CN208326391U - A kind of pipeline mounting device - Google Patents
A kind of pipeline mounting device Download PDFInfo
- Publication number
- CN208326391U CN208326391U CN201820544678.XU CN201820544678U CN208326391U CN 208326391 U CN208326391 U CN 208326391U CN 201820544678 U CN201820544678 U CN 201820544678U CN 208326391 U CN208326391 U CN 208326391U
- Authority
- CN
- China
- Prior art keywords
- pipeline
- piping lane
- roll row
- steel construction
- roller
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The utility model discloses a kind of pipeline mounting devices, by the way that power roll row and conveying roller are both secured on piping lane steel construction to be installed, conveying roller is arranged at intervals on piping lane steel construction to be installed, power roll row and conveying roller include roller bearing and bearing block, roller bearing both ends are mounted on bearing block by bearing, bearing block is fixed on piping lane steel construction to be installed by steel plate clamp, roller bearing one end of power roll row is driven by driving device, it further include the conduit bracket for fixing pipeline to be installed, conduit bracket is fixed on piping lane steel construction to be installed, utilize pipe riser, pipeline section is promoted to operation platform, counterpart is carried out using special pipeline roll row, welding, the conveying of pipeline integral level is carried out using pipeline roller, the above process is repeated until Pipe installing is completed, roller is replaced with conduit bracket, complete Pipe installing Work, forms assembly line construction, personnel's Fixed Point Operation, and machinery repeats lifting movement, high production efficiency, reliable welding quality.
Description
Technical field
The utility model relates to technical field of pipeline construction, and in particular to pipeline roller conveys installation engineering method.
Background technique
" installation " in construction project is the concept of one " big installation ", it includes civilian, public and Industrial Engineering
In the systems such as various kinds of equipment, electric appliance, communication, fire-fighting, HVAC, plumbing, automatic control installation.Therefore its face that is related to is
Very extensive, and versatility is very strong.Especially at this stage with the development of economy, the continuous improvement of scientific and technological level,
The development of electronics and information industry construction is also getting faster.The technology of electromechanical installation is used as and directly affects production line integral device
It is safely operated and uses function key factor, through among the work progress of entire construction project, and gradually by people
Concern.Social development be unable to do without construction, builds and be unable to do without installation.
Electromechanical installation enterprises are wanted to establish oneself in an unassailable position in increasingly keen competition existing it is necessary to understand electromechanical installation industry
Shape holds industry future thrust, updates upgrading construction equipment, required new technology, new process is grasped early, for electromechanics
The management of installing engineering should also constantly improve.With the development of the society, installation industry tend to integrated, intelligent, modularization,
Enlargement development, past mounting technique have been unsatisfactory for market now.Conventional outdoor steel structure piping lane Pipe installing uses
Crane cooperation is artificial, and installation procedure of following the prescribed order, mechanical one-shift utilization rate is low, and labour cost is high and safety coefficient is low, matter of constructing
Amount cannot be guaranteed, and in steelframe pipe network structure, carries out pipeline, be typically necessary and manually carry out dragging movement, increase
The labor intensity of worker, while increasing installation danger coefficient.
Utility model content
The purpose of this utility model is to provide a kind of pipeline mounting devices, with overcome the deficiencies in the prior art.
In order to achieve the above objectives, the utility model adopts the following technical solution:
A kind of pipeline mounting device, including power roll row and conveying roller, power roll row and conveying roller are fixed
In on piping lane steel construction to be installed, conveying roller is arranged at intervals on piping lane steel construction to be installed, power roll row and conveying roller
It include roller bearing and bearing block, roller bearing both ends are mounted on bearing block by bearing, and bearing block is fixed on by steel plate clamp wait pacify
On tubulature corridor steel construction, it further includes for fixing pipeline to be installed that roller bearing one end of power roll row is driven by driving device
Conduit bracket, conduit bracket are fixed on piping lane steel construction to be installed.
Further, wherein power roll row and conveying roller are installed on same straight line, two neighboring conveying roller it
Between be at least spaced a piping lane steel structure girder to be installed.
Further, tooth of the driving device driving including driving motor and roller bearing (4) one end for being fixed on power roll row
Wheel.
Further, piping lane steel construction to be installed be equipped with no less than two power roll rows, two neighboring power roll row it
Between pass through chain pitch wheel drive.
Further, power roll row is fixedly installed in the end of piping lane steel construction to be installed.
Further, roller bearing is equipped with cone rubber set.
Further, piping lane steel construction to be installed is being set equipped with power roll row one end equipped with pipeline canopy to be installed.
Compared with prior art, the utility model has technical effect beneficial below:
A kind of pipeline mounting device of the utility model, it is to be installed by the way that power roll row and conveying roller to be both secured to
On piping lane steel construction, conveying roller is arranged at intervals on piping lane steel construction to be installed, and power roll row and conveying roller include rolling
Axis and bearing block, roller bearing both ends are mounted on bearing block by bearing, and bearing block is fixed on piping lane steel to be installed by steel plate clamp
In structure, it further includes the conduit bracket for fixing pipeline to be installed that roller bearing one end of power roll row is driven by driving device,
Conduit bracket is fixed on piping lane steel construction to be installed, using pipe riser, promotes pipeline section to operation platform, utilization is special
Pipeline roll row carries out counterpart, welding, carries out the conveying of pipeline integral level using pipeline roller, repeats the above process until pipeline is pacified
It installs into, replaces roller with pipe insulation bracket, complete pipe fitting, form assembly line construction, personnel's Fixed Point Operation, machine
Tool repeats lifting movement, high production efficiency, reliable welding quality.
Detailed description of the invention
Fig. 1 is the utility model mounting structure top view.
Fig. 2 is the utility model mounting structure main view.
Fig. 3 is the utility model mounting structure side view.
Fig. 4 be in Fig. 2 A to partial enlarged view.
Wherein, 1, power roll row;2, conveying roller;3, piping lane steel construction to be installed;4, roller bearing;5, bearing block;6, steel plate
Card;7, gear;8, conduit bracket;9, cone rubber set;10, pipeline canopy to be installed;11, pipeline to be installed;12, job platform.
Specific embodiment
The utility model is described in further detail with reference to the accompanying drawing:
As shown in Figures 1 to 4, a kind of pipeline mounting device, including power roll row 1 and conveying roller 2, power roll row
1 and conveying roller 2 be both secured on piping lane steel construction 3 to be installed, conveying roller 2 is arranged at intervals on piping lane steel construction 3 to be installed
On, power roll row 1 and conveying roller 2 include roller bearing 4 and bearing block 5, and 4 both ends of roller bearing are mounted on bearing block 5 by bearing,
Bearing block 5 is fixed on piping lane steel construction 3 to be installed by steel plate clamp 6, and 4 one end of roller bearing of power roll row 1 is fixed with gear 7,
Gear 7 further includes the conduit bracket 8 for fixing pipeline 11 to be installed by 8 chain drive of driving motor, and conduit bracket 8 is solid
Due on piping lane steel construction 3 to be installed.
Wherein power roll row 1 and conveying roller 2 are installed on same straight line, between two neighboring conveying roller 2 at least
It is spaced 3 beam of piping lane steel construction to be installed, convenient for the fixed installation of conduit bracket 8 and pipeline to be installed.
Piping lane steel construction 3 to be installed is equipped with no less than two power roll rows 1, passes through between two neighboring power roll row 1
Chain pitch wheel driving.
Power roll row 1 is fixedly installed in the end of piping lane steel construction 3 to be installed;
Roller bearing 4 is equipped with cone rubber set 9.
Specifically, being equipped with 1 one end of power roll row equipped with pipeline canopy 10 to be installed piping lane steel construction 3 to be installed is arranged.
It is described further with reference to the accompanying drawing to the structural principle of the utility model and using step:
The following steps are included:
Power roll row 1 and the interval of conveying roller 2 are fixed on piping lane steel construction 3 to be installed by step 1), make power roll row
1 and conveying roller 2 be located on the same line;
Step 2), using boom hoisting by Pipeline lift to be installed to parallel with power roll row 1, by pipeline one end to be installed
It rides in power roll row 1, is rotated by motor driven power roll row 1, realize pipeline longitudinal movement to be installed;
Step 3) after welding first pipeline to be installed and second pipeline to be installed, is realized and is moved integrally, successively real
Now back pipeline and installation;
After the completion of step 4), pipeline to be installed welding, on the piping lane steel construction 3 to be installed of two neighboring conveying roller 2
Pipeline 11 to be installed is fixed on piping lane steel construction 3 to be installed using conduit bracket 8, then mobile removal conveying roller 2, from
And realize the fixed installation of pipeline to be installed.
In step 3), by first pipeline to be installed it is in place after, by second pipeline to be installed lifting with first wait pacify
It after tubulature road is concordant, is welded, after the completion of to be welded, then carries out pipeline longitudinal movement to be installed, can effectively prevent wait pacify
Sideslip in tubulature road moving process.
In step 3), before two pipeline welding to be installed, first passes through pipe butt joint apparatus progress pipe string and fix, prevent
Only pipeline sideslip to be installed in welding process.
Job platform 12 is had in power roll row 1, welds nozzle and operation convenient for worker;
Pipeline is carried out using roll row, carries motor driven using pipeline roll row, the promotion of previous procedure is managed in place
Road carries out horizontal sliding, and pipe level position is made to join end to end with preceding pipeline section, carries out pipe string using pipe butt joint apparatus, makes pipe
Road installation of modular, flow line production, construction personnel moves with Pipe installing progress during avoiding conventional construction method
Dynamic drawback, effectively improves tube group butt welding installation quality, construction personnel's personal safety is secure;
This engineering method is directed to outdoor steel structure piping lane feature, promotes pipeline section using pipe riser using its high structures
To operation platform, counterpart, welding are carried out using special pipeline roll row, carries out the conveying of pipeline integral level, weight using pipeline roller
The multiple above process is until Pipe installing is completed, and with pipe insulation bracket replacement roller, completion pipe fitting forms assembly line
Construction, personnel's Fixed Point Operation, machinery repeat lifting movement, high production efficiency, reliable welding quality.
Claims (7)
1. a kind of pipeline mounting device, which is characterized in that including power roll row (1) and conveying roller (2), power roll row
(1) it is both secured on piping lane steel construction (3) to be installed with conveying roller (2), conveying roller (2) is arranged at intervals on piping lane to be installed
On steel construction (3), power roll row (1) and conveying roller (2) include roller bearing (4) and bearing block (5), and roller bearing (4) both ends pass through
Bearing is mounted on bearing block (5), and bearing block (5) is fixed on piping lane steel construction (3) to be installed by steel plate clamp (6), power
Roller bearing (4) one end of roll row (1) is driven by driving device, further includes the conduit bracket for fixing pipeline to be installed (11)
(8), conduit bracket (8) is fixed on piping lane steel construction (3) to be installed.
2. a kind of pipeline mounting device according to claim 1, which is characterized in that wherein power roll row (1) and conveying
Idler wheel (2) is installed on same straight line, and a piping lane steel construction to be installed is at least spaced between two neighboring conveying roller (2)
(3) beam.
3. a kind of pipeline mounting device according to claim 1, which is characterized in that driving device driving includes driving electricity
Machine and be fixed on power roll row (1) roller bearing (4) one end gear (7).
4. a kind of pipeline mounting device according to claim 2, which is characterized in that on piping lane steel construction (3) to be installed
Equipped with no less than two power roll rows (1), driven between two neighboring power roll row (1) by chain pitch wheel.
5. a kind of pipeline mounting device according to claim 1, which is characterized in that power roll row (1) is fixedly installed in
The end of piping lane steel construction (3) to be installed.
6. a kind of pipeline mounting device according to claim 1, which is characterized in that roller bearing (4) is equipped with cone rubber
It covers (9).
7. a kind of pipeline mounting device according to claim 1, which is characterized in that piping lane steel construction to be installed is being arranged
(1) it is equipped with power roll row (1) one end and is equipped with pipeline canopy (10) to be installed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820544678.XU CN208326391U (en) | 2018-04-17 | 2018-04-17 | A kind of pipeline mounting device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820544678.XU CN208326391U (en) | 2018-04-17 | 2018-04-17 | A kind of pipeline mounting device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208326391U true CN208326391U (en) | 2019-01-04 |
Family
ID=64781731
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820544678.XU Active CN208326391U (en) | 2018-04-17 | 2018-04-17 | A kind of pipeline mounting device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208326391U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110306420A (en) * | 2019-06-29 | 2019-10-08 | 中国二十二冶集团有限公司 | Pipe bridge interior conduit transport device and its construction method |
-
2018
- 2018-04-17 CN CN201820544678.XU patent/CN208326391U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110306420A (en) * | 2019-06-29 | 2019-10-08 | 中国二十二冶集团有限公司 | Pipe bridge interior conduit transport device and its construction method |
CN110306420B (en) * | 2019-06-29 | 2024-04-12 | 中国二十二冶集团有限公司 | Pipe transportation device in pipe bridge and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106013233B (en) | Sliding system and its construction method for underground pipe gallery cast-in-place construction | |
CN104528500A (en) | Double-platform scaffold-free elevator installation method | |
CN102720432A (en) | Self-propelled underground boring jumbo | |
CN208326391U (en) | A kind of pipeline mounting device | |
CN108343783B (en) | The installation method and hanging apparatus of high-altitude large-diameter pipeline under complex environment | |
CN101255942B (en) | Automatic spraying attachment for on-site complete overhaul of pipe | |
CN101774092A (en) | Large steel tube technology and equipment | |
CN211545873U (en) | Boiler tube mounting tool | |
CN202116985U (en) | Automatic traveling system of hanging basket | |
CN108482940A (en) | A kind of pipeline mounting device and installation method | |
CN205169563U (en) | Chain scraper conveyor | |
CN114986048B (en) | Automatic pipeline welding device and installation and construction method | |
CN103612983A (en) | Underground coal mine self-moving type electric monorail crane | |
CN111173305A (en) | Sliding device for dust removal pipeline with newly increased diameter in old factory building in narrow space and using method | |
CN203624851U (en) | Self-moving electric monorail hoist in coal mine | |
CN204001778U (en) | New mobile type Semi-automatic combination formula steel stranded wire penetrating adapter all-in-one | |
CN210213802U (en) | Device for conveying concrete pipe in sleeve | |
CN202249006U (en) | Self-moving type steel structure workshop | |
CN203404486U (en) | Hydraulic pipeline installation machine | |
CN110652753A (en) | Automatic cleaning device and method for inclined plate sedimentation tank of converter | |
CN217451474U (en) | Contaminated site removes restoration treatment system | |
CN211922709U (en) | Bogie frame | |
CN211308558U (en) | Sliding trolley for installing air pipe in limited area | |
CN220226919U (en) | Shield split originating pipeline extension self-moving device | |
CN219806264U (en) | Concrete processing spraying equipment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |