridor truss Active CN105113803B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510517159.5A CN105113803B (en) 2015-08-21 2015-08-21 A high-altitude sliding hoisting device and its implementation method for a mountain corridor truss

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510517159.5A CN105113803B (en) 2015-08-21 2015-08-21 A high-altitude sliding hoisting device and its implementation method for a mountain corridor truss

Publications (2)

Publication Number Publication Date
CN105113803A CN105113803A (en) 2015-12-02
CN105113803B true CN105113803B (en) 2017-05-10

Family

ID=54661894

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510517159.5A Active CN105113803B (en) 2015-08-21 2015-08-21 A high-altitude sliding hoisting device and its implementation method for a mountain corridor truss

Country Status (1)

Country Link
CN (1) CN105113803B (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108265987B (en) * 2018-01-29 2019-12-20 江苏江中集团有限公司 Installation method of large-span space truss
CN109098452B (en) * 2018-08-09 2020-11-27 上海宝冶建筑装饰有限公司 Scenic spot complex terrain steel structure installation method
CN115405106A (en) * 2021-05-28 2022-11-29 中国核工业二三建设有限公司 Method for fixing first framework of nuclear power drum filter screen
CN113982100B (en) * 2021-11-11 2023-03-28 防城港中一重工有限公司 Overall sliding installation method for steel gallery in complex environment
CN114362034B (en) * 2021-11-26 2023-12-08 宁波送变电建设有限公司 Method for replacing overhead ground wire by corridor wiring
CN114197530A (en) * 2022-01-12 2022-03-18 中国建筑土木建设有限公司 Accurate positioning and mounting equipment for oversized-diameter pipeline in pipe gallery and construction method thereof
CN116892407A (en) * 2023-08-11 2023-10-17 中建五局安装工程有限公司 A method for installing inverted columns at the top of a tunnel
CN118495368B (en) * 2024-07-22 2024-10-18 中建四局安装工程有限公司 Large-span pipe rack sliding and lifting device, control method thereof and related products

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07279434A (en) * 1994-04-13 1995-10-27 Shimizu Corp Construction method of structure and construction apparatus used therefor
CN201158944Y (en) * 2007-12-28 2008-12-03 浙江东南网架股份有限公司 Support ball node slipping device of arched network frame accumulation slippage method
CN101343949A (en) * 2008-08-19 2009-01-14 河北建工集团有限责任公司 A hoisting construction method and hoisting system for dislocation assembled grid frame
CN204510844U (en) * 2015-03-23 2015-07-29 中建八局第三建设有限公司 A kind of large-span steel girder high-altitude mounting slip device
CN204983693U (en) * 2015-08-21 2016-01-20 中国五冶集团有限公司 Hoist device slides in mountain area corridor truss high altitude

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07279434A (en) * 1994-04-13 1995-10-27 Shimizu Corp Construction method of structure and construction apparatus used therefor
CN201158944Y (en) * 2007-12-28 2008-12-03 浙江东南网架股份有限公司 Support ball node slipping device of arched network frame accumulation slippage method
CN101343949A (en) * 2008-08-19 2009-01-14 河北建工集团有限责任公司 A hoisting construction method and hoisting system for dislocation assembled grid frame
CN204510844U (en) * 2015-03-23 2015-07-29 中建八局第三建设有限公司 A kind of large-span steel girder high-altitude mounting slip device
CN204983693U (en) * 2015-08-21 2016-01-20 中国五冶集团有限公司 Hoist device slides in mountain area corridor truss high altitude

Also Published As

Publication number Publication date
CN105113803A (en) 2015-12-02

Similar Documents

Publication Publication Date Title
CN105113803B (en) A high-altitude sliding hoisting device and its implementation method for a mountain corridor truss
CN108532465B (en) Construction method of the main bridge of a bottom-supported steel box arch bridge
CN101736700B (en) Construction method for hoisting broad width steel box girder cantilever
CN103741601B (en) Tower, beam and cable synchronous bridge forming technology
CN100577915C (en) Erection method of long-span continuous steel truss arch
CN203377546U (en) High speed railway spanning construction apparatus
CN113685040A (en) Large-span steel truss hoisting construction method
CN107059656B (en) Construction Method of Suspended Scaffolding Operating Platform for Maintenance and Repair of Active Bridges
CN114673088B (en) A construction method applied to the catwalk of space main cable suspension bridge
CN104562936A (en) Construction method for continuous tie bar steel tube arch bridge
CN103866986B (en) Long span variable cross-section bolted spherical node net shell mounting method
CN102359303A (en) Extra-high voltage common circuit iron tower assembling method
CN116043713B (en) Overhead swivel erection method for vertically splicing and lifting suspension bridge steel beams
CN115506604B (en) Method for installing first truss of large-span steel structure
CN104790301B (en) A kind of cable-styled bridge system transform hoist cable tensioning one-time-reach-place construction method
CN104032967B (en) Prefabricated assembled frame structure component construction method for hanging
WO2024148715A1 (en) Method for erecting continuous steel truss bridge
CN108643584A (en) A kind of construction method of the steel construction overlength overhanging crossbeam without support installation
CN106192776A (en) A kind of big Span Continuous Flexible arch bridge with steel truss beam free cantilever erection construction technology
CN105442446B (en) Hanging basket for detecting and maintaining anchor mooring heads of boom and stay cable of bridge
CN205205685U (en) Span wire pier is function portal device at most
CN204983693U (en) Hoist device slides in mountain area corridor truss high altitude
CN109083395B (en) A large-span cable suspension operating platform and its erection method
CN110469102A (en) A high-altitude combined steel beam component installation and operation platform and its construction method
CN212077660U (en) Large-span wide width bridge girder rhombus hanging basket construction structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant