CN208310282U - A kind of structure demolition works combined type auxiliary tool - Google Patents
A kind of structure demolition works combined type auxiliary tool Download PDFInfo
- Publication number
- CN208310282U CN208310282U CN201820340646.8U CN201820340646U CN208310282U CN 208310282 U CN208310282 U CN 208310282U CN 201820340646 U CN201820340646 U CN 201820340646U CN 208310282 U CN208310282 U CN 208310282U
- Authority
- CN
- China
- Prior art keywords
- steel plate
- fork
- hole
- steel
- combined type
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Forklifts And Lifting Vehicles (AREA)
Abstract
The utility model discloses a kind of structure demolition works combined type auxiliary tools, wedge-shaped iron block including fork of forklift truck, for releasing fork of forklift truck inclination angle, at least one be used to be promoted the standard knot of fork height of fork truck;Wedge-shaped iron block is set on fork of forklift truck, and standard knot is set on wedge-shaped iron block;Standard knot include the cuboid being made of angle steel and positioned at cuboid tiltedly to the oblique angle steel in payment to a porter;Cuboid includes being located at bottom surface to constitute rectangular four the first angle steel, constitute rectangular four the second angle steel, the third angle steel between bottom surface and top surface positioned at top surface;Oblique angle steel by fixation steel plate respectively with the first angle steel, the second Bolted angle connection;The beneficial effects of the utility model are: by design it is knockdown increase standard knot realize operation height promoted, can according to operation height voluntarily selection criteria joint number amount substantially increase fork truck cooperation dismounting structure component using height, flexibly it is convenient.
Description
Technical field
The utility model belongs to technical field of building construction, and in particular to a kind of structure demolition works combined type backman
Tool.
Background technique
The common concrete structure method for dismounting of common buildings have manually beat tear open, big gun machine beat tear open, be cut and disassembled, demolition blasting
Deng.When removing the components such as beam, plate using cutting disassembling method, it is frequently subjected to the restriction of handling condition.To current cutting disassembling
The main construction of method is analyzed as follows:
Component to be torn open directly is hung using vertical transportation machinery (tower crane, loop wheel machine etc.), after cutting tool cutting separation, directly
It connects and hangs away.Its advantage is that it is highly-safe, preliminary preparation is less, the lifting scale of construction is larger, it is straight generally will directly to remove component
It connects and transports outside the venue;The disadvantage is that requiring to have vertical transport condition and having certain elevating capacity, occupied to vertical transportation machinery
Time long influence project process.
Bottle gouard moved by hands is used using expansion bolt installation anchor slab as suspension centre using peripheral structure component as auxiliary suspension centre
Suspension centre and component to be torn open are connected, after cutting tool cutting separation, dismounting component is slowly put into ground with bottle gouard moved by hands and is transported
Outside the venue.Its advantage is that being not seriously limited by the site;The disadvantage is that preparation is cumbersome, low efficiency, risk are high, is easy to damage anchor point
Structure.
Using fork truck support component to be torn open, after cutting tool separates, declines fork of forklift truck, component is transported outside the venue.Its
Advantage is that preliminary preparation is few, transport is flexible;The disadvantage is that the pallet fork lifting altitude by fork truck is limited operation height, by fork truck
Sideboard obstruction is difficult to remove the planar plate members such as floor.
Utility model content
The purpose of the utility model is to overcome the defects of the prior art, provide a kind of structure demolition works combined type backman
Tool solves the technical issues of pallet fork lifting altitude limitation operation height of fork truck.
To solve the above-mentioned problems, the utility model is achieved by following technical scheme:
A kind of structure demolition works combined type auxiliary tool, including fork of forklift truck, for releasing the fork of forklift truck inclination angle
Wedge-shaped iron block, at least one is used to promote the standard knot of fork of forklift truck support height;The wedge shape iron block is set to the fork
On vehicle pallet fork, the standard knot is set on the wedge-shaped iron block;The standard knot includes the cuboid being made of angle steel and position
In the cuboid tiltedly to the oblique angle steel in payment to a porter;The cuboid includes being located at bottom surface to constitute rectangular four first jiao
Steel constitutes rectangular four the second angle steel, the third angle steel between the bottom surface and the top surface positioned at top surface;It is described
Oblique angle steel by fixation steel plate respectively with first angle steel, second Bolted angle connection.
More preferably, the both ends of the third angle steel are provided with the angle cleat for connection, the angle cleat
Top is provided with the first hole.
More preferably, the cuboid one side opposite with the fork truck is equipped with to climb and mark time, described to climb two to mark time
End is fixed on the third angle steel.
More preferably, first hole is passed through by the first screw rod between the standard knot and carries out bolt and nut connection.
It more preferably, further include the first steel plate, the second steel plate and the second screw rod, first steel plate is set to the wedge-shaped iron
Between block and the standard knot, first steel plate is equipped with the second hole;Second steel plate is located at the bottom of the fork of forklift truck
Portion, second steel plate are equipped with third hole corresponding with second hole, and second screw rod passes through second hole and institute
It states third hole and carries out bolt and nut connection.
More preferably, further include third screw rod, the 4th hole is set with first hole corresponding position on first steel plate, it is described
Third screw rod passes through first hole and connects with the 4th hole progress nut.
It more preferably, further include third steel plate and the guardrail for manual work;The third steel plate is set to the standard
On the top of section;The guardrail is set on the third steel plate, and guardrail surrounds one week.
It more preferably, further include skirting board, the skirting board is set on the third steel plate, and is located in the guardrail.
It more preferably, further include the 4th screw rod, the third steel plate is equipped with the 5th hole corresponding with first hole, described
4th screw rod passes through the 5th hole and connects with first hole progress bolt and nut.
It more preferably, further include third steel plate and channel steel, the third steel plate is set on the top of the standard knot, described
Channel steel is set on the third steel plate.
The beneficial effects of the utility model are:
1, wedge-shaped iron block and standard knot are set on fork of forklift truck, makes full use of the operation flexibility of fork truck, properly increases
Fork of forklift truck can support height, expand the scope of application;The obstruction of fork truck sideboard is solved the problems, such as, so that fork truck bearing dismounting method is same
Slab construction suitable for floor class;In the state of forbidding fork truck mobile and lifting, in conjunction with safety requirements, trouble free service is doubled as
Platform uses, and carries out such as drilling, nailing, wears cable wire light weight operation, greatly improves the efficiency of Demolition Construction.
2, the support height for improving fork truck disassembly component solves pallet fork divider and asks the obstruction for removing slab construction
Topic uses the efficiency for improving Demolition Construction as safe work platform.
3, it realizes that operation height is promoted by designing knockdown standard knot of increasing, can voluntarily select to mark according to operation height
Quasi- joint number amount substantially increases the height that uses of fork truck cooperation dismounting structure component, flexibly convenient.
4, top installation third steel plate installs guardrail as platform, can set as safe work platform in each standard knot
It sets climbing to mark time, without in addition setting operating platform, improve efficiency.
Detailed description of the invention
Fig. 1 is the main view of the utility model structure demolition works combined type auxiliary tool embodiment one;
Fig. 2 is the A-A cross-sectional view of Fig. 1 in the utility model structure demolition works combined type auxiliary tool;
Fig. 3 is the main view of the utility model structure demolition works combined type auxiliary tool standard knot;
Fig. 4 is the top view of the utility model structure demolition works combined type auxiliary tool standard knot;
Fig. 5 is the plan view of the utility model structure demolition works combined type the first steel plate of auxiliary tool;
Fig. 6 is the plan view of the utility model structure demolition works combined type the second steel plate of auxiliary tool;
Fig. 7 is the main view of the utility model structure demolition works combined type auxiliary tool embodiment two.
Wherein:
1- fork of forklift truck, 2- wedge shape iron block, 3- standard knot, 31- cuboid, the first angle steel of 311-, the second angle steel of 312-,
313- third angle steel, the oblique angle 32- steel, 33- fixation steel plate, 34- angle cleat, the first hole 341-, 35- climbing is marked time, 4- is pitched
Vehicle, the first screw rod of 5-, the first steel plate of 6-, the second hole 61-, the 4th hole 62-, the second steel plate of 7-, 71- third hole, the second spiral shell of 8-
Bar, 9- third screw rod, 10- third steel plate, 11- guardrail, 12- skirting board, the 4th screw rod of 13-, 14- channel steel, 15- component to be torn open,
16- I-steel.
Specific embodiment
It is illustrated below in conjunction with preferred embodiment of the attached drawing to the utility model, it should be understood that described herein excellent
It selects embodiment to be only used for describing and explaining the present invention, is not used to limit the utility model.
Embodiment one
As shown in figures 1 to 6, the utility model provides a kind of structure demolition works combined type auxiliary tool, including fork of forklift truck
1, for releasing, the wedge-shaped iron block 2 at 1 inclination angle of fork of forklift truck, at least one is used to promote the standard knot of 1 support height of fork of forklift truck
3;Wedge-shaped iron block 2 is set on fork of forklift truck 1, and standard knot 3 is set on wedge-shaped iron block 2;Standard knot 3 includes being made of angle steel
Cuboid 31 and positioned at cuboid tiltedly to the oblique angle steel 32 in payment to a porter;Cuboid 31 includes being located at bottom surface to constitute rectangular four
First angle steel 311 constitutes rectangular four the second angle steel 312, the third angle steel between bottom surface and top surface positioned at top surface
313;Oblique angle steel 32 is connect with the first angle steel 311, the second angle steel 312 respectively by fixation steel plate 33.
The both ends of third angle steel 313 are provided with the angle cleat 34 for connection, the top setting of angle cleat 34
There is the first hole 341.
The one side opposite with fork truck 4 of cuboid 31, which is equipped with to climb, marks time 35, climbs 35 both ends of marking time and is fixed on third
On angle steel 313.
First hole 341 is passed through by the first screw rod 5 between standard knot 3 and carries out bolt and nut connection.
Structure demolition works combined type auxiliary tool further includes the first steel plate 6, the second steel plate 7 and the second screw rod 8, the first steel
Plate 6 is set between wedge-shaped iron block 2 and standard knot 3, and the first steel plate 6 is equipped with the second hole 61;Second steel plate 7 is located at fork truck goods
The bottom of fork 1, the second steel plate 7 are equipped with third hole 71 corresponding with the second hole 61, and the second screw rod 8 passes through the second hole 61 and the
Three holes 71 carry out bolt and nut connection.
Structure demolition works combined type auxiliary tool further includes third screw rod 9, corresponding with the first hole 341 on the first steel plate 6
Place the 4th hole 62 of setting, third screw rod 9 pass through the first hole 341 and connect with the 4th hole 62 progress nut.
Structure demolition works combined type auxiliary tool further includes third steel plate 10 and the guardrail 11 for manual work;Third
Steel plate 10 is set on the top of standard knot 3;Guardrail 11 is set on third steel plate 10, and guardrail 11 surrounds one week.
Structure demolition works combined type auxiliary tool further includes skirting board 12, and skirting board 12 is set on third steel plate 10,
And it is located in guardrail 11.
Structure demolition works combined type auxiliary tool further includes the 4th screw rod 13, and third steel plate 10 is equipped with and the first hole
341 corresponding 5th holes, the 4th screw rod 13 pass through the 5th hole and connect with the first hole 341 progress bolt and nut.
Embodiment two
As shown in fig. 7, the present embodiment and embodiment one the difference is that, structure demolition works combined type auxiliary tool
It further include third steel plate 10 and channel steel 14, third steel plate 10 is set on the top of standard knot 3, and channel steel 14 is set to third steel plate
On 10.
The installation steps of the utility model are as follows:
1, surveying setting-out determines the position of component 15 to be torn open, and determines component 15 to be torn open according to the elevating capacity of fork truck 4
Piecemeal size;
2, fork truck 4 is in place, and installs wedge-shaped iron block 2 to eliminate 1 inclination angle of fork of forklift truck.Fork truck 4 is in design in order to anti-
Only in brake or deceleration, cargo is slid forward, and fork of forklift truck 1 has 6 ° -13 ° of adjustable inclination angle, therefore first in fork of forklift truck 1
Top is laid with one piece of wedge-shaped iron block 2 to make levelling purposes.1 inclination angle of fork of forklift truck is adjusted to 9 ° or so, the bottom surface of wedge-shaped iron block 2 is set
Counting gradient is -9 °, is realized substantially after the two fitting levelling;
3, the first steel plate 6 of the 20mm of 1100 × 1100mm is laid with above wedge-shaped iron block 2.Have on first steel plate 6 multiple
The 4th hole 62 having a size of φ 10, the 4th hole 62 are fixed for wearing bolt.Wherein the second hole 61 of middle part is for wearing bolt fixation fork
Vehicle pallet fork 1 and wedge-shaped iron block 2, and play the role of limiting 2 lateral sliding of wedge-shaped iron block, due to the fork of forklift truck 1 of different model
Width and distance may be slightly changed, therefore the second hole 61 of different distance is arranged to adapt to change;
4, standard knot 3 is increased in installation, and standard knot 3 is having a size of 1000 × 1000 × 500mm, the first angle steel 311, the second angle steel
312, third angle steel 313 is all made of 50 × 50 × 5 angle steel production, and each face is arranged a bearing diagonal and reinforces, and all connection uses
The welding of 3mm fillet welding complete cycle.The top of angle cleat 34 is provided with the first hole, for the connection between standard knot 3;
5, need to select the quantity of installation standard knot 3 according to disassembly height.The quantity of standard knot 3 should not surpass 5 sections, and (height is small
In 3m, removal component 15 to be torn open after the completion of making convenient for cutter);
6, after standard knot 3 is installed, it is laid with one block of 5mm third steel plate 10 in the most top surface of standard knot 3, with bolt by third
The connection of 10 standard knot 3 of steel plate.It acts as upper people's operations to provide platform (if you need to), also can reinforced top stiffness of structural member;
7, if you need to upper people's operation, four-way guardrail 11 is installed at the top of standard knot 3, wherein side can open the door, and use with standard knot 3
It is bolted fixation.After the completion of preparation, guardrail 11 is removed, personnel return to ground;
8, after the completion of preparation, guardrail 11 is removed, two 14 (120*53* of 12# channel steel are installed on third steel plate 10
5.5), its role is to making spaces to allow fork truck 4 can self-unloading component 15 to be torn open.After completing installation, personnel return to ground;
9, inspection work is carried out.Check whether all bolts fasten, with spirit level check a whole set of auxiliary tool flatness,
Verticality is adjusted to smooth using the Inclination maneuver function of fork of forklift truck 1;
10, fork of forklift truck 1 jacks auxiliary tool to 15 bottom support of component to be torn open, carries out cutting work;
11, after tearing component 15 open by cutting separation, slowly decline fork of forklift truck 1, it is big with I-steel 16 or other rigidity
Material is padded on the bottom of the first steel plate 6, stablizes and unclamps bolt after laying flat, and discharges fork of forklift truck 1;
12, sky in 15 lower section channel steel 14 of component to be torn open is protruded into fork of forklift truck 1, forks the structural elements removed, it will
Component is removed to transport outside the venue.Assembling auxiliary external member again carries out next section of disassembly.
The beneficial effects of the utility model are:
1, wedge-shaped iron block and standard knot are set on fork of forklift truck, makes full use of the operation flexibility of fork truck, properly increases
Fork of forklift truck can support height, expand the scope of application;The obstruction of fork truck sideboard is solved the problems, such as, so that fork truck bearing dismounting method is same
Slab construction suitable for floor class;In the state of forbidding fork truck mobile and lifting, in conjunction with safety requirements, trouble free service is doubled as
Platform uses, and carries out such as drilling, nailing, wears cable wire light weight operation, greatly improves the efficiency of Demolition Construction.
2, the support height for improving fork truck disassembly component solves pallet fork divider and asks the obstruction for removing slab construction
Topic uses the efficiency for improving Demolition Construction as safe work platform.
3, it realizes that operation height is promoted by designing knockdown standard knot of increasing, can voluntarily select to mark according to operation height
Quasi- joint number amount substantially increases the height that uses of fork truck cooperation dismounting structure component, flexibly convenient.
4, top installation third steel plate installs guardrail as platform, can set as safe work platform in each standard knot
It sets climbing to mark time, without in addition setting operating platform, improve efficiency.
The above descriptions are merely preferred embodiments of the present invention, not makees in any form to the utility model
Limitation, therefore it is all without departing from the content of the technical scheme of the utility model, implement according to the technical essence of the utility model to above
Any modification, equivalent variations and modification, are still within the scope of the technical solutions of the present invention made by example.
Claims (10)
1. a kind of structure demolition works combined type auxiliary tool, which is characterized in that including fork of forklift truck, for releasing the fork truck
The wedge-shaped iron block at pallet fork inclination angle, at least one is used to promote the standard knot of fork of forklift truck support height;
The wedge shape iron block is set on the fork of forklift truck, and the standard knot is set on the wedge-shaped iron block;
The standard knot include the cuboid being made of angle steel and positioned at the cuboid tiltedly to the oblique angle steel in payment to a porter;
The cuboid includes being located at bottom surface to constitute rectangular four article of first angle steel, be located at top surface and constitute rectangular four articles the
Two angle steel, the third angle steel between the bottom surface and the top surface;
The oblique angle steel by fixation steel plate respectively with first angle steel, second Bolted angle connection.
2. structure demolition works combined type auxiliary tool according to claim 1, which is characterized in that the third angle steel
Both ends are provided with the angle cleat for connection, and the first hole is provided at the top of the angle cleat.
3. structure demolition works combined type auxiliary tool according to claim 2, which is characterized in that the cuboid and institute
It states the opposite one side of fork truck to mark time equipped with climbing, the both ends marked time of climbing are fixed on the third angle steel.
4. structure demolition works combined type auxiliary tool according to claim 3, which is characterized in that between the standard knot
First hole, which is passed through, by the first screw rod carries out bolt and nut connection.
5. structure demolition works combined type auxiliary tool according to claim 2, which is characterized in that further include the first steel
Plate, the second steel plate and the second screw rod, first steel plate are set between the wedge-shaped iron block and the standard knot, and described first
Steel plate is equipped with the second hole;
Second steel plate is located at the bottom of the fork of forklift truck, and second steel plate is equipped with corresponding with second hole the
Three holes, second screw rod pass through second hole and connect with third hole progress bolt and nut.
6. structure demolition works combined type auxiliary tool according to claim 5, which is characterized in that further include third spiral shell
Bar, the 4th hole is arranged on first steel plate with first hole corresponding position, and the third screw rod passes through first hole and institute
It states the 4th hole and carries out nut connection.
7. structure demolition works combined type auxiliary tool according to claim 2, which is characterized in that further include third steel plate
With the guardrail for manual work;
The third steel plate is set on the top of the standard knot;The guardrail is set on the third steel plate, and guardrail
It surrounds one week.
8. structure demolition works combined type auxiliary tool according to claim 7, which is characterized in that it further include skirting board,
The skirting board is set on the third steel plate, and is located in the guardrail.
9. structure demolition works combined type auxiliary tool according to claim 7, which is characterized in that further include the 4th spiral shell
Bar, the third steel plate are equipped with the 5th hole corresponding with first hole, and the 4th screw rod passes through the 5th hole and institute
It states the first hole and carries out bolt and nut connection.
10. structure demolition works combined type auxiliary tool according to claim 2, which is characterized in that further include third steel
Plate and channel steel, the third steel plate are set on the top of the standard knot, and the channel steel is set on the third steel plate.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820340646.8U CN208310282U (en) | 2018-03-13 | 2018-03-13 | A kind of structure demolition works combined type auxiliary tool |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820340646.8U CN208310282U (en) | 2018-03-13 | 2018-03-13 | A kind of structure demolition works combined type auxiliary tool |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208310282U true CN208310282U (en) | 2019-01-01 |
Family
ID=64721321
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820340646.8U Active CN208310282U (en) | 2018-03-13 | 2018-03-13 | A kind of structure demolition works combined type auxiliary tool |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208310282U (en) |
-
2018
- 2018-03-13 CN CN201820340646.8U patent/CN208310282U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US10738488B2 (en) | Lift truck operated stacking formwork table system and a method of operation thereof | |
CN201158933Y (en) | High-rise maintaining scaffold device with extruding structure | |
CN204152176U (en) | Assembly type large span Mobile operating platform | |
CN105442866B (en) | Protective demolition and installation method for large-scale highrise steel structure | |
CN111997342B (en) | Cantilever framework supporting structure protruding out of building and construction method thereof | |
CN105908960B (en) | Scaffold for large space construction | |
CN209011528U (en) | A kind of all steel attachment type raise scaffold | |
CN110094051A (en) | Indoor ultrahigh large form Bailey beam support system and its construction method are built in a kind of room | |
CN211775640U (en) | Modular staircase regularization steel protection passageway | |
CN115162594A (en) | Construction method based on BIM floor support plate process deepening | |
WO2011072328A1 (en) | A loading platform | |
CN208310282U (en) | A kind of structure demolition works combined type auxiliary tool | |
CN203795311U (en) | Multi-leg high pier and slip form construction device | |
CN206329024U (en) | Hanging large-span steel-reinforced concrete structure construction steel platform | |
CN210598083U (en) | Elevator shaft construction platform | |
CN112267692A (en) | Assembly type building component hoisting comprehensive equipment and construction method thereof | |
CN208152583U (en) | A kind of high-building construction ancillary equipment | |
CN101967902A (en) | Basic guide rail for helicopter assembly transmission line iron tower leg section | |
CN204098493U (en) | The dismantled and assembled input and output material movable platform of a kind of modular for building | |
CN212984662U (en) | Self-climbing type discharging platform | |
CN103669219B (en) | Many limbs height pier is with sliding construction equipment | |
CN109403674B (en) | Assembled prefabrication factory for bridge construction and construction method thereof | |
CN207484921U (en) | Assembled moving operating platform | |
CN201720833U (en) | Operating platform for quickly mounting steel box girder cantilevers and treating cantilever welds | |
CN112173043A (en) | Hyperboloid segmentation bed-jig |