CN110094051A - Indoor ultrahigh large form Bailey beam support system and its construction method are built in a kind of room - Google Patents

Indoor ultrahigh large form Bailey beam support system and its construction method are built in a kind of room Download PDF

Info

Publication number
CN110094051A
CN110094051A CN201910452512.4A CN201910452512A CN110094051A CN 110094051 A CN110094051 A CN 110094051A CN 201910452512 A CN201910452512 A CN 201910452512A CN 110094051 A CN110094051 A CN 110094051A
Authority
CN
China
Prior art keywords
bailey
support system
bailey beam
steel
beams
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910452512.4A
Other languages
Chinese (zh)
Inventor
刘伟
于非
林圣杰
许武
武争艳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Sixth Engineering Division Co Ltd
China Construction Sixth Bureau Construction Development Co Ltd
Original Assignee
China Construction Sixth Engineering Division Co Ltd
China Construction Sixth Bureau Construction Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Sixth Engineering Division Co Ltd, China Construction Sixth Bureau Construction Development Co Ltd filed Critical China Construction Sixth Engineering Division Co Ltd
Priority to CN201910452512.4A priority Critical patent/CN110094051A/en
Publication of CN110094051A publication Critical patent/CN110094051A/en
Pending legal-status Critical Current

Links

Classifications

    • E—FIXED CONSTRUCTIONS
    • E04—BUILDING
    • E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • E04G11/48—Supporting structures for shutterings or frames for floors or roofs
    • E—FIXED CONSTRUCTIONS
    • E04—BUILDING
    • E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • E04G11/48—Supporting structures for shutterings or frames for floors or roofs
    • E04G11/50—Girders, beams, or the like as supporting members for forms

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明属于室内施工搭设装置技术领域,涉及一种房建室内超高大模板贝雷梁支撑体系及其施工方法;支撑体系包括多根下支撑梁、多根贝雷梁和多根工字钢,一种房建室内超高大模板贝雷梁支撑体系施工方法,包括如下步骤:步骤A、将下支撑梁放置好;步骤B、将贝雷片运送至指定位置并组合成贝雷梁;步骤C、将贝雷梁搭设在下支撑梁上;步骤D、将工字钢连接在贝雷梁的上端;步骤E、将定位筋安装在工字钢上;步骤F、在工字钢上铺满踏板,并在踏板下方挂满防坠落网;步骤G、在该支撑体系的上方安装脚手架;步骤H、在每根贝雷梁的中间位置设置一个钢筋头作为沉降观测点;本发明可以解决现有技术中超高大模板架设过程中存在的施工不便且结构不稳固的问题。

The invention belongs to the technical field of indoor construction and erection devices, and relates to a super-high formwork Bailey beam support system and a construction method thereof in a house construction room; the support system includes multiple lower support beams, multiple Bailey beams and multiple I-beams, A method for constructing an indoor ultra-high formwork Bailey beam support system, comprising the following steps: step A, placing the lower support beam; step B, transporting the Bailey sheets to a designated position and combining them into a Bailey beam; step C 1. Set up the Bailey beam on the lower support beam; Step D, connect the I-beam to the upper end of the Bailey beam; Step E, install the positioning rib on the I-beam; Step F, spread the pedals on the I-beam , and hang the anti-falling net under the pedal; step G, install scaffolding above the support system; step H, set a steel bar head in the middle of each Bailey beam as the settlement observation point; the present invention can solve the problem of existing In the process of erecting super-high formwork in the technology, there are problems of inconvenient construction and unstable structure.

Description

一种房建室内超高大模板贝雷梁支撑体系及其施工方法An indoor ultra-high formwork Bailey beam support system and its construction method

技术领域technical field

本发明属于室内施工搭设装置技术领域,尤其是涉及一种房建室内超高大模板贝雷梁支撑体系及其施工方法。The invention belongs to the technical field of erecting devices for indoor construction, and in particular relates to a Bailey beam support system for super-high formwork indoors in house construction and a construction method thereof.

背景技术Background technique

随着社会的高速发展,建筑物的风格更是日新月异,越来越多的超高层不规则建筑物出现在人们的视野,伴随着建筑物的不断升高,传统满堂支撑脚手架高架支模支撑体系的弊端就显现出来,不但难以保证支架的搭设高度和稳定性,更是延长了工期,因此,需要发明一种新的支撑体系。With the rapid development of society, the style of buildings is changing with each passing day. More and more super high-rise irregular buildings appear in people's field of vision. The disadvantages of this method have emerged. Not only is it difficult to ensure the height and stability of the support, but it also prolongs the construction period. Therefore, it is necessary to invent a new support system.

发明内容Contents of the invention

有鉴于此,本发明旨在提出一种房建室内超高大模板贝雷梁支撑体系及其施工方法,以解决现有技术中房建室内不规则超高大模板架设过程中存在的造价高,安全性较低,施工方式固定而且难以保证支撑的稳定等问题。In view of this, the present invention aims to propose a Bailey beam support system for super-high and large formwork indoors in house construction and its construction method to solve the problems of high cost and safety in the erection process of irregular super-high formwork in house construction in the prior art. The stability is low, the construction method is fixed, and it is difficult to ensure the stability of the support.

为达到上述目的,本发明的技术方案是这样实现的:In order to achieve the above object, technical solution of the present invention is achieved in that way:

一种房建室内超高大模板贝雷梁支撑体系,包括多根下支撑梁、多根贝雷梁和多根工字钢,贝雷梁由多个贝雷片和连接网架搭接而成,下支撑梁放置在建筑结构框架梁上,且下支撑梁首尾相接拼接在一起形成一个异形的框架形状;多根贝雷梁搭设在下支撑梁上,多根工字钢可拆卸连接在贝雷梁的上端,工字钢将所有的贝雷梁纵向连接在一起形成一个整体支撑体系;A Bailey beam support system for ultra-high and large formwork indoors in house construction, including multiple lower support beams, multiple Bailey beams and multiple I-beams. The Bailey beam is formed by overlapping multiple Bailey sheets and connecting grids , the lower support beams are placed on the frame beams of the building structure, and the lower support beams are spliced end to end to form a special-shaped frame shape; multiple Bailey beams are erected on the lower support beams, and multiple I-beams are detachably connected to the shell At the upper end of the beam, the I-beam connects all the beams longitudinally together to form an integral support system;

工字钢的末端通过一个卡接结构可拆卸连接有一段定位筋,工字钢的上表面铺设有多块踏板,踏板的下方吊装有防坠落网,防坠落网的四角固定安装在贝雷梁的上部弦杆处;The end of the I-beam is detachably connected with a section of positioning ribs through a clamping structure. The upper surface of the I-beam is laid with multiple pedals. The bottom of the pedals is hoisted with an anti-fall net. The four corners of the anti-fall net are fixed on the Bailey beam. at the upper chord of the

卡接结构包括一号卡接部和二号卡接部,一号卡接部为“匚”字形的槽状结构,二号卡接部为反“匚”字形的槽状结构,一号卡接部和二号卡接部抱合卡接在工字钢的上部翼板上,同时一号卡接部和二号卡接部可拆卸连接在一起,定位筋竖直固接在一号卡接部上。The clamping structure includes the first clamping part and the second clamping part. The first clamping part is a "匚"-shaped groove-shaped structure, the second clamping part is a reverse "匚"-shaped groove-shaped structure, and the first clamping part is a "匚"-shaped groove-shaped structure. The connecting part and the No. 2 snapping part are clung together and connected to the upper wing plate of the I-beam. At the same time, the No. 1 snapping part and the No. 2 snapping part are detachably connected together, and the positioning rib is vertically fixed on the No. 1 snapping joint. department.

进一步地,下支撑梁采用枕木或者方木;贝雷梁采用上弦加强型贝雷梁。Further, the lower supporting beam adopts sleepers or square timbers; the Bailey beam adopts upper chord reinforced Bailey beam.

进一步地,工字钢通过U形螺栓可拆卸连接在贝雷梁的上端;U形螺栓的底杆贯穿通过上部弦杆,U形螺栓的两根侧杆贯穿通过工字钢,且U形螺栓的两根侧杆上端拧接有螺母。Further, the I-shaped steel is detachably connected to the upper end of the Bailey beam through U-shaped bolts; the bottom rod of the U-shaped bolt passes through the upper chord, the two side rods of the U-shaped bolt pass through the I-shaped steel, and the U-shaped bolt The upper ends of the two side bars are screwed with nuts.

一种房建室内超高大模板贝雷梁支撑体系施工方法,应用上述房建室内超高大模板贝雷梁支撑体系,包括如下步骤:A method for constructing an indoor ultra-high and large formwork Bailey beam support system for house construction, using the above-mentioned Bailey beam support system for super-high and large formwork in the interior of a house construction, comprising the following steps:

步骤A、将多根下支撑梁放置在建筑结构框架梁上,下支撑梁首尾相接拼接在一起形成一个异形的框架形状,形成贝雷梁的支撑底座;Step A, placing a plurality of lower support beams on the frame beam of the building structure, the lower support beams are spliced end to end to form a special-shaped frame shape, and form the support base of the Bailey beam;

步骤B、将贝雷片运送至指定位置并组合成贝雷梁;Step B, transporting the Bailey sheets to a designated location and combining them into Bailey beams;

步骤C、将多根组合好的贝雷梁搭设在下支撑梁上;Step C, erecting a plurality of assembled Bailey beams on the lower support beam;

步骤D、将多根工字钢可拆卸连接在贝雷梁的上端,工字钢将所有的贝雷梁纵向连接在一起形成一个整体支撑体系,此处,工字钢间距根据设计要求确定;Step D, a plurality of I-beams are detachably connected to the upper end of the Bailey beams, and the I-beams connect all the Bailey beams longitudinally together to form an integral support system. Here, the distance between the I-beams is determined according to the design requirements;

步骤E、将定位筋可拆卸安装在工字钢上的合适位置处;Step E, detachably install the positioning rib at a suitable position on the I-beam;

步骤F、在工字钢的上表面铺满踏板,并在踏板下方挂满防坠落网,防坠落网的四角固定安装在贝雷梁的上部弦杆处;Step F, the upper surface of the I-beam is covered with pedals, and the anti-fall net is hung under the pedal, and the four corners of the anti-fall net are fixed on the upper chord of the Bailey beam;

步骤G、在该支撑体系的上方安装脚手架,将脚手架的立杆钢管插接在定位筋上即可;Step G, installing a scaffold above the support system, and inserting the vertical rod steel pipe of the scaffold on the positioning rib;

步骤H、在每根贝雷梁2的中间位置设置一个钢筋头作为沉降观测点,在使用该支撑体系进行作业的过程中进行该支撑体系的沉降监测,当监测结果发现异常时立即停止使用,研究处理措施。Step H, set a steel bar head in the middle of each Bailey beam 2 as a settlement observation point, carry out the settlement monitoring of the support system during the operation using the support system, stop using it immediately when the monitoring results are found to be abnormal, Research treatments.

进一步地,所述步骤A中,将多根下支撑梁放置在建筑结构框架梁上时,该支撑体系以下三层内的框梁模板架体不拆除,即三层楼面框架梁共同承受支撑体系的重力荷载。Further, in the step A, when multiple lower support beams are placed on the frame beams of the building structure, the frame beam formwork frames in the lower three floors of the support system are not removed, that is, the frame beams on the three floors are jointly supported The gravity load of the system.

进一步地,所述步骤B中,贝雷梁组合施工的具体方法为:首先将所有的贝雷片运输至指定位置后,现场将贝雷片组装成贝雷梁;将贝雷片运送至指定位置时采用人工运输,人工运输采用四轮推车将所有的贝雷片运到相应位置,之后进行组装;在现场把贝雷片依次首尾相接连接成组合的单片形式,把组合好的整体贝雷片用连接网架进行加固使其成为整体的贝雷梁,每两组整体贝雷片之间通过一个连接网架连接在一起形成一组贝雷梁。Further, in the step B, the specific method for the combined construction of Bailey beams is as follows: first, after transporting all the Bailey sheets to the designated location, assemble the Bailey sheets into Bailey beams on site; transport the Bailey sheets to the designated location Manual transportation is used for location, and four-wheeled carts are used for manual transportation to transport all the Bailey sheets to the corresponding positions, and then assembled; the Bailey sheets are connected end-to-end in sequence on site to form a combined single piece, and the combined The integral Bailey sheets are reinforced with connecting grids to form a whole Bailey beam, and every two groups of integral Bailey sheets are connected together by a connecting grid to form a group of Bailey beams.

进一步地,所述步骤B中,贝雷梁组合施工的具体方法为:首先将贝雷片依次首尾相接连接成组合的单片形式,把组合好的整体贝雷片运输至指定位置后,在现场将组合好的整体贝雷片组装成贝雷梁;把整体贝雷片用连接网架进行加固使其成为整体的贝雷梁,每两组整体贝雷片之间通过一个连接网架连接在一起形成一组贝雷梁。Further, in the step B, the specific method for the combined construction of Bailey beams is as follows: firstly connect the Bailey sheets end-to-end in order to form a combined single piece, and after transporting the assembled whole Bailey sheets to the designated location, Assemble the combined overall Bailey sheets into Bailey beams on site; reinforce the integral Bailey sheets with connecting grids to make them an integral Bailey beam, and pass a connecting grid between each two groups of integral Bailey sheets connected together to form a set of Bailey beams.

进一步地,所述步骤B中,把整体贝雷片运输至指定位置时可采用塔吊运输或者滑移法进行运输,采用塔吊运输时使用的钢梁、钢丝绳,卡环等应和桁架重量匹配;Further, in the step B, when the whole Bailey piece is transported to the designated location, it can be transported by tower crane or slip method, and the steel beams, wire ropes, snap rings, etc. used when transporting by tower crane should match the weight of the truss;

当整体贝雷片长度较大,无法利用塔吊整体吊装到位时,采用滑移法进行运输,利用电动葫芦配合滑道进行运输,滑道由数根钢管平行放置在地面上组成,利用现场混凝土柱作为提拉支架,将两台电动葫芦固定在提拉支架上,每台电动葫芦下连接一根钢丝绳,钢丝绳的末端固定在整体贝雷片端部,采用这两台电动葫芦和两根钢丝绳交替提拉;为确保提拉安全,保证整体贝雷片后端不滑空,在整体贝雷片后端再设一组电动葫芦进行牵引。When the overall Bailey piece is too long to be hoisted in place by the tower crane, the sliding method is used for transportation, and the electric hoist is used for transportation with the slideway. The slideway is composed of several steel pipes placed in parallel on the ground, and the on-site concrete column is used As a lifting bracket, two electric hoists are fixed on the lifting bracket, and a wire rope is connected under each electric hoist, and the end of the wire rope is fixed at the end of the overall sheller. Pulling; in order to ensure the safety of lifting and ensure that the rear end of the overall Bailey sheet does not slip, a set of electric hoists is installed at the rear end of the overall Bailey sheet for traction.

进一步地,所述步骤E中,将定位筋可拆卸安装在工字钢上的方法为:Further, in the step E, the method of detachably installing the positioning rib on the I-beam is as follows:

确定好定位筋的位置后,将卡接结构中的一号卡接部和二号卡接部抱合卡接在工字钢的上部翼板上,如需要调整定位筋的位置,只需要将一号卡接部和二号卡接部拆下,重新安装即可。After determining the position of the positioning rib, engage the No. 1 and No. 2 snapping parts in the clamping structure on the upper wing plate of the I-beam. If you need to adjust the position of the positioning rib, you only need to place a The No. 1 snap joint and the No. 2 snap joint are removed and reinstalled.

进一步地,所述步骤H中,观测时采用水准仪观测钢筋头的水平标高,测量应达到二等水准测量标准,测量精度应达到±1mm,读数精确到0.1mm;对该支撑体系进行监测时,监测频率为每6h观测一次,当发现钢筋头沉降速度较快,达到1mm/h时,观测频次提高到2h测一次;钢筋头下沉位移一共不允许超过40mm。Further, in the step H, when observing, use a level to observe the horizontal elevation of the steel bar head, the measurement should reach the second-class level measurement standard, the measurement accuracy should reach ±1mm, and the reading should be accurate to 0.1mm; when monitoring the support system, The monitoring frequency is to observe once every 6 hours. When the settlement speed of the steel bar head is found to be fast, reaching 1mm/h, the observation frequency is increased to once every 2 hours; the total sinking displacement of the steel bar head is not allowed to exceed 40mm.

相对于现有技术,本发明具有以下优势:Compared with the prior art, the present invention has the following advantages:

传统的满堂支撑脚手架高架支模施工方式造价高,安全性较低,施工方式固定而且难以保证支撑的稳定。该支撑体系的主要构件均由标准化的构件组成,可以根据建筑物的尺寸和规格、脚手架搭设纵横间距等进行组合设计。贝雷梁和工字钢组合后作为上部混凝土现浇结构的施工支撑体系,具有承载能力大、结构稳定性强的特点,将该支撑体系结合支撑体系的施工方法,可以达到提高施工效率,加快施工进度,节约施工成本的效果。The traditional construction method of elevated formwork for full-support scaffolding is high in cost, low in safety, fixed in construction method and difficult to ensure the stability of support. The main components of the support system are composed of standardized components, which can be combined and designed according to the size and specification of the building, the vertical and horizontal spacing of the scaffolding, etc. The combination of Bailey beams and I-beams is used as the construction support system of the upper concrete cast-in-place structure, which has the characteristics of large bearing capacity and strong structural stability. The construction method of combining the support system with the support system can improve construction efficiency and speed up construction. Construction progress, the effect of saving construction costs.

附图说明Description of drawings

构成本发明的一部分的附图用来提供对本发明的进一步理解,本发明的示意性实施例及其说明用于解释本发明,并不构成对本发明的不当限定。在附图中:The drawings constituting a part of the present invention are used to provide a further understanding of the present invention, and the schematic embodiments and descriptions of the present invention are used to explain the present invention, and do not constitute an improper limitation of the present invention. In the attached picture:

图1为本发明的结构示意图;Fig. 1 is a structural representation of the present invention;

图2为卡接结构在工字钢上的连接结构示意图;Fig. 2 is a schematic diagram of the connection structure of the clamping structure on the I-beam;

图3为下支撑梁上未安装贝雷梁和工字钢时的俯视图;Fig. 3 is the top view when no Bailey beam and I-beam are installed on the lower support beam;

图4为下支撑梁上安装好贝雷梁和工字钢时的俯视图;Fig. 4 is the top view when Bailey beam and I-beam are installed on the lower supporting beam;

图5为图4中A截面处的剖视图。FIG. 5 is a cross-sectional view at section A in FIG. 4 .

附图标记说明:Explanation of reference signs:

1-下支撑梁;2-贝雷梁;21-贝雷片;211-上部弦杆;22-连接网架;3-工字钢;4-定位筋;5-踏板;6-防坠落网;7-U形螺栓;8-卡接结构;81-一号卡接部;811-一号连接板;82-二号卡接部;821-二号连接板;9-脚手架。1-lower support beam; 2-Bayley beam; 21-Bayley sheet; 211-upper chord; 22-connecting grid; 3-I-beam; 4-positioning rib; 5-pedal; ; 7-U-shaped bolt; 8-clamping structure; 81-1st clamping part; 811-1st connecting plate; 82-2nd clamping part; 821-2nd connecting plate; 9-scaffolding.

具体实施方式Detailed ways

需要说明的是,在不冲突的情况下,本发明中的实施例及实施例中的特征可以相互组合。It should be noted that, in the case of no conflict, the embodiments of the present invention and the features in the embodiments can be combined with each other.

在本发明的描述中,需要理解的是,术语“中心”、“纵向”、“横向”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”、“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。此外,术语“第一”、“第二”等仅用于描述目的,而不能理解为指示或暗示相对重要性或者隐含指明所指示的技术特征的数量。由此,限定有“第一”、“第二”等的特征可以明示或者隐含地包括一个或者更多个该特征。在本发明的描述中,除非另有说明,“多个”的含义是两个或两个以上。In describing the present invention, it should be understood that the terms "center", "longitudinal", "transverse", "upper", "lower", "front", "rear", "left", "right", " The orientations or positional relationships indicated by "vertical", "horizontal", "top", "bottom", "inner" and "outer" are based on the orientations or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and Simplified descriptions, rather than indicating or implying that the device or element referred to must have a particular orientation, be constructed and operate in a particular orientation, and thus should not be construed as limiting the invention. In addition, the terms "first", "second", etc. are used for descriptive purposes only, and should not be understood as indicating or implying relative importance or implicitly specifying the quantity of the indicated technical features. Thus, a feature defined as "first", "second", etc. may expressly or implicitly include one or more of that feature. In the description of the present invention, unless otherwise specified, "plurality" means two or more.

在本发明的描述中,需要说明的是,除非另有明确的规定和限定,术语“安装”、“相连”、“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通。对于本领域的普通技术人员而言,可以通过具体情况理解上述术语在本发明中的具体含义。In the description of the present invention, it should be noted that unless otherwise specified and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense, for example, it can be a fixed connection or a detachable connection. Connected, or integrally connected; it may be mechanically connected or electrically connected; it may be directly connected or indirectly connected through an intermediary, and it may be the internal communication of two components. Those of ordinary skill in the art can understand the specific meanings of the above terms in the present invention based on specific situations.

下面将参考附图并结合实施例来详细说明本发明。The present invention will be described in detail below with reference to the accompanying drawings and examples.

如图1-5所示,一种房建室内超高大模板贝雷梁支撑体系,包括多根下支撑梁1、多根贝雷梁2和多根工字钢3,贝雷梁2由多个贝雷片21和连接网架22搭接而成,本实施例中,贝雷梁2采用上弦加强型贝雷梁,贝雷梁2的上端加设有加强弦杆。贝雷片21选产1500×3000型贝雷桁架片,高度1.5m,每单片长度3.0m,由于增加了加强弦杆,所以高度增加0.1-0.15m,采用6片贝雷片21组装成长度为18m的整体贝雷片,为保证支架稳定,贝雷梁2是由双排整体贝雷片组装成的桁梁,贝雷架之间以宽450mm/900mm的连接网架22为连接构件,之间用螺栓固定连接。As shown in Figure 1-5, a Bailey beam support system for super-high formwork indoors in house construction includes multiple lower support beams 1, multiple Bailey beams 2 and multiple I-beams 3, and Bailey beams 2 are composed of multiple A Bailey sheet 21 is overlapped with a connecting grid 22. In this embodiment, the Bailey beam 2 adopts an upper chord reinforced Bailey beam, and the upper end of the Bailey beam 2 is provided with a reinforcing chord. 1500×3000 type Bailey truss pieces are selected for Bailey sheet 21, the height is 1.5m, and the length of each single piece is 3.0m. Due to the increase of reinforcing chords, the height is increased by 0.1-0.15m, and 6 pieces of Bailey sheet 21 are used to assemble and grow. Integral Bailey sheets with a height of 18m, in order to ensure the stability of the support, the Bailey beam 2 is a truss beam assembled from double rows of integral Bailey sheets, and the connecting grid 22 with a width of 450mm/900mm is used as a connecting member between the Bailey frames , between the fixed connection with bolts.

下支撑梁1放置在建筑结构框架梁上,且下支撑梁1首尾相接拼接在一起形成一个异形的框架形状;多根贝雷梁2搭设在下支撑梁1上,多根工字钢3通过U形螺栓7可拆卸连接在贝雷梁2的上端,U形螺栓7的底杆贯穿通过上部弦杆211,U形螺栓7的两根侧杆贯穿通过工字钢3,且U形螺栓7的两根侧杆上端拧接有螺母,工字钢3将所有的贝雷梁2纵向连接在一起形成一个整体支撑体系。贝雷梁2上安装工字钢3作为横向分配梁,贝雷梁2的数量及其与工字钢3的组合根据上部荷载确定,该实施例中,贝雷梁2上铺设间距750mm的16#工字钢3作为横向分配梁。工字钢3采用可拆卸安装的方式,方便安装和拆卸,比起传统的焊接方式,施工简单,避免了焊接、切割工序,减少了焊接切割对原件的损伤。The lower support beam 1 is placed on the frame beam of the building structure, and the lower support beam 1 is spliced end to end to form a special-shaped frame shape; multiple Bailey beams 2 are erected on the lower support beam 1, and multiple I-beams 3 pass through The U-shaped bolt 7 is detachably connected to the upper end of the Bailey beam 2, the bottom rod of the U-shaped bolt 7 passes through the upper chord 211, the two side rods of the U-shaped bolt 7 pass through the I-beam 3, and the U-shaped bolt 7 The upper ends of the two side bars are screwed with nuts, and the I-beam 3 connects all the Bailey beams 2 longitudinally to form an integral support system. I-beams 3 are installed on Bailey beams 2 as transverse distribution beams. The number of Bailey beams 2 and their combination with I-beams 3 are determined according to the upper load. #I-beam 3 acts as a transverse distribution beam. The I-beam 3 adopts a detachable installation method, which is convenient for installation and disassembly. Compared with the traditional welding method, the construction is simple, avoiding welding and cutting processes, and reducing the damage to the original parts caused by welding and cutting.

优选地,下支撑梁1采用枕木或者方木,该支撑体系作为上部混凝土现浇结构的施工支架平台,因其支撑在建筑结构框架梁上,因此选用用枕木或者方木作为贝雷梁2的平台支座,不仅成本低廉,方便移动,而且,木材相对于钢材具有一定的柔性,可以起到一定的柔性缓冲作用,将贝雷梁2与混凝土板分离开来。Preferably, the lower support beam 1 adopts sleepers or square logs, and the support system is used as the construction support platform of the upper concrete cast-in-place structure. Because it is supported on the frame beam of the building structure, sleepers or square logs are selected as the Bailey beam 2. The platform support is not only low in cost and easy to move, but also, wood has a certain flexibility compared to steel, which can play a certain flexible buffer role and separate the Bailey beam 2 from the concrete slab.

工字钢3的末端通过一个卡接结构8可拆卸连接有一段直径20mm的定位筋4,定位筋4长度为150mm,卡接结构8包括一号卡接部81和二号卡接部82,一号卡接部81为“匚”字形的槽状结构,二号卡接部82为反“匚”字形的槽状结构,一号卡接部81和二号卡接部82抱合卡接在工字钢3的上部翼板上,同时一号卡接部81和二号卡接部82通过螺栓可拆卸连接在一起,定位筋4竖直固接在一号卡接部81上。The end of the I-beam 3 is detachably connected to a positioning rib 4 with a diameter of 20 mm through a clamping structure 8. The length of the positioning rib 4 is 150 mm. The clamping structure 8 includes a first clamping part 81 and a second clamping part 82. The first clamping part 81 is a "匚"-shaped groove-shaped structure, the second clamping part 82 is a reverse "匚"-shaped groove-shaped structure, and the first clamping part 81 and the second clamping part 82 are entangled and clamped on the On the upper wing plate of the I-beam 3, the No. 1 clamping part 81 and the No. 2 clamping part 82 are detachably connected together by bolts, and the positioning rib 4 is vertically fixed on the No. 1 clamping part 81.

定位筋4通过一个可拆卸的卡接结构8安装在工字钢3上,方便按照施工要求及时调整定位筋4的位置,确定好定位筋4的位置后,将卡接结构8中的一号卡接部81和二号卡接部82抱合卡接在工字钢3的上部翼板上,如需要调整定位筋4的位置,只需要将一号卡接部81和二号卡接部82拆下,重新安装即可。The positioning rib 4 is installed on the I-beam 3 through a detachable clamping structure 8, which is convenient for adjusting the position of the positioning rib 4 in time according to the construction requirements. The clamping part 81 and the second clamping part 82 are clung together and clamped on the upper wing plate of the I-beam 3. If the position of the positioning rib 4 needs to be adjusted, only the first clamping part 81 and the second clamping part 82 need to be adjusted. Remove it and reinstall it.

工字钢3的上表面铺设有多块踏板5,踏板5的下方吊装有防坠落网6,防坠落网6的四角固定安装在贝雷梁2的上部弦杆211处;踏板5既方便工人行走,又起到的硬性防护的作用,不会把人或物掉落下去,防坠落网6起到了进一步加强防护的作用。The upper surface of the I-beam 3 is laid with a plurality of pedals 5, the bottom of the pedals 5 is hoisted with an anti-fall net 6, and the four corners of the anti-fall net 6 are fixedly installed at the upper chord 211 of the Bailey beam 2; the pedal 5 is convenient for workers Walking plays the role of hard protection again, and people or things can not be dropped, and the anti-falling net 6 has played the effect of further strengthening the protection.

一种房建室内超高大模板贝雷梁支撑体系施工方法,包括如下步骤:A construction method for a super-high formwork Bailey beam support system in an indoor building, comprising the following steps:

步骤A、将多根下支撑梁1放置在建筑结构框架梁上,下支撑梁1首尾相接拼接在一起形成一个异形的框架形状,形成贝雷梁2的支撑底座(如图3所示),该支撑体系作为上部混凝土现浇结构的施工支架平台,因其支撑在建筑结构框架梁上,考虑到该支撑体系支撑在高层楼面两侧框架梁上,为了保证该层楼面框架梁有足够承载力,施工时,该支撑体系以下三层内的框梁模板架体不拆除,即三层楼面框架梁共同承受支撑体系的重力荷载。Step A, placing a plurality of lower support beams 1 on the frame beam of the building structure, the lower support beams 1 are spliced end to end to form a special-shaped frame shape, and form the support base of the Bailey beam 2 (as shown in Figure 3) , the support system is used as the construction support platform of the upper concrete cast-in-place structure. Because it is supported on the frame beams of the building structure, considering that the support system is supported on the frame beams on both sides of the high-rise floor, in order to ensure that the floor frame beams have Sufficient bearing capacity, during construction, the frame beam formwork frame in the lower three floors of the support system will not be removed, that is, the frame beams on the three floors jointly bear the gravity load of the support system.

步骤B、将贝雷片21运送至指定位置并组合成贝雷梁2;现场施工中,可以根据施工条件,灵活选择贝雷梁2的施工方法,本实施例中提供了两种方法以供选择:Step B, transport the Bailey sheet 21 to the designated location and combine it into the Bailey beam 2; during the on-site construction, the construction method of the Bailey beam 2 can be flexibly selected according to the construction conditions, and two methods are provided in this embodiment for choose:

第一种方法:首先将所有的贝雷片21运输至指定位置后,现场将贝雷片21组装成贝雷梁2。该方法属于单纯人工施工,适用于施工场地有限制,吊装和搬运设备超出作业区,不适合机械施工的场所。The first method: firstly, after all the Bailey sheets 21 are transported to the designated location, the Bailey sheets 21 are assembled into the Bailey beam 2 on site. This method belongs to purely manual construction, and is suitable for places where the construction site is limited, and the hoisting and handling equipment exceeds the work area, which is not suitable for mechanical construction.

将贝雷片21运送至指定位置时采用人工运输,人工运输采用四轮推车将所有的贝雷片21运到相应位置,之后进行组装;在现场把贝雷片21依次首尾相接连接成组合的单片形式,把组合好的整体贝雷片用连接网架22进行加固使其成为整体的贝雷梁2,每两组整体贝雷片之间通过一个连接网架22连接在一起形成一组贝雷梁2。Manual transportation is used when the Bailey sheets 21 are transported to the designated location. The manual transportation uses a four-wheel cart to transport all the Bailey sheets 21 to the corresponding positions, and then assembles them; Combined single-piece form, the combined overall Bailey sheet is reinforced with a connecting grid 22 to form an integral Bailey beam 2, and every two groups of integral Bailey sheets are connected together by a connecting grid 22 to form A set of Bailey beams 2.

第二种方法:首先将贝雷片21依次首尾相接连接成组合的单片形式,把组合好的整体贝雷片运输至指定位置后,在现场将组合好的整体贝雷片组装成贝雷梁2,只需把整体贝雷片用连接网架22进行加固使其成为整体的贝雷梁2,每两组整体贝雷片之间通过一个连接网架22连接在一起形成一组贝雷梁2。该方法相比于人工施工,免去了人工搬运贝雷片21的繁琐步骤,加快了施工进度。The second method: first connect the Bailey sheets 21 end-to-end in sequence to form a combined single-piece form, and after transporting the assembled whole Bailey sheets to a designated location, assemble the combined whole Bailey sheets into a Beiley sheet on site. Thunder beam 2, only need to reinforce the overall Bailey sheet with the connecting grid 22 to make it a whole Bailey beam 2, every two groups of integral Bailey sheets are connected together by a connecting grid 22 to form a group of Bailey beams. Lei Liang 2. Compared with manual construction, this method eliminates the cumbersome steps of manually transporting the Bailey sheet 21 and speeds up the construction progress.

其中,把整体贝雷片运输至指定位置时可采用塔吊运输,吊运时使用的钢梁、钢丝绳,卡环等应和桁架重量匹配。Among them, the tower crane can be used to transport the whole Bailey sheet to the designated location, and the steel beams, wire ropes, snap rings, etc. used for lifting should match the weight of the truss.

当整体贝雷片长度较大,无法利用塔吊整体吊装到位时,采用滑移法进行运输,可解决这一问题。因每榀整体贝雷片重量约为3.366t,此处,利用电动葫芦配合滑道进行运输,滑道由数根钢管平行放置在地面上组成,利用现场混凝土柱作为提拉支架,将两台5T电动葫芦固定在提拉支架上,每台电动葫芦下连接一根φ25的钢丝绳,钢丝绳的末端固定在距离整体贝雷片端部1.5m处,采用这两台电动葫芦和两根钢丝绳交替提拉;为确保提拉安全,保证整体贝雷片后端不滑空,在整体贝雷片后端再设一组电动葫芦进行牵引。When the overall Bailey piece is too long to be hoisted in place by the tower crane, the sliding method can be used for transportation, which can solve this problem. Because the weight of each Bailey piece is about 3.366t, here, the electric hoist is used to cooperate with the slideway for transportation. The 5T electric hoist is fixed on the lifting bracket, and a φ25 steel wire rope is connected under each electric hoist. The end of the steel wire rope is fixed at a distance of 1.5m from the end of the overall Bailey piece. These two electric hoists and two steel wire ropes are used to lift alternately ;In order to ensure the safety of lifting and ensure that the rear end of the overall Bailey sheet does not slip empty, a group of electric hoists are set at the rear end of the overall Bailey sheet for traction.

步骤C、将多根组合好的贝雷梁2搭设在下支撑梁1上。Step C, erecting multiple assembled Bailey beams 2 on the lower support beam 1 .

步骤D、将多根工字钢3通过U形螺栓7可拆卸连接在贝雷梁2的上端,工字钢3将所有的贝雷梁2纵向连接在一起形成一个整体支撑体系,工字钢3起到加固纵向连接的作用;此处,工字钢3间距根据设计要求确定。Step D, multiple I-beams 3 are detachably connected to the upper end of the Bailey beam 2 through U-shaped bolts 7, and the I-beam 3 connects all Bailey beams 2 longitudinally to form an integral support system. 3 plays the role of strengthening the longitudinal connection; here, the spacing of the I-beam 3 is determined according to the design requirements.

步骤E、将定位筋4安装在工字钢3上的合适位置处,以便安装脚手架9。Step E, install the positioning rib 4 at a suitable position on the I-beam 3 so as to install the scaffold 9 .

确定好定位筋4的位置后,将卡接结构8中的一号卡接部81和二号卡接部82抱合卡接在工字钢3的上部翼板上,如需要调整定位筋4的位置,只需要将一号卡接部81和二号卡接部82拆下,重新安装即可;定位筋4可拆卸安装方便按照施工要求及时调整定位筋4的位置。After the position of the positioning rib 4 is determined, the No. 1 clamping part 81 and the No. 2 clamping part 82 in the clamping structure 8 are engaged and clamped on the upper wing plate of the I-beam 3, and the position of the positioning rib 4 is adjusted if necessary. position, only need to remove the No. 1 clamping part 81 and the No. 2 clamping part 82, and reinstall it; the positioning rib 4 can be disassembled and installed to facilitate timely adjustment of the position of the positioning rib 4 according to construction requirements.

步骤F、在工字钢3的上表面铺满踏板5,并在踏板5下方挂满防坠落网6,防坠落网6的四角系牢在贝雷梁2的上部弦杆211上即可。Step F, spread the pedal 5 on the upper surface of the I-beam 3, and hang the anti-fall net 6 under the pedal 5, and fasten the four corners of the anti-fall net 6 to the upper chord 211 of the Bailey beam 2.

步骤G、在该支撑体系的上方安装脚手架9,将脚手架9的立杆钢管插接在定位筋4上即可。Step G: install the scaffolding 9 above the supporting system, and insert the vertical rod steel pipe of the scaffolding 9 onto the positioning ribs 4 .

步骤H、在每根贝雷梁2的中间位置设置一个钢筋头作为沉降观测点,钢筋头的安装方法同定位筋4的安装方法,在使用该支撑体系进行作业的过程中进行该支撑体系的沉降和位移监测,当监测结果发现异常时立即停止使用,研究处理措施,可见,设置监测可以提高施工安全性能。Step H, set a steel bar head at the middle position of each Bailey beam 2 as the settlement observation point, the installation method of the steel bar head is the same as the installation method of the positioning rib 4, and carry out the installation of the support system in the process of using the support system for operation Settlement and displacement monitoring, when the monitoring results are found to be abnormal, stop using it immediately, and study the treatment measures. It can be seen that setting up monitoring can improve construction safety performance.

观测时采用水准仪观测钢筋头的水平标高,测量应达到二等水准测量标准,测量精度应达到±1mm,读数精确到0.1mm;对该支撑体系进行监测时,监测频率为每6h观测一次,当发现钢筋头沉降速度较快,达到1mm/h时,观测频次提高到2h测一次;钢筋头下沉位移一共不允许超过40mm。When observing, use a level instrument to observe the horizontal elevation of the steel bar head. The measurement should meet the second-class level measurement standard, the measurement accuracy should reach ±1mm, and the reading should be accurate to 0.1mm; when monitoring the support system, the monitoring frequency is once every 6h. It was found that the settlement speed of the steel bar head was fast, and when it reached 1mm/h, the observation frequency was increased to once every 2 hours; the total sinking displacement of the steel bar head was not allowed to exceed 40mm.

以上所述仅为本发明的较佳实施例而已,并不用以限制本发明,凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present invention shall be included in the scope of the present invention. within the scope of protection.

Claims (10)

1. indoor ultrahigh large form Bailey beam support system, including more lower supporting beams (1), more Bailey beams (2) are built in a kind of room With more I-steel (3), Bailey beam (2) is formed by overlapping by multiple beret slices (21) and connection rack (22), it is characterised in that: under Supporting beam (1) is placed on building structure frame beam, and lower supporting beam (1) it is end to end be stitched together to be formed one it is special-shaped Frame shape;More Bailey beams (2) ride upon on lower supporting beam (1), and more I-steel (3) are detachably connected on Bailey beam (2) Upper end, I-steel (3) by all Bailey beams (2) it is longitudinally connected together formed an integrated support system;
The end of I-steel (3) is removably connected with one section of positioning bar (4) by a clamping structure (8), I-steel (3) it is upper Surface is equipped with muti-piece pedal (5), be lifted with below pedal (5) it is anti-fall be caught (6), it is anti-fall be caught (6) Corner Strapped peace At the upper chord (211) of Bailey beam (2);
Clamping structure (8) includes No.1 clamping portion (81) and No. two clamping portions (82), and No.1 clamping portion (81) are " Fang " shape Groove-like structure, No. two clamping portions (82) are the groove-like structure of anti-" Fang " shape, No.1 clamping portion (81) and No. two clamping portions (82) Obvolvent is connected on the top wing plate of I-steel (3), while No.1 clamping portion (81) and No. two clamping portions (82) are detachably connected Together, positioning bar (4) is fixed on No.1 clamping portion (81) vertically.
2. indoor ultrahigh large form Bailey beam support system is built in room according to claim 1, it is characterised in that: lower supporting beam (1) sleeper or the lumps of wood are used;Bailey beam (2) is using reinforced Bailey beam of winding up.
3. indoor ultrahigh large form Bailey beam support system is built in room according to claim 2, it is characterised in that: I-steel (3) upper end of Bailey beam (2) is detachably connected on by U bolt (7);The bottom bar of U bolt (7) extends through upper chord (211), two side levers of U bolt (7) extend through I-steel (3), and two side lever upper end twist-ons of U bolt (7) have Nut.
4. indoor ultrahigh large form Bailey beam support system construction method is built in a kind of room, it is characterised in that: apply claim 1-3 Indoor ultrahigh large form Bailey beam support system is built in described in any item rooms, is included the following steps:
Step A, more lower supporting beams (1) are placed on building structure frame beam, the lower end to end splicing of supporting beam (1) is one It rises and forms a special-shaped frame shape, form the support base of Bailey beam (2);
Step B, beret slice (21) is transported to designated position and is combined into Bailey beam (2);
Step C, the Bailey beam (2) that more combine is ridden upon on lower supporting beam (1);
Step D, more I-steel (3) are detachably connected on to the upper end of Bailey beam (2), I-steel (3) is by all Bailey beams (2) longitudinally connected to form an integrated support system together, herein, I-steel (3) spacing is determined according to design requirement;
Step E, positioning bar (4) is removably mounted at the suitable position on I-steel (3);
Step F, be paved with pedal (5) in the upper surface of I-steel (3), and overwork below the pedal (5) it is anti-fall be caught (6), it is anti-fall The Corner Strapped of (6) of being caught is mounted at the upper chord (211) of Bailey beam (2);
Step G, scaffold (9) are installed in the top of the support system, the pole steel tube of scaffold (9) is plugged on positioning bar (4) on;
Step H, one steel bar end is set in the middle position of every Bailey beam 2 and is used as settlement observation point, in the use supporter System carries out the settlement monitoring that the support system is carried out during operation, stops using immediately when monitoring result notes abnormalities, Study treatment measures.
5. indoor ultrahigh large form Bailey beam support system construction method is built in room according to claim 4, it is characterised in that: In the step A, when more lower supporting beams (1) are placed on building structure frame beam, below the support system in three layers Grid beam template frame body is not removed, i.e. three floor surface frames are set a roof beam in place bears the gravity laod of support system jointly.
6. indoor ultrahigh large form Bailey beam support system construction method is built in room according to claim 4, it is characterised in that: In the step B, Bailey beam (2) combination construction method particularly includes: first by all beret slice (21) transports to specific bit It postpones, beret slice (21) is assembled into Bailey beam (2) by scene;Using artificial fortune when beret slice (21) is transported to designated position Defeated, all beret slices (21) are transported to corresponding position using four wheel barrows by hand haulage, are assembled later;At the scene shellfish Thunder piece (21) the successively end to end monolithic form for connecting into combination, whole beret slice connection rack (22) combined into Row is reinforced and is become whole Bailey beam (2), is connected between every two groups of entirety beret slices by a connection rack (22) It is formed together one group of Bailey beam (2).
7. indoor ultrahigh large form Bailey beam support system construction method is built in room according to claim 4, it is characterised in that: In the step B, Bailey beam (2) combination construction method particularly includes: connect into first by beret slice (21) is successively end to end Combined monolithic form transports the whole beret slice combined to designated position, the whole shellfish thunder that will be combined at the scene Piece is assembled into Bailey beam (2);Whole beret slice reinforce with connection rack (22) and becomes whole Bailey beam (2), One group of Bailey beam (2) is joined together to form by a connection rack (22) between every two groups of entirety beret slices.
8. indoor ultrahigh large form Bailey beam support system construction method is built in room according to claim 7, it is characterised in that: In the step B, tower crane transport can be used when entirety beret slice is transported to designated position or sliding method is transported, use Girder steel, the wirerope that tower crane uses when transporting, snap ring etc. should be with truss weight-matched;
When whole beret slice length is larger, can not using tower crane integral hoisting in place when, transported using sliding method, utilize electricity Dynamic cucurbit cooperation slideway is transported, and slideway is placed in parallel by several steel pipes and is formed on the ground, is made using on-site concrete column To lift bracket, two electric blocks are fixed on lifting bracket, steel cable, wirerope are connected under every electric block End be fixed on whole beret slice end, alternately lifted using this two electric blocks and two wirerope;In whole shellfish thunder Piece rear end sets one group of electric block again and is drawn, so that the not sliding sky in whole beret slice rear end.
9. indoor ultrahigh large form Bailey beam support system construction method is built in room according to claim 4, it is characterised in that: In the step E, positioning bar (4) is removably mounted at the method on I-steel (3) are as follows:
Behind the position for determining positioning bar (4), by clamping structure (8) No.1 clamping portion (81) and No. two clamping portions (82) embrace Conjunction is connected on the top wing plate of I-steel (3), such as needs to adjust the position of positioning bar (4), it is only necessary to by No.1 clamping portion (81) it removes, reinstalls with No. two clamping portions (82).
10. indoor ultrahigh large form Bailey beam support system construction method is built in room according to claim 4, feature exists In: in the step H, using the horizontal absolute altitude of level observation steel bar end when observation, measurement should reach second-order levelling mark Standard, measurement accuracy should reach ± 1mm, and reading is accurate to 0.1mm;When being monitored to the support system, monitoring frequency is every 6h Observation is primary, and when discovery steel bar end sinking speed is very fast, when reaching 1mm/h, it is primary that the observation frequency is increased to 2h survey;Under steel bar end Heavy displacement does not allow more than altogether 40mm.
CN201910452512.4A 2019-05-28 2019-05-28 Indoor ultrahigh large form Bailey beam support system and its construction method are built in a kind of room Pending CN110094051A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910452512.4A CN110094051A (en) 2019-05-28 2019-05-28 Indoor ultrahigh large form Bailey beam support system and its construction method are built in a kind of room

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910452512.4A CN110094051A (en) 2019-05-28 2019-05-28 Indoor ultrahigh large form Bailey beam support system and its construction method are built in a kind of room

Publications (1)

Publication Number Publication Date
CN110094051A true CN110094051A (en) 2019-08-06

Family

ID=67449456

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910452512.4A Pending CN110094051A (en) 2019-05-28 2019-05-28 Indoor ultrahigh large form Bailey beam support system and its construction method are built in a kind of room

Country Status (1)

Country Link
CN (1) CN110094051A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111691460A (en) * 2020-06-24 2020-09-22 中国建筑第七工程局有限公司 Subway upper cover large-section transfer beam supporting system and construction method thereof
CN112459471A (en) * 2020-11-30 2021-03-09 中国二十二冶集团有限公司 Beam slab support construction method
CN113979321A (en) * 2021-11-25 2022-01-28 山西建筑工程集团有限公司 Telescopic movable simple lifting device
CN115492390A (en) * 2022-11-04 2022-12-20 北京城建北方集团有限公司 Construction process of overlong overhanging corridor bailey frame support system
CN115726564A (en) * 2022-10-25 2023-03-03 中建海峡建设发展有限公司 Method for mounting and dismounting super-heavy-load high formwork supporting system
CN116397879A (en) * 2022-11-25 2023-07-07 中国五冶集团有限公司 A construction method for high-altitude formwork support of Bailey beam

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104141383A (en) * 2014-07-16 2014-11-12 北京万兴建筑集团有限公司 Bailey beam suspension formwork supporting system and construction method thereof
CN206721691U (en) * 2017-05-16 2017-12-08 中交三公局桥梁隧道工程有限公司 A kind of fastening structure of I-steel and beret truss
CN207079904U (en) * 2017-07-24 2018-03-09 中国一冶集团有限公司 A kind of positioning bar packaged type is encorbelmented I-steel
US20180127979A1 (en) * 2016-11-08 2018-05-10 University Of Notre Dame Du Lac Modular truss joint
CN109629445A (en) * 2019-01-17 2019-04-16 广州市高速公路有限公司 Bailey beam connecting mechanism and installation method thereof
CN210369895U (en) * 2019-05-28 2020-04-21 中建六局建设发展有限公司 A kind of indoor super-large formwork Bailey beam support system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104141383A (en) * 2014-07-16 2014-11-12 北京万兴建筑集团有限公司 Bailey beam suspension formwork supporting system and construction method thereof
US20180127979A1 (en) * 2016-11-08 2018-05-10 University Of Notre Dame Du Lac Modular truss joint
CN206721691U (en) * 2017-05-16 2017-12-08 中交三公局桥梁隧道工程有限公司 A kind of fastening structure of I-steel and beret truss
CN207079904U (en) * 2017-07-24 2018-03-09 中国一冶集团有限公司 A kind of positioning bar packaged type is encorbelmented I-steel
CN109629445A (en) * 2019-01-17 2019-04-16 广州市高速公路有限公司 Bailey beam connecting mechanism and installation method thereof
CN210369895U (en) * 2019-05-28 2020-04-21 中建六局建设发展有限公司 A kind of indoor super-large formwork Bailey beam support system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
陈胜文;杜昌宝: "贝雷梁平台模板支撑体系在超高大空间混凝土结构施工中的应用", 建筑施工 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111691460A (en) * 2020-06-24 2020-09-22 中国建筑第七工程局有限公司 Subway upper cover large-section transfer beam supporting system and construction method thereof
CN112459471A (en) * 2020-11-30 2021-03-09 中国二十二冶集团有限公司 Beam slab support construction method
CN113979321A (en) * 2021-11-25 2022-01-28 山西建筑工程集团有限公司 Telescopic movable simple lifting device
CN115726564A (en) * 2022-10-25 2023-03-03 中建海峡建设发展有限公司 Method for mounting and dismounting super-heavy-load high formwork supporting system
CN115492390A (en) * 2022-11-04 2022-12-20 北京城建北方集团有限公司 Construction process of overlong overhanging corridor bailey frame support system
CN115492390B (en) * 2022-11-04 2024-03-15 北京城建北方集团有限公司 Construction process of support system of ultra-long overhanging corridor bailey frame
CN116397879A (en) * 2022-11-25 2023-07-07 中国五冶集团有限公司 A construction method for high-altitude formwork support of Bailey beam

Similar Documents

Publication Publication Date Title
CN201158933Y (en) High-rise maintaining scaffold device with extruding structure
CN206053274U (en) The external scaffolding device of the perpendicular BAIYE outer visor of skyscraper and glass curtain wall dual-purpose
CN103225408A (en) Construction method for long-span net rack multiple-mast independent type integral lifting
CN113931313B (en) Construction method of super high-rise core tube horizontal structure
CN201297036Y (en) Discharging platform
CN106592962A (en) Large-height-difference long-span stiff-skeleton cladding concrete formwork construction method and apparatus
CN101775896B (en) Rigid suspended scaffold for installing pipeline of steel roof equipment
WO2023240812A1 (en) Overall construction platform structure and method for adding core tube wall body in air
CN209780193U (en) Suspension type scaffold
CN109469083B (en) Foundation beam reinforcement cage assembling system and construction method thereof
CN205314519U (en) High altitude operation platform based on truss
CN208168317U (en) A kind of lower extension platform of high-altitude construction
CN108277994B (en) Method for quickly dismantling safety protection shed of overhead high-speed rail operation line
CN212954042U (en) Lattice formula cable saddle hoist and mount portal
CN211689948U (en) A suspension operation platform device for the construction of a cable-stayed bridge tower
CN210369895U (en) A kind of indoor super-large formwork Bailey beam support system
CN219638367U (en) High-altitude large-scale sliding type operation platform
CN209742334U (en) Steel structure corridor bottom curtain wall construction platform
CN106639303B (en) Hydraulic climbing formwork for lift
CN214462394U (en) High-altitude overhanging scaffold
CN213571554U (en) A suspended anchorage gantry
CN112502473B (en) Supporting bearing capacity conversion device and method for dismantling large steel framework by using same
CN210685313U (en) Safe convenient house steel connection structure
CN210289068U (en) Elevator shaft lifting platform
CN115897975A (en) A high-altitude suspended platform formwork system and its construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190806