CN208439250U - A kind of three layer of three vertical group hole underground station - Google Patents

A kind of three layer of three vertical group hole underground station Download PDF

Info

Publication number
CN208439250U
CN208439250U CN201820898835.7U CN201820898835U CN208439250U CN 208439250 U CN208439250 U CN 208439250U CN 201820898835 U CN201820898835 U CN 201820898835U CN 208439250 U CN208439250 U CN 208439250U
Authority
CN
China
Prior art keywords
station
layer
outbound
channel
staircase
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820898835.7U
Other languages
Chinese (zh)
Inventor
吕刚
曹永刚
赵勇
俞祖法
韩志伟
蔡珏
蒋伟平
陈红念
乔俊飞
李汶京
岳岭
赵琳
刘建友
陈学峰
马福东
王瑾
何佳
徐治中
于晨昀
张斌
刘方
张宇宁
王婷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Engineering Consulting Group Co Ltd
Original Assignee
China Railway Engineering Consulting Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Engineering Consulting Group Co Ltd filed Critical China Railway Engineering Consulting Group Co Ltd
Priority to CN201820898835.7U priority Critical patent/CN208439250U/en
Application granted granted Critical
Publication of CN208439250U publication Critical patent/CN208439250U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

The utility model discloses a kind of three layer three vertical group hole underground stations comprising is built in that the outbound layer of subsurface, enter the station layer and station layer, and the outbound layer, enters the station layer and station layer is set gradually from top to bottom;The ground floor of the outbound layer connection ground station;The subterranean layer of the layer connection ground station that enter the station;And the station layer include at least one for train operation tunnel.The underground railway station of the utility model is the group hole structure of a kind of " three layer three vertical ", thus can reduce cavern span, reduce difficulty of construction, be conducive to construction safety;Meanwhile group hole layout also helps operation security, improves operation, the efficiency of management.

Description

A kind of three layer of three vertical group hole underground station
Technical field
The utility model relates to geotechnical engineering fields, more particularly to a kind of three layer of three vertical group hole underground station.
Background technique
Currently, the most underground railway station in China mainly uses cut and cover tunneling, but due to underground environment complexity, especially In areas such as the mountain ridges, difficulty of construction is big, and be easy influence subsurface geology environment, cause security risk, therefore, how into It is carried out when row underground railway station is built effectively and the station of safety layout is problem of crucial importance, but at present in underground train In the construction stood, there is no both can guarantee construction safety, reduce difficulty of construction, and can guarantee route high efficiency operation, be convenient for line pipe The placement scheme of reason.
Utility model content
The utility model in view of the above drawbacks of the prior art, provides a kind of underground station, is a kind of " three layer three vertical " Group hole structure, thus can reduce cavern span, reduce difficulty of construction, be conducive to construction safety;Meanwhile group hole layout is also Conducive to operation security, operation, the efficiency of management are improved.
The technical scheme adopted by the utility model to solve the technical problem is as follows:
A kind of three layer of three vertical group hole underground station is provided comprising be built in the outbound layer of subsurface, enter the station layer and Station layer, and the outbound layer, enter the station layer and station layer is set gradually from top to bottom;
The ground floor of the outbound layer connection ground station;The subterranean layer of the layer connection ground station that enter the station;And institute State station layer include at least one for train operation tunnel.
Preferably, the outbound layer includes: outbound staircase;Outbound channel, describedly by the outbound staircase connection The ground floor of face station;Outbound channel staircase connects the outbound channel and station layer, for for personnel from station layer into Enter outbound channel;Side/the two sides in the outbound channel are arranged in battery limits, for placing railway station operating relevant device; And first emergency staircase, be provided with the first escape stair, and first escape stair one end connection it is described go out It stands channel, the other end is connected to the ground floor of the ground station.
Preferably, be arranged in the ipsilateral outbound channel staircase in the outbound channel at least there are two, and the equipment position Between ipsilateral, the adjacent two outbound channel staircase.
Preferably, the outbound layer further include: outbound stair, the outbound channel pass through described in the outbound stair connection The ground floor of ground station;And/or outbound access staircase, connect the outbound channel and station layer, for for personnel from Station layer enters outbound channel.
Preferably, the layer that enters the station includes: the staircase that enters the station;It enters the station channel, enters the station staircase connection describedly by described The subterranean layer of face station;Enter the station channel staircase, enters the station channel and station layer described in connection, for for personnel from channel of entering the station Into station layer;And second emergency staircase, it is provided with the second escape stair, and one end of second escape stair It enters the station described in connection channel, the other end is connected to the ground floor of the outbound layer and/or ground station.
Preferably, be arranged in the channel of entering the station it is ipsilateral enter the station channel staircase at least there are two.
Preferably, the layer that enters the station further include: enter the station stair, and the channel of entering the station is entered the station described in stair connection by described The subterranean layer of ground station;And/or the access staircase that enters the station, enter the station channel and station layer described in connection, for for personnel from Channel of entering the station enters station layer.
Preferably, the tunnel for train operation includes: left to hair line tunnel, the right side to hair line tunnel and to be set to two Intermediate main track tunnel between person;The left side is used to train stop to hair line tunnel, the right side to hair line tunnel and passenger gets on or off the bus; The intermediate main track tunnel passes through for the not parking train driving that misses the stop.
Preferably, the intermediate main track tunnel has several.
The beneficial effect of technical solutions of the utility model is:
The underground station of the utility model thus reduces cavern span using the group hole topology layout of " three layer three is vertical ", Difficulty of construction is reduced, construction safety is conducive to;Meanwhile group hole layout provides partition management item for Fire prevention and evacuation Part, middle folder rock mass can effectively obstruct fire or fire and smoke spread, be conducive to operation security, and reduce excavated volume, can make full use of Rock mass supporting role reduces supporting intensity, reduces project cost;In addition, group hole layout can be to avoid the passenger flow of different directions It interferes with each other, is conducive to the flowing of passenger flow effective, improves efficiency of operation.
Detailed description of the invention
Below in conjunction with accompanying drawings and embodiments, the utility model is described in further detail, in attached drawing:
Fig. 1 is the profilograph of underground station in the utility model embodiment one;
Fig. 2 is the drawing in side sectional elevation of underground station in the utility model embodiment one;
Fig. 3 is the floor plan of outbound layer in the utility model embodiment one;
Fig. 4 is the floor plan of layer of entering the station in the utility model embodiment one.
Specific embodiment
In order to which the purpose of this utility model, technical solution and advantage is more clearly understood, below in conjunction with attached drawing and reality Example is applied, the present invention will be further described in detail.It should be understood that specific embodiment described herein is only used for It explains the utility model, is not used to limit the utility model.
Embodiment one:
As shown in Figs. 1-2, the underground station of the utility model includes being built in subsurface (the preferably ground of mountain terrain Under) outbound layer 1, enter the station layer 2 and station layer 3, and the outbound layer 1, enter the station layer 2 and station layer 3 from top to bottom successively Setting;
The outbound layer 1 is connected to the ground floor 4 of ground station;The layer 2 that enters the station is connected to the subterranean layer 5 of ground station; And the station layer 3 include at least one for train operation tunnel, it is preferred that the length of the station layer 3 be 450-500m, Particularly preferably 470m;The tunnel for train operation includes: left to hair line tunnel 31, the right side to hair line tunnel 32 and setting In intermediate main track tunnel 33 between the two, and three is parallel to each other, is arranged independently of each other;Wherein, described left to hair line tunnel 31, the right side is used to train stop to hair line tunnel 32 and passenger gets on or off the bus;The intermediate main track tunnel 33 can have several, use In missing the stop, not parking train driving passes through, and thus can guarantee the high efficiency flow of the orderly operation and passenger flow between different routes, The passenger flow of different directions is avoided to interfere with each other;
As shown in figure 3, the outbound layer 1 includes: outbound staircase 13;Outbound channel 12 passes through the outbound staircase 13 It is connected to the ground floor 4 of the ground station;Outbound channel staircase 11 connects the outbound channel 12 and station layer 3, is used for Enter outbound channel 12 from station layer 3 for personnel;Battery limits 14 are arranged in the side/two sides in the outbound channel 12, are used for It places railway station and operates relevant device;And first emergency staircase 15, it is provided with the first escape stair, and described first One end of escape stair is connected to the outbound channel 12, the ground that the other end is connected to the ground station by evacuating entrance 16 Layer 4;
Preferably, be arranged in the ipsilateral outbound channel staircase 11 in the outbound channel 12 at least there are two, and the equipment Area 14 is between ipsilateral, the adjacent two outbound channel staircase 11;Thus maximum convenient for being carried out to the underground space Utilize, in addition, for alleviate passenger flow, avoid congestion, improve out line efficiency, the outbound layer 1 further include: outbound stair, it is described go out Channel 12 of standing is connected to the ground floor 4 of the ground station by the outbound stair;And/or outbound access staircase, connect institute Outbound channel 12 and station layer 3 are stated, for entering outbound channel from station layer for personnel;
As a result, under normal circumstances, passenger flow can pass through outbound 11/ stair of channel staircase of station layer 3-- -- outbound channel 12-- Outbound 11/ stair of staircase reach the ground floor 4 of ground station, leave railway station, under emergency, can enable the first escape stair Between 15 so that personnel can quickly through outbound the first emergency staircase of channel 12-- 15 reach ground station ground floor 4 carry out Evacuation reduces security risk.
Similar, as shown in figure 4, the layer 2 that enters the station includes: the staircase 21 that enters the station;It enters the station channel 22, is entered the station by described Staircase 21 is connected to the subterranean layer 5 of the ground station;Enter the station channel staircase 23, and enter the station channel 22 and station layer described in connection 3, for entering station layer 3 from channel 22 of entering the station for personnel;And second emergency staircase 24, it is provided with the second evacuation building Ladder, and channel 22 of entering the station described in one end connection of second escape stair, the other end are connected to the outbound layer 1 and/or ground The ground floor 4 of station;
Likewise, be arranged in the channel 22 of entering the station it is ipsilateral enter the station channel staircase at least there are two;It is described to enter the station layer also It include: the stair that enter the station, the channel 22 of entering the station is connected to the subterranean layer 5 of the ground station by the stair that enter the station;And/or Enter the station access staircase, and enter the station channel 22 and station layer 3 described in connection, for entering station layer 3 from channel of entering the station for personnel, Alleviate passenger flow with this;
As a result, under normal circumstances, passenger flow can be entered the station 21/ stair of staircase by the subterranean layer 5-- of ground station -- it enters the station logical The 22-- 23/ stair in-track platform layer 3 of channel staircase that enters the station in road is waited, and under emergency, can be enabled the second emergency staircase 24, be made The personnel of obtaining can evacuate quickly through the ground floor 4 that the second emergency staircase of channel 22-- 24 that enters the station reaches ground station, subtract Few security risk, or first reach outbound layer 1, then reach the ground floor 4 of ground station by outbound layer 1, it realizes and shunts, avoid Congestion.
In conclusion the underground railway station of the utility model is thus reduced using the group hole topology layout of " three layer three vertical " Cavern span, reduces difficulty of construction, is conducive to construction safety;Meanwhile group hole layout provides for Fire prevention and evacuation Partition management condition, middle folder rock mass can effectively obstruct fire or fire and smoke spread, be conducive to operation security, and reduce excavated volume, Rock mass supporting role can be made full use of to reduce supporting intensity, reduce project cost;In addition, group hole layout can be to avoid difference The passenger flow in direction interferes with each other, and is conducive to the flowing of passenger flow effective, improves efficiency of operation.
The above is only the preferred embodiment of the present invention, is not intended to limit the utility model, all practical at this Within novel spirit and principle, any modification, equivalent replacement, improvement and so on should be included in the guarantor of the utility model Within the scope of shield.

Claims (9)

1. a kind of three layer three vertical group hole underground station, which is characterized in that including be built in the outbound layer of subsurface, enter the station layer with And station layer, and the outbound layer, enter the station layer and station layer is set gradually from top to bottom;
The ground floor of the outbound layer connection ground station;The subterranean layer of the layer connection ground station that enter the station;And the platform Layer include at least one for train operation tunnel.
2. underground station as described in claim 1, which is characterized in that the outbound layer includes:
Outbound staircase;
Outbound channel is connected to the ground floor of the ground station by the outbound staircase;
Outbound channel staircase connects the outbound channel and station layer, for entering outbound channel from station layer for personnel;
Side/the two sides in the outbound channel are arranged in battery limits, for placing railway station operating relevant device;
And first emergency staircase, it is provided with the first escape stair, and one end of first escape stair is connected to institute Outbound channel is stated, the other end is connected to the ground floor of the ground station.
3. underground station as claimed in claim 2, which is characterized in that the ipsilateral outbound channel in the outbound channel is arranged in and helps Ladder at least there are two, and the battery limits are between ipsilateral, the adjacent two outbound channel staircase.
4. underground station as claimed in claim 2, which is characterized in that the outbound layer further include: outbound stair, it is described outbound Channel is connected to the ground floor of the ground station by the outbound stair;
And/or outbound access staircase, the outbound channel and station layer are connected, for entering from station layer for personnel It stands channel.
5. underground station as described in claim 1, which is characterized in that the layer that enters the station includes:
Enter the station staircase;
It enters the station channel, the subterranean layer of the ground station is connected to by the staircase that enters the station;
Enter the station channel staircase, and enter the station channel and station layer described in connection, for entering station layer from channel of entering the station for personnel;
And second emergency staircase, it is provided with the second escape stair, and one end of second escape stair is connected to institute Channel of entering the station is stated, the other end is connected to the ground floor of the outbound layer and/or ground station.
6. underground station as claimed in claim 5, which is characterized in that the ipsilateral channel of entering the station in the channel of entering the station is arranged in and helps Ladder at least there are two.
7. underground station as claimed in claim 5, which is characterized in that the layer that enters the station further include: enter the station stair, described to enter the station Channel is connected to the subterranean layer of the ground station by the stair that enter the station;
And/or the access staircase that enters the station, it enters the station channel and station layer described in connection, for entering for personnel from channel of entering the station Station layer.
8. underground station as described in claim 1, which is characterized in that the tunnel for train operation includes: left to hair line Tunnel right to hair line tunnel and is set to intermediate main track tunnel between the two;It is described left to hair line tunnel, the right side to hair line tunnel Road is used to train stop and passenger gets on or off the bus;The intermediate main track tunnel passes through for the not parking train driving that misses the stop.
9. underground station as claimed in claim 8, which is characterized in that the intermediate main track tunnel has several.
CN201820898835.7U 2018-06-11 2018-06-11 A kind of three layer of three vertical group hole underground station Active CN208439250U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820898835.7U CN208439250U (en) 2018-06-11 2018-06-11 A kind of three layer of three vertical group hole underground station

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820898835.7U CN208439250U (en) 2018-06-11 2018-06-11 A kind of three layer of three vertical group hole underground station

Publications (1)

Publication Number Publication Date
CN208439250U true CN208439250U (en) 2019-01-29

Family

ID=65089529

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820898835.7U Active CN208439250U (en) 2018-06-11 2018-06-11 A kind of three layer of three vertical group hole underground station

Country Status (1)

Country Link
CN (1) CN208439250U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109017816A (en) * 2018-06-11 2018-12-18 中铁工程设计咨询集团有限公司 A kind of three layer of three vertical group hole underground station

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109017816A (en) * 2018-06-11 2018-12-18 中铁工程设计咨询集团有限公司 A kind of three layer of three vertical group hole underground station

Similar Documents

Publication Publication Date Title
CN201460962U (en) Emergency evacuation and rescue system for two-lane railway round tunnel
CN201599052U (en) Emergency evacuation and rescue system of double-track railway circular tunnel with mid partition wall
CN203685276U (en) Emergent rescue station for double single-track railway tunnels
CN106014442B (en) A kind of vcehicular tunnel escape and rescue transverse passage-way method to set up
CN103670437A (en) Evacuation route arrangement structure for combined highway and metro shield tunnel
CN208439250U (en) A kind of three layer of three vertical group hole underground station
CN209430241U (en) One-tunnel two-tracks railway tunnel Rescue Station
CN109538284A (en) A kind of double hole single-track railway tunnels stop rescue system and rescue mode at random
CN104966373A (en) Fire prevention and control system
CN102330564B (en) Pipeline escape system in tunnel construction accident
CN109488367A (en) A kind of one-tunnel two-tracks railway tunnel is stopped rescue system and rescue mode at random
CN102251802A (en) Bottom independent evacuation safety passage structure for single-hole double-track magnetic levitation tunnel
CN102505595A (en) Vehicle escape structure of double-layered underground passage
CN109017816A (en) A kind of three layer of three vertical group hole underground station
CN210264723U (en) Single-hole double-layer mine method tunnel vehicle evacuation system
CN204532422U (en) A kind of escape way of tunnel structure
Xu et al. Feasibility analysis on natural ventilation scheme for large underground spaces based on the top cover design
CN201756966U (en) Three-hole double-line railway underwater tunnel
CN202510155U (en) Pipeline escape system in tunnel construction accident
CN207078146U (en) Air traffic transportation system
CN208792069U (en) A kind of underground railway station traffic system
CN205934625U (en) Tunnel type truck escape ramp
TW201609470A (en) Pipeline network for transport and pipeline transport system
CN203685201U (en) Double-track co-construction bridge and tunnel combined rescue station
CN209799978U (en) Double-deck shield tunnel upper and lower floor's driving liaison passageway

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant