CN208535316U - Assembled piping lane bracket - Google Patents

Assembled piping lane bracket Download PDF

Info

Publication number
CN208535316U
CN208535316U CN201820474005.1U CN201820474005U CN208535316U CN 208535316 U CN208535316 U CN 208535316U CN 201820474005 U CN201820474005 U CN 201820474005U CN 208535316 U CN208535316 U CN 208535316U
Authority
CN
China
Prior art keywords
cross bar
piping lane
column
lane bracket
assembled piping
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820474005.1U
Other languages
Chinese (zh)
Inventor
战福军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Lianzhong Engineering Technology Co ltd
Original Assignee
Nanjing Lianzhong Construction Engineering Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Lianzhong Construction Engineering Technology Co Ltd filed Critical Nanjing Lianzhong Construction Engineering Technology Co Ltd
Priority to CN201820474005.1U priority Critical patent/CN208535316U/en
Application granted granted Critical
Publication of CN208535316U publication Critical patent/CN208535316U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of assembled piping lane bracket, including column and cross bar, the column and cross bar detachable connection are equipped with the diagonal brace for enhancing cross bar bearing capacity in its connecting portion.The utility model has the advantages that: the piping lane bracket connects into an entirety by column, cross bar and diagonal brace three parts, supporting structure is more stable, easy to operate, and economic performance is improved, receiving carries pipeline, the ability of cable further enhances, and substantially increases the space utilization rate of piping lane.

Description

Assembled piping lane bracket
Technical field
The utility model relates to a kind of bracket, in particular to a kind of assembled piping lane bracket.
Background technique
Since the underground space below traditional direct-burried pipeline occupancy road is more, and the laying of pipeline tends not to and road The construction on road is synchronous, causes road frequently to excavate, not only affects the normal pass of road, while also bringing noise and fugitive dust Environmental pollution, the direct-burried pipeline in some cities frequently occurs safety accident, thus pipe gallery engineering is built in countries in the world.It is comprehensive Piping lane can be used for accommodating the pipelines such as combustion gas, heating power, plumbing and communication cable etc., in order to further increase piping lane space The laying of the pipelines such as utilization rate and cable, being especially inside corridor body needs to lay supporting support on side plate.But conventional stent Column and cross bar mostly use angle steel form (such as C-type steel), and for the two using being welded to form one, scene can not be according to actually adjusting Spacing between whole cross bar, at the same to it is subsequent it is all kinds of enter corridor line size and trend limited.
Utility model content
Purpose of utility model: the utility model is intended to provide a kind of assembled piping lane that can improve bearing capacity and stability Bracket.
Technical solution: assembled piping lane bracket described in the utility model, including column and cross bar, the column and cross bar Detachable connection is equipped with the diagonal brace for enhancing cross bar bearing capacity in its connecting portion.
Specifically, the diagonal brace is the bloom with bevel edge, and further, bevel edge can be rolled into flange or bevel edge On have reinforcement structure;Meanwhile bloom can be triangle, or trapezoidal.
Using C-type steel as column, the anti-bending strength of column is improved;Using C-type steel or angle steel as cross bar, cross bar is improved Bearing capacity.Wherein, C-type steel includes bottom and the long-armed and galianconism positioned at two sides of the bottom, wherein is had on long-armed and galianconism Reinforcement structure.In addition, column and cross bar are equipped with bolt hole, realize its detachable connection and relative position is adjustable.
The utility model has the advantages that compared with prior art, the advantages of the utility model are as follows: the piping lane bracket is by column, cross bar and tiltedly Support three parts connect into an entirety, and supporting structure is more stable, and bearing capacity is enhanced;Meanwhile column and cross bar select C Fashioned iron improves the anti-bending strength of bracket, reduces wall thickness, increases integrally-built economy.
Detailed description of the invention
Fig. 1-2 is the structural schematic diagram of piping lane bracket;
Fig. 3 (a), 3 (b) be the C-type steel with reinforcement structure structural schematic diagram.
Specific embodiment
As shown in Figure 1, the assembled piping lane bracket of the utility model forms one by column 1, cross bar 2 and 3 three parts of diagonal brace A entirety, wherein column 1 replaces traditional angle steel using the superior C-type steel of anti-bending strength, is able to achieve anti-bending strength enhancing, together When can be reduced wall thickness, save the cost.Cross bar can be angle steel or C-type steel etc., can improve the bearing capacity of cross bar.
As shown in Fig. 3 (a), 3 (b), C-type steel includes bottom 101 and long-armed 102 and galianconism 103 positioned at two sides of the bottom, In, long-armed 102 and galianconism 103 ends curved inwards formed it is hook-shaped, meanwhile, long-armed 102 and galianconism 103 on have reinforcement structure 104, reinforcement structure here can also be considered as reinforcing rib.
Bolt hole 4 is opened up on the side wall and cross bar 2 of column 1, cross bar 2 and column 1 and diagonal brace 3 can be adjusted according to actual needs Relative position, realize that cross bar 2 and diagonal brace 3 in the adjustment up and down of column 1, overcome prior art central post 1 and cross bar 2 to weld one The case where body can not adjust.
Meanwhile the utility model is equipped with diagonal brace 3 in the connecting portion of column 1 and cross bar 2, which can be used for enhancing cross Bar bearing capacity.As shown in Figs. 1-2, diagonal brace 3 is triangle bloom or trapezoidal bloom, they all have bevel edge 301, which can To be rolled into flange 302, as shown in Fig. 2, have reinforcement structure on bevel edge 301, the support energy of diagonal brace is further enhanced with this Power improves the intensity of bracket entirety.
The piping lane supporting structure advantages of simple of the utility model, it is easy to operate, it is crucial that, overall structure is more Stablize, accommodates and the ability of carrying pipeline, cable further enhances, greatly improve piping lane space utilization rate.

Claims (6)

1. a kind of assembled piping lane bracket, including column (1) and cross bar (2), the column (1) and cross bar (2) detachable company It connects, is equipped with the diagonal brace (3) for enhancing cross bar bearing capacity in its connecting portion, it is characterised in that: the diagonal brace (3) is with oblique The bloom on side (301), the bevel edge (301), which is rolled on flange (302) or bevel edge (301), reinforcement structure.
2. assembled piping lane bracket according to claim 1, it is characterised in that: the bloom is triangle or trapezoidal.
3. assembled piping lane bracket according to claim 1, it is characterised in that: the column (1) is C-type steel.
4. assembled piping lane bracket according to claim 1, it is characterised in that: the cross bar (2) is C-type steel or angle steel.
5. assembled piping lane bracket according to claim 3 or 4, it is characterised in that: the C-type steel includes bottom (101) With long-armed (102) and the galianconism (103) for being located at two sides of the bottom, wherein have on long-armed (102) and galianconism (103) and reinforce Structure (104).
6. assembled piping lane bracket according to claim 1, it is characterised in that: the column (1) and cross bar (2) are equipped with Bolt hole (4).
CN201820474005.1U 2018-04-04 2018-04-04 Assembled piping lane bracket Expired - Fee Related CN208535316U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820474005.1U CN208535316U (en) 2018-04-04 2018-04-04 Assembled piping lane bracket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820474005.1U CN208535316U (en) 2018-04-04 2018-04-04 Assembled piping lane bracket

Publications (1)

Publication Number Publication Date
CN208535316U true CN208535316U (en) 2019-02-22

Family

ID=65395219

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820474005.1U Expired - Fee Related CN208535316U (en) 2018-04-04 2018-04-04 Assembled piping lane bracket

Country Status (1)

Country Link
CN (1) CN208535316U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116581701A (en) * 2023-07-14 2023-08-11 中建八局第二建设有限公司 Spliced cable bracket and construction method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116581701A (en) * 2023-07-14 2023-08-11 中建八局第二建设有限公司 Spliced cable bracket and construction method thereof
CN116581701B (en) * 2023-07-14 2023-11-03 中建八局第二建设有限公司 Spliced cable bracket and construction method thereof

Similar Documents

Publication Publication Date Title
CN203671023U (en) Natural gas line height fine setting support device
CN208535316U (en) Assembled piping lane bracket
CN202927262U (en) Pipeline installation pillar in oil/gas pipeline tunnel
CN208685678U (en) A kind of float Structure of subway station
CN205276313U (en) Modular box piping lane
CN204626453U (en) The supporting device of pipeline in Urban Underground pipe gallery
CN107634706A (en) A kind of photovoltaic plant array bracket
CN204691020U (en) A kind of T-shaped supporting steel keel of curtain wall
CN204754945U (en) Mine method tunnel preliminary bracing lining cutting grid steel support make
CN206943591U (en) A kind of petroleum pipeline support frame
CN205504205U (en) Pipeline bracket node structure
CN204434129U (en) The undersetting structure of tower crane
CN203320420U (en) Temporary locking structure for corrugated steel webs of steel and concrete combined box girder
CN208346630U (en) A kind of gap bridge pipeline K font door frame
CN204531467U (en) A kind of superposed beam, plate support bar tripod
CN202181611U (en) Single-frame saddle-shaped pipe truss
CN204920416U (en) Simple and easy transmission tower structure
CN204358665U (en) A kind of reversing warning lamp bearing
CN204627098U (en) Electric line pole self guy wire support
CN202628138U (en) L-shaped connecting piece for steel support and feet-lock anchor rod
CN217129123U (en) Local reinforced structure of communication tower pipeline section
CN204265253U (en) A kind of crane girder and hoisting crane
CN207194240U (en) The connector that a kind of out-hung panel is connected with main body
CN209603174U (en) Underground pipe gallery line holder fixed structure
CN106300166A (en) A kind of piping lane inner cable support

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 211215 Zhetang Town Industrial Park, Lishui District, Nanjing City, Jiangsu Province

Patentee after: NANJING LIANZHONG ENGINEERING TECHNOLOGY Co.,Ltd.

Address before: 211215 No. 331 Zhening East Road, Zhetang Industrial Concentration Zone, Lishui Economic Development Zone, Nanjing City, Jiangsu Province

Patentee before: NANJING LIANZHONG CONSTRUCTION ENGINEERING TECHNOLOGY Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190222