CN201534851U - Blast furnace baking device - Google Patents
Blast furnace baking device Download PDFInfo
- Publication number
- CN201534851U CN201534851U CN2009200169442U CN200920016944U CN201534851U CN 201534851 U CN201534851 U CN 201534851U CN 2009200169442 U CN2009200169442 U CN 2009200169442U CN 200920016944 U CN200920016944 U CN 200920016944U CN 201534851 U CN201534851 U CN 201534851U
- Authority
- CN
- China
- Prior art keywords
- furnace
- blast
- blast furnace
- diameter
- air inlet
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Vertical, Hearth, Or Arc Furnaces (AREA)
Abstract
The utility model relates to a blast furnace baking device, which is mainly applied to newly built blast furnaces and blast furnace overhaul. The utility model is characterized in that an air inlet pipe is communicated into a furnace tank through an air inlet opening, an outlet opening of the air inlet pipe is arranged in the center of the furnace tank, and is inserted into the furnace bottom, the upper part of the air inlet pipe is provided with a circular iron plate, and an air exhaust pipe is inserted into an iron outlet opening. The outlet opening of the air inlet pipe is arranged on the circumference which has the diameter of the 1/3 furnace tank diameter and is concentric with the furnace tank, and the outlet opening of the air inlet pipe is arranged on the circumference which has the diameter of the 2/3 furnace tank diameter and is concentric with the furnace tank. Temperature measuring couples are arranged in the air opening circumference direction at intervals of 120 degrees. The utility model has the advantages that the baking device can meet the requirements of furnace baking of the blast furnace so that the furnace tank of the blast furnace can be uniformly heated, the temperature of carbon bricks at the furnace bottom reaches higher than 100 DEG C, refractory moisture of the whole furnace can be discharged, the structure is simple, and the repeated use can be realized.
Description
Technical field
The utility model relates to a kind of blast furnace apparatus for baking that is mainly used in newly-built blast furnace and blast furnace overhaul.
Background technology
The iron-smelting blast furnace body is to be welded into the stove skin by steel plate, and its inboard hangs with the water flowing cooling stave, and the cooling stave inboard is built refractory materials by laying bricks or stones, and generation blast furnace life is more than 15 years.The liner of blast-furnace body contains a large amount of moisture content in refractory materials and the mortar in building process, and blast furnace production just is in the pyritous Working environment from the beginning of going into operation always, is the encloses container of a long term high temperature job, and will keeps temperature stably as far as possible.In order to make inner lining refractory adapt to smelting environment in the State of Blast Furnace as early as possible, and given play to the effect of protection blast-furnace body, before high furnace igniting, blast furnace must carry out the baker operation, with the most moisture content on the thorough removal body, makes the blast furnace operation of lighting a fire smoothly.Blast oven is the hot blast that blows into from the air port by the hotblast stove heating, utilizes the temperature of hot blast, gradually the moisture content in the body is heated up, and finally drains from venting hole and Blast Furnace Throat Ventilation Valve with the form of water vapour.Generally speaking, blast oven needs 10-15 days, comprising intensification, insulation, several stages again heats up, is incubated, lowers the temperature, baker cools at last, when the inlet front end temperature drops to 100 ℃ of left and right sides in the stove, stop to be blown into hot blast, use instead and be blown into natural wind blast furnace is cooled down.The emphasis of baker is cupola well, furnace bottom, otherwise emit a large amount of steam after the blow-on, not only can absorb the cupola well heat, reduce slag iron temperature, make the start-up of the furnace difficulty, and the moisture rapid evaporation, a large amount of steam are run out of from brickwork joint, may make bricking cracking and furnace expansion and be damaged, influence blast furnace campaign.Therefore, the quality of blast oven has very big influence to the life-span of blast furnace.
At present, the blast oven temperature that generally adopts gas blower by hotblast stove air-supply cold wind to be heated to regulation is sent into the mode of blast furnace by the air port.Old-fashioned furnace drying device is to adopt 1/3rd air ports to connect the baker pipe to reach in the cupola well, 2/3rds air ports directly are blown into the mode baker of hot blast, its shortcoming is that the cupola well heating is inhomogeneous, heat does not arrive cupola well and has directly run away from furnace roof by shaft, cause cupola well not heat up effectively, 10-15 days bakers finish the back blast furnace hearth and do not dry by the fire, and furnace bottom carbon brick temperature has only about 70 ℃, illustrates that some water does not evaporate.
Summary of the invention
The purpose of this utility model provides a kind of blast furnace apparatus for baking, and it is inhomogeneous to solve the heating of old-fashioned apparatus for baking cupola well, and the moisture of anti-material and brickwork joint is the problem of evaporation fully not.
For solving the problems of the technologies described above, the technical solution of the utility model is:
A kind of blast furnace apparatus for baking is characterized in that blast pipe feeds cupola well from the air port, and the outlet of blast pipe is at the cupola well center, and is inserted into furnace bottom, and blast pipe top is provided with round iron plate, and exhaust duct inserts iron notch.
The outlet of described blast pipe be arranged on diameter be 1/3 cupola well diameter with the concentric circumference of cupola well on.
The outlet of described blast pipe be arranged on diameter be 2/3 cupola well diameter with the concentric circumference of cupola well on.
Circumferential direction every interval in described air port is provided with a thermometric galvanic couple for 120 °.
Compared with prior art, the beneficial effects of the utility model are: this apparatus for baking can satisfy the requirement of blast oven, make the blast furnace hearth even heating, furnace bottom carbon brick temperature reaches more than 100 ℃, the whole blast furnace moisture of anti-the material is evaporated fully, simple in structure, reliable, can reuse, reduce facility investment, satisfy requirement newly-built, the overhaul blast oven.
Description of drawings
Fig. 1 is the structural representation of the utility model embodiment;
Fig. 2 is Fig. 1 vertical view.
1-cupola well 2-blast pipe 3-round iron plate 4-exhaust duct 5-iron notch 6-air port 7-thermometric galvanic couple among the figure
Embodiment
Below in conjunction with accompanying drawing embodiment of the present utility model is described further:
With reference to accompanying drawing 1, accompanying drawing 2, a kind of blast furnace apparatus for baking, blast pipe 2 is 6 feeding cupola wells 1 from the air port, the outlet of blast pipe 2 is at cupola well 1 center, and be inserted into furnace bottom, and blast pipe 2 tops are provided with round iron plate 3, and exhaust duct 4 inserts iron notch 5, slit refractory materials tamping between itself and the iron notch 5, hot blast is discharged from exhaust duct 4 during blast oven.Blast pipe 2 outlet also be arranged on diameter be 1/3 cupola well, 1 diameter with cupola well 1 concentric circumference on.Blast pipe 2 outlet also be arranged on diameter be 2/3 cupola well, 1 diameter with cupola well 1 concentric circumference on.6 circumferential directions every interval in air port is provided with a thermometric galvanic couple 7 for 120 °.
During installation, unload next air port 6 little covers from blast furnace hearth 1, the operating personnel can enter in the blast furnace hearth 1.Blast pipe 2 is sent in the stove from blast-furnace tuyere 6, in stove, be welded into "
" shape, one is inserted 6, one in air port and inserts cupola well 1; be fixed on furnace bottom with angle bar frame, and blast pipe 2 outlets are 1.5 meters with the distance of anti-material at the bottom of the State of Blast Furnace, and all the other half blast pipes 2 are apart from 2 meters of cupola well 1 sidewalls; generally apart from 4 meters of cupola well 1 sidewalls, and two kinds of specification pipes intert mutually to be opened.Diameter also 6 is sent in the stove from the air port less than the round iron plate 3 of 1 meter of cupola well diameter, welding assembly in stove, and round iron plate 3 is welded on the blast pipe 2 round iron plate 3 plaies when preventing baker.Insert exhaust ducts 4 from blast furnace iron notch 5, slit refractory materials tamping between itself and the iron notch 5.Hot blast is discharged from exhaust duct 4 during blast oven.Evenly choose three direction air ports 6 and insert thermometric galvanic couple 7, receive on the baker instrument, be used for observing wind-warm syndrome to change.When blast furnace overhaul, thermometric galvanic couple 7 can use the original throat temperature of blast furnace, furnace throat temperature, temperature of the furnace hearth, bottom temperature galvanic couple.
During blast oven, start gas blower, heat the wind-warm syndrome that reaches regulation through hotblast stove and send into blast furnace hearth 1 by hot air duct, blast pipe 2, hot blast is blown at the bottom of the State of Blast Furnace by blast pipe 2, upwards stop again through round iron plate 3, the hot blast secondary distribution is to blast furnace hearth 1, diffuses from blast furnace furnace roof and exhaust duct 4 to blow out.
Claims (4)
1. a blast furnace apparatus for baking is characterized in that blast pipe feeds cupola well from the air port, and the outlet of blast pipe is at the cupola well center, and is inserted into furnace bottom, and blast pipe top is provided with round iron plate, and exhaust duct inserts iron notch.
2. a kind of blast furnace apparatus for baking according to claim 1 is characterized in that, the outlet of described blast pipe be arranged on diameter be 1/3 cupola well diameter with the concentric circumference of cupola well on.
3. a kind of blast furnace apparatus for baking according to claim 1 and 2 is characterized in that, the outlet of described blast pipe be arranged on diameter be 2/3 cupola well diameter with the concentric circumference of cupola well on.
4. according to claim 1,2 or 3 described a kind of blast furnace apparatus for baking, it is characterized in that circumferential direction every interval in described air port is provided with a thermometric galvanic couple for 120 °.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009200169442U CN201534851U (en) | 2009-08-26 | 2009-08-26 | Blast furnace baking device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009200169442U CN201534851U (en) | 2009-08-26 | 2009-08-26 | Blast furnace baking device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201534851U true CN201534851U (en) | 2010-07-28 |
Family
ID=42534633
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2009200169442U Expired - Fee Related CN201534851U (en) | 2009-08-26 | 2009-08-26 | Blast furnace baking device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201534851U (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104928427A (en) * | 2015-07-01 | 2015-09-23 | 宝钢集团新疆八一钢铁有限公司 | Blast furnace drying air guide pipe device |
CN107779532A (en) * | 2017-11-15 | 2018-03-09 | 攀钢集团西昌钢钒有限公司 | A kind of blast furnace opening device and method |
CN108823344A (en) * | 2018-08-09 | 2018-11-16 | 上海二十冶建设有限公司 | The method for dismounting of dry-off oven device for blast furnace under a kind of restricted clearance |
CN112981026A (en) * | 2021-02-23 | 2021-06-18 | 山西太钢不锈钢股份有限公司 | Arrangement method of blast furnace drying hot air guide pipe |
CN113106180A (en) * | 2021-04-09 | 2021-07-13 | 广东韶钢松山股份有限公司 | Blast furnace drying temperature detection couple mounting method, blast furnace and furnace drying method |
-
2009
- 2009-08-26 CN CN2009200169442U patent/CN201534851U/en not_active Expired - Fee Related
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104928427A (en) * | 2015-07-01 | 2015-09-23 | 宝钢集团新疆八一钢铁有限公司 | Blast furnace drying air guide pipe device |
CN104928427B (en) * | 2015-07-01 | 2023-07-04 | 新疆八一钢铁股份有限公司 | Blast furnace baking air guide pipe device |
CN107779532A (en) * | 2017-11-15 | 2018-03-09 | 攀钢集团西昌钢钒有限公司 | A kind of blast furnace opening device and method |
CN107779532B (en) * | 2017-11-15 | 2019-10-11 | 攀钢集团西昌钢钒有限公司 | A kind of blast furnace opening device and method |
CN108823344A (en) * | 2018-08-09 | 2018-11-16 | 上海二十冶建设有限公司 | The method for dismounting of dry-off oven device for blast furnace under a kind of restricted clearance |
CN112981026A (en) * | 2021-02-23 | 2021-06-18 | 山西太钢不锈钢股份有限公司 | Arrangement method of blast furnace drying hot air guide pipe |
CN112981026B (en) * | 2021-02-23 | 2022-05-17 | 山西太钢不锈钢股份有限公司 | Arrangement method of blast furnace drying hot air guide pipe |
CN113106180A (en) * | 2021-04-09 | 2021-07-13 | 广东韶钢松山股份有限公司 | Blast furnace drying temperature detection couple mounting method, blast furnace and furnace drying method |
CN113106180B (en) * | 2021-04-09 | 2022-03-11 | 广东韶钢松山股份有限公司 | Blast furnace drying temperature detection couple mounting method, blast furnace and furnace drying method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206339094U (en) | Heating using microwave produces the product line device of alloy | |
CN201534851U (en) | Blast furnace baking device | |
CN112410483B (en) | 2500m3Blast furnace drying operation method | |
CN104611487A (en) | Furnace top temperature control method for heating-up of blast furnace | |
CN114921599A (en) | Method for introducing coal gas by blowing in blast furnace | |
CN201367436Y (en) | Baking device of blast-furnace hot blast stove | |
CN201081538Y (en) | Tubular oven | |
CN106546096A (en) | The product line device and production method of microwave heating production alloy | |
CN105948048B (en) | Energy saving and environment friendly carbon disulfide gasification reacting furnace | |
CN208505002U (en) | Hot air circulation heat accumulation type radiant tube heating sealing roller way kiln | |
CN104374081B (en) | A kind of Vertical Steel Plate hot-blast stove of novel high-efficiency and energy-saving | |
CN111910035A (en) | Quick furnace cooling method of improved top combustion type hot blast furnace | |
CN207498403U (en) | A kind of inner lining structure of fire-proof | |
CN102260034A (en) | Novel crucible glass kiln | |
CN204097107U (en) | Novel energy-conserving potassium sulfate Reaktionsofen | |
CN206425543U (en) | A kind of big bag roaster | |
CN206616244U (en) | A kind of blast furnace air-supply arrangement | |
CN86103119B (en) | Blast furnace blowing process and its appts | |
CN209623352U (en) | A kind of fireproofing prefabricated member or precast concrete roasting kiln | |
JPH0376788A (en) | Drying and heating dry quenching equipment of coke oven | |
CN113124255B (en) | Hot air piping system maintenance cooling method | |
CN213335593U (en) | Steam treatment system for shaft furnace burden gallery | |
CN201203342Y (en) | Direct combustion type overhead combustion chamber cupola | |
CN218910467U (en) | Heat accumulating type energy-saving refining furnace for metal magnesium smelting gas | |
CN204084840U (en) | A kind of Vertical Steel Plate hot-blast stove of novel high-efficiency and energy-saving |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20100728 Termination date: 20150826 |
|
EXPY | Termination of patent right or utility model |