CN208502249U - A kind of steel die for presetting hole for concrete floor - Google Patents

A kind of steel die for presetting hole for concrete floor Download PDF

Info

Publication number
CN208502249U
CN208502249U CN201820937132.0U CN201820937132U CN208502249U CN 208502249 U CN208502249 U CN 208502249U CN 201820937132 U CN201820937132 U CN 201820937132U CN 208502249 U CN208502249 U CN 208502249U
Authority
CN
China
Prior art keywords
steel die
concrete floor
steel
pilot pin
bucket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820937132.0U
Other languages
Chinese (zh)
Inventor
盛于洲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Temuxinke (Zhejiang) Metal Structure Co., Ltd.
Original Assignee
Tongxiang Zhong Zhuo Metal Component Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tongxiang Zhong Zhuo Metal Component Co Ltd filed Critical Tongxiang Zhong Zhuo Metal Component Co Ltd
Priority to CN201820937132.0U priority Critical patent/CN208502249U/en
Application granted granted Critical
Publication of CN208502249U publication Critical patent/CN208502249U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model discloses a kind of steel dies that hole is preset for concrete floor.Including steel die bucket, handle;Steel die bucket bottom is fixed with bottom steel plate, and bottom steel board bottom face center weldment has a pilot pin, and pilot pin is vertical with bottom steel plate, and outside foam pad pasting is posted in steel die bucket outer surface, is equipped with handle at the top of steel die bucket;Pilot pin is used to drill and be inserted at the telltale mark of concrete floor module and hold out against.The utility model simple structure, standardization, can be used repeatedly convenient and quick construction, can be widely applied in the construction technology of building concrete floor slab preformed hole mouth.

Description

A kind of steel die for presetting hole for concrete floor
Technical field
The utility model relates to building concrete floor field, and in particular to a kind of to preset hole for concrete floor Steel die.
Background technique
Concrete floor is that the main level primary structure member in building is needed due to the cooperation with water power profession in floor , there are water pipe, fulgurite, equipment pipe etc. in the pipeline hole of upper reserved various sizes, due to Standardization instrument, the size at these holes is all There is certain standard specification.
Currently used way is easily gone wrong in construction with iron nail and iron wire binding and fixing casing, this mode, It is mainly manifested in and is not fixed firmly, with template contacts imprecision, be easy spillage in concrete casting, it must after causing casing to take out Floor must can be also destroyed sometimes, causes artificial, material waste, construction is also inconvenient by picking chisel ability pore-forming.
Utility model content
In order to solve the problems in background technique, the utility model, which provides, a kind of presets hole for concrete floor Steel die, the mold structure is simple, easy to operate, and site operation is quick, and hole Forming Quality is reliable, and benefit can be repeated several times With can be widely applied in the construction technology of building concrete floor slab preformed hole mouth.
The technical solution adopted in the utility model is:
The utility model includes steel die bucket and handle;Steel die bucket bottom is fixed with bottom steel plate, bottom steel plate Bottom surface center weldment has a pilot pin, and pilot pin is vertical with bottom steel plate, and outside foam pad pasting is posted in steel die bucket outer surface, Handle is installed at the top of steel die bucket;Pilot pin is used to drill at the telltale mark of concrete floor module and is inserted into top Tightly.
The pilot pin is made of steel nail, and outer end is sharp.
The foam pad pasting thickness about 2mm.
The steel die bucket is made using steel plate, and shape is cartridge type, and cross section is round or rectangular.
The cross sectional dimensions of the steel die bucket is consistent with the size of reserving hole.
The beneficial effects of the utility model are:
1, simple structure.The material selection and production method of steel die bucket are simple and convenient, can be selected that steel plate is reserved, waste material Production, and material to steel plate and thickness do not require.
2, it is convenient to construct.Placement need to be only positioned when construction in template, is conveniently taken out after concrete hardening.
3, it standardizes.It, can be with batch making at standard drum, root according to the limited standard dimension of opening demand of mechanical discipline It is selected according to the standard specification of drawings marked.
4, it can be used repeatedly.Steel die bucket good rigidity reliable in quality, only need to paste one layer of foam pad pasting again can weigh It is multiple to utilize.
Detailed description of the invention
Fig. 1 is to preset the steel die at hole for concrete floor to cut open elevation;
Fig. 2 is to preset the rectangular steel die at hole for concrete floor to cut open plan view;
Fig. 3 is to preset the round steel die at hole for concrete floor to cut open plan view;
Steel die connects positioning figure with the template of concrete floor before Fig. 4 is concreting;
Fig. 5 is the relative position figure before steel die is removed after concreting;
Fig. 6 is the reserving hole sectional view of formation after steel die is removed.
In figure: 1, steel die bucket;2, bottom steel plate;3, pilot pin;4, handle;5, outside foam pad pasting;6, concrete Slab form;7, cast-in-place concrete floor;8, reserving hole.
Specific embodiment
With reference to the accompanying drawing and specific embodiment is described in further detail the utility model.
As shown in Figure 1, the mold of the utility model includes steel die bucket 1, handle 4;1 bottom of steel die bucket is fixed with Bottom steel plate 2,2 bottom surface center weldment of bottom steel plate have a pilot pin 3, and pilot pin 3 is vertical with bottom steel plate 2, steel die bucket 1 Outside foam pad pasting 5 is posted in outer surface, is equipped with handle 4 at the top of steel die bucket 1;Pilot pin is used in concrete floor module Telltale mark at drill and be inserted into and hold out against.
As shown in Figures 2 and 3, steel die bucket 1 is made using steel plate, and shape is cartridge type, and cross section is round or side Shape.
As shown in Figures 4 and 5, pilot pin is used to drill and be inserted at the telltale mark of concrete floor module and hold out against.
As shown in fig. 6, the cross sectional dimensions of steel die bucket 1 is consistent with the size of reserving hole 8.
The specific implementation reserving hole process of the utility model is as follows:
Before concrete floor pours, the position defence line of reserved opening is needed to position on concrete floor module, and do Good label.The steel die that corresponding size is selected by the specification at design hole, an aperture is bored at the telltale mark of template, will be determined Position needle insertion aperture is simultaneously held out against.After cast-in-place concrete floor pours and finishes and harden, steel die bucket is pulled out, due to mould There is the foam of the soft elasticity of 2mm on the outside of tool bucket, the extraction of steel die bucket is easy to.It can be in cast-in-place coagulation after extraction steel die bucket Reserving hole is formed at the telltale mark of native slab form.
Content described in this specification embodiment is only an enumeration of the implementation forms of the utility model concept, this is practical new The protection scope of type should not be construed as being limited to the specific forms stated in the embodiments, the protection scope of the utility model also and In those skilled in the art according to the utility model design it is conceivable that equivalent technologies mean.

Claims (5)

1. a kind of steel die for presetting hole for concrete floor, it is characterised in that: including steel die bucket (1), handle (4);Steel die bucket (1) bottom is fixed with bottom steel plate (2), and bottom steel plate (2) bottom surface center weldment has a pilot pin (3), Pilot pin (3) is vertical with bottom steel plate (2), and outside foam pad pasting (5), steel die bucket are posted in steel die bucket (1) outer surface (1) top is equipped with handle (4);Pilot pin is used to drill and be inserted at the telltale mark of concrete floor module and hold out against.
2. a kind of steel die for presetting hole for concrete floor according to claim 1, it is characterised in that: described Pilot pin (3) is made of steel nail, and outer end is sharp.
3. a kind of steel die for presetting hole for concrete floor according to claim 1, it is characterised in that: described Foam pad pasting (5) thickness about 2mm.
4. a kind of steel die for presetting hole for concrete floor according to claim 1, it is characterised in that: described Steel die bucket (1) is made using steel plate, and shape is cartridge type, and cross section is round or rectangular.
5. a kind of steel die for presetting hole for concrete floor according to claim 1, it is characterised in that: described The cross sectional dimensions of steel die bucket (1) is consistent with the size of reserving hole (8).
CN201820937132.0U 2018-06-15 2018-06-15 A kind of steel die for presetting hole for concrete floor Active CN208502249U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820937132.0U CN208502249U (en) 2018-06-15 2018-06-15 A kind of steel die for presetting hole for concrete floor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820937132.0U CN208502249U (en) 2018-06-15 2018-06-15 A kind of steel die for presetting hole for concrete floor

Publications (1)

Publication Number Publication Date
CN208502249U true CN208502249U (en) 2019-02-15

Family

ID=65286820

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820937132.0U Active CN208502249U (en) 2018-06-15 2018-06-15 A kind of steel die for presetting hole for concrete floor

Country Status (1)

Country Link
CN (1) CN208502249U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110821170A (en) * 2019-11-19 2020-02-21 中冶天工集团天津有限公司 Portable anti-leakage steel sleeve and use method thereof
CN114541766A (en) * 2022-03-07 2022-05-27 中建八局第二建设有限公司 Die and method for controlling thickness of floor slab

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110821170A (en) * 2019-11-19 2020-02-21 中冶天工集团天津有限公司 Portable anti-leakage steel sleeve and use method thereof
CN114541766A (en) * 2022-03-07 2022-05-27 中建八局第二建设有限公司 Die and method for controlling thickness of floor slab

Similar Documents

Publication Publication Date Title
CN208502249U (en) A kind of steel die for presetting hole for concrete floor
CN106013529B (en) The arrangement of reinforcement method of concrete shear force wall based on 3D printing
CN206495501U (en) A kind of cast-in-place concrete floor reserving hole template
CN203247600U (en) Equipment foundation bolt preformed hole die
CN112709431A (en) Material conveying port device with embedded steel bars and method for presetting material conveying port
KR102210482B1 (en) Flat tie cutting apparatus and its cutting method
CN202202561U (en) Floor preformed hole construction sleeve
CN109667389A (en) A kind of slab thickness control module and construction method
CN206220502U (en) A kind of concrete blinding
CN214740053U (en) Drawer type detachable die for accurately pre-burying shear groove of steel structure
CN212507353U (en) Side template structure of building cast-in-place structure body
JP3015646U (en) Concrete block for earth retaining
JPH022568Y2 (en)
CN209989959U (en) Concrete post-cast plate reinforcing steel bar reservation device
CN201187148Y (en) Umbrella-shaped formwork edge joint strip
CN208280596U (en) Hole pre-embedded device on a kind of floor
CN203403679U (en) Inner fixing connector, not penetrating through beam bottom template, of pre-buried line pipe
CN202187553U (en) Floor prepared hole die with steel bed die
CN205918116U (en) Reservation hole for building mould
CN208870391U (en) Building template reserves wire box plugging structure
CN111101705A (en) Plastic formwork plug for fixing reserved steel bars and construction method
CN201087549Y (en) Obligate bolt hole reinforcing bar cage of apparatus foundation
CN205600957U (en) Mould unloading shovel
CN217000957U (en) Pre-buried mould of aluminium mould spool location
CN202745373U (en) Mould used for preforming water and electricity openings on concrete slabs

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: 314500 No. 307, gaoxinxi 1st Road, Tongxiang Development Zone, Tongxiang City, Jiaxing City, Zhejiang Province

Patentee after: Temuxinke (Zhejiang) Metal Structure Co., Ltd.

Address before: 314515 Zhejiang Jiaxing Tongxiang Gaoqiao Town Xiang Zhuang village Cao Jia Bang (formerly riding Tang brick and tile factory)

Patentee before: TONGXIANG ZHONGZHUO METAL COMPONENTS Co.,Ltd.

CP03 Change of name, title or address