CN208456071U - A kind of operation work platform suitable for steep slope topography - Google Patents
A kind of operation work platform suitable for steep slope topography Download PDFInfo
- Publication number
- CN208456071U CN208456071U CN201721795099.4U CN201721795099U CN208456071U CN 208456071 U CN208456071 U CN 208456071U CN 201721795099 U CN201721795099 U CN 201721795099U CN 208456071 U CN208456071 U CN 208456071U
- Authority
- CN
- China
- Prior art keywords
- operation work
- work platform
- spud pile
- steep slope
- pedal
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
The utility model relates to the technical fields of electric operating device, and more particularly, to a kind of operation work platform suitable for steep slope topography, including fixing bracket and being used to support the pedal of operator, the pedal is set on the fixed bracket;The fixed bracket includes the spud pile fixed with abrupt slope inclined-plane and the carrying platform for carrying pedal, and the carrying platform and the horizontal plane are horizontally disposed.The operation work platform suitable for steep slope topography of the utility model, operation work platform is fixed on by spud pile and forms the carrying platform for being used to support construction personnel on the inclined-plane of abrupt slope, structure is simple, it is easy to operate, securely and reliably, the problem of can effectively solve the problem that constructional difficulties under the environment of abrupt slope eliminates the personal safety hidden danger of construction personnel, improves security reliability and construction efficiency;In addition, the operation work platform of the utility model is fixed, good operating stability can ensure the safety of construction personnel's construction.
Description
Technical field
The utility model relates to the technical field of electric operating device, more particularly, to a kind of suitable for steep slope topography
Operation work platform.
Background technique
In recent years, accelerate the requirement of investment construction speed, high pressure according to national " 13 " planning and Southern Power Grid Company
The application range of cable will expand increasingly, and high-tension cable project operation amount will constantly increase.Meanwhile being limited to environmental factor
It restricts and the requirement of O&M safety management, high-tension cable tunnel has become the superior solution of transmission line of electricity, there is wide development
Prospect.
But when high-tension cable tunnel carries out work progress, it is limited by the influence of orographic factor, especially in slope road
Under the big environment of path length, difference in height, at cable passage bracket installation etc. work there are certain difficulty and limitations.It is existing
Some construction methods are usually that staff strides semi-crouch on the slope, and carries out auxiliary branch by safety belt oblique pull fixed point
Support.However, on the one hand construction limitation is big and working efficiency is low for this operational method, need constantly to adjust work in the construction process
Posture adapts to the variation of environment, while prolonged operation easily leads to construction personnel leg and lumbar strain, reduces work
Efficiency;On the other hand, security risk is high;The purpose of safety belt that construction personnel wears is safeguard protection when ensureing high-rise working,
But man-hour requirement is applied on slope and carries out Auxiliary support using safety belt oblique pull fixed point, does not both meet safety standard requirements, simultaneously
Increase the probability for losing safety belt protection.
Utility model content
The purpose of the utility model is to overcome the deficiencies in the prior art, provide it is a kind of it is easy to operate, safe and reliable, can
Effectively solve the problems, such as the operation work platform suitable for steep slope topography of steep slope topography constructional difficulties.
In order to solve the above technical problems, the technical solution adopted in the utility model is:
A kind of operation work platform suitable for steep slope topography is provided, including fixed bracket and is used to support operator's
Pedal, the pedal are set on the fixed bracket;The fixed bracket includes the spud pile and use fixed with abrupt slope inclined-plane
In the carrying platform of carrying pedal, the carrying platform and the horizontal plane are horizontally disposed.
The operation work platform suitable for steep slope topography of the utility model, by fixing bracket for entire operation work platform
It is fixed on the inclined-plane of abrupt slope, support bracket fastened upper end plane forms the carrying platform for being used to support load-bearing;By stepping on for surfacing
Plate is placed on carrying platform, and construction personnel stands on to carry out the work on the horizontally disposed pedal of horizontal plane, and work efficiency is high, applies
The problem of work limitation is small, can effectively solve the problem that the constructional difficulties under the environment of abrupt slope, eliminates the personal safety hidden danger of construction personnel,
Improve security reliability and construction efficiency.
Further, the spud pile includes the first spud pile and the second spud pile, and first spud pile is set to steep
On the inclined-plane of slope, second spud pile is arranged with first spud pile and connect.First spud pile is embedded in constructing tunnel
In the inclined-plane of abrupt slope, the second spud pile is inserted into the first spud pile the fixation that entire operation work platform can be completed when use,
It is easy for installation, it is time saving and energy saving.
Further, the carrying platform includes two groups of first connecting rods disposed in parallel and two groups disposed in parallel the
Two connecting rods, the first connecting rod is vertical with second connecting rod to be connect.Setting forms a rectangular carrying in this way
The load bearing effect of platform, carrying platform is good, and is convenient for the standing of construction personnel on the carrying platform.
Further, the first connecting rod is to set internal thread cylinder, and the both ends of the first connecting rod are connected with
For withstanding the adjusting screw rod of abrupt slope side walls, the adjusting screw rod and the first connecting rod cooperate.Setting can be in this way
The length of adjusting screw rod stretching is adjusted by precession of the adjusting screw rod in first connecting rod or back-out, rotation adjusting screw rod is extremely
Side walls are withstood, dual fail-safe fixed operation workbench avoids the inclination of operation work platform caused by being not fixed firmly.
Further, one end of the adjusting screw rod is equipped with nut, and the outer surface of the nut is evenly equipped with several knurlings.Rolling
The setting of line increases the frictional force of rotation process, and nut is welded on the both ends of adjusting screw rod, plays the role of supporting load-bearing.
Further, reinforcing rod is connected between the spud pile and the carrying platform, the reinforcing rod, described second connect
Extension bar and the spud pile, which are surround, forms triangle.The setting of reinforcing rod increases the stability of fixed bracket load-bearing, and guarantee is applied
The safety of worker person's construction.
Further, several support rods disposed in parallel, the reinforcing rod and the fixation are connected between two groups of reinforcing rods
Angle between stake is 45 ° ~ 60 °.The purpose being arranged in this way is to increase support bracket fastened stability, further ensures construction personnel
The safety of construction.
Further, the pedal is equipped with the card slot cooperated with the carrying platform.Two sides are according to fixed below pedal
Card slot is arranged in the spacing of second connecting rod of bracket, can be fixed firmly in pedal in the second connecting rod.
Further, the pedal is the plank that thickness is 2cm ~ 5cm.The low manufacture cost of plank has certain load-bearing
Ability, and big compared to the frictional force of metal paddles and construction personnel's sole, can effectively prevent because frictional force it is small caused by slip.
Further, the fixed bracket is welded by coating steel pipe, the diameter of the coating steel pipe be 30mm ~
50mm.The manufacturing cost of coating steel pipe is low, and corrosion resistance and good is durable, it is ensured that the work operations of the utility model are flat
The service life of platform.
Compared with prior art, the utility model has the beneficial effects that
Operation work platform is fixed on by the operation work platform suitable for steep slope topography of the utility model by spud pile
The carrying platform for being used to support construction personnel is formed on the inclined-plane of abrupt slope, structure is simple, and it is easy to operate, it securely and reliably, can be effective
Solve the problems, such as constructional difficulties under the environment of abrupt slope, eliminate the personal safety hidden danger of construction personnel, improve security reliability and
Construction efficiency;In addition, the setting of the adjusting screw rod in the utility model further fixes operation work platform, reinforcing rod and support
The setting of bar both increases the stability of operation work platform, ensures the safety of construction personnel's construction.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the operation work platform suitable for steep slope topography of the utility model.
Specific embodiment
The utility model is further described With reference to embodiment.Wherein, being given for example only property of attached drawing
Illustrate, expression is only schematic diagram, rather than pictorial diagram, should not be understood as the limitation to this patent;In order to which this reality is better described
With novel embodiment, the certain components of attached drawing have omission, zoom in or out, and do not represent the size of actual product;To ability
For field technique personnel, the omitting of some known structures and their instructions in the attached drawings are understandable.
The same or similar label correspond to the same or similar components in the attached drawing of the utility model embodiment;It is practical at this
In novel description, it is to be understood that if the orientation or positional relationship for having the instructions such as term " on ", "lower", "left", "right" is
It is based on the orientation or positional relationship shown in the drawings, is merely for convenience of describing the present invention and simplifying the description, rather than indicate
Or imply that signified device or element must have a particular orientation, be constructed and operated in a specific orientation, therefore retouch in attached drawing
The term for stating positional relationship only for illustration, should not be understood as the limitation to this patent, for the common skill of this field
For art personnel, the concrete meaning of above-mentioned term can be understood as the case may be.
Embodiment 1
It is as shown in Figure 1 the first embodiment of the operation work platform suitable for steep slope topography of the utility model, including solid
Fixed rack 1 and the pedal 2 for being used to support operator, pedal 2 are set on fixed bracket 1;Fixed bracket 1 includes oblique with abrupt slope
The fixed spud pile 11 in face and the carrying platform 12 for carrying pedal, carrying platform 12 and horizontal plane are horizontally disposed;This reality
The fixation bracket 1 for applying example is welded by coating steel pipe, and the diameter of coating steel pipe is 30mm ~ 50mm.The present embodiment implement when,
Entire operation work platform is fixed on the inclined-plane of abrupt slope by fixed bracket 1, the upper end plane of fixed bracket 1 is formed for branch
Support the carrying platform 12 of load-bearing;The pedal 2 of surfacing is placed on carrying platform 12, construction personnel stands on and horizontal plane water
It carries out the work on the pedal 2 of flat setting, eliminates the personal safety hidden danger of construction personnel.
Specifically, spud pile 11 includes the first spud pile 13 and the second spud pile 14, and the second spud pile 14 and first is solid
Determine stake 13 and is arranged connection;First spud pile 13 is embedded in the inclined-plane of abrupt slope in constructing tunnel, by the second spud pile 144 when use
The fixation that entire operation work platform can be completed is inserted into the first spud pile 13.Carrying platform 12 includes two groups disposed in parallel
First connecting rod 15 and two groups of second connecting rods 16 disposed in parallel, first connecting rod 15 is vertical with the second connecting rod 16 to be connected
It connects;A rectangular carrying platform 12 is formed, load bearing effect is good, and is convenient for standing of the construction personnel on carrying platform 12.
For dual fail-safe fixed operation workbench, first connecting rod 15 is set setting internal thread by the present embodiment
Cylinder connects adjusting screw rod 17 at the both ends of cylinder, and nut is arranged in one end of adjusting screw rod 17, equal in the outer surface of nut
Several knurlings of cloth;The length of the stretching of adjusting screw rod 17 is adjusted by precession of the adjusting screw rod 17 in first connecting rod or back-out
Degree, rotation adjusting screw rod 17 avoid being not fixed firmly caused work to side walls, dual fail-safe fixed operation workbench is withstood
The inclination of industry workbench.
In order to increase the stability of fixed bracket load-bearing, ensures the safety of construction personnel, put down in spud pile 11 and carrying
12 connection reinforcement bars 18 of platform, reinforcing rod 18, the second connecting rod 16 surround with spud pile 11 and form triangle;And in reinforcing rod 18
Between connect several support rods disposed in parallel 19, the angle between reinforcing rod 18 and spud pile 11 is 45 ° ~ 60 °.
The pedal 2 of the present embodiment is the plank that thickness is 2cm ~ 5cm, and is equipped on the inside of pedal 2 and cooperates with carrying platform 12
Card slot 21;Card slot 21 is arranged according to the spacing of support bracket fastened second connecting rod in 1 lower section two sides of pedal, can be firm by pedal 2
It is fixed in the second connecting rod 16.
Obviously, the above embodiments of the present invention is merely examples for clearly illustrating the present invention, and
It is not limitations of the embodiments of the present invention.For those of ordinary skill in the art, in above description
On the basis of can also make other variations or changes in different ways.There is no need and unable to give all embodiments
Exhaustion.Any modifications, equivalent replacements, and improvements made within the spirit and principle of the present invention etc., should be included in
Within the protection scope of the utility model claims.
Claims (10)
1. a kind of operation work platform suitable for steep slope topography, which is characterized in that including fixed bracket (1) and be used to support behaviour
Make the pedal (2) of personnel, the pedal (2) is set on the fixed bracket (1);The fixed bracket (1) includes oblique with abrupt slope
The fixed spud pile (11) in face and the carrying platform (12) for carrying pedal, the carrying platform (12) and the horizontal plane
It is horizontally disposed.
2. the operation work platform according to claim 1 suitable for steep slope topography, which is characterized in that the spud pile (11)
Including the first spud pile (13) and the second spud pile (14), first spud pile (13) is set on the inclined-plane of abrupt slope, and described the
Two spud piles (14) are arranged with first spud pile (13) and connect.
3. the operation work platform according to claim 1 suitable for steep slope topography, which is characterized in that the carrying platform
(12) include two groups of first connecting rods (15) disposed in parallel and two groups of second connecting rods (16) disposed in parallel, described first
Connecting rod (15) is vertical with second connecting rod (16) to be connect.
4. the operation work platform according to claim 3 suitable for steep slope topography, which is characterized in that the first connecting rod
(15) to set internal thread cylinder, the both ends of the first connecting rod (15) are connected with the tune for withstanding abrupt slope side walls
It saves screw rod (17), the adjusting screw rod (17) and the first connecting rod (15) cooperate.
5. the operation work platform according to claim 4 suitable for steep slope topography, which is characterized in that the adjusting screw rod
(17) one end is equipped with nut, and the outer surface of the nut is evenly equipped with several knurlings.
6. the operation work platform according to claim 3 suitable for steep slope topography, which is characterized in that the spud pile (11)
Be connected between the carrying platform (12) reinforcing rod (18), the reinforcing rod (18), second connecting rod (16) with it is described
Spud pile (11) surround and forms triangle.
7. the operation work platform according to claim 6 suitable for steep slope topography, which is characterized in that two groups of reinforcing rods (18)
Between be connected with several support rods disposed in parallel (19), the angle between the reinforcing rod (18) and the spud pile (11) is
45°~60°。
8. the operation work platform according to claim 1 suitable for steep slope topography, which is characterized in that on the pedal (2)
Equipped with the card slot (21) cooperated with the carrying platform (12).
9. the operation work platform according to claim 1 suitable for steep slope topography, which is characterized in that the pedal (2) is
Thickness is the plank of 2cm ~ 5cm.
10. the operation work platform according to any one of claims 1 to 9 suitable for steep slope topography, which is characterized in that described
Fixed bracket (1) is welded by coating steel pipe, and the diameter of the coating steel pipe is 30mm ~ 50mm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721795099.4U CN208456071U (en) | 2017-12-20 | 2017-12-20 | A kind of operation work platform suitable for steep slope topography |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721795099.4U CN208456071U (en) | 2017-12-20 | 2017-12-20 | A kind of operation work platform suitable for steep slope topography |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208456071U true CN208456071U (en) | 2019-02-01 |
Family
ID=65140999
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721795099.4U Active CN208456071U (en) | 2017-12-20 | 2017-12-20 | A kind of operation work platform suitable for steep slope topography |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208456071U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111335605A (en) * | 2020-03-19 | 2020-06-26 | 重庆科技学院 | Integral adjustable scaffold for slope construction |
CN112605580A (en) * | 2020-10-30 | 2021-04-06 | 沪东中华造船(集团)有限公司 | Corrugated plate welding auxiliary device for lower inclined plane of liquid cargo tank |
-
2017
- 2017-12-20 CN CN201721795099.4U patent/CN208456071U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111335605A (en) * | 2020-03-19 | 2020-06-26 | 重庆科技学院 | Integral adjustable scaffold for slope construction |
CN112605580A (en) * | 2020-10-30 | 2021-04-06 | 沪东中华造船(集团)有限公司 | Corrugated plate welding auxiliary device for lower inclined plane of liquid cargo tank |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208456071U (en) | A kind of operation work platform suitable for steep slope topography | |
CN105952239B (en) | The anti-bending unstability bracing means of steel tower corner iron | |
CN209114332U (en) | A kind of long big section bent cap bracket system of overhanging | |
CN205688924U (en) | Steel tower corner iron anti-bending unstability bracing means | |
CN206319631U (en) | A kind of shear wall vertical adjustment mechanism | |
CN102926554A (en) | Steel hanging seat formwork support and construction method thereof | |
CN102444082A (en) | Light shelf protection structure for over crossing electrified railway bridge | |
CN203006792U (en) | Single-attachment-point tower crane wall attaching device | |
CN104787687A (en) | Tower crane attachment device for complex building | |
CN202023298U (en) | Roof truss-sectioned roof girder structure capable of being hoisted by cross type tower crane | |
CN203022409U (en) | Iron tower support assembly | |
CN104591006A (en) | Single-edge extended truss mechanism of tower crane and construction method thereof | |
CN107100271A (en) | A kind of method that utilization adjustable drawbar adjusts steel member camber | |
CN206376397U (en) | A kind of across lightweight steel construction wall of metal crane span structure | |
CN208662206U (en) | A kind of steel beam web plate straightening adjustment paving helps device | |
CN206051226U (en) | A kind of wall-attaching equipment of construction elevator | |
CN110593299A (en) | Leveling device for embedded part of transformer | |
CN205369292U (en) | Control framing formula bridge steel structure tower crane basis | |
CN201546366U (en) | Steel girder | |
CN204826220U (en) | Location built -in fitting with U type groove | |
CN206279539U (en) | Assembled equalizer bar foundation pit support system | |
CN205907703U (en) | Electric power tower pole base apparatus | |
CN206512885U (en) | A kind of across lightweight steel construction wall of electric pipeline | |
CN219931654U (en) | Cantilever unloading platform construction device | |
CN204023603U (en) | A kind of shearing resistance screw communication base station basis |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder |
Address after: No. 40, Dongfeng West Road, Liwan District, Guangzhou, Guangdong 510160 Patentee after: Guangdong Power Grid Energy Development Co.,Ltd. Address before: No. 40, Dongfeng West Road, Liwan District, Guangzhou, Guangdong 510160 Patentee before: GUANGDONG POWER TRANSMISSION AND TRANSFORMATION ENGINEERING Co.,Ltd. |
|
CP01 | Change in the name or title of a patent holder |