CN208414469U - Repairing mould for blast furnace ironmaking hot air duct - Google Patents

Repairing mould for blast furnace ironmaking hot air duct Download PDF

Info

Publication number
CN208414469U
CN208414469U CN201820667165.8U CN201820667165U CN208414469U CN 208414469 U CN208414469 U CN 208414469U CN 201820667165 U CN201820667165 U CN 201820667165U CN 208414469 U CN208414469 U CN 208414469U
Authority
CN
China
Prior art keywords
air duct
mould
blast furnace
hot air
furnace ironmaking
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820667165.8U
Other languages
Chinese (zh)
Inventor
杨文光
贾秀龙
龚宪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Meishan Iron and Steel Co Ltd
Original Assignee
Shanghai Meishan Iron and Steel Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Meishan Iron and Steel Co Ltd filed Critical Shanghai Meishan Iron and Steel Co Ltd
Priority to CN201820667165.8U priority Critical patent/CN208414469U/en
Application granted granted Critical
Publication of CN208414469U publication Critical patent/CN208414469U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Furnace Housings, Linings, Walls, And Ceilings (AREA)

Abstract

The utility model relates to a kind of repairing moulds for blast furnace ironmaking hot air duct, belong to technical field of blast furnace ironmaking.The hot air duct is equipped with steel pipe walls, and the repairing mould includes the mould that hangs being put together by two panels curved plate, and two panels curved plate is crosslinked by hinge to be hinged;The mould that hangs is removable on the suspension centre to be connected with wirerope equipped with several suspension centres.The utility model can quickly repair the blast furnace high-temperature hot-air pipeline for the refractory material that falls off online, and blast furnace is avoided to stop production for a long time.

Description

Repairing mould for blast furnace ironmaking hot air duct
Technical field
The utility model relates to a kind of repairing moulds for blast furnace ironmaking hot air duct, belong to blast furnace technology neck Domain.
Background technique
It is exactly that iron ore, coke and portion is added from the top of blast furnace according to certain charging system for blast furnace ironmaking is popular Point flux, while the cold wind that air blower conveying comes is heated to 1230 DEG C or so in hot-blast stove, it is continuous by hot air duct It is constantly sent into inside blast furnace from blast-furnace tuyere position, and the iron ore, coke and the portion of flux that are added from top are in blast furnace Reduction reaction is carried out, the coal gas of generation enters gas recovery system from Top of BF, and high temperature liquid iron, the clinker of production are arranged from iron mouth Out.
The hot air duct of blast furnace is one of hot air duct, and air blower conveying comes to have the cold wind of certain pressure, in hot wind After being heated to 1230 DEG C or so under furnace hot environment, continuously it is sent into blast furnace by hot air duct from blast-furnace tuyere position Portion.
The hot air duct of blast furnace is made of internal refractory material and external steel shell, and internal refractory material has resistance to invade The function of erosion, heat preservation.Most the inside is the heavy pipeline brick that not only high temperature resistant but also resistance to hot wind wash away, is two layers of light-weight insulating brick above Layer, it has excellent incubation and thermal insulation function, under steel shell is aluminosilicate fiber cotton, has and is insulated and absorbs expansion function.Blast furnace The heat 30% or so of cupola well is brought by the hot wind that hot air duct conveys, and belongs to a part of technical field of blast furnace ironmaking.Once hot The refractory material of air piping part is fallen off, and one side refractory material falls off the hot air duct steel shell oxygen at high temperature at position Change, generation fatigue stress lose out compression strength, and the hot air duct steel shell that can cause the position when serious is burnt and hot air duct is disconnected Accident is split, blast furnace is caused to stop production for a long time;On the other hand the refractory material that falls off is by high-temperature hot-air band air intake vent, if fire proofed wood Material product it is larger, it will blocking portion air-supply air port so that the air port can not heat air delivery, influence conditions of blast furnace direct motion and Production.
Summary of the invention
The utility model will solve technical problem: provide a kind of blast furnace that can quickly repair the refractory material that falls off online High-temperature hot-air pipeline, the repairing mould for avoiding blast furnace from stopping production for a long time.
In order to solve the above-mentioned technical problem, the utility model proposes technical solution be: one kind is for blast furnace ironmaking hot wind The repairing mould of pipeline, the hot air duct are equipped with steel pipe walls;The repairing mould includes being put together by two panels curved plate Hang mould, two panels curved plate is crosslinked by hinge to be hinged;The mould that hangs is removable on the suspension centre equipped with several suspension centres Formula is connected with wirerope.
Preferably, described hang is set on mould there are four suspension centre.
When the utility model is used, according to internal refractories at hot air duct steel shell fall off place size make Mould accordingly is being hung, mould is being hung and should be slightly bigger than refractory material and fall off the area at place.After blast furnace staying, hot air duct internal refractories The steel shell at position of falling off is opened, and is winding is effectively cooled the position, the refractory brick of manual cleaning damage at this time uses special tool Tool takes out the remaining refractory material to fall off in hot air duct.Then pipe will be put into after mould closure (i.e. hinge crosslinking closure) will be hung Road domestic demand pouring position, stretching the wirerope on four suspension centres makes to hang mould opening (i.e. hinge crosslinking will open) and fix;Then will Reinforcement welding by reinforcing bar and hangs mould firm welding on hot air duct steel shell;It can be extractd after welding on four suspension centres Wirerope;It is poured using working lining castable, then is poured using insulating layer castable later, finally by the steel at this Shell welding restores;The refractory material originally to fall off in this way is repaired finish online.
Preferably, the mould that hangs is additionally provided with anchoring piece for being welded to connect with the steel pipe walls.In this way, reinforcing bar and hanging mould When welding, reinforcing bar and anchoring piece can be welded together.
It should be noted that hanging mould size should be slightly bigger than internal refractory at hot air duct steel shell when repairing hot air duct Area at material falls back, otherwise hanging mould and bricking original in hot air duct can not be in close contact, and castable can be flowed into from gap In hot air duct, this certainly will influence the quality of casting and the draught area of hot air duct.But if hanging mould using monoblock type, It may result in again and be difficult to be put into hot air duct, therefore hang mould using what two panels curved plate was put together in the utility model, And be crosslinked and be hinged by hinge, it is put into hot air duct after can thus folding, and avoid castable that from flowing from gap Enter in hot air duct.
The utility model structure is simple, reliable operation and can repair hot wind in time (less than 18 hours) within a short period of time The refractory material of shedding stops production for a long time so as to avoid blast furnace.The utility model is suitable for industrialized production and processing It is at low cost, it is with good economic efficiency.
Detailed description of the invention
The utility model is described in further detail with reference to the accompanying drawing.
Fig. 1 is the schematic diagram of blast furnace and hot air duct.
Fig. 2 is the structural schematic diagram of the utility model embodiment.
Fig. 3 is the schematic diagram of the utility model embodiment when in use.
Appended drawing reference: hot-blast stove 1, hot-blast valve 2, hot air duct 3, refractory material fall off place 4, flow backwards damping down valve 5, refluence is stopped Air piping 6, blast furnace 7, air outlet 8, suspension centre 9, hinge crosslinking 10, curved plate 11 hang mould 12, anchoring piece 13, working lining casting Material 14, insulating layer castable 15, reinforcing bar 16.
Specific embodiment
Embodiment
As shown in Figure 1, the air outlet 8 of blast furnace 7 is connect by hot air duct 3 with hot-blast stove 1, the tube wall of hot air duct 3 is Steel pipe walls are equipped at air outlet 8 in hot air duct 3 and flow backwards damping down pipeline 6, flow backwards damping down pipeline 6 and are equipped with and flow backwards damping down Valve 5.Hot air duct 3 is equipped with hot-blast valve 2 close to the position of hot-blast stove.
The repairing mould for blast furnace ironmaking hot air duct of the present embodiment is as shown in Figures 2 and 3, including by two panels arc What steel plate 11 was put together hangs mould 12, and two panels curved plate 11 is hinged by hinge 10;The mould that hangs is equipped with several hang Point 9, it is removable on the suspension centre 9 to be connected with wirerope (being not shown on figure).
Preferably, the mould 12 that hangs is additionally provided with anchoring piece 13 for being welded to connect with the steel pipe walls.In this way, reinforcing bar 16 When with hanging the welding of mould 12, reinforcing bar 16 and anchoring piece 13 can be welded together.
When the present embodiment is in use, first using the temperature of instrument detection hot-blast main's steel shell, according to hot-blast main's steel shell Temperature anomaly, confirmation hot air duct steel shell refractory material falls off place 4.It falls off according to steel shell refractory material and locates the size of 4 areas Production hangs mould 12 accordingly, as shown in Fig. 2, it includes that four suspension centres, 9, two hinge crosslinkings 10 and two panels have centainly that this, which hangs mould 12, Radian steel plate 11.
Blast furnace 7 by flow backwards 6 damping down of damping down pipeline after, open 3 internal refractories of hot air duct fall off place 4 steel Shell, under the premise of the position is winding is effectively cooled, the refractory brick of manual cleaning damage, the remnants that will be fallen off using specific purpose tool Refractory material takes out in hot air duct.The casting of heat pipeline domestic demand is put into after it will hang the closure of mould 12 (i.e. closure hinge crosslinking 10) Position, stretching the wirerope on four suspension centres 9 makes to hang the opening of mould 12 and fix.Then reinforcing bar 16 is welded on hot air duct 3 On steel shell, and using anchoring piece 13 and hang 12 firm welding of mould.The wirerope on four suspension centres 9 can be extractd after welding;It It is poured using working lining castable 14, then is poured using insulating layer castable 15 afterwards, finally welded the steel shell at this Recovery is connect, the structure after reparation is as shown in Figure 3;The refractory material originally to fall off in this way is repaired finish online.
The utility model is not limited to the above embodiment, and the technical solution of above-mentioned each embodiment of the utility model is each other New technical solution can be formed with combined crosswise, in addition all technical solutions formed using equivalent replacement, it is practical new to all fall within this In the protection scope that type requires.

Claims (3)

1. a kind of repairing mould for blast furnace ironmaking hot air duct, the hot air duct is equipped with steel pipe walls;It is characterized by: packet It includes and hangs mould by what two panels curved plate was put together, two panels curved plate is crosslinked by hinge to be hinged;Described hang sets on mould There are several suspension centres, it is removable on the suspension centre to be connected with wirerope.
2. the repairing mould according to claim 1 for blast furnace ironmaking hot air duct, it is characterised in that: described to hang on mould If there are four suspension centres.
3. the repairing mould according to claim 1 for blast furnace ironmaking hot air duct, it is characterised in that: described to hang mould also Equipped with the anchoring piece for being welded to connect with the steel pipe walls.
CN201820667165.8U 2018-05-07 2018-05-07 Repairing mould for blast furnace ironmaking hot air duct Active CN208414469U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820667165.8U CN208414469U (en) 2018-05-07 2018-05-07 Repairing mould for blast furnace ironmaking hot air duct

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820667165.8U CN208414469U (en) 2018-05-07 2018-05-07 Repairing mould for blast furnace ironmaking hot air duct

Publications (1)

Publication Number Publication Date
CN208414469U true CN208414469U (en) 2019-01-22

Family

ID=65117002

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820667165.8U Active CN208414469U (en) 2018-05-07 2018-05-07 Repairing mould for blast furnace ironmaking hot air duct

Country Status (1)

Country Link
CN (1) CN208414469U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112359155A (en) * 2020-10-30 2021-02-12 张家港宏昌钢板有限公司 Method for repairing local lining refractory falling of blast furnace top gas ascending pipeline

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112359155A (en) * 2020-10-30 2021-02-12 张家港宏昌钢板有限公司 Method for repairing local lining refractory falling of blast furnace top gas ascending pipeline

Similar Documents

Publication Publication Date Title
CN103820655B (en) A kind of 11t being applicable to titanium sponge production combines also-steam stove
CN208414469U (en) Repairing mould for blast furnace ironmaking hot air duct
CN102251094B (en) Heat accumulating type soaking pit furnace capable of combusting low-calorific value coal gas
CN201534851U (en) Blast furnace baking device
CN109437576A (en) A kind of rock wool and preparation method thereof, the preparation multi-functional total oxygen natural gas smelting furnace of rock wool
CN206330432U (en) It is a kind of to eliminate the process structure that Mialz lime kiln runs wind
CN207095311U (en) Ferroalloy toasts feed bin
CN109022660B (en) A kind of heating furnace heating high hydrogen content reducing gas
CN204608066U (en) A kind of single loop formula hot air valve plate
CN104748571B (en) Mobile top cap type high temperature smelting furnace slag runner regenerative heat exchanger and exhaust heat recovering method
CN206616244U (en) A kind of blast furnace air-supply arrangement
CN201560206U (en) Heat-resistant hot blast valve for hot-blast furnace
CN201277706Y (en) Temperature keeping apparatus for heat accumulation type hot air stove
CN207119786U (en) A kind of big bag roaster clad
CN202116623U (en) Heat storage type soaking pit combusting gas with low heat value
CN103063011B (en) Energy-saving environment-friendly high-blast-temperature cupola system equipment
CN203163468U (en) Novel cast iron hot-air smelting furnace
CN102287818B (en) Passage structure for burning equipment and heat-storing type burning equipment
CN201560196U (en) Blast-furnace novel tuyere-belt cooling wall
CN107327819A (en) A kind of power station burning boiler
CN201074236Y (en) Blast furnace blasting branch pipe
CN212357284U (en) Hot-blast furnace is able to bear or endure firebrick and repairs structure
CN205897841U (en) Metallurgical smelting furnace of copper scrap
CN209689400U (en) A kind of off-gas recovery utilizes furnace cupola
CN204718422U (en) A kind of furnace cupola of waste heat recovery

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant