CN208293624U - The steel plate for sealing water support construction of sole plate post-poured strip - Google Patents

The steel plate for sealing water support construction of sole plate post-poured strip Download PDF

Info

Publication number
CN208293624U
CN208293624U CN201820786946.9U CN201820786946U CN208293624U CN 208293624 U CN208293624 U CN 208293624U CN 201820786946 U CN201820786946 U CN 201820786946U CN 208293624 U CN208293624 U CN 208293624U
Authority
CN
China
Prior art keywords
block piece
sealing water
steel plate
plate
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820786946.9U
Other languages
Chinese (zh)
Inventor
董幸发
许乐
朱人杰
邵思奇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Wuxi Construction Group Co Ltd
Original Assignee
Jiangsu Wuxi Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Wuxi Construction Group Co Ltd filed Critical Jiangsu Wuxi Construction Group Co Ltd
Priority to CN201820786946.9U priority Critical patent/CN208293624U/en
Application granted granted Critical
Publication of CN208293624U publication Critical patent/CN208293624U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

The utility model discloses a kind of steel plate for sealing water support constructions of sole plate post-poured strip, are related to a kind of steel plate for sealing water support construction, it is intended to solve the problems, such as that the support construction of existing steel plate for sealing water affects the construction efficiency of post-cast strip.Its key points of the technical solution are that, the first upper reinforcement block piece, the first steel plate for sealing water, the first lower rebar block piece are fixed by the first spacer bar, fixed the second upper reinforcement block piece, the second steel plate for sealing water, the second lower rebar block piece by the second spacer bar.When post-cast strip pours, the step of eliminating form removal, have the advantages that post empiricism efficiency can be effectively improved.

Description

The steel plate for sealing water support construction of sole plate post-poured strip
Technical field
The utility model relates to a kind of steel plate for sealing water support constructions, more specifically, it relates to pour after a kind of sole plate The steel plate for sealing water support construction of band.
Background technique
Concrete pours again after initial set, will form cold seam, and water is oozed out from cold seam in order to prevent, so past in construction Toward at post-cast strip be arranged one piece of steel plate for sealing water, the concrete inside interface position of first after-pouring at the half of steel plate for sealing water center, this Sample concrete and the closely knit combination of steel plate for sealing water, cold seam position prevents from seeping water by steel plate for sealing water.
Existing Authorization Notice No. discloses a kind of post-cast strip antirust arbor for the Chinese patent of CN204608839U, including A channel is arranged in sole plate, the sole plate middle part, and channel two sides are reinforced mesh, and the reinforced mesh is equipped with steel plate Sealing piece, the reinforced mesh side are equipped with stiffened wire lath.Steel plate waterstop strip needs under steel plate waterstop strip in setting Portion's supporting module.
But in above-mentioned post-cast strip antirust arbor, before post-cast strip pours, need to remove the mould of steel plate waterstop strip lower part Plate.Due to the covering of steel plate waterstop strip, people can not be protruded into below steel plate for sealing water, so that the template of steel plate waterstop strip lower part exists It is relatively difficult when dismounting, the construction efficiency of post-cast strip is affected, this problem has to be solved.
Utility model content
In view of the deficienciess of the prior art, stopping the purpose of this utility model is to provide a kind of sole plate post-poured strip Water steel plate support construction has the advantage that can effectively improve post empiricism efficiency.
To achieve the above object, the utility model provides following technical solution:
A kind of steel plate for sealing water support construction of sole plate post-poured strip, including main building bottom plate, underground garage bottom plate and inclination The sole plate steel bar layer being set between main building bottom plate and underground garage bottom plate is vertically arranged in the sole plate steel bar layer There are the first lower rebar being parallel to each other block piece and the second lower rebar block piece, the top of the first lower rebar block piece End is vertically arranged with the first upper reinforcement block piece, and the top of the second lower rebar block piece is vertically arranged with the second top Reinforcing bar block piece;It is provided with the first steel plate for sealing water between the first upper reinforcement block piece and the first lower rebar block piece, The second steel plate for sealing water is provided between the second upper reinforcement block piece and the second lower rebar block piece;First top Several are respectively connected between reinforcing bar block piece, the first steel plate for sealing water, the first lower rebar block piece and sole plate steel bar layer First spacer bar;The second upper reinforcement block piece, the second steel plate for sealing water, the second lower rebar block piece and sole plate Several second spacer bars are respectively connected between steel bar layer.
By using above-mentioned technical proposal, the first upper reinforcement block piece, the first steel plate for sealing water, the first lower rebar block Piece is welded to connect by the first spacer bar and sole plate steel bar layer, and the second upper reinforcement is blocked piece, the second steel plate for sealing water, the Two lower rebars block piece is welded to connect by the second spacer bar and sole plate steel bar layer.When post-cast strip pours, save The step of form removal, effectively increase the construction efficiency of post-cast strip.On the other hand, each reinforcing bar block piece makes concrete Rough surface after solidification contacts convenient for the post-cast strip concrete of after-pouring therewith, ensure that construction quality.
Further, the top surface of first steel plate for sealing water and the bottom end of the first upper reinforcement block piece are welded and fixed, bottom Face and the top of the first lower rebar block piece are welded and fixed;The top surface of second steel plate for sealing water and the second upper reinforcement are blocked The bottom end of piece is welded and fixed, and bottom surface and the top of the second lower rebar block piece are welded and fixed.
By using above-mentioned technical proposal, plays and the first steel plate for sealing water and the second steel plate for sealing water be tentatively welded and fixed Effect.
Further, first spacer bar and the second spacer bar are obliquely installed.
By using above-mentioned technical proposal, since triangle has the principle of stability, by the first spacer bar and second After spacer bar is obliquely installed, the support fixed function of the first spacer bar and the second spacer bar is improved.
Further, first spacer bar is respectively positioned on side of first steel plate for sealing water far from the second steel plate for sealing water, institute It states the second spacer bar and is respectively positioned on side of second steel plate for sealing water far from the first steel plate for sealing water.
By using above-mentioned technical proposal, after concrete setting, so that the first spacer bar and the second spacer bar are embedded Portion in the inner ensure that the stability of the first spacer bar and the second spacer bar fixed effect.On the other hand, the first supporting steel Muscle and the second spacer bar are located in the concrete of solidification, and it is right will not to influence its due to emergency situations (as bent, fractureing) The fixed effect of corresponding steel plate for sealing water and reinforcing bar block piece.
Further, the first upper reinforcement block piece, the first lower rebar block piece, the second upper reinforcement block Piece, the second lower rebar block piece are made of ommatidium expanded metal lath, thin eye steel wire and criss-cross block reinforcing bar, described small Eye expanded metal lath is located between block reinforcing bar and thin eye steel wire.
By using above-mentioned technical proposal, the structural strength of reinforcing bar block piece, ommatidium expanded metal lath and thin eye steel wire are improved The cooperation of net will not make concrete slurry leak hunting when pouring into post-cast strip.
Further, the diameter of the block reinforcing bar is 12mm.
By using above-mentioned technical proposal, diameter is strong for the structure that the block reinforcing bar of 12mm meets each reinforcing bar block piece Degree requires.
Further, resistance rust paint layer is provided on the ommatidium expanded metal lath and thin eye steel wire.
By using above-mentioned technical proposal, the corrosion of reinforcing bar block piece is effectively slowed down, will not occur to block due to reinforcing bar The case where piece corrosion damages and concrete slurry is caused to leak hunting.
Further, between the bottom end and sole plate steel bar layer of first lower rebar block piece, the second lower part steel Cement sand bed is provided between the bottom end and sole plate steel bar layer of muscle block piece.
By using above-mentioned technical proposal, adopted in the bottom end of the first lower rebar block piece and the second lower rebar block piece Blocked, effectively prevented during casting concrete slurry with cement mortar, concrete slurry from bottom overflow the case where.
In conclusion the utility model has the following beneficial effects:
1, by the first spacer bar of setting and the second spacer bar, the construction efficiency of post-cast strip is effectively increased;
2, by setting ommatidium expanded metal lath and thin eye steel wire, have the function of to prevent concrete slurry from leaking hunting;
3, by setting cement sand bed, having can prevent concrete slurry from the first lower rebar block piece and second The effect that the bottom of lower rebar block piece is overflowed.
Detailed description of the invention
Fig. 1 is the overall structure diagram of the steel plate for sealing water support construction of sole plate post-poured strip in embodiment;
Fig. 2 is the structural schematic diagram of the second upper reinforcement block piece in embodiment.
In figure: 1, main building bottom plate;2, underground garage bottom plate;3, sole plate steel bar layer;31, upper reinforcement layer;4, first Lower rebar block piece;41, the first upper reinforcement block piece;42, the first steel plate for sealing water;5, the second lower rebar block piece;51, Second upper reinforcement block piece;511, ommatidium expanded metal lath;512, thin eye steel wire;513, block reinforcing bar;52, the second water-stopping steel Plate;6, the first spacer bar;7, the second spacer bar;8, cement sand bed;9, post-cast strip.
Specific embodiment
The utility model is described in further detail below in conjunction with attached drawing.
This specific embodiment is only the explanation to the utility model, is not limitations of the present invention, ability Field technique personnel can according to need the modification that not creative contribution is made to the present embodiment after reading this specification, but As long as all by the protection of Patent Law in the scope of the claims of the utility model.
Embodiment:
A kind of steel plate for sealing water support construction of sole plate post-poured strip, referring to Fig.1 comprising main building bottom plate 1, underground garage Bottom plate 2 and sole plate steel bar layer 3, sole plate steel bar layer 3 are obliquely installed between main building bottom plate 1 and underground garage bottom plate 2, And the tilt angle of sole plate steel bar layer 3 is 30 degree.In the present embodiment, between main building bottom plate 1 and upper reinforcement layer 31 Distance is 5 meters, and the distance between underground garage bottom plate 2 and upper reinforcement layer 31 are 2.25 meters.
Referring to Fig.1, the first lower rebar block piece 4 and the second lower rebar are vertically arranged in sole plate steel bar layer 3 Block piece 5, the first lower rebar block piece 4 and the second lower rebar block piece 5 be parallel to each other, and bottom end with sole plate steel Muscle layer 3 is welded and fixed.The top of first lower rebar block piece 4 is vertically arranged with the first upper reinforcement block piece 41, under second The top of portion's reinforcing bar block piece 5 is vertically arranged with the second upper reinforcement block piece 51.
Referring to Fig.1, array is provided with several pieces between the first upper reinforcement block piece 41 and the first lower rebar block piece 4 First steel plate for sealing water 42, array is provided with several pieces between the second upper reinforcement block piece 51 and the second lower rebar block piece 5 Second steel plate for sealing water 52.The top surface of first steel plate for sealing water 42 and the bottom end of the first upper reinforcement block piece 41 are welded and fixed, bottom surface It is welded and fixed with the top of the first lower rebar block piece 4.The top surface of second steel plate for sealing water 52 and the second upper reinforcement block piece 51 bottom end is welded and fixed, and bottom surface and the top of the second lower rebar block piece 5 are welded and fixed.
Referring to Fig.1, between the first upper reinforcement block piece 41 and sole plate steel bar layer 3, the first steel plate for sealing water 42 and base Several first are welded between plinth baseplate reinforcing bar layer 3, between the first lower rebar block piece 4 and sole plate steel bar layer 3 Spacer bar 6.Second upper reinforcement blocks between piece 51 and sole plate steel bar layer 3, the second steel plate for sealing water 52 and sole plate Several second supporting steels are welded between steel bar layer 3, between the second lower rebar block piece 5 and sole plate steel bar layer 3 Muscle 7.In the present embodiment, the first spacer bar 6 is obliquely installed in the first steel plate for sealing water 42 far from the second steel plate for sealing water 52 Side, the second spacer bar 7 are obliquely installed in side of second steel plate for sealing water 52 far from the first steel plate for sealing water 42.
Referring to Fig.1, the one end of the first steel plate for sealing water 42 far from the second steel plate for sealing water 52 is with the first spacer bar 6 far from basis One end of baseplate reinforcing bar layer 3 is welded and fixed, the one end of the second steel plate for sealing water 52 far from the first steel plate for sealing water 42 and the second supporting steel Muscle 7 is welded and fixed far from one end of sole plate steel bar layer 3.The top of first upper reinforcement block piece 41, the first lower rebar The top of block piece 4 is welded and fixed with corresponding first spacer bar 6 far from one end of sole plate steel bar layer 3.On second Top, the top of the second lower rebar block piece 5 of portion's reinforcing bar block piece 51 are separate basic with corresponding second spacer bar 7 One end of baseplate reinforcing bar layer 3 is welded and fixed.First lower rebar block piece 4 bottom end and sole plate steel bar layer 3 between, second Cement sand bed 8, cement sand bed 8 are fixedly installed between the bottom end and sole plate steel bar layer 3 of lower rebar block piece 5 It is poured by cement mortar, has the function of that can be avoided concrete slurry casting is spilled over to post-cast strip 9 from bottom in the process.
Referring to Figures 1 and 2, the first upper reinforcement block piece 41, the first lower rebar block piece 4, the second upper reinforcement block Mesh sheet 51, the second lower rebar block piece 5 are by ommatidium expanded metal lath 511, thin eye steel wire 512 and criss-cross block reinforcing bar 513 compositions, ommatidium expanded metal lath 511 and thin eye steel wire 512 binds on reinforcing bar 513 of blocking, and ommatidium expanded metal lath 511 is located at It blocks between reinforcing bar 513 and thin eye steel wire 512.In the present embodiment, the diameter of block reinforcing bar 513 is 12mm, vertical direction The spacing of adjacent two blocks reinforcing bar 513 is 250mm in the spacing and horizontal direction of upper adjacent two blocks reinforcing bar 513.Separately Outside, in the present embodiment, the mesh size of thin eye steel wire 512 is 6.4mm × 6.4mm, the mesh size of ommatidium expanded metal lath 511 For 10.6mm × 10.6mm, the mesh of thin eye steel wire 512 and the mesh of ommatidium expanded metal lath 511 are staggered, so that respective steel The mesh of muscle block piece is smaller, the better effect for preventing concrete slurry from leaking hunting.Thin eye steel wire 512 and ommatidium expanded metal lath 511 On be additionally provided with resistance rust paint layer (not shown), resistance rust paint layer by resistance rust paint coats, the material used can refer to disclosure A kind of resistance rust paint disclosed in Chinese patent number for " CN103740273A ".
Working principle is as follows:
When building support construction, first by the bottom end of the first lower rebar block piece 4 and the second lower rebar block piece 5 It is welded and fixed with sole plate steel bar layer 3, then the first steel plate for sealing water 42 is welded in the top of the first lower rebar block piece 4 End, the top that the second steel plate for sealing water 52 is welded in the second lower rebar block piece 5.
After the first steel plate for sealing water 42 and the second steel plate for sealing water 52 is welded, the first lower rebar block piece 4 and first is stopped Water steel plate 42 is welded and fixed by the first spacer bar 6 with sole plate steel bar layer 3, the second lower rebar is blocked piece 5 and Second steel plate for sealing water 52 is welded and fixed by the second spacer bar 7 with sole plate steel bar layer 3.At this point, in the first water-stopping steel It welds the first upper reinforcement block piece 41, weld the second upper reinforcement block in the top surface of the second steel plate for sealing water 52 in the top surface of plate 42 Then first upper reinforcement block piece 41 is welded and fixed by the first spacer bar 6 with sole plate steel bar layer 3, is incited somebody to action by piece 51 Second upper reinforcement block piece 51 is welded and fixed by the second spacer bar 7 with sole plate steel bar layer 3.
When needing to pour post-cast strip 9, the step of capable of directly pouring, eliminate form removal, having can be effectively improved The advantage of 9 construction efficiency of post-cast strip.

Claims (8)

1. a kind of steel plate for sealing water support construction of sole plate post-poured strip, including main building bottom plate (1), underground garage bottom plate (2) and The sole plate steel bar layer (3) being obliquely installed between main building bottom plate (1) and underground garage bottom plate (2), it is characterised in that: described It is vertically arranged with the first lower rebar block piece (4) being parallel to each other in sole plate steel bar layer (3) and the second lower rebar is blocked Mesh sheet (5), the top of the first lower rebar block piece (4) is vertically arranged with the first upper reinforcement block piece (41), described The top of second lower rebar block piece (5) is vertically arranged with the second upper reinforcement block piece (51);First upper reinforcement It is provided with the first steel plate for sealing water (42) between block piece (41) and the first lower rebar block piece (4), second upper reinforcement The second steel plate for sealing water (52) are provided between block piece (51) and the second lower rebar block piece (5);
First upper reinforcement block piece (41), the first steel plate for sealing water (42), the first lower rebar block piece (4) and basic bottom Several first spacer bars (6) are respectively connected between plate steel bar layer (3);The second upper reinforcement block piece (51), second Several second is respectively connected between steel plate for sealing water (52), the second lower rebar block piece (5) and sole plate steel bar layer (3) It supports reinforcing bar (7).
2. the steel plate for sealing water support construction of sole plate post-poured strip according to claim 1, it is characterised in that: described first The top surface of steel plate for sealing water (42) and the bottom end of the first upper reinforcement block piece (41) are welded and fixed, and bottom surface is blocked with the first lower rebar The top of mesh sheet (4) is welded and fixed;The bottom of the top surface of second steel plate for sealing water (52) and the second upper reinforcement block piece (51) End is welded and fixed, and bottom surface and the top of the second lower rebar block piece (5) are welded and fixed.
3. the steel plate for sealing water support construction of sole plate post-poured strip according to claim 1, it is characterised in that: described first Spacer bar (6) and the second spacer bar (7) are obliquely installed.
4. the steel plate for sealing water support construction of sole plate post-poured strip according to claim 3, it is characterised in that: described first Spacer bar (6) is respectively positioned on the side of the first steel plate for sealing water (42) far from the second steel plate for sealing water (52), second spacer bar (7) it is respectively positioned on the side of the second steel plate for sealing water (52) far from the first steel plate for sealing water (42).
5. the steel plate for sealing water support construction of sole plate post-poured strip according to claim 1, it is characterised in that: described first Upper reinforcement is blocked piece (41), the first lower rebar is blocked piece (4), the second upper reinforcement block piece (51), the second lower rebar Block piece (5) is made of ommatidium expanded metal lath (511), thin eye steel wire (512) and criss-cross block reinforcing bar (513), institute Ommatidium expanded metal lath (511) are stated to be located between block reinforcing bar (513) and thin eye steel wire (512).
6. the steel plate for sealing water support construction of sole plate post-poured strip according to claim 5, it is characterised in that: the block The diameter of reinforcing bar (513) is 12mm.
7. the steel plate for sealing water support construction of sole plate post-poured strip according to claim 5, it is characterised in that: the ommatidium Resistance rust paint layer is provided on expanded metal lath (511) and thin eye steel wire (512).
8. the steel plate for sealing water support construction of sole plate post-poured strip described in any one of -7, feature exist according to claim 1 In: between the bottom end and sole plate steel bar layer (3) of first lower rebar block piece (4), the second lower rebar block piece (5) cement sand bed (8) are provided between bottom end and sole plate steel bar layer (3).
CN201820786946.9U 2018-05-23 2018-05-23 The steel plate for sealing water support construction of sole plate post-poured strip Expired - Fee Related CN208293624U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820786946.9U CN208293624U (en) 2018-05-23 2018-05-23 The steel plate for sealing water support construction of sole plate post-poured strip

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820786946.9U CN208293624U (en) 2018-05-23 2018-05-23 The steel plate for sealing water support construction of sole plate post-poured strip

Publications (1)

Publication Number Publication Date
CN208293624U true CN208293624U (en) 2018-12-28

Family

ID=64728712

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820786946.9U Expired - Fee Related CN208293624U (en) 2018-05-23 2018-05-23 The steel plate for sealing water support construction of sole plate post-poured strip

Country Status (1)

Country Link
CN (1) CN208293624U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111501846A (en) * 2020-05-06 2020-08-07 无锡锡晟建设有限公司 Water stop steel plate supporting structure of foundation bottom plate post-cast strip

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111501846A (en) * 2020-05-06 2020-08-07 无锡锡晟建设有限公司 Water stop steel plate supporting structure of foundation bottom plate post-cast strip
CN111501846B (en) * 2020-05-06 2021-06-15 无锡锡晟建设有限公司 Water stop steel plate supporting structure of foundation bottom plate post-cast strip

Similar Documents

Publication Publication Date Title
CN214061703U (en) Seepage-proofing structure for post-cast strip of bottom plate of underground chamber
CN107326940B (en) basement advanced water stop post-cast strip structure and construction method thereof
CN207512697U (en) Post-cast strip antipriming
CN109183825A (en) The construction method of raft board post poured band side form
CN208293624U (en) The steel plate for sealing water support construction of sole plate post-poured strip
CN206233560U (en) Wall formwork erecting structure
CN208168479U (en) A kind of prefabricated rod structure in inspection hole
CN201473974U (en) Novel steel plate water stopper
CN113585351A (en) Soil covering plane settlement post-cast strip prefabrication advanced reverse order closed construction method
CN213174773U (en) Support system is exempted from to tear open type post-cast strip structure
CN208918266U (en) One kind exempting from support formula steel plate post-cast strip template structure system
CN209603277U (en) Basement waterproofing structure
CN112112292A (en) Construction method for preventing concrete from permeating into two sides of post-cast strip of bottom plate of garage
KR101120588B1 (en) Vertical joint frame for improving monolithic concrete
CN110005112A (en) A kind of pitched roof concrete structure and its construction method
CN213296440U (en) Water stop structure for post-cast strip of underground chamber bottom plate
CN209837333U (en) Reinforced concrete induction belt structure for post-cast strip position
CN208934012U (en) A kind of poured band of outer wall of basement structure
CN207646861U (en) A kind of prefabricated air-conditioning harden structure with drain function
CN218205758U (en) Different strength concrete intercepting device
CN215562825U (en) Advanced water stop structure of post-cast strip of foundation beam
CN208472794U (en) A kind of basement bottom board post-concreted expansion strip structure
CN214885531U (en) Side edge steel breast board of post-cast strip for construction
CN209369347U (en) The steel plate for sealing water support construction of sole plate variable cross-section pouring after settlement
CN205742662U (en) Node installed by a kind of connector and Side fascia

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181228

Termination date: 20210523

CF01 Termination of patent right due to non-payment of annual fee