CN208563028U - A kind of Prefabricated road road shoulder structure in included gutter - Google Patents

A kind of Prefabricated road road shoulder structure in included gutter Download PDF

Info

Publication number
CN208563028U
CN208563028U CN201820635504.4U CN201820635504U CN208563028U CN 208563028 U CN208563028 U CN 208563028U CN 201820635504 U CN201820635504 U CN 201820635504U CN 208563028 U CN208563028 U CN 208563028U
Authority
CN
China
Prior art keywords
gutter
road
roadbed
lateral block
screed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820635504.4U
Other languages
Chinese (zh)
Inventor
连应鸿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Zhongjin Longitudinal And Lateral Traffic Survey And Design Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201820635504.4U priority Critical patent/CN208563028U/en
Application granted granted Critical
Publication of CN208563028U publication Critical patent/CN208563028U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Landscapes

  • Road Paving Structures (AREA)

Abstract

The utility model discloses a kind of Prefabricated road road shoulder structures in included gutter, including roadbed, lateral block is fixedly connected on the right side of roadbed upper surface, lateral block includes stop body, gutter and diversion trench, stop body internal run-through is connected with gutter, stop body upper surface is provided with diversion trench, it is successively equipped with underlayment from below to up on the left of roadbed upper surface, it goes to a grassroots level, upper base and surface layer, surface layer includes pervious bed, guiding gutter and screed, pervious bed bottom surface is fixedly connected with screed, guiding gutter is provided between pervious bed and screed, utilize inclined guiding gutter, the rainwater guiding gutter discharge that pervious bed can be permeated, avoid rain erosion roadbed;Using diversion trench, drainage efficiency can be improved in the ponding diversion road surface in surface layer;The packing layer formed using road waste material, not only economize on resources waste utilization, and can use when driveway.

Description

A kind of Prefabricated road road shoulder structure in included gutter
Technical field
The utility model relates to road shoulder correlative technology field, the Prefabricated road road shoulder knot in specially a kind of included gutter Structure.
Background technique
Road shoulder refers to being located at driveway outer rim to shoulder, the band-like portions with one fixed width comprising hard road Shoulder and protectiveness road shoulder, to keep function and the temporary parking of driveway to use, and the lateral support as road surface.Prefabricated road Seepage of water it is strong, the rainy day, prolonged ponding can damage roadbed, the stability of road be destroyed, although existing roadbed aesthetic qualities It is good, but drainage performance is poor, is not suitable for the use of Prefabricated road, and the utility model proposes a kind of the prefabricated of included gutter thus Road road shoulder structure is for solving the above problems.
Utility model content
The purpose of this utility model is to provide a kind of Prefabricated road road shoulder structures in included gutter, to solve above-mentioned back The problem of being proposed in scape technology.
To achieve the above object, the utility model provides the following technical solutions: a kind of Prefabricated road road in included gutter Shoulder structure, including roadbed, the roadbed upper surface right side are fixedly connected with lateral block, and the lateral block includes block master Body, gutter and diversion trench, the stop body internal run-through are connected with gutter, and the stop body upper surface, which is provided with, leads Chute is successively equipped with underlayment on the left of the roadbed upper surface from below to up, goes to a grassroots level, upper base and surface layer, the surface layer Including pervious bed, guiding gutter and screed, the pervious bed bottom surface is fixedly connected with screed, the pervious bed and screed it Between be provided with guiding gutter, the adjacent lateral block inner wall bottom end is equipped with lateral block, the transverse direction block bottom surface and roadbed Connection is inlayed, is filled with packing layer between the adjacent lateral block.
Preferably, the lateral block lateral section is right-angled trapezium, and the lateral block gradient is 30o~40o.
Preferably, guiding gutter inclined upward 10o to the left, and guiding gutter right end is connected to gutter.
Preferably, the lateral block is T-type structure, and lateral block is at least equipped with three groups.
Preferably, described filler layer is made of road waste material, and packing layer upper surface is concordant with lateral block.
Compared with prior art, the utility model has the beneficial effects that
1, using inclined guiding gutter, the rainwater guiding gutter discharge that pervious bed can be permeated avoids rain erosion Roadbed;
2, using diversion trench, drainage efficiency can be improved in the ponding diversion road surface in surface layer;
3, the packing layer formed using road waste material, not only economize on resources waste utilization, and can use when driveway.
Detailed description of the invention
FIG. 1 is a schematic structural view of the utility model;
Fig. 2 is the utility model top view;
Fig. 3 is the lateral stop block structure schematic diagram of the utility model;
Fig. 4 is the utility model surface layer structure schematic diagram.
In figure: roadbed 1, lateral block 2, stop body 21, gutter 22, diversion trench 23, underlayment 3, go to a grassroots level 4, on Base 5, surface layer 6, pervious bed 61, guiding gutter 62, screed 63, lateral block 7 and packing layer 8.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
Fig. 1-4 is please referred to, the utility model provides a kind of technical solution: a kind of Prefabricated road road shoulder knot in included gutter Structure, including roadbed 1,1 upper surface of roadbed right side are fixedly connected with lateral block 2, and lateral block 2 includes stop body 21, draining Ditch 22 and diversion trench 23,21 internal run-through of stop body are connected with gutter 22, and 21 upper surface of stop body is provided with diversion trench 23, it is successively equipped with underlayment 3 from below to up on the left of 1 upper surface of roadbed, go to a grassroots level 4, upper base 5 and surface layer 6, surface layer 6 includes Pervious bed 61, guiding gutter 62 and screed 63,61 bottom surface of pervious bed are fixedly connected with screed 63, pervious bed 61 and screed 63 Between be provided with guiding gutter 62, the adjacent lateral 2 inner wall bottom end of block is equipped with lateral block 7,7 bottom surface of the transverse direction block It inlays and connect with roadbed 1, packing layer 8 is filled between the adjacent lateral block 2.
Further, 2 lateral section of lateral block is right-angled trapezium, and lateral 2 gradient of block is 30o~40o.
Further, the guiding gutter 62 inclined upward 10o to the left, and 62 right end of guiding gutter is connected to gutter 22, benefit With inclined guiding gutter 62, the rainwater guiding gutter 22 that pervious bed 61 permeates can be discharged, avoid rain erosion roadbed.
Further, the lateral block 7 is T-type structure, substantially increases the Prefabricated road road shoulder in the included gutter Structural soundness, and lateral block 7 is at least equipped with three groups.
Further, described filler layer 8 is made of road waste material, and 8 upper surface of packing layer is concordant with lateral block 2, benefit The packing layer 8 formed with road waste material, not only economize on resources waste utilization, and can use when driveway.
Working principle: when practical operation, rainwater first passes through 23 diversion road surface of diversion trench, penetrates into and leads using pervious bed 61 It is discharged in sink 62 and by gutter 22, lateral block 7 is T-type structure, substantially increases the prefabricated road in the included gutter Road road shoulder structural soundness, the packing layer 8 formed using road waste material, not only economize on resources waste utilization, and can work as vehicle Trade uses.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art, It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.

Claims (5)

1. a kind of Prefabricated road road shoulder structure in included gutter, including roadbed (1), it is characterised in that: table on the roadbed (1) Right side of face is fixedly connected with lateral block (2), and the lateral block (2) includes stop body (21), gutter (22) and water conservancy diversion Slot (23), stop body (21) internal run-through are connected with gutter (22), and stop body (21) upper surface is provided with Diversion trench (23), roadbed (1) the upper surface left side is successively equipped with underlayment (3) from below to up, go to a grassroots level (4), upper base (5) and surface layer (6), the surface layer (6) include pervious bed (61), guiding gutter (62) and screed (63), the pervious bed (61) Bottom surface is fixedly connected with screed (63), is provided with guiding gutter (62) between the pervious bed (61) and screed (63), adjacent Lateral block (2) the inner wall bottom end is equipped with lateral block (7), and company is inlayed in transverse direction block (7) bottom surface and roadbed (1) It connects, is filled with packing layer (8) between the adjacent lateral block (2).
2. a kind of Prefabricated road road shoulder structure in included gutter according to claim 1, it is characterised in that: described lateral Block (2) lateral section is right-angled trapezium, and lateral block (2) gradient is 30o~40o.
3. a kind of Prefabricated road road shoulder structure in included gutter according to claim 1, it is characterised in that: the water guide Slot (62) inclined upward 10o to the left, and guiding gutter (62) right end is connected to gutter (22).
4. a kind of Prefabricated road road shoulder structure in included gutter according to claim 1, it is characterised in that: the transverse direction Block (7) is T-type structure, and lateral block (7) is at least equipped with three groups.
5. a kind of Prefabricated road road shoulder structure in included gutter according to claim 1, it is characterised in that: the filler Layer (8) is made of road waste material, and packing layer (8) upper surface is concordant with lateral block (2).
CN201820635504.4U 2018-05-01 2018-05-01 A kind of Prefabricated road road shoulder structure in included gutter Expired - Fee Related CN208563028U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820635504.4U CN208563028U (en) 2018-05-01 2018-05-01 A kind of Prefabricated road road shoulder structure in included gutter

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820635504.4U CN208563028U (en) 2018-05-01 2018-05-01 A kind of Prefabricated road road shoulder structure in included gutter

Publications (1)

Publication Number Publication Date
CN208563028U true CN208563028U (en) 2019-03-01

Family

ID=65480896

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820635504.4U Expired - Fee Related CN208563028U (en) 2018-05-01 2018-05-01 A kind of Prefabricated road road shoulder structure in included gutter

Country Status (1)

Country Link
CN (1) CN208563028U (en)

Similar Documents

Publication Publication Date Title
CN206538698U (en) A kind of municipal works road drainage structure
CN106320433A (en) Urban road rainwater collection structure
CN207714482U (en) A kind of novel overflow well of dirty counterflow-preventing in sponge city section
CN208563028U (en) A kind of Prefabricated road road shoulder structure in included gutter
CN206529867U (en) Row's structure is oozed in a kind of simple retaining
CN208965349U (en) Environment friendly pervious brick
CN206157519U (en) A device that permeates water that is arranged in ecological terrestrial system in sponge city
CN105401660A (en) Waterproof structure of toilet and water collecting tank
CN109457562A (en) Conducive to the asphalt concrete road structure of draining
CN202440922U (en) Infiltration system capable of reducing discharge intensity of house surface rainwater
CN208533302U (en) A kind of water-permeable brick of the sponge city with anti-skid chequer
CN108867243A (en) A kind of area of heavy rainfull peripheral path ponding collects exhaust system and construction method
CN205443854U (en) Notch cuttype curb
CN204098198U (en) A kind of pervious concrete being provided with filtrate well is mated formation system
CN208899274U (en) A kind of environmental protection water permeable brick structure
CN209669626U (en) A kind of pervious concrete brick
CN209602906U (en) The waterproof floor tile reconstruction structure in sponge city
CN209338953U (en) A kind of urban road ecological side drain with sponge municipal drainage facility
CN206457682U (en) A kind of water storage type water-permeable brick
CN208201562U (en) A kind of sponge city kerbstone
CN207891680U (en) A kind of regeneration concrete water-permeable brick
CN213925712U (en) Sponge city roadbed that permeates water that rainwater can evacuation fast
CN206189227U (en) Road rainwater recycle device
CN205999747U (en) A kind of drainage type Route for pedestrians structure
CN206873225U (en) A kind of novel garden road pavior brick

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20190531

Address after: 030032 Yongli International Building, 219 Sports Road, Xiaodian District, Taiyuan City, Shanxi Province, 13th Floor, 2017-451

Patentee after: Shanxi Zhongjin Longitudinal and Lateral Traffic Survey and Design Co., Ltd.

Address before: 364015 No. 13 Pai tou Road, Chishui Town, Longmen Town, Xinluo District, Longyan, Fujian.

Patentee before: Lian Yinghong

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190301

Termination date: 20210501