CN208455859U - A kind of prefabricated thermal insulation combined wall board - Google Patents

A kind of prefabricated thermal insulation combined wall board Download PDF

Info

Publication number
CN208455859U
CN208455859U CN201820561090.5U CN201820561090U CN208455859U CN 208455859 U CN208455859 U CN 208455859U CN 201820561090 U CN201820561090 U CN 201820561090U CN 208455859 U CN208455859 U CN 208455859U
Authority
CN
China
Prior art keywords
wall board
combined wall
thermal insulation
described sleeve
sleeve pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820561090.5U
Other languages
Chinese (zh)
Inventor
权浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Foshan Construction And Construction Technology Co Ltd
Original Assignee
Foshan Construction And Construction Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Foshan Construction And Construction Technology Co Ltd filed Critical Foshan Construction And Construction Technology Co Ltd
Priority to CN201820561090.5U priority Critical patent/CN208455859U/en
Application granted granted Critical
Publication of CN208455859U publication Critical patent/CN208455859U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/24Structural elements or technologies for improving thermal insulation
    • Y02A30/244Structural elements or technologies for improving thermal insulation using natural or recycled building materials, e.g. straw, wool, clay or used tires

Landscapes

  • Building Environments (AREA)

Abstract

The utility model discloses a kind of prefabricated thermal insulation combined wall boards, it is related to wallboard manufacturing technology field, including reinforced mesh, several are arranged in the sleeve of wallboard lower part, several casings being arranged side by side along the combined wall board length direction and are cast in the concrete of the sleeve, the reinforced mesh and described sleeve pipe periphery;The sleeve and the setting of described sleeve pipe interval, described sleeve pipe is interior to fill thermal insulation material;The reinforced mesh is parallel to the length direction of the combined wall board.The utility model not only light thermal-insulation, can modular construction, but also included waterproofing design can effective waterproof.

Description

A kind of prefabricated thermal insulation combined wall board
Technical field
The utility model relates to wallboard manufacturing technology field more particularly to a kind of prefabricated thermal insulation combined wall boards.
Background technique
The production of building industrialization in recent years is had become with its cheap cost, outstanding performance, energy-saving and environment-friendly construction concept For the development trend of building trade.Total-prefabricated construction is built especially with precast concrete wall panel, it has also become China is to building Build one of the approach of industrialization development.
Currently, since precast concrete wall panel standardization level is low, traditional precast concrete load-bearing wall panel is from great, heat preservation Performance is poor, at high cost, and secondary construction is time-consuming and laborious.
Utility model content
The utility model provides a kind of prefabricated thermal insulation combined wall board in view of the deficiencies of the prior art, not only light thermal-insulation, energy Enough modular constructions, but also included waterproofing design, can effective waterproof.
The utility model provides a kind of prefabricated thermal insulation combined wall board, including reinforced mesh, several settings are under wallboard The sleeve in portion, several along the combined wall board length direction be arranged side by side casing and be cast in the sleeve, the reinforcing bar The concrete of mesh sheet and described sleeve pipe periphery;The sleeve and the setting of described sleeve pipe interval, described sleeve pipe is interior to fill thermal insulation material; The reinforced mesh is parallel to the length direction of the combined wall board.
Further, described sleeve pipe is set as parallel two rows, and the reinforced mesh is arranged between two rows of described sleeve pipes.
Further, described sleeve pipe is the string configuration of hollow form.
Further, the thermal insulation material includes following one: rock wool, EPS, XPS, insulating rubber plastic, mineral wool, foam Concrete.
Further, the wherein one side of the narrow side of the combined wall board width direction is equipped with the first groove, another side Equipped with protrusion, first groove and the protrusion are arranged and are mutually matched along the short transverse of the combined wall board.
Further, the length of first groove and the protrusion is equal with the height of the combined wall board.
Further, the bottom surface of the combined wall board is provided along its length the second groove.
Further, the equal length of the length of second groove and the combined wall board.
Compared with prior art, the utility model also has the advantages that
1. the utility model by the way that light heat insulation material is arranged in wallboard, not only makes the weight saving of wallboard 25%, Facilitate lifting, but also its thermal insulation property is made to improve 40%.
2. casing and set that the utility model designs reasonable reinforced mesh, proportional spacing arrangement by being arranged in wallboard Cylinder, makes wallboard have certain load-bearing capacity, and anti-seismic performance is good, can be used as load bearing wall use.
3. the utility model is by not only increasing the reliable of connection at left and right sides of wallboard and anti-bank is arranged in bottom surface Property, moreover it is possible to the generation of traditional prefabricated panel leakage problems is effectively reduced.
4. the utility model production method is simple, construction and installation are convenient, the production time is not only saved, moreover it is possible to greatly reduce The workload of secondary construction reduces the production cost of enterprise.
Detailed description of the invention
Fig. 1 is a kind of overlooking structure diagram of prefabricated thermal insulation combined wall board provided by the utility model.
Fig. 2 is side structure and its bottom amplification signal of a kind of prefabricated thermal insulation combined wall board provided by the utility model Figure.
1-sleeve;2-reinforced mesh;3-casings;4-concrete;5-the first groove;6-protrusions;7-the second is recessed Slot.
Specific embodiment
The utility model is further described With reference to embodiment.Wherein, being given for example only property of attached drawing Illustrate, expression is only schematic diagram, rather than pictorial diagram, should not be understood as the limitation to this patent;In order to which this reality is better described With novel embodiment, the certain components of attached drawing have omission, zoom in or out, and do not represent the size of actual product;To ability For field technique personnel, the omitting of some known structures and their instructions in the attached drawings are understandable.
The same or similar label correspond to the same or similar components in the attached drawing of the utility model embodiment;It is practical at this In novel description, it is to be understood that if the orientation or positional relationship for having the instructions such as term " on ", "lower", "left", "right" is It is based on the orientation or positional relationship shown in the drawings, is merely for convenience of describing the present invention and simplifying the description, rather than indicate Or imply that signified device or component must have a particular orientation, be constructed and operated in a specific orientation, therefore retouch in attached drawing The term for stating positional relationship only for illustration, should not be understood as the limitation to this patent, for the common skill of this field For art personnel, the concrete meaning of above-mentioned term can be understood as the case may be.
As shown in Figs. 1-2, a kind of prefabricated thermal insulation combined wall board, including reinforced mesh 2, several wallboard lower part is set Sleeve 1, several casings 3 and the concrete 4 for being cast in 3 periphery of the sleeve 1, the reinforced mesh 2 and described sleeve pipe;It is several A sleeve 1 is divided into equidistant several columns, and each column sleeve 1 is parallel to the width direction of the combined wall board. Described sleeve pipe (3) is the string configuration of hollow form, is filled with thermal insulation material in described sleeve pipe 3, several described sleeve pipes 3 are along institute State combined wall board length direction be arranged side by side, and with 1 arranged for interval of sleeve.The height of described sleeve pipe 3 is lower than described compound The height of wallboard, the upper and lower ends of described sleeve pipe 3 are arranged in the concrete 4, avoid to be exposed to outside the concrete 4 Face.The thermal insulation material of the both ends end of described sleeve pipe 3 can directly be contacted with the concrete 4, can not also with it is described Concrete 4 directly contacts, and when not contacting with the concrete 4, end cap can be arranged at the both ends of described sleeve pipe 3, i.e., described End cap is arranged in thermal insulation material and the direct contact position of the concrete 4.Several described sleeve pipes 3 are arranged in the reinforced mesh 2 The same side and the length direction for being parallel to the combined wall board.Between respectively arranging the sleeve 1 and several described sleeve pipes 3 as desired It is arranged every any distance, the utility model is preferably by the 2-3 one column sleeve 1 of the setting of described sleeve pipe 3.The sleeve 1 is set It is set to hollow string configuration, wherein one end is equipped with female connection structure, and is arranged in the combined wall board Reinforcing rod is threadedly coupled.Specifically, one end of the reinforcing rod is threadedly coupled with the sleeve 1, other end protrusion is described compound Top end surface a distance of wallboard.The other end face of the sleeve 1 is concordant with the bottom end face of the combined wall board.It is described Different sizes can be arranged in combined wall board according to the demand of client, and the size includes length dimension, width dimensions and height gauge It is very little.Under normal circumstances, the height of the combined wall board be equal to floor height, top protrude the reinforcing rod and flooring and The combined wall board on upper layer is fixed together by way of poured in place concrete 4.The reinforced mesh 2 mainly by The reinforcing bar of several vertical and horizontal arrangement is fixed together by way of welding or bundling, and forms the latticed knot of rectangle Structure.2 size of reinforced mesh and the size of the combined wall board are adapted, and are completely covered on the reinforced mesh 2 described In concrete 4.
In an embodiment of the utility model, described sleeve pipe 3 is set as parallel two rows, and two rows of described sleeve pipes 3 one are a pair of It should be arranged, the reinforced mesh 2 is arranged between two rows of described sleeve pipes 3.Described sleeve pipe 3 uses metal material or plastic material system At stainless steel can be selected in metal material or PVC or PPR can be selected in aluminium alloy, plastic material.The cross section shape of described sleeve pipe 3 Shape includes following one: rectangle, circle, the shape of ellipse or other closures.In the present embodiment, it is preferred to use plastic material It is made, cross section is rectangle.Specifically, the size of described sleeve pipe 3 can be according to the size and setting of the combined wall board The quantity of described sleeve pipe 3 in the combined wall board is correspondingly arranged.For example, the combined wall board be sized to length × Width × height=2000mm × 250mm × 2900mm, it is contemplated that the whole load-bearing capacity and heat insulating ability of the combined wall board Can, for the cross sectional dimensions of described sleeve pipe 3 no more than length x width=180mm × 80mm, the height dimension of described sleeve pipe 3 is few In the height of the combined wall board, preferably less 100mm, to guarantee that it is described mixed that the upper and lower ends of described sleeve pipe 3 are not exposed to Solidifying 4 outside of soil.Thermal insulation material is filled in described sleeve pipe 3, the thermal insulation material can be the light thermal-insulation material of heat-insulating sound-insulating fire resisting Material, including following one: rock wool, EPS (polystyrene foam), XPS (extruded polystyrene foam board), insulating rubber plastic, Mineral wool, foam concrete and its derivative some light heat insulation materials etc., the present embodiment is preferably rock wool.In other embodiments In, described sleeve pipe 3 can also be several rows setting parallel in wallboard.The size of two rows of described sleeve pipes 3 can be kept It unanimously, can also be inconsistent.If the size of two rows of described sleeve pipes 3 is consistent, two rows of described sleeve pipes 3 are equally spacedly arranged In a row and correspond;If 3 size of two rows of described sleeve pipes is different, preferably, two rows of described sleeve pipes 3 include big tubing and ruler The very little small tubing more smaller than the big tubing, in the case where guaranteeing that the combined wall board integral thickness is constant, using described big Tubing and the small tubing alternatively mixing close setting, can further decrease the weight of described combined wall board itself, also make its heat preservation effect More preferably, cost is lower for fruit.
In one the present embodiment of the utility model, the sleeve 1 is set as 24, is divided into six column, and each column is respectively provided with There are four the sleeves 1.In order to make combined wall board that there is better structural strength, in the left and right of the combined wall board length direction Two sides are respectively arranged with the sleeve 1 of biserial, be spaced a predetermined distance in the middle part of the combined wall board setting it is single-row described in Sleeve 1 increases the integral strength of the combined wall board by the reinforcing bar connecting respectively with the sleeve 1.
In order to realize the modularization assembling of the combined wall board, the narrow side of the combined wall board width direction wherein One side is equipped with the first groove 5, and another side is equipped with protrusion 6, and first groove 5 and described raised 6 is along the composite wall The short transverse of plate is arranged and is mutually matched.Preferably, the cross section of first groove 5 is set as rectangle, accordingly, institute It states protrusion 6 and is set as rectangle with 5 dimensional fits of the first groove.First groove 5 and described raised 6 cross section shape Shape can also be the mutually matched shape of trapezoidal or other energy.When installing combined wall board, described the first of the combined wall board The protrusion 6 of groove 5 and an adjacent combined wall board is clamped.First groove 5 and the combined wall board are integrated into Type, first groove 5 are arranged in the wherein side side of the combined wall board along the short transverse of the combined wall board Middle position, length are equal with the height of the combined wall board.Accordingly, described raised 6 and the combined wall board be integrated Molding, the middle position of the other side side of the combined wall board is arranged in along the short transverse of the combined wall board, is grown It spends equal with the height of the combined wall board.Connection in the short transverse of the combined wall board passes through 5 He of the first groove Raised 6 clamping is realized, the reliability of adjacent two pieces of combined wall board connection is not only substantially increased, recessed by described first The anti-bank setting of slot 5 and described raised 6 can also improve the leakage resistance energy of its junction.
The bottom surface middle position of the combined wall board is equipped with the second groove 7, and second groove 7 is along the combined wall board Length direction arrangement, the equal length of length and the combined wall board.In combined wall board installation, second groove 7 It is clamped, can quickly be positioned with the interconnecting piece of protrusion pre-set on ground or flooring, can be also effectively reduced traditional pre- The leakage problems of wallboard processed.The interconnecting piece first passes through the mode shape of casting concrete in advance before installing the combined wall board At the shape and size of the interconnecting piece are matched with second groove 7.Preferably, the cross section setting of second groove 7 For rectangle, accordingly, the interconnecting piece is set as the rectangle with 7 dimensional fits of the second groove.Second groove 7 and institute The cross-sectional shape for stating interconnecting piece can also be the mutually matched shape of trapezoidal or other energy.
Several are arranged in the installation of the combined wall board, the generally suitable position at the combined wall board edge for convenience It lifts embedded part (being not drawn into figure).The lifting embedded part includes that hanging ring, screw built-in fitting, round end hang nail etc., when pre-buried Can make appropriate choice on demand with it is pre-buried.
The invention also discloses a kind of preparation methods of prefabricated thermal insulation combined wall board, include the following steps:
1. punching block platform is cleaned, formwork, and several the first pads are spaced apart on the bottom surface that mold encloses the inside got up Block.
2. pre-fabricated reinforced mesh 2 is put into mold and is placed horizontally on first cushion block, and in institute It states reinforced mesh 2 and several the second cushion blocks is placed above.The steel that the reinforced mesh 2 is mainly arranged by several vertical and horizontal Muscle is fixed together by way of welding or bundling, and forms the fenestral fabric of rectangle.
3. several casings 3 for being filled with thermal insulation material are placed horizontally on second cushion block, described in several It is parallel to each other between casing 3 and parallel with the short transverse of combined wall board.
4. several pre-buried sleeves 1 and several lifting embedded parts, several described sleeves 1 are arranged with the interval of described sleeve pipe 3. Wherein, the sleeve 1 of each column is that several described sleeves 1 are divided into several layers, between the sleeve 1 of neighbouring two layers It is separated by the 4th cushion block;When pre-buried, one end abuts the sleeve 1 with mold side, the other end and reinforcing rod screw thread Connection.Pass through respectively between the sleeve 1, between the sleeve 1 and punching block platform and between the sleeve 1 and reinforced mesh 2 4th cushion block interval.The sleeve 1, which can be, distinguishes phase for the sleeve 1 being spaced apart from each other by the 4th cushion block by way of plant It should plant between punching block platform and reinforced mesh 2 and on reinforced mesh 2;Or with regard to first placement section before placing reinforced mesh 2 Divide the sleeve 1 being spaced apart from each other by the 4th cushion block, then reinforced mesh 2 is placed on it, and continuation is right on the reinforced mesh 2 The remaining sleeve 1 being spaced apart from each other by the 4th cushion block should be placed, the sleeve 2 of multiple row and respectively column and described sleeve pipe 3 are formed Interval setting.It is threadedly coupled between wherein one end of the reinforcing rod and the sleeve 1, it is pre- that the other end protrudes described mold one end If distance.In order to facilitate the lifting of combined wall board, need to place several liftings in the suitable position in combined wall board edge Embedded part.The lifting embedded part includes but is not limited to that hanging ring, screw built-in fitting, round end hang nail etc., can be on demand when pre-buried Make appropriate choice with it is pre-buried.
5. the sleeve 1, the reinforced mesh 2 and 3 periphery casting concrete 4 of described sleeve pipe and carry out receive surface treatment and Post-processing guarantees that 4 any surface finish of concrete is smooth.Specifically, sufficient, uniform vibration is not only carried out in casting process It smashes, also often to observe lifting embedded part, casing 3 and sleeve 1 etc. whether there is or not movement, deformation or stopping state, finding the problem should immediately Stop pouring, and the concrete 4 that pours of Ying Yi condense before amendment it is intact.The receipts surface treatment refers mainly to be smeared with plasterer's trowel or wood Son is pressed repeatedly on 4 surface of concrete and is smeared, until reaching the requirement of any surface finish needed for engineering.The post-processing refers mainly at moisturizing Reason, i.e. interval predetermined time toward moisturizing of watering on the combined wall board, prevent 4 face checking of concrete.
6. demoulding can carry out demoulding when the concrete 4 condenses to a certain extent to get the combined wall board is arrived.
As an embodiment of the present invention, step a is executed before step is 2.: several are filled with thermal insulation material Casing 3 is placed horizontally on first cushion block, and places several for supporting the steel mesh on described sleeve pipe 3 It is separated between the third cushion block of piece 2, i.e. described sleeve pipe 3 and the reinforced mesh 2 by the third cushion block.The present embodiment is logical It crosses the two sides up and down in the reinforced mesh 2 and is equipped with several described sleeve pipes 3, then primary concreting concrete 4, Ji Neng Mitigate the weight of the combined wall board under the premise of the requirement for meeting the combined wall board thickness as far as possible, and can be existed by setting Thermal insulation material in described sleeve pipe 3 realizes double-layer heat insulation function, substantially increases the heat preserving heat insulating noise insulation of the combined wall board Energy.Resulting combined wall board is prepared using the manufacturing method of the utility model, heat insulation effect is good, and inner and outer surfaces are bright and clean smooth, Later period can handle without finishing and directly use.
The utility model not only makes the weight saving of wallboard 25% by the way that light heat insulation material is arranged in wallboard, side Just it lifts, but also its thermal insulation property is made to improve 40%.The utility model designs reasonable reinforcing bar by being arranged in wallboard The casing and sleeve of mesh sheet, proportional spacing arrangement, make wallboard have certain load-bearing capacity, anti-seismic performance is good, can be used as load bearing wall It uses.The utility model is by not only increasing the reliability of connection at left and right sides of wallboard and anti-bank is arranged in bottom surface, moreover it is possible to The generation of traditional prefabricated panel leakage problems is effectively reduced.The utility model production method is simple, construction and installation are convenient, not only saves The production time is saved, moreover it is possible to which the workload for greatly reducing secondary construction reduces the production cost of enterprise.
Above embodiments are only to illustrate the technical solution of the utility model, rather than its limitations;Although referring to aforementioned reality Example is applied the utility model is described in detail, those skilled in the art should understand that: it still can be to preceding Technical solution documented by each embodiment is stated to modify or equivalent replacement of some of the technical features;And these It modifies or replaces, the protection model for various embodiments of the utility model technical solution that it does not separate the essence of the corresponding technical solution It encloses.

Claims (8)

1. a kind of prefabricated thermal insulation combined wall board, it is characterised in that: including reinforced mesh (2), several settings under combined wall board The sleeve (1) in portion, several along the combined wall board length direction be arranged side by side casing (3) and be cast in the sleeve (1), The concrete (4) of the reinforced mesh (2) and described sleeve pipe (3) periphery;The sleeve (1) and the setting of described sleeve pipe (3) interval, Thermal insulation material is filled in described sleeve pipe (3);The reinforced mesh (2) is parallel to the length direction of the combined wall board.
2. a kind of prefabricated thermal insulation combined wall board according to claim 1, it is characterised in that: described sleeve pipe (3) is set as simultaneously Capable two rows, the reinforced mesh (2) are arranged between two rows of described sleeve pipes (3).
3. a kind of prefabricated thermal insulation combined wall board according to claim 2, it is characterised in that: described sleeve pipe (3) is hollow form String configuration.
4. a kind of prefabricated thermal insulation combined wall board according to claim 1, it is characterised in that: the thermal insulation material includes following One of rock wool, EPS, XPS, insulating rubber plastic, mineral wool, foam concrete.
5. a kind of prefabricated thermal insulation combined wall board according to claim 1, it is characterised in that: the combined wall board width direction The wherein one side of narrow side be equipped with the first groove (5), another side is equipped with raised (6), first groove (5) and described Raised (6) are arranged and are mutually matched along the short transverse of the combined wall board.
6. a kind of prefabricated thermal insulation combined wall board according to claim 5, it is characterised in that: first groove (5) and institute The length for stating raised (6) is equal with the height of the combined wall board.
7. a kind of prefabricated thermal insulation combined wall board according to claim 1, it is characterised in that: the bottom surface edge of the combined wall board Its length direction is equipped with the second groove (7).
8. a kind of prefabricated thermal insulation combined wall board according to claim 7, it is characterised in that: the length of second groove (7) The equal length of degree and the combined wall board.
CN201820561090.5U 2018-04-18 2018-04-18 A kind of prefabricated thermal insulation combined wall board Active CN208455859U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820561090.5U CN208455859U (en) 2018-04-18 2018-04-18 A kind of prefabricated thermal insulation combined wall board

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820561090.5U CN208455859U (en) 2018-04-18 2018-04-18 A kind of prefabricated thermal insulation combined wall board

Publications (1)

Publication Number Publication Date
CN208455859U true CN208455859U (en) 2019-02-01

Family

ID=65157071

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820561090.5U Active CN208455859U (en) 2018-04-18 2018-04-18 A kind of prefabricated thermal insulation combined wall board

Country Status (1)

Country Link
CN (1) CN208455859U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108385861A (en) * 2018-04-18 2018-08-10 佛山建装建筑科技有限公司 A kind of prefabricated thermal insulation combined wall board and its manufacturing method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108385861A (en) * 2018-04-18 2018-08-10 佛山建装建筑科技有限公司 A kind of prefabricated thermal insulation combined wall board and its manufacturing method

Similar Documents

Publication Publication Date Title
WO2019007224A1 (en) Thermal-insulation external wall board, special mold and manufacturing method therefor
CN107740531A (en) Assembled wallboard and its attachment structure
CN206693432U (en) Fabricated shear wall and fabric structure
CN104695662B (en) Stone facing prefabricated outer wall panel and its production method and external wall system
CN209817249U (en) A compound wallboard of prefabricated foam concrete for building infilled wall
CN107989238A (en) A kind of cast-in-place sandwiched heat-preservation shear wall structure, assembled architecture and engineering method
CN205369689U (en) Keep warm and decorate assembled precast floor plank of integration
CN106894541A (en) A kind of combinable prefabricated regeneration concrete sandwiched thermal-insulating wall
CN103352537A (en) Integral load-bearing heat-insulating wall plate and production and construction technology thereof
CN208455859U (en) A kind of prefabricated thermal insulation combined wall board
CN204781575U (en) Structure keeps warm and decorates outer wall hanging plate of large -scale prefabrication of integration
CN107700697B (en) A kind of exterior wall prefabricated construction
CN108396905A (en) A kind of insulated compound trabs and its manufacturing method of prefabricated band ceramic tile layer
CN206289832U (en) A kind of hollow light precast body
CN208455933U (en) A kind of insulated compound trabs of prefabricated band ceramic tile layer
CN206957042U (en) Light composite heat insulation outer wall plate and particular manufacturing craft
CN208907279U (en) Outer wall self heat-preserving assembled wallboard
CN106351373A (en) Lattice type prefabricated heat insulation and sound insulation floor
CN206707052U (en) A kind of combinable prefabricated regeneration concrete sandwiched thermal-insulating wall
CN206110422U (en) Prefabricated sound insulation floor that keeps warm of lattice formula
CN115977278A (en) Assembled light steel combined truss supported steel wire mesh frame mortar-perlite-polyphenyl composite shear wall and manufacturing method thereof
CN214062112U (en) Insulation construction integration board in passive form house
CN108385861A (en) A kind of prefabricated thermal insulation combined wall board and its manufacturing method
CN208455931U (en) A kind of heat preservation assembled wallboard with decorative layer
CN207597652U (en) A kind of cast-in-place sandwiched heat-preservation shear wall structure and assembled architecture

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant