Steel box girder construction hanging basket device Download PDFInfo
- Publication number
- CN208280029U CN208280029U CN201820571333.3U CN201820571333U CN208280029U CN 208280029 U CN208280029 U CN 208280029U CN 201820571333 U CN201820571333 U CN 201820571333U CN 208280029 U CN208280029 U CN 208280029U
- Authority
- CN
- China
- Prior art keywords
- hanging basket
- steel box
- girder
- basket device
- workbench
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The utility model discloses a kind of steel box girder construction hanging basket devices comprising top walking steelframe, connecting rod, workbench, idler wheel and the fixed mechanism for connecting with steel box-girder top panel;Top walking steelframe is located above the outrigger of steel box-girder, is connect by connecting rod with workbench, workbench is located at below outrigger;Top steelframe of walking is equipped with idler wheel, can on outrigger panel along bridge to walking;Fixed mechanism is located at the end of top walking steelframe, and hanging basket device and steel box-girder are fixed by magnetism;In use, drawn by manpower or motor, after so that Hanging Basket is moved longitudinally to construction point along bridge, hanging basket device and steel box-girder are fixed by fixed mechanism.The use of the utility model will not cause to damage to box beam top plate, just be able to maintain Hanging Basket balance without counterweight is increased.
Description
Technical field
The utility model belongs to technical field of bridge construction, and in particular to a kind of steel box girder construction hanging basket device.
Background technique
With the continuous maturation of economic continuous development and technology, steel box girder bridge is gradually shown one's talent in urban construction.
In the construction of steel box girder bridge, the welding, internal weld seams coating, decoration to outrigger tabula is carried out below the outrigger after lifting are needed
The construction operations such as plate closing.When constructing below to outrigger, Hanging Basket is generallyd use.It is steel wire that existing Hanging Basket, which usually relies on,
Rope adds counterweight in tail end to maintain to balance, but is that wirerope needs to weld multiple hanging points on box beam surface, to box beam top surface
Damage larger, counterweight then has the problems such as greatly increasing hanging basket weight, Hanging Basket difficulty in walking, counterweight is easily fallen.
Utility model content
The purpose of this utility model is to provide a kind of steel box girder construction hanging basket devices, and the use of the hanging basket device will not
Box beam top plate is caused to damage, is just able to maintain Hanging Basket balance without additional weight is increased.
The technical scheme adopted by the utility model is
A kind of steel box girder construction hanging basket device comprising walking steelframe in top, workbench, idler wheel and is used for connecting rod
The fixed mechanism being connect with steel box-girder top surface;
The top walking steelframe is located above the outrigger of steel box-girder, is connect by connecting rod with workbench, the work
Platform is located at below outrigger;
The idler wheel is mounted on top walking steelframe;
The fixed mechanism is located at the end of top walking steelframe, is consolidated hanging basket device and steel box-girder by magnetism
It is fixed;
In use, drawn by manpower or motor, after so that Hanging Basket is moved longitudinally to construction point along bridge, by solid
Determine mechanism hanging basket device and steel box-girder are fixed.
According to the above scheme, the fixed mechanism includes sucked type electromagnet, and sucked type electromagnet uses self-powered power supply
Or it is powered using external power supply;Sucked type electromagnet is powered, and generates ferromagnetism, and hanging basket device and steel box-girder are firmly adsorbed on one
It rises, is fixedly connected with hanging basket device with steel box-girder, to play the role of fixed Hanging Basket;The power-off of sucked type electromagnet, magnetism disappear
It loses, in the case where manpower or motor are drawn, hanging basket device is vertically moved along bridge.Using the magnetism of sucked type electromagnet to Hanging Basket
It is fixed, without welding hanging point in bridge floor, box beam top surface will not be caused to damage, be just able to maintain without additional weight is increased
Hanging Basket balance;And device is simple, safe and reliable.
According to the above scheme, the fixed mechanism includes permanent magnet;In use, permanent magnet is adsorbed on steel box-girder top surface, when need
When wanting hanging basket device mobile, device is disconnected by magnetism and separates permanent magnet and steel box-girder, in the case where manpower or motor are drawn,
Hanging basket device is vertically moved along bridge;It is adsorbed by permanent magnet, box beam top surface will not be caused to damage, it is additional heavy without increasing
Amount is just able to maintain Hanging Basket balance.
According to the above scheme, top walking steelframe, connecting rod, workbench are structure as a whole, to improve the stabilization of hanging basket device
Property.
According to the above scheme, top walking steelframe, connecting rod, workbench form U-shaped structure, and outrigger lower part is facilitated to construct.
According to the above scheme, the periphery of the workbench is equipped with guardrail, to ensure the safety of worker.
The utility model has the beneficial effects that:
Hanging basket device and steel box-girder top panel are fixed by magnetism for fixed mechanism, will not be made to steel box-girder top panel
At damage;
Using the suction-operated of magnet, hanging device is fixed on steel box-girder, is just able to maintain Hanging Basket without increasing counterweight
Balance;
Structure is simple, easy to use.
Detailed description of the invention
Below in conjunction with accompanying drawings and embodiments, the utility model is described in further detail, in attached drawing:
Fig. 1 is the structural schematic diagram of the utility model embodiment;
In figure: 1, top walking steelframe, 2, workbench, 3, idler wheel, 4, sucked type electromagnet, 5, connecting rod, 6, guardrail, 7,
Steel box-girder, 8, outrigger.
Specific embodiment
In order to make the purpose of the utility model, technical solutions and advantages more clearly understood, below in conjunction with attached drawing and implementation
Example, the present invention will be further described in detail.It should be appreciated that specific embodiment described herein is only to explain this
Utility model is not used to limit the utility model.
Embodiment 1, referring to Fig. 1, a kind of steel box girder construction hanging basket device comprising top row steelframe 1, connecting rod 5, work
Platform 2, idler wheel 3 and the sucked type electromagnet 4 for being connect with the top panel of steel box-girder 7.Top walking steelframe 1 is located at outrigger 8
Top is connect by connecting rod 5 with workbench 2, and workbench 2 is located at 8 lower section of outrigger;Top walking steelframe 1, connecting rod 5, work
Platform 2 is structure as a whole, and forms U-shaped structure;In order to ensure the safety of worker, guardrail 6 is set on the periphery of workbench 2.Rolling
Wheel 3 is mounted on top walking steelframe 1.Sucked type electromagnet 4 is connect with the end of top walking steelframe 1, sucked type electromagnet 4
It powers using self-powered power supply or using external power supply.Sucked type electromagnet 4 be powered, generate ferromagnetism, by hanging basket device with
Outrigger 8 is firmly attached together, and is fixedly connected with hanging basket device with steel box-girder, to play the role of fixed Hanging Basket;Sucked type
Electromagnet 4 powers off, and magnetism disappears, and in the case where manpower or motor are drawn, hanging basket device is vertically moved along bridge;Work as hanging basket device
After being moved to construction point, sucked type electromagnet 4 is powered, and hanging basket device and steel box-girder 7 are firmly attached together, arrived under worker
It constructs on workbench;When needing the power-off of sucked type electromagnet 4 in the construction of next construction point, by manpower or
Motor is drawn, and Hanging Basket is made to move longitudinally to construction point along bridge, then sucked type electromagnet 4 is made to be powered, by hanging basket device
It is fixed with steel box-girder.
Embodiment 2, with embodiment 1 the difference is that top walking steelframe 1 end connect is permanent magnet, permanent magnet
Pass through the magnetic magnetic absorption for disconnecting device control and bridge floor.In use, permanent magnet is adsorbed on steel box-girder top surface, when needing Hanging Basket
When device is mobile, magnetism disconnects device and separates permanent magnet and steel box-girder, in the case where manpower or motor are drawn, hanging basket device edge
Bridge longitudinal movement.
In the utility model, hanging basket device has certain width, is supported using two pairs of idler wheels.Hanging Basket is on the outside of bridge
Be provided with staircase for worker above and below.
It should be understood that for those of ordinary skills, it can be modified or changed according to the above description,
And all these modifications and variations all should belong to the protection scope of the appended claims for the utility model.
Claims (6)
1. a kind of steel box girder construction hanging basket device, it is characterised in that: including top walking steelframe, connecting rod, workbench, idler wheel
With the fixed mechanism for being connect with steel box-girder top panel;
The top walking steelframe is located above the outrigger of steel box-girder, is connect by connecting rod with workbench, the workbench
Below outrigger;
The idler wheel is mounted on top walking steelframe;
The fixed mechanism is located at the end of top walking steelframe, and hanging basket device and steel box-girder are fixed by magnetism;
In use, drawn by manpower or motor, after so that Hanging Basket is moved longitudinally to construction point along bridge, pass through fixed machine
Hanging basket device and steel box-girder are fixed structure.
2. steel box girder construction hanging basket device according to claim 1, it is characterised in that: the fixed mechanism includes sucker
Formula electromagnet, sucked type electromagnet are powered using self-powered power supply or using external power supply;When sucked type electromagnet is powered,
Hanging basket device and steel box-girder are fixedly connected by fixed mechanism, when the power-off of sucked type electromagnet, are carried out in manpower or motor
Under traction, Hanging Basket is vertically moved along bridge.
3. steel box girder construction hanging basket device according to claim 1, it is characterised in that: the fixed mechanism includes permanent magnetism
Iron, when needing hanging basket device mobile, disconnects device for permanent magnetism by magnetism in use, permanent magnet is adsorbed on steel box-girder top surface
Iron is separated with steel box-girder.
4. steel box girder construction hanging basket device according to claim 1, it is characterised in that: top walking steelframe, connecting rod, work
It is structure as a whole as platform.
5. steel box girder construction hanging basket device according to claim 1 or 4, it is characterised in that: walking steelframe in top connects
Bar, workbench form U-shaped structure.
6. steel box girder construction hanging basket device according to claim 1, it is characterised in that: the periphery of the workbench is set
There is guardrail.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820571333.3U CN208280029U (en) | 2018-04-20 | 2018-04-20 | Steel box girder construction hanging basket device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820571333.3U CN208280029U (en) | 2018-04-20 | 2018-04-20 | Steel box girder construction hanging basket device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208280029U true CN208280029U (en) | 2018-12-25 |
Family
ID=64751734
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820571333.3U Active CN208280029U (en) | 2018-04-20 | 2018-04-20 | Steel box girder construction hanging basket device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208280029U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110777666A (en) * | 2019-11-12 | 2020-02-11 | 广州市第一市政工程有限公司 | Steel box girder construction platform and use method |
CN111608381A (en) * | 2020-06-20 | 2020-09-01 | 中国二十二冶集团有限公司 | Horizontal annular welding construction platform for bin |
CN113172891A (en) * | 2020-01-08 | 2021-07-27 | 塑成科技(北京)有限责任公司 | Control system and control method for controlling operation trough and 3D printing equipment |
-
2018
- 2018-04-20 CN CN201820571333.3U patent/CN208280029U/en active Active
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110777666A (en) * | 2019-11-12 | 2020-02-11 | 广州市第一市政工程有限公司 | Steel box girder construction platform and use method |
CN113172891A (en) * | 2020-01-08 | 2021-07-27 | 塑成科技(北京)有限责任公司 | Control system and control method for controlling operation trough and 3D printing equipment |
CN113172891B (en) * | 2020-01-08 | 2023-10-03 | 塑成科技(北京)有限责任公司 | Control system and control method for controlling operation trough and 3D printing equipment |
CN111608381A (en) * | 2020-06-20 | 2020-09-01 | 中国二十二冶集团有限公司 | Horizontal annular welding construction platform for bin |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208280029U (en) | Steel box girder construction hanging basket device | |
CN206108800U (en) | Special moving staircase of aircraft maintenance personnel | |
CN210505300U (en) | Gantry crane with electric hoist | |
CN102587277A (en) | Mobile equipment special for construction and maintenance of bridge barriers | |
CN205529883U (en) | Guardrail fitment platform | |
CN204098952U (en) | A kind of coal mine roadway centre mounted type container handling equipment | |
CN204474174U (en) | A kind of general-purpose overhead crane | |
CN201587828U (en) | Gantry crane | |
CN206691869U (en) | A kind of single pile movement system | |
CN202611340U (en) | Self-propelled road bed protective barrier transportation and installation all-in-one machine | |
CN204096946U (en) | A kind of lifting appliance and container handling crane | |
CN204057696U (en) | A kind of gate type portal gantry | |
CN202247682U (en) | Curtain board mounting bridge crane | |
CN104555837A (en) | Boiler overhauling platform | |
CN205893895U (en) | Tunnel construction small cross section is lifting and horizontal moving device of access bridge platform truck by oneself | |
CN205275061U (en) | Semi -portal crane | |
CN204727495U (en) | A kind of large-tonnage cable carries hoisting crane | |
CN204173776U (en) | Frame-type low clearance armored rope electric hoist dolly | |
CN103569842A (en) | Lifting appliance for gantry crane | |
CN207469857U (en) | Vehicle conveying equipment | |
CN205954488U (en) | A work dolly that is used for bridge seam form setting that wets | |
CN205616533U (en) | A drive arrangement for high -speed stacker | |
CN206157498U (en) | Sleeper hoisting gate frame of walking on railway ballastless track construction section of track | |
CN208362932U (en) | Anticollision barrier construction hanging basket | |
CN204324738U (en) | With the lifting mechanism of balanced system |