CN208329592U - A kind of moving die plate for culvert walls pouring molding - Google Patents
A kind of moving die plate for culvert walls pouring molding Download PDFInfo
- Publication number
- CN208329592U CN208329592U CN201820935936.7U CN201820935936U CN208329592U CN 208329592 U CN208329592 U CN 208329592U CN 201820935936 U CN201820935936 U CN 201820935936U CN 208329592 U CN208329592 U CN 208329592U
- Authority
- CN
- China
- Prior art keywords
- riser
- cabinet
- plate
- pouring
- bottom end
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Sewage (AREA)
Abstract
The utility model discloses a kind of moving die plate for culvert walls pouring molding, it include be fastenedly connected by top plate, the riser of two sides and front end riser form pour cabinet;The rear end and bottom end for pouring cabinet are in Open architecture;The bottom end of riser is equipped with mobile pulley;Mobile pulley corresponds to each other clamping with the bottom end of riser by support base, and riser level is driven to slide.The utility model overall structure is simple, and production is low with use cost, reliable and stable.Respectively by fastening bolt or to drawing anchoring silk to be mutually fastenedly connected between top plate, the riser of two sides and front end riser, when disassembly, carries out certain release, guarantees that pine without de-, achievees the purpose that mutually relaxation is not detached from thoroughly mutually again, convenient for overall movement.After preceding lower plate disassembly, cabinet is poured by upper plate promotion before very heavy withstand, smoothly realization and the disengaging for pouring wall.Mobile pulley realizes that stable horizontal shifting, conveniently moving are quick.
Description
Technical field
The utility model belongs to culvert walls formwork for placing technical field, and in particular to one kind is poured for culvert walls and built up
The moving die plate of type.
Background technique
In the prior art, municipal sector needs to carry out pouring molding, tradition to the wall of culvert during culvert construction
Way be in a certain distance by adding template, then casting concrete molding dismantles template after molding to be cooled;So
Afterwards with the wall tandem array installation template that is cooled and shaped early period, to carry out the pouring molding of lower A set of wall.
This mode is widely used, but the time that wall is cooled and shaped needs is longer, and dismantles template and assembling
Template requires additionally to pay the time, causes work progress progress slow, and the construction speed of entire engineering is severely impacted;Often
Secondary dismounting needs for one and half time.Often second day afternoon after reaching disassembly template condition can just carry out all beam workers
Make, so that carry out next board concrete wall pours operation, working efficiency is seriously affected.
The dismounting of traditional construction template at least needs five to six workers to cooperate, according to present construction market
The price of each 200 yuan/day of worker calculates, and dismounts a template and needs 100 × 6 × 1.5=900 yuan of labour cost;Its
Secondary, present design and construction specification is required when constructing culvert walls template using large-scale combined template, is applied according to tradition
Work engineering method carry out dismounting requires using large-scale crane equip cooperation construct, according to every crane 800 yuan of One-Shift Costs/
Day calculates, and dismounting needs 800 × 1.5=1200 yuan of machinery expenses altogether every time.
To sum up, using traditional construction engineering method, the dismounting of each wall form needs artificial, machinery expenses to add up to 2100 yuan,
And entirely culvert is according to the difference of engineering target, short then several hundred rice are then several kilometers long, and every one of wall of culvert requires to carry out
The number of dismounting, entire culvert wall disassembly is very various, then the artificial and machine cost of entire engineering is very high, engineering
Cost is difficult to be effectively controlled.
Therefore, design that a kind of convenient disassembly is quick, the new type formwork that operation difficulty is low and construction cost is effectively reduced guarantees
The smooth quick completion of duration is to seem very necessary.
Summary of the invention
The purpose of this utility model be solve the disassembly assembling of above-mentioned template it is cumbersome it is bothersome, working efficiency is low and construction cost is high
The technical issues of, a kind of moving die plate for culvert walls pouring molding is provided, to change the deficiencies in the prior art.
In order to achieve the above object, the technical solution adopted in the utility model is:
A kind of moving die plate for culvert walls pouring molding, it includes being erected by top plate, the riser of two sides and front end
What plate was mutually fastenedly connected composition pours cabinet;
The rear end for pouring cabinet and bottom end are in Open architecture;The bottom end of the riser is equipped with mobile pulley;It is described
Mobile pulley corresponds to each other clamping with the bottom end of riser by support base, and riser level is driven to slide.
For the ease of loosening movement, pass through fastening bolt respectively between the top plate, the riser of two sides and front end riser
Or drawing anchoring silk is mutually fastenedly connected.
For the ease of construction, the front end riser is by preceding upper plate and front lower board group at and preceding upper plate and preceding lower plate are mutually tight
It is solidly connected.
The beneficial effects of the utility model are:
1, overall structure is simple, and production is low with use cost, reliable and stable.
2, it is mutually fastened by fastening bolt or to drawing anchoring silk respectively between top plate, the riser of two sides and front end riser
Connection, when disassembly, carry out certain release, guarantee that pine without de-, reaches top plate, the riser of two sides and front end riser phase
The mutually purpose that relaxation is not detached from thoroughly mutually again, convenient for moving integrally.
3, after preceding lower plate disassembly, cabinet is poured by upper plate promotion before very heavy withstand, smoothly realizes and pours wall
Disengaging.
4, mobile pulley is put into bottom when pouring cabinet and being promoted, and pours case by chain block or other modes pulling
Body realizes that stable horizontal shifting, conveniently moving are quick.
Detailed description of the invention
Attached drawing 1 is the structural representation perspective view of the utility model.
Attached drawing 2 is the using state structure diagram of the utility model.
1- pours before cabinet 2- riser 3- top plate 4- lower plate 6- support base 7- mobile pulley 8- before upper plate 5- in figure
Wall.
Specific embodiment
It is clearly and completely described below in conjunction with attached drawing 1 and 2 the technical solution of the utility model of attached drawing, it is clear that institute
The embodiment of description is the utility model a part of the embodiment, instead of all the embodiments.Based on the reality in the utility model
Example is applied, every other embodiment obtained by those of ordinary skill in the art without making creative efforts all belongs to
In the range of the utility model protection.
Referring to attached drawing 1 and attached drawing 2, the utility model it include mutual by top plate 3, the riser 2 of two sides and front end riser
Be fastenedly connected composition pours cabinet 1;
The rear end for pouring cabinet 1 and bottom end are in Open architecture;The bottom end of the riser 2 is equipped with mobile pulley 7;Institute
It states mobile pulley 7 and clamping is corresponded to each other with the bottom end of riser 2 by support base 6, and drive the horizontal sliding of riser 2.
For the ease of loosening movement, the top plate 3, two sides riser 2 and front end riser between pass through fastening spiral shell respectively
Bolt is mutually fastenedly connected drawing anchoring silk.
For the ease of construction, the front end riser is made of preceding upper plate 4 and preceding lower plate 5, and 5 phase of preceding upper plate 4 and preceding lower plate
Mutually it is fastenedly connected.
Working principle: what top plate 3, the riser 2 of two sides and front end riser were mutually fastenedly connected composition pours cabinet 1, pours
Open be bonded with ground in bottom end for building cabinet 1 contacts, and rear end is moved horizontally in open;It is preceding after 8 pouring molding of wall
Lower plate 5, which is removed, to be removed, and the bottom end of upper plate before jack is withstood gradually firmly jacks up and pours cabinet, makes to pour cabinet and wall
Between separate, and place mobile pulley;Top plate 3, the riser 2 of two sides and front end riser are mutually unclamped but be not thorough de- again
From level pulling pours cabinet 1 and integral translation can be realized.
The utility model specific operational sequence in the construction process are as follows: first plate culvert walls cabinet of constructing → pour loosens
Lower plate before → dismounting → upper plate → placement mobile pulley → pours cabinet monolithic stability and supports before jack jacks → pours cabinet
Horizontal displacement → dismounting mobile pulley → pours cabinet and re-secures board wall body concrete construction in place → next.
The utility model needs to be stopped the rear end for pouring cabinet with partition in the construction of first plate culvert wall,
It in this way can be by first plate culvert wall pouring molding;When the rear end of first wall molding after-pouring cabinet is without stopping, in horizontal position
When shifting, the rear end for pouring cabinet is corresponding with the front end of previous wall, and the head and the tail that can be achieved between wall in this way are corresponding
Pouring molding, entire culvert wall realize the operation purpose of head and the tail pouring molding.
The utility model structure is simple to operation, and the duration can be saved one day by dismounting template every time;Overall cost is very cheap,
Save considerable engineering cost;The composite assembly number for reducing template, reduces the possibility of template deformation, to control
Wall concrete quality has good effect;It does not need to employ big machinery, eliminates security risk when mechanical hoisting template,
Substantially increase the safety of construction personnel.
Above description is only a specific implementation of the present invention, but the protection scope of the utility model is not limited to
In this, anyone skilled in the art within the technical scope disclosed by the utility model, the change that can be readily occurred in
Change or replace, should be covered within the scope of the utility model.
Claims (3)
1. a kind of moving die plate for culvert walls pouring molding, it is characterized in that: it includes by the riser of top plate (3), two sides
(2) and front end riser be mutually fastenedly connected composition pour cabinet (1);
The rear end for pouring cabinet (1) and bottom end are in Open architecture;The bottom end of the riser (2) is equipped with mobile pulley (7);
The mobile pulley (7) corresponds to each other clamping with the bottom end of riser (2) by support base (6), and drives riser (2) horizontal sliding
It is dynamic.
2. a kind of moving die plate for culvert walls pouring molding according to claim 1, it is characterized in that the top plate
(3), it is mutually fastenedly connected by fastening bolt or to drawing anchoring silk respectively between the riser (2) and front end riser of two sides.
3. a kind of moving die plate for culvert walls pouring molding according to claim 1, it is characterized in that the front end
Riser is made of preceding upper plate (4) and preceding lower plate (5), and preceding upper plate (4) and preceding lower plate (5) are mutually fastenedly connected.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820935936.7U CN208329592U (en) | 2018-06-18 | 2018-06-18 | A kind of moving die plate for culvert walls pouring molding |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820935936.7U CN208329592U (en) | 2018-06-18 | 2018-06-18 | A kind of moving die plate for culvert walls pouring molding |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208329592U true CN208329592U (en) | 2019-01-04 |
Family
ID=64771663
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820935936.7U Expired - Fee Related CN208329592U (en) | 2018-06-18 | 2018-06-18 | A kind of moving die plate for culvert walls pouring molding |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208329592U (en) |
-
2018
- 2018-06-18 CN CN201820935936.7U patent/CN208329592U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102425140B (en) | Construction method for high-altitude arch closing | |
CN216380561U (en) | Supporting device for laminated floor with bottom die | |
CN111608662A (en) | Shaft oversized-diameter integral moving metal template | |
CN108468348B (en) | The porous piping lane construction technology of box quick assembly and disassembly mould | |
CN205276572U (en) | Novel double -deck prefabricated wall structure based on filling construction | |
CN208329592U (en) | A kind of moving die plate for culvert walls pouring molding | |
CN207747197U (en) | A kind of prefabricated wind power tower equipmentization mold of high-precision | |
CN218346803U (en) | Construction structure of inverted cone round barrel concrete structure | |
CN204552774U (en) | A kind of monolithic inverted arch mould bases of locating longitudinal waterstop | |
CN208201919U (en) | A kind of piping lane monoblock type, which is quickly pacified, tears aluminium alloy mould bases support construction open | |
CN109914476A (en) | A kind of construction technology of cast-in-place city integrated piping lane | |
CN206053965U (en) | A kind of tunnel ditch cable trough construction trolley | |
CN205928992U (en) | Prefabricated machine of mortar hollow brick | |
CN202672744U (en) | Turntable type concrete hopper for construction for super high-rise building | |
CN210732757U (en) | Interior gliding style high leakproofness prefabricated staircase mould | |
CN210658449U (en) | Remove aluminum alloy template structure | |
CN110606435B (en) | Suspension type electric hoist suitable for reverse construction method soil taking port transferring materials | |
CN209352419U (en) | A kind of composite beam hanging beam | |
CN208632967U (en) | A kind of high pier concrete-pouring template | |
CN209394930U (en) | A kind of assembled wallboard formwork erection casting platform | |
CN110093988A (en) | A kind of precast concrete | |
CN107022956B (en) | A kind of bridge pier column steel form climbing system and its implementation method | |
CN101509380B (en) | Ultra-large diameter integral slide metal matrix for vertical shaft well bore concrete construction | |
CN112575812B (en) | Inner support conversion system applied to demolition and transformation project and construction method thereof | |
CN215887968U (en) | Non-pressure box culvert concrete slip aluminum alloy template device that shears |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190104 |