CN208362258U - A kind of oil sands bitumen extraction element based on the extraction of thermokalite water - Google Patents

A kind of oil sands bitumen extraction element based on the extraction of thermokalite water Download PDF

Info

Publication number
CN208362258U
CN208362258U CN201821025493.4U CN201821025493U CN208362258U CN 208362258 U CN208362258 U CN 208362258U CN 201821025493 U CN201821025493 U CN 201821025493U CN 208362258 U CN208362258 U CN 208362258U
Authority
CN
China
Prior art keywords
pipeline
outlet
water
screw conveyor
mixing channel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821025493.4U
Other languages
Chinese (zh)
Inventor
沈剑
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ningbo University of Technology
Original Assignee
Ningbo University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ningbo University of Technology filed Critical Ningbo University of Technology
Priority to CN201821025493.4U priority Critical patent/CN208362258U/en
Application granted granted Critical
Publication of CN208362258U publication Critical patent/CN208362258U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Production Of Liquid Hydrocarbon Mixture For Refining Petroleum (AREA)

Abstract

A kind of oil sands bitumen extraction element based on the extraction of thermokalite water of the utility model, using by ore crusher, first mixing channel, first jacket type screw conveyor, second jacket type screw conveyor, settling tank, second mixing channel, defecator, extractant recovery tower, condenser, centrifuge, neutralization chamber, sand storage tank, boiler, evaporator, the device that crystallization kettle and relevant feedstocks pipeline and the pipeline for connecting the above equipment form, pass through mixing, helical feed, sedimentation, extraction, rectifying, it neutralizes, it burns, evaporation, the cell arrangements such as crystallization, reduce the discharge of waste water, improve the quality of pitch.

Description

A kind of oil sands bitumen extraction element based on the extraction of thermokalite water
Technical field
The present invention relates to petroleum refining and separation technology field more particularly to a kind of oil sands bitumens based on the extraction of thermokalite water Extraction element.
Background technique
Oil-sand is a kind of unconventional energy resource risen in recent years, because it contains bitumen therefore is also designated as pitch Sand.Oil-sand is mostly black or grey black, is a kind of mixture by material compositions such as sand grains, pitch, clay particles, mean containing The sedimentary rock of pitch or other mink cell focuses.World economy to energy demand be continuously increased and the continuous consumption of conventional oil resource Receive more and more attention non-conventional oil resource;In addition International Petroleum Price is hovered in a high position for a long time, oil-sand will be in future It will be occupied an important position in energy resource structure.China's oil-sand resource is abundant, and oil-sand geological resources are 59.7 hundred million tons, mining resources Amount is 22.58 hundred million tons.China's oil-sand is widely distributed, oil content is medium, oily preferable, and exploration prospect is very considerable.Have in China For a little area oil-sand oil contents 12% or more, oil product is preferable, carries out in-depth study, reasonable development and utilization to oil-sand resource, There is important strategic importance to Chinese energy safety.
Oil-sand exploitation is there are two types of method: the oil-sand mine buried for underground, usually to underground inject steam or hot-air, Even solvent makes oil-sand viscous crude reduce viscosity, have mobility, can separate from gravel (solid mineral grain), then use It is pumped to ground, this extracts heavy oil process for the underground of oil-sand on the spot.Oil-sand mine close to earth's surface be usually have an opencast mining of it is fuel-displaced Sand, then separated viscous crude and gravel using oil sand separation technology on ground.The main of pitch is extracted from opencast oil-sand Method has thermokalite washing process, solvent extraction technology, thermal cracking process etc. several, (application number 201510999342.3, Yi Zhongqin The method of aqueous reversible solvent assisting oil-sand separation;A kind of oil sand continuous separation process of 201410699046 .7 of application number;Application Number a kind of oil-sand Atmospheric vacuum destructive distillation complex solvent extraction device and method of 201510245619 .3).Industrial use is compared at present Mature is thermokalite WATER-WASHING METHOD, which first crushes oil-sand, be re-fed into heat alkali liquid and be mixed, then into mixed serum Being passed through gas makes in pitch flotation, after collecting pitch and alkane dilution being added to reduce its viscosity, is sent to refinery and is refined Obtain various oil products.The technical operation is simple, but has the disadvantage that and technical bottleneck: water consumption is big, energy consumption is high, at tailing Manage that extremely difficult, environmental pollution is serious.The method for separating pitch in the slave oil-sand of environmental protection, economy, sustainable development is found to compel In the eyebrows and eyelashes.
Summary of the invention
The present invention is to solve the above-mentioned state of the art and provide a kind of oil sands bitumen extraction element based on the extraction of thermokalite water, energy Discharge of wastewater is enough reduced, solid waste pollutant level is reduced, improves asphalt quality.
It is a kind of oil sands bitumen based on the extraction of thermokalite water that the present invention, which solves technical solution used by above-mentioned technical problem, Extraction element, including ore crusher (1), the first mixing channel (2), the first jacket type screw conveyor (3), the second jacket type spiral shell Revolve conveyer (4), settling tank (5), the second mixing channel (6), defecator (7), extractant recovery tower (8), condenser (9), centrifugation Machine (10), neutralization chamber (11), sand storage tank (12), boiler (13), evaporator (14), crystallization kettle (15) and relevant feedstocks pipeline and Connect the pipeline of the above equipment;
First jacket type screw conveyor (3) is identical with the structure of the second jacket type screw conveyor (4), be equipped with into Mouth, outlet, collet import and jacket outlet;The top of settling tank (5) be equipped with row pitch mouth, side middle position be equipped with import and Water out, bottom are equipped with sediment ejection opening;Defecator (7) is equipped with import, oil mutually outlet and water phase outlet;Extractant recovery tower (8) is set There are import, tower top outlet, tower reactor outlet;Centrifuge (10) is equipped with import, discharge outlet and sediment ejection opening;Boiler (13) be equipped with it is husky into Mouthful, husky outlet, inside is equipped with heating coil, and the both ends of heating coil are respectively water inlet and steam (vapor) outlet, use natural gas for Fuel;Evaporation coil is equipped in evaporator (14), the both ends of evaporation coil are respectively steam inlet and condensation-water drain, are additionally provided with Import, concentrated solution outlet, secondary steam outlet;Crystallization kettle (15) is equipped with mother liquor import, salt outlet and waste liquid outlet;
Ore crusher (1) is connected to by pipeline with the first mixing channel (2);First mixing channel (2) passes through pipeline and first It is divided into two-way pipeline after threeway connection, all the way the inlet communication of pipeline and the first jacket type screw conveyor (3), another way pipeline With the outlet of the second jacket type screw conveyor (4);The outlet of first jacket type screw conveyor (3) passes through pipeline and the It is divided into two-way pipeline after two threeways connection, all the way the inlet communication of pipeline and settling tank (5), another way pipeline and the second jacket type The inlet communication of screw conveyor (4);Row's pitch mouth of settling tank (5) is connected to by pipeline with the second mixing channel (6);Settling tank (5) water out is divided into the first and second pipelines, the first pipeline and the second mixing channel (6) after being connected to by pipeline with third threeway Connection after the second pipeline is connected to the 4th threeway and is divided into the third and fourth pipeline, third pipeline and the second jacket type spiral transferring Send the jacket outlet of machine (4) to be connected to, after the 4th pipeline is connected to the 5th threeway and be divided into the 5th and the 6th pipeline, the 5th pipeline with First mixing channel (2) connection, the 6th pipeline are to supplement buck pipeline;The sediment ejection opening of settling tank (5) passes through pipeline and sand storage tank (12) it is connected to;Second mixing channel (6) passes through the inlet communication of pipeline and defecator (7);The water phase outlet of defecator (7) passes through pipe The inlet communication of line and centrifuge (10);Mutually outlet is connected the oil of defecator (7) by the import of pipeline and extractant recovery tower (8) It is logical;The tower top outlet of extractant recovery tower (8) is connected to by pipeline with the second mixing channel (6), in extractant recovery tower (8) and the Condenser (9) are provided on pipeline between two mixing channels (6);The tower reactor outlet of extractant recovery tower (8) is pitch discharge Mouthful;The sediment ejection opening of centrifuge (10) is connected to by pipeline with sand storage tank (12), and discharge outlet is connected to by pipeline with neutralization chamber (11); Neutralization chamber (11) passes through the inlet communication of pipeline and evaporator (14);Sand storage tank (12) passes through the husky import of pipeline and boiler (13) Connection;The steam (vapor) outlet of boiler (13) is connected to by pipeline with the steam inlet of evaporator (14), and water inlet is by pipeline and steams Send out the condensation-water drain connection of device (14);The concentrated solution outlet of evaporator (14) passes through the mother liquor import of pipeline and crystallization kettle (15) Connection, secondary steam outlet pass through the collet inlet communication of pipeline and the first jacket type screw conveyor (3);First jacket type spiral shell The jacket outlet for revolving conveyer (3) passes through the collet inlet communication of pipeline and the second jacket type screw conveyor (4);Crystallization kettle (15) waste liquid outlet is connected to by pipeline with the first mixing channel (2).
Using a kind of oil sands bitumen that the oil sands bitumen extraction element based on the extraction of thermokalite water extracted based on thermokalite water Extracting method is that oil-sand raw material feeding ore crusher (1) is crushed, and broken oil-sand raw material enters the first mixing channel (2);Recirculated water from the 5th pipeline and the waste liquid from crystallization kettle (15) also enter the first mixing channel (2);Oil-sand raw material follows Ring water and waste liquid obtain mixture in the first mixing channel (2) after mixing, mixture enters the first threeway and presss from both sides with from second Pretreatment material is obtained by the first jacket type screw conveyor (3) after the circulation mixture mixing of shell type screw conveyor (4);In advance Processing material is divided into first and second strands of pretreatment material, and first strand of pretreatment material enters settling tank (5), and second strand of pretreatment material passes through Circulation mixture is obtained after second jacket type screw conveyor (4);The mixture of mixture, circulation mixture and the two is passing through When crossing the first and second jacket type screw conveyors, oil-sand particle surface is attached under the collective effect of collet heating and screw extruding Pitch shed into water;First and second jacket type screw conveyors and connecting pipeline constitute the circulatory system, can To increase the residence time and then improve pitch removal effect;First burst of pretreatment material sedimentation, split-phase, top in settling tank (5) Obtain primary bitumen, middle part obtains water, bottom obtains rough sand, primary bitumen enter the second mixing channel (6), water pass through third threeway After be divided into first and second strands of water, first strand of water enters the second mixing channel (6), and the second water stock enters the 4th threeway and comes from second The 5th threeway is entered back into after the condensed water mixing of jacket type screw conveyor (4) and supplement buck is mixed to get recirculated water, rough sand It is discharged into sand storage tank (12);The extractant for carrying out condenser (9) also enters the second mixing channel (6);Extractant is toluene and dichloromethane The mixture of alkane;Primary bitumen, first strand of water and extractant are stirred in the second mixing channel (6) and enter back into defecator (7) Split-phase is carried out, oily phase and water phase are obtained;Oily is mutually the mixture of primary bitumen and extractant, and the water phase is water and a small amount of fine sand Mixture;Oily mutually enter extractant recovery tower (8) carry out rectifying, and tower top obtains extractant, and tower reactor obtains pitch;Extractant into Enter condenser (9) and condenses to 25 DEG C;Water phase enters centrifuge (10) and carries out isolated fine sand and alkaline water, and it is husky that fine sand enters storage Tank (12), the hydrochloric acid that alkaline water enters neutralization chamber (11) and is added are neutralized to pH=7 and obtain salt water;Salt water enters evaporator (14) Evaporation obtains secondary steam and concentrate, and concentrate enters crystallization kettle (15) cooling, crystallization obtains salt and waste water, and secondary steam is logical It crosses the chuck layer of the first jacket type screw conveyor (3), then is obtained by the chuck layer of the second jacket type screw conveyor (4) cold Condensate;Sand in sand storage tank (12) enters the burner hearth of boiler (13) by flame incineration, burns up grains of sand pitch remained on surface and obtains Dry gravel, dry gravel discharge boiler (13);The steam that heating coil in boiler (13) generates enters evaporator (14) evaporation coil obtains condensed water, and the heating coil that condensed water returns in boiler (13) is vaporized into steam.
As an improvement, 20 ~ 200 mesh of grain diameter of the broken oil-sand raw material.
As an improvement, the temperature of the pretreatment material is 90 ~ 98 DEG C.
As an improvement, the volume flow ratio of first and second strands of pretreatment material is 1:3 ~ 10.
As an improvement, the volume flow ratio in first and second strands of water is 1:2 ~ 5.
As an improvement, the mass ratio of the secondary steam and concentrate is 1 ~ 2:1.
It improves again, the mass ratio of toluene and methylene chloride is 2 ~ 5:1 in the extractant.
It is further improved, is for 5 ~ 8% sodium hydroxide and mass fraction containing mass fraction in the supplement buck 0.5 ~ 1.5% neopelex.
Compared with the prior art, the advantages of the present invention are as follows: 1, it using two jacket type screw conveyors forms one and follows Loop system is acted on using collet heating and screw extrusion, improves the removal effect of middle pitch;2, by being followed to alkali waste water Ring utilizes, and the means such as evaporation, concentration, crystallization eliminate the discharge of waste water;3, crude asphalt is handled using extraction-rectification, be stripped of Fine sand in pitch, the quality for improving pitch.
Detailed description of the invention
Fig. 1 is a kind of flow diagram of oil sands bitumen extraction element based on the extraction of thermokalite water of the invention.
Wherein: 1 is ore crusher, and 2 be the first mixing channel, and 3 be the first jacket type screw conveyor, and 4 be the second collet Formula screw conveyor, 5 be settling tank, and 6 be the second mixing channel, and 7 be defecator, and 8 be extractant recovery tower, and 9 be condenser, and 10 are Centrifuge, 11 be neutralization chamber, and 12 be sand storage tank, and 13 be boiler, and 14 be evaporator, and 15 be crystallization kettle.
Specific embodiment
Below in conjunction with attached drawing 1, by embodiment, present invention is further described in detail.
Embodiment 1
It is a kind of oil sands bitumen based on the extraction of thermokalite water that the present invention, which solves technical solution used by above-mentioned technical problem, Extraction element, including ore crusher (1), the first mixing channel (2), the first jacket type screw conveyor (3), the second jacket type spiral shell Revolve conveyer (4), settling tank (5), the second mixing channel (6), defecator (7), extractant recovery tower (8), condenser (9), centrifugation Machine (10), neutralization chamber (11), sand storage tank (12), boiler (13), evaporator (14), crystallization kettle (15) and relevant feedstocks pipeline and Connect the pipeline of the above equipment;The structure phase of first jacket type screw conveyor (3) and the second jacket type screw conveyor (4) Together, import, outlet, collet import and jacket outlet are equipped with;The top of settling tank (5) is equipped with row pitch mouth, side interposition It has installed import and water out, bottom is equipped with sediment ejection opening;Defecator (7) is equipped with import, oil mutually outlet and water phase outlet;Extractant Recovery tower (8) is equipped with import, tower top outlet, tower reactor outlet;Centrifuge (10) is equipped with import, discharge outlet and sediment ejection opening;Boiler (13) it is equipped with husky import, husky outlet, inside is equipped with heating coil, and the both ends of heating coil are respectively water inlet and steam (vapor) outlet, Use natural gas for fuel;Evaporation coil is equipped in evaporator (14), the both ends of evaporation coil are respectively steam inlet and condensation Water out is additionally provided with import, concentrated solution outlet, secondary steam outlet;Crystallization kettle (15) is equipped with mother liquor import, salt outlet and waste liquid Outlet;Ore crusher (1) is connected to by pipeline with the first mixing channel (2);First mixing channel (2) passes through pipeline and the first threeway It is divided into two-way pipeline after connection, all the way the inlet communication of pipeline and the first jacket type screw conveyor (3), another way pipeline and The outlet of two jacket type screw conveyors (4);The outlet of first jacket type screw conveyor (3) passes through pipeline and the two or three It is divided into two-way pipeline after leading to, all the way the inlet communication of pipeline and settling tank (5), another way pipeline and the second jacket type spiral The inlet communication of conveyer (4);Row's pitch mouth of settling tank (5) is connected to by pipeline with the second mixing channel (6);Settling tank (5) Water out be connected to by pipeline with third threeway after be divided into the first and second pipelines, the first pipeline and the second mixing channel (6) company It is logical, after the second pipeline is connected to the 4th threeway and it is divided into the third and fourth pipeline, third pipeline and the second jacket type helical feed The jacket outlet of machine (4) is connected to, and the 4th pipeline is divided into the 5th and the 6th pipeline again after being connected to the 5th threeway, the 5th pipeline and the One mixing channel (2) connection, the 6th pipeline are to supplement buck pipeline;The sediment ejection opening of settling tank (5) passes through pipeline and sand storage tank (12) it is connected to;Second mixing channel (6) passes through the inlet communication of pipeline and defecator (7);The water phase outlet of defecator (7) passes through pipe The inlet communication of line and centrifuge (10);Mutually outlet is connected the oil of defecator (7) by the import of pipeline and extractant recovery tower (8) It is logical;The tower top outlet of extractant recovery tower (8) is connected to by pipeline with the second mixing channel (6), in extractant recovery tower (8) and the Condenser (9) are provided on pipeline between two mixing channels (6);The tower reactor outlet of extractant recovery tower (8) is pitch discharge Mouthful;The sediment ejection opening of centrifuge (10) is connected to by pipeline with sand storage tank (12), and discharge outlet is connected to by pipeline with neutralization chamber (11); Neutralization chamber (11) passes through the inlet communication of pipeline and evaporator (14);Sand storage tank (12) passes through the husky import of pipeline and boiler (13) Connection;The steam (vapor) outlet of boiler (13) is connected to by pipeline with the steam inlet of evaporator (14), and water inlet is by pipeline and steams Send out the condensation-water drain connection of device (14);The concentrated solution outlet of evaporator (14) passes through the mother liquor import of pipeline and crystallization kettle (15) Connection, secondary steam outlet pass through the collet inlet communication of pipeline and the first jacket type screw conveyor (3);First jacket type spiral shell The jacket outlet for revolving conveyer (3) passes through the collet inlet communication of pipeline and the second jacket type screw conveyor (4);Crystallization kettle (15) waste liquid outlet is connected to by pipeline with the first mixing channel (2).
Using a kind of oil sands bitumen that the oil sands bitumen extraction element based on the extraction of thermokalite water extracted based on thermokalite water Extracting method is that oil-sand raw material feeding ore crusher (1) is crushed, and the grain diameter of broken oil-sand raw material is 20 mesh, Broken oil-sand raw material enters the first mixing channel (2);Recirculated water from the 5th pipeline and the waste liquid from crystallization kettle (15) Also enter the first mixing channel (2);Oil-sand raw material, recirculated water and waste liquid obtain mixture after mixing in the first mixing channel (2), mix It closes after material enters the first threeway and mixes with the circulation mixture from the second jacket type screw conveyor (4) through the first collet Formula screw conveyor (3) obtains pretreatment material;The temperature of pretreatment material is 98 DEG C;Pretreatment material is divided into first and second bursts of pre- places Reason material, the volume flow ratio of first and second strands of pretreatment material are 1:10, and first strand of pretreatment material enters settling tank (5), second Stock pretreatment material is by obtaining circulation mixture after the second jacket type screw conveyor (4);Mixture, circulation mixture and two The mixture of person is when by the first and second jacket type screw conveyors, under the collective effect of collet heating and screw extruding The pitch of oil-sand particle surface attachment sheds into water;First and second jacket type screw conveyors and connecting pipeline composition The circulatory system can increase the residence time and then improve pitch removal effect;First strand of pretreatment material sinks in settling tank (5) Drop, split-phase, top obtains primary bitumen, middle part obtains water, bottom obtains rough sand, and primary bitumen enters the second mixing channel (6), water By being divided into first and second strands of water after third threeway, the volume flow ratio of first and second strands of water is 1:5, and first strand of water enters Second mixing channel (6), after the second water stock is mixed into the 4th threeway with the condensed water from the second jacket type screw conveyor (4) Enter back into the 5th threeway and supplement buck be mixed to get recirculated water, supplement the sodium hydroxide for being 5% containing mass fraction in buck and The neopelex that mass fraction is 1.5%;Rough sand is discharged into sand storage tank (12);Come the extractant of condenser (9) also into Enter the second mixing channel (6);Extractant is the mixture of toluene and methylene chloride, and wherein the mass ratio of toluene and methylene chloride is 2:1;Primary bitumen, first strand of water and extractant, which are stirred in the second mixing channel (6), to be entered back into defecator (7) and is divided Phase obtains oily phase and water phase;Oily is mutually the mixture of primary bitumen and extractant, and the water phase is the mixing of water and a small amount of fine sand Object;Oily mutually enter extractant recovery tower (8) carry out rectifying, and tower top obtains extractant, and tower reactor obtains pitch;Extractant enters condensation Device (9) condenses to 25 DEG C;Water phase enters the isolated fine sand of centrifuge (10) progress and alkaline water, fine sand enter sand storage tank (12), the hydrochloric acid that alkaline water enters neutralization chamber (11) and is added is neutralized to pH=7 and obtains salt water;Salt water enters evaporator (14) steaming It sends out and obtains secondary steam and concentrate, the mass ratio of secondary steam and concentrate is 1:1, and concentrate enters crystallization kettle (15) drop Temperature, crystallization obtain salt and waste water, and secondary steam passes through the chuck layer of the first jacket type screw conveyor (3), then passes through the second folder The chuck layer of shell type screw conveyor (4) obtains condensed water;Sand in sand storage tank (12) enters the burner hearth of boiler (13) by flame It burns, burn-up grains of sand pitch remained on surface obtains dry gravel, dry gravel discharge boiler (13);In boiler (13) The evaporation coil that the steam that heating coil generates enters evaporator (14) obtains condensed water, and condensed water returns in boiler (13) Heating coil is vaporized into steam.
Embodiment 2
The device of embodiment 2 is same as Example 1.
Using a kind of oil sands bitumen that the oil sands bitumen extraction element based on the extraction of thermokalite water extracted based on thermokalite water Extracting method is that oil-sand raw material feeding ore crusher (1) is crushed, 200 mesh of grain diameter of broken oil-sand raw material, Broken oil-sand raw material enters the first mixing channel (2);Recirculated water from the 5th pipeline and the waste liquid from crystallization kettle (15) Also enter the first mixing channel (2);Oil-sand raw material, recirculated water and waste liquid obtain mixture after mixing in the first mixing channel (2), mix It closes after material enters the first threeway and mixes with the circulation mixture from the second jacket type screw conveyor (4) through the first collet Formula screw conveyor (3) obtains pretreatment material;The temperature of pretreatment material is 95 DEG C;Pretreatment material is divided into first and second bursts of pre- places Reason material, the volume flow ratio of first and second strands of pretreatment material are 1:3, and first strand of pretreatment material enters settling tank (5), second strand Pretreatment material is by obtaining circulation mixture after the second jacket type screw conveyor (4);Mixture, circulation mixture and the two Mixture when by the first and second jacket type screw conveyors, the oil under the collective effect of collet heating and screw extruding The pitch of sand particle surface attachment sheds into water;First and second jacket type screw conveyors and connecting pipeline constitute The circulatory system can increase the residence time and then improve pitch removal effect;First strand of pretreatment material sinks in settling tank (5) Drop, split-phase, top obtains primary bitumen, middle part obtains water, bottom obtains rough sand, and primary bitumen enters the second mixing channel (6), water By being divided into first and second strands of water after third threeway, the volume flow ratio of first and second strands of water is 1:2, and first strand of water enters Second mixing channel (6), after the second water stock is mixed into the 4th threeway with the condensed water from the second jacket type screw conveyor (4) Enter back into the 5th threeway and supplement buck be mixed to get recirculated water, supplement the sodium hydroxide for being 8% containing mass fraction in buck and The neopelex that mass fraction is 0.5%;Rough sand is discharged into sand storage tank (12);Come the extractant of condenser (9) also into Enter the second mixing channel (6);Extractant is the mixture of toluene and methylene chloride, and wherein the mass ratio of toluene and methylene chloride is 3:1;Primary bitumen, first strand of water and extractant, which are stirred in the second mixing channel (6), to be entered back into defecator (7) and is divided Phase obtains oily phase and water phase;Oily is mutually the mixture of primary bitumen and extractant, and the water phase is the mixing of water and a small amount of fine sand Object;Oily mutually enter extractant recovery tower (8) carry out rectifying, and tower top obtains extractant, and tower reactor obtains pitch;Extractant enters condensation Device (9) condenses to 25 DEG C;Water phase enters the isolated fine sand of centrifuge (10) progress and alkaline water, fine sand enter sand storage tank (12), the hydrochloric acid that alkaline water enters neutralization chamber (11) and is added is neutralized to pH=7 and obtains salt water;Salt water enters evaporator (14) steaming It sends out and obtains secondary steam and concentrate, the mass ratio of secondary steam and concentrate is 2:1, and concentrate enters crystallization kettle (15) drop Temperature, crystallization obtain salt and waste water, and secondary steam passes through the chuck layer of the first jacket type screw conveyor (3), then passes through the second folder The chuck layer of shell type screw conveyor (4) obtains condensed water;Sand in sand storage tank (12) enters the burner hearth of boiler (13) by flame It burns, burn-up grains of sand pitch remained on surface obtains dry gravel, dry gravel discharge boiler (13);In boiler (13) The evaporation coil that the steam that heating coil generates enters evaporator (14) obtains condensed water, and condensed water returns in boiler (13) Heating coil is vaporized into steam.
Embodiment 3
The device of embodiment 3 is same as Example 1.
Using a kind of oil sands bitumen that the oil sands bitumen extraction element based on the extraction of thermokalite water extracted based on thermokalite water Extracting method is that oil-sand raw material feeding ore crusher (1) is crushed, 100 mesh of grain diameter of broken oil-sand raw material, Broken oil-sand raw material enters the first mixing channel (2);Recirculated water from the 5th pipeline and the waste liquid from crystallization kettle (15) Also enter the first mixing channel (2);Oil-sand raw material, recirculated water and waste liquid obtain mixture after mixing in the first mixing channel (2), mix It closes after material enters the first threeway and mixes with the circulation mixture from the second jacket type screw conveyor (4) through the first collet Formula screw conveyor (3) obtains pretreatment material;The temperature of pretreatment material is 90 DEG C;Pretreatment material is divided into first and second bursts of pre- places Reason material, the volume flow ratio of first and second strands of pretreatment material are 1:8, and first strand of pretreatment material enters settling tank (5), second strand Pretreatment material is by obtaining circulation mixture after the second jacket type screw conveyor (4);Mixture, circulation mixture and the two Mixture when by the first and second jacket type screw conveyors, the oil under the collective effect of collet heating and screw extruding The pitch of sand particle surface attachment sheds into water;First and second jacket type screw conveyors and connecting pipeline constitute The circulatory system can increase the residence time and then improve pitch removal effect;First strand of pretreatment material sinks in settling tank (5) Drop, split-phase, top obtains primary bitumen, middle part obtains water, bottom obtains rough sand, and primary bitumen enters the second mixing channel (6), water By being divided into first and second strands of water after third threeway, the volume flow ratio of first and second strands of water is 1:2 ~ 5, first strand of water into Enter the second mixing channel (6), the second water stock enters the 4th threeway and mixes with the condensed water from the second jacket type screw conveyor (4) After enter back into the 5th threeway and supplement buck is mixed to get recirculated water, supplement the sodium hydroxide for being 6% containing mass fraction in buck The neopelex for being 1% with mass fraction;Rough sand is discharged into sand storage tank (12);Come the extractant of condenser (9) also into Enter the second mixing channel (6);Extractant is the mixture of toluene and methylene chloride, and wherein the mass ratio of toluene and methylene chloride is 5:1;Primary bitumen, first strand of water and extractant, which are stirred in the second mixing channel (6), to be entered back into defecator (7) and is divided Phase obtains oily phase and water phase;Oily is mutually the mixture of primary bitumen and extractant, and the water phase is the mixing of water and a small amount of fine sand Object;Oily mutually enter extractant recovery tower (8) carry out rectifying, and tower top obtains extractant, and tower reactor obtains pitch;Extractant enters condensation Device (9) condenses to 25 DEG C;Water phase enters the isolated fine sand of centrifuge (10) progress and alkaline water, fine sand enter sand storage tank (12), the hydrochloric acid that alkaline water enters neutralization chamber (11) and is added is neutralized to pH=7 and obtains salt water;Salt water enters evaporator (14) steaming It sends out and obtains secondary steam and concentrate, the mass ratio of secondary steam and concentrate is 1.5:1, and concentrate enters crystallization kettle (15) Cooling, crystallization obtain salt and waste water, and secondary steam passes through the chuck layer of the first jacket type screw conveyor (3), then passes through second The chuck layer of jacket type screw conveyor (4) obtains condensed water;The burner hearth that sand in sand storage tank (12) enters boiler (13) is fiery Flame burns, and burn-up grains of sand pitch remained on surface obtains dry gravel, dry gravel discharge boiler (13);In boiler (13) The steam that generates of heating coil enter the evaporation coil of evaporator (14) and obtain condensed water, condensed water returns in boiler (13) Heating coil be vaporized into steam.
Embodiment 4
The device of embodiment 4 is same as Example 1.
Using a kind of oil sands bitumen that the oil sands bitumen extraction element based on the extraction of thermokalite water extracted based on thermokalite water Extracting method is that oil-sand raw material feeding ore crusher (1) is crushed, and 80 mesh of grain diameter of broken oil-sand raw material is broken Oil-sand raw material after broken enters the first mixing channel (2);Recirculated water from the 5th pipeline and the waste liquid from crystallization kettle (15) Into the first mixing channel (2);Oil-sand raw material, recirculated water and waste liquid obtain mixture after mixing in the first mixing channel (2), mix Material enters the first threeway and passes through the first jacket type after mixing with the circulation mixture from the second jacket type screw conveyor (4) Screw conveyor (3) obtains pretreatment material;The temperature of pretreatment material is 96 DEG C;Pretreatment material is divided into first and second bursts of pretreatments Material, the volume flow ratio of first and second strands of pretreatment material are 1:4, and first strand of pretreatment material enters settling tank (5), and second strand pre- Processing material is by obtaining circulation mixture after the second jacket type screw conveyor (4);Mixture, circulation mixture and the two Mixture is when by the first and second jacket type screw conveyors, the oil-sand under the collective effect of collet heating and screw extruding The pitch of particle surface attachment sheds into water;First and second jacket type screw conveyors and connecting pipeline are constituted and are followed Loop system can increase the residence time and then improve pitch removal effect;First burst of pretreatment material in settling tank (5) sedimentation, Split-phase, top obtains primary bitumen, middle part obtains water, bottom obtains rough sand, and primary bitumen enters the second mixing channel (6), and water is logical It crosses after third threeway and is divided into first and second strands of water, the volume flow ratio of first and second strands of water is 1:3, and first strand of water enters the Two mixing channels (6), the second water stock enter after the 4th threeway is mixed with the condensed water from the second jacket type screw conveyor (4) again It is mixed to get recirculated water into the 5th threeway and supplement buck, supplements the sodium hydroxide for being 7% containing mass fraction in buck and matter Measure the neopelex that score is 1.2%;Rough sand is discharged into sand storage tank (12);The extractant for carrying out condenser (9) also enters Second mixing channel (6);Extractant be toluene and methylene chloride mixture, wherein the mass ratio of toluene and methylene chloride be 2 ~ 5:1;Primary bitumen, first strand of water and extractant, which are stirred in the second mixing channel (6), to be entered back into defecator (7) and is divided Phase obtains oily phase and water phase;Oily is mutually the mixture of primary bitumen and extractant, and the water phase is the mixing of water and a small amount of fine sand Object;Oily mutually enter extractant recovery tower (8) carry out rectifying, and tower top obtains extractant, and tower reactor obtains pitch;Extractant enters condensation Device (9) condenses to 25 DEG C;Water phase enters the isolated fine sand of centrifuge (10) progress and alkaline water, fine sand enter sand storage tank (12), the hydrochloric acid that alkaline water enters neutralization chamber (11) and is added is neutralized to pH=7 and obtains salt water;Salt water enters evaporator (14) steaming It sends out and obtains secondary steam and concentrate, the mass ratio of secondary steam and concentrate is 1:1, and concentrate enters crystallization kettle (15) drop Temperature, crystallization obtain salt and waste water, and secondary steam passes through the chuck layer of the first jacket type screw conveyor (3), then passes through the second folder The chuck layer of shell type screw conveyor (4) obtains condensed water;Sand in sand storage tank (12) enters the burner hearth of boiler (13) by flame It burns, burn-up grains of sand pitch remained on surface obtains dry gravel, dry gravel discharge boiler (13);In boiler (13) The evaporation coil that the steam that heating coil generates enters evaporator (14) obtains condensed water, and condensed water returns in boiler (13) Heating coil is vaporized into steam.

Claims (1)

1. a kind of oil sands bitumen extraction element based on the extraction of thermokalite water, including ore crusher (1), the first mixing channel (2), the One jacket type screw conveyor (3), the second jacket type screw conveyor (4), settling tank (5), the second mixing channel (6), defecator (7), extractant recovery tower (8), condenser (9), centrifuge (10), neutralization chamber (11), sand storage tank (12), boiler (13), evaporation Device (14), crystallization kettle (15) and relevant feedstocks pipeline and the pipeline for connecting the above equipment;
The first jacket type screw conveyor (3) is identical with the structure of the second jacket type screw conveyor (4), be equipped with into Mouth, outlet, collet import and jacket outlet;The top of the settling tank (5) is equipped with row's pitch mouth, side middle position is equipped with Import and water out, bottom are equipped with sediment ejection opening;The defecator (7) is equipped with import, oil mutually outlet and water phase outlet;Described Extractant recovery tower (8) is equipped with import, tower top outlet, tower reactor outlet;The centrifuge (10) is equipped with import, discharge outlet and row Husky mouth;The boiler (13) is equipped with husky import, husky outlet, and inside is equipped with heating coil, and the both ends of heating coil are respectively water Import and steam (vapor) outlet, use natural gas for fuel;Evaporation coil, the both ends of evaporation coil are equipped in the evaporator (14) Respectively steam inlet and condensation-water drain are additionally provided with import, concentrated solution outlet, secondary steam outlet;The crystallization kettle (15) mother liquor import, salt outlet and waste liquid outlet are equipped with;
The ore crusher (1) is connected to by pipeline with the first mixing channel (2);First mixing channel (2) passes through pipe Line is divided into two-way pipeline after being connected to the first threeway, all the way the inlet communication of pipeline and the first jacket type screw conveyor (3), separately The outlet of pipeline and the second jacket type screw conveyor (4) all the way;The first jacket type screw conveyor (3) goes out Mouth is divided into two-way pipeline after being connected to by pipeline with the second threeway, all the way the inlet communication of pipeline and settling tank (5), another way pipe The inlet communication of line and the second jacket type screw conveyor (4);Row's pitch mouth of the settling tank (5) passes through pipeline and second Mixing channel (6) connection;The water out of the settling tank (5) is divided into the first and second pipes after being connected to by pipeline with third threeway Line, the first pipeline are connected to the second mixing channel (6), after the second pipeline is connected to the 4th threeway and are divided into the third and fourth pipeline, Third pipeline is connected to the jacket outlet of the second jacket type screw conveyor (4), after the 4th pipeline is connected to the 5th threeway and is divided At the 5th and the 6th pipeline, the 5th pipeline is connected to the first mixing channel (2), and the 6th pipeline is to supplement buck pipeline;Described The sediment ejection opening of settling tank (5) is connected to by pipeline with sand storage tank (12);Second mixing channel (6) passes through pipeline and defecator (7) inlet communication;The water phase outlet of the defecator (7) passes through the inlet communication of pipeline and centrifuge (10);Described The oil inlet communication that mutually outlet passes through pipeline and extractant recovery tower (8) of defecator (7);The extractant recovery tower (8) Tower top outlet be connected to the second mixing channel (6) by pipeline, between extractant recovery tower (8) and the second mixing channel (6) Condenser (9) are provided on pipeline;The tower reactor outlet of the extractant recovery tower (8) is pitch outlet;It is described from The sediment ejection opening of scheming (10) is connected to by pipeline with sand storage tank (12), and discharge outlet is connected to by pipeline with neutralization chamber (11);It is described Neutralization chamber (11) pass through the inlet communication of pipeline and evaporator (14);The sand storage tank (12) passes through pipeline and boiler (13) Husky inlet communication;The steam (vapor) outlet of the boiler (13) is connected to by pipeline with the steam inlet of evaporator (14), water into Mouth is connected to by pipeline with the condensation-water drain of evaporator (14);The concentrated solution outlet of the evaporator (14) by pipeline with The mother liquor inlet communication of crystallization kettle (15), secondary steam outlet pass through the collet of pipeline and the first jacket type screw conveyor (3) Inlet communication;The jacket outlet of the first jacket type screw conveyor (3) passes through pipeline and the second jacket type helical feed The collet inlet communication of machine (4);The waste liquid outlet of the crystallization kettle (15) is connected to by pipeline with the first mixing channel (2).
CN201821025493.4U 2018-06-30 2018-06-30 A kind of oil sands bitumen extraction element based on the extraction of thermokalite water Active CN208362258U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821025493.4U CN208362258U (en) 2018-06-30 2018-06-30 A kind of oil sands bitumen extraction element based on the extraction of thermokalite water

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821025493.4U CN208362258U (en) 2018-06-30 2018-06-30 A kind of oil sands bitumen extraction element based on the extraction of thermokalite water

Publications (1)

Publication Number Publication Date
CN208362258U true CN208362258U (en) 2019-01-11

Family

ID=64927815

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821025493.4U Active CN208362258U (en) 2018-06-30 2018-06-30 A kind of oil sands bitumen extraction element based on the extraction of thermokalite water

Country Status (1)

Country Link
CN (1) CN208362258U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108587670A (en) * 2018-06-30 2018-09-28 宁波工程学院 A kind of oil sands bitumen extraction element and method based on the extraction of thermokalite water

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108587670A (en) * 2018-06-30 2018-09-28 宁波工程学院 A kind of oil sands bitumen extraction element and method based on the extraction of thermokalite water

Similar Documents

Publication Publication Date Title
CN101260308B (en) Separating agent for extracting asphalt from oil-sand
CN105693055B (en) A kind of method of greasy filth sub-prime gasification recycling
CN103739137B (en) The harmless treatment recovery method of oilfield sump oil and device
CN105349166A (en) Solvent separation method of oil sand
CN102925190A (en) Method and device for separating oil and sand
CN207193205U (en) The organic solvent continuous extraction system of tar sand oil
CN105498280A (en) Hydrophilic reversible solvent assisted oil-sand separation method
CN208362258U (en) A kind of oil sands bitumen extraction element based on the extraction of thermokalite water
CN103113912A (en) Method for separating and extracting crude oil from oil sand
CN107177367A (en) Oil-sand cavitation process technique
CN108587670A (en) A kind of oil sands bitumen extraction element and method based on the extraction of thermokalite water
CA2768522C (en) Processes for treating tailings streams from oil sands ore
CN105733642B (en) A kind of method for the double solvents and extraction that pitch is extracted for oil-sand
CN102010732B (en) Method and device for condensing and recovering shale oil in gas tower section of oil shale distillation system
CN109848177B (en) Oil field solid waste treatment agent and recycling treatment process
CN209292290U (en) A kind of oil-sand and greasy filth comprehensive utilization device
CA2915851C (en) Process for recovering bitumen from oil sands ore with aluminum-containing compounds
CN105349165B (en) The processing method of oil sand tailings after extracting pitch
CN108753338A (en) A kind of system obtaining pitch and construction sand from oil-sand
CN204111678U (en) The device of separated from solvent oil-sand
CN105925298B (en) A kind of method and system of the continuous separation and recovery rich in carbonate oil-sand ore deposit
CN203741274U (en) Oil-sand bitumen oil extraction device
CN205287697U (en) System for supplementary organic solvent separation oil sand of reversible auxiliary agent of hydrophilicity
CN109911960A (en) One kind pretreatment method for wastewater containing the dregs of fat and equipment
CN105462605A (en) Method for separating oil and sands by adopting mixed solvent

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant