CN208502764U - Anti-settling supporting construction - Google Patents

Anti-settling supporting construction Download PDF

Info

Publication number
CN208502764U
CN208502764U CN201821112819.7U CN201821112819U CN208502764U CN 208502764 U CN208502764 U CN 208502764U CN 201821112819 U CN201821112819 U CN 201821112819U CN 208502764 U CN208502764 U CN 208502764U
Authority
CN
China
Prior art keywords
settling
supporting
supporting pipeline
pipeline
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821112819.7U
Other languages
Chinese (zh)
Inventor
俞剑龙
王渊
刘念武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Keyi College of ZSTU
Original Assignee
Keyi College of ZSTU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Keyi College of ZSTU filed Critical Keyi College of ZSTU
Priority to CN201821112819.7U priority Critical patent/CN208502764U/en
Application granted granted Critical
Publication of CN208502764U publication Critical patent/CN208502764U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

A kind of anti-settling supporting construction provided by the utility model, for reinforcing existing landmark;It include: a pair of of construction well, the construction well is located at the two sides of landmark;More anti-settling supporting pipelines positioned at the bottom of the landmark, and penetrate through a pair of of construction well;Cement slurry is perfused in the anti-settling supporting pipeline.The utility model, which uses, first excavates construction well in landmark two sides, and the anti-settling supporting pipeline of simultaneously slip casting is excavated under landmark, and construction is simple, structural strength are high, can effectively prevent the sedimentation of historical relic.

Description

Anti-settling supporting construction
Technical field
The utility model relates to underground pile support technology fields, and in particular to a kind of anti-settling supporting construction.
Background technique
With the continuous propulsion of urban development, it is often necessary to construct under landmark.Such as under landmark Fang Jinhang constructing tunnel needs current shield machine, how to protect landmark to prevent its sedimentation just at urgent problem.
The existing patent document application No. is CN201710778115.7 discloses a kind of " polyethylene pipe non-excavating construction Method " patent document, excavate scale very little, the sedimentation of landmark can not be effectively prevent, anti-settling effect is poor.
Utility model content
(1) technical problems to be solved
The purpose of the utility model is to provide a kind of anti-settling supporting construction, solve existing supporting construction anti-settling effect The defect of fruit difference.
(2) technical solution
In order to solve the above-mentioned technical problem, a kind of anti-settling supporting construction provided by the utility model, it is existing for reinforcing Landmark;Include: a pair of of construction well, be used for constructing operation, the construction well is located at the two sides of landmark;It is more Root anti-settling supporting pipeline positioned at the bottom of the landmark, and penetrates through a pair of of construction well, the tube wall of anti-settling supporting pipeline On be provided with multiple injected holes.The utility model excavates construction well in landmark two sides using first, and digs under landmark It digs and the anti-settling supporting pipeline of slip casting, construction is simple, structural strength height can effectively prevent the sedimentation of historical relic.
Preferably, the horizontal distance between the construction well and landmark is greater than landmark length in this direction One third.
Preferably, the elevation of bottom of the construction well is lower than the foundation elevation of landmark.
Preferably, the minimum range of the bottom end of the anti-settling supporting pipeline and landmark is more than or equal to 1m.
Preferably, the anti-settling supporting pipeline is at least two layers, each layer have more anti-settling supporting pipeline enclosures every Parallel arrangement.
Preferably, the horizontal distance between each layer of anti-settling supporting pipeline is 1-1.5m.
Preferably, the area of anti-settling supporting pipeline covering is greater than the area of the landmark bottom of foundation, outermost anti- Horizontal distance between sedimentation supporting pipeline and the nearest edge of the landmark bottom of foundation is at least 50cm.
Preferably, the anti-settling supporting pipeline on upper layer and the anti-settling supporting pipeline of lower layer mutually stagger, lower layer it is anti-settling The caliber in descending branch pillar road is less than the caliber of upper layer anti-settling supporting pipeline.
Preferably, the injected hole is distributed in the half portion of anti-settling supporting pipeline, after the setting of anti-settling supporting pipeline, Injected hole is upward;Cement slurry is perfused in the anti-settling supporting pipeline, cement slurry forms compound in the injected hole injection soil body Carry the soil body.
Preferably, the anti-settling supporting pipeline lower part is additionally provided in more filled with the first supporting pipeline of steel column and interior The more second supporting pipelines filled with armored concrete, the first supporting pipeline are located at below anti-settling supporting pipeline, institute It states the first supporting pipeline and the width of anti-settling supporting pipe level arranged crosswise and more first supporting pipelines expansion is big In the spreading width of anti-settling supporting pipeline;The second supporting pipeline is located at below the first supporting pipeline, second supporting The width that pipeline and the first supporting pipe level arranged crosswise and the more second supporting pipelines are unfolded is greater than first pillar Road spreading width;The internal diameter of the second supporting pipeline, the first supporting pipeline and anti-settling supporting pipeline once increases.
(3) beneficial effect
A kind of anti-settling supporting construction provided by the utility model, has the advantage that
1, the utility model, which uses, first excavates construction well in landmark two sides, and simultaneously slip casting is excavated under landmark Anti-settling supporting pipeline, construction is simple, structural strength are high, can effectively prevent the sedimentation of historical relic.
Detailed description of the invention
Fig. 1 is the anti-settling supporting construction the schematic diagram of the section structure of the embodiments of the present invention 1;
Fig. 2 is the side structure schematic diagram of the anti-settling supporting construction of the embodiments of the present invention 1;
Fig. 3 is the anti-settling supporting pipeline cross-section structure signal of the anti-settling supporting construction of the embodiments of the present invention 1 Figure.
1, construction well;2, anti-settling supporting pipeline;3, injected hole;4, the first supporting pipeline;5, the second supporting pipeline;100, Landmark.
Specific embodiment
With reference to the accompanying drawings and examples, specific embodiment of the present utility model is described in further detail.Below Example is not intended to limit the scope of the present invention for illustrating the utility model.
Embodiment 1:
As shown in Figure 1, Figure 2, Figure 3 shows, a kind of anti-settling supporting construction provided by the utility model, for reinforcing existing text Object building;Include: a pair of of construction well 1, be used for constructing operation, the construction well is located at the two sides of landmark;More anti- Supporting pipeline 2 is settled, positioned at the bottom of the landmark, and a pair of of construction well is penetrated through, on the tube wall of anti-settling supporting pipeline It is provided with multiple injected holes 3.The injected hole is distributed in the half portion of anti-settling supporting pipeline, the setting of anti-settling supporting pipeline Afterwards, injected hole is upward;Cement slurry is perfused in the anti-settling supporting pipeline, cement slurry forms multiple in the injected hole injection soil body Close the carrying soil body.
It is described construction well and landmark between horizontal distance be greater than landmark in this direction length three/ One.The elevation of bottom of the construction well is lower than the foundation elevation of landmark.The anti-settling supporting pipeline and landmark The minimum range of bottom end is more than or equal to 1m.
The anti-settling supporting pipeline is at least two layers, and each layer has the more spaced and parallel cloth of anti-settling supporting pipeline It sets.Horizontal distance between each layer of anti-settling supporting pipeline is 1-1.5m.
The area of anti-settling supporting pipeline covering is greater than the area of the landmark bottom of foundation, outermost anti-settling supporting Horizontal distance between pipeline and the nearest edge of the landmark bottom of foundation is at least 50cm.The anti-settling supporting pipeline on upper layer It is mutually staggered with the anti-settling supporting pipeline of lower layer, the caliber of the anti-settling supporting pipeline of lower layer is less than upper layer anti-settling branch pillar The caliber in road.
The anti-settling supporting pipeline lower part is additionally provided with the first supporting pipeline 4 in more filled with steel column and interior is filled with More second supporting pipelines 5 of armored concrete, the first supporting pipeline are located at below anti-settling supporting pipeline, and described first Supporting pipeline and the width of anti-settling supporting pipe level arranged crosswise and more first supporting pipelines expansion are greater than anti-settling The spreading width in descending branch pillar road;The second supporting pipeline is located at below the first supporting pipeline, the second supporting pipeline with The width that first supporting pipe level arranged crosswise and the more second supporting pipelines are unfolded is unfolded greater than the first supporting pipeline Width;The internal diameter of the second supporting pipeline, the first supporting pipeline and anti-settling supporting pipeline once increases.
When the embodiments of the present invention are implemented, the construction well along house length direction is excavated in landmark two sides, is applied The elevation of bottom of work well is lower than the foundation elevation 2.5m of landmark.The minimum of the bottom end of anti-settling supporting pipeline and landmark Distance is equal to 1m.Horizontal distance between each layer of anti-supporting pipeline is 1-1.5m.Outermost anti-settling supporting pipeline with Horizontal distance between the nearest edge of the landmark bottom of foundation is 50cm.Shield is used below the bottom end of landmark Machine excavates more anti-settling supporting pipelines, the first supporting pipeline and the second supporting pipeline, then by injected hole in anti-settling descending branch Cement slurry is injected in pillar road;It is inserted into steel column into the first supporting pipeline, reinforcing bar is added into the second supporting pipeline and by both ends Inject armored concrete.
Embodiment 2:
A kind of anti-settling supporting construction provided by the utility model, for reinforcing existing landmark;It include: a pair Construction well, is used for constructing operation, and the construction well is located at the two sides of landmark;More anti-settling supporting pipelines, are located at The bottom of the landmark, and a pair of of construction well is penetrated through, multiple injected holes are provided on the tube wall of anti-settling supporting pipeline.
The various embodiments described above are merely to illustrate the utility model, wherein the structure of each component, connection type etc. are all can be with It is varied, all equivalents and improvement carried out on the basis of technical solutions of the utility model should not exclude Except the protection scope of the utility model.

Claims (10)

1. a kind of anti-settling supporting construction characterized by comprising
A pair of construction well, is used for constructing operation, and the construction well is located at the two sides of landmark;
More anti-settling supporting pipelines positioned at the bottom of the landmark, and penetrate through a pair of of construction well, anti-settling supporting pipeline Tube wall on be provided with multiple injected holes.
2. anti-settling supporting construction as described in claim 1, which is characterized in that the water between the construction well and landmark Flat distance is greater than the one third of landmark length in this direction.
3. anti-settling supporting construction as described in claim 1, which is characterized in that the elevation of bottom of the construction well is lower than historical relic The foundation elevation of building.
4. anti-settling supporting construction as described in claim 1, which is characterized in that the anti-settling supporting pipeline and landmark Bottom end minimum range be more than or equal to 1m.
5. anti-settling supporting construction as claimed in claim 1 or 2 or 3 or 4, which is characterized in that the anti-settling supporting pipeline At least two layers, each layer has more anti-settling supporting pipeline enclosures every parallel arrangement.
6. anti-settling supporting construction according to claim 5, which is characterized in that between each layer of anti-settling supporting pipeline Horizontal distance be 1-1.5m.
7. anti-settling supporting construction according to claim 5, which is characterized in that the area of anti-settling supporting pipeline covering is big In the area of the landmark bottom of foundation, outermost anti-settling supporting pipeline and the nearest edge of the landmark bottom of foundation it Between horizontal distance be at least 50cm.
8. anti-settling supporting construction according to claim 5, which is characterized in that the anti-settling supporting pipeline on upper layer and lower layer Anti-settling supporting pipeline mutually stagger, the caliber of the anti-settling supporting pipeline of lower layer is less than the pipe of upper layer anti-settling supporting pipeline Diameter.
9. anti-settling supporting construction as claimed in claim 1 or 2 or 3 or 4, which is characterized in that the injected hole is distributed in In the half portion of anti-settling supporting pipeline, after the setting of anti-settling supporting pipeline, injected hole is upward;It is filled in the anti-settling supporting pipeline It is marked with cement slurry, cement slurry forms the composite bearing soil body in the injected hole injection soil body.
10. the anti-settling supporting construction as described in claims 1 or 2 or 3, which is characterized in that under the anti-settling supporting pipeline Portion is additionally provided with the first supporting pipeline and the interior more second supporting pipelines filled with armored concrete that steel column is filled in more, The first supporting pipeline is located at below anti-settling supporting pipeline, and the first supporting pipeline and anti-settling supporting pipe level are handed over Fork arrangement and the width of more first supporting pipelines expansion are greater than the spreading width of anti-settling supporting pipeline;Described second Pillar road is located at below the first supporting pipeline, the second supporting pipeline and the first supporting pipe level arranged crosswise and described more The width of root the second supporting pipeline expansion is greater than the first supporting pipeline spreading width;The second supporting pipeline, first pillar The internal diameter of road and anti-settling supporting pipeline once increases.
CN201821112819.7U 2018-07-13 2018-07-13 Anti-settling supporting construction Active CN208502764U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821112819.7U CN208502764U (en) 2018-07-13 2018-07-13 Anti-settling supporting construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821112819.7U CN208502764U (en) 2018-07-13 2018-07-13 Anti-settling supporting construction

Publications (1)

Publication Number Publication Date
CN208502764U true CN208502764U (en) 2019-02-15

Family

ID=65284548

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821112819.7U Active CN208502764U (en) 2018-07-13 2018-07-13 Anti-settling supporting construction

Country Status (1)

Country Link
CN (1) CN208502764U (en)

Similar Documents

Publication Publication Date Title
CN104533446B (en) Construction method and its structure that a kind of big cross section Support System in Soft Rock Tunnels bilayer pre- Geological disaster prevention of preliminary bracing occurs
CN102562075B (en) Large cross-section weak surrounding rock tunnel three-step and six-part short-distance construction method
CN110094213B (en) Space combined supporting structure and supporting method for water-rich broken stratum tunnel
CN103306289B (en) Foundation pit piled anchor dado concrete anchor cable top beam structure and construction method thereof
CN201412163Y (en) Circular tunnel lining structure for construction of open-type tunnel boring machine
CN106498953A (en) Cut slope composite supporting construction and its construction method
CN106120801B (en) Pipeline crosses the construction method at foundation ditch in water-rich sand layer
CN209924998U (en) Shallow earthing shield tunnel is worn road reinforcement protection architecture down
CN105625298B (en) Using the continuous underground wall structure and its construction method of glass fiber-reinforced polymer lap joint sleeve milling
CN202689031U (en) Deep foundation pit retaining and protecting retaining wall
CN104847365B (en) A kind of small interval Four-Lane Road Shallow-buried Large-span Tunnel construction method
CN109653772A (en) A kind of shallow buried tube curtain support system and its construction method
CN110158649A (en) The construction method of Adjacent Underground Pipeline when a kind of caisson sinking construction
CN109457709A (en) A kind of supporting construction and construction method of double-row pile combination wide-angle anchor cable
CN109653222A (en) Friction pile means of defence, anti-slide pile construction method and friction pile safeguard structure
CN109296371A (en) MJS method and horizontal freezing joint reinforcement pressure-bearing rich water arenaceous stratum overlap the system and its construction method that section is worn under station
CN201538975U (en) Seepage-proofing joint of underground continuous wall
CN101575859B (en) Anti-seepage joint of underground continuous walls and construction method thereof
CN203161244U (en) Existing subway underground excavation running tunnel protection structure
CN203939509U (en) The waterproof construction of bolt-spary supports traffic tunnel
CN110387889A (en) A kind of multi-arch type foundation pit supporting method for strip deep basal pit
CN204851266U (en) Secretly dig shaft structure directly over station
CN104594297A (en) Double-deck concrete faced rock-fill dam and construction method thereof
CN105862875A (en) Support structure and construction method thereof
CN106498957B (en) Steel sheet pile cofferdam construction platform and integral construction method