CN208266614U - Novel cold regeneration asphalt pavement structure - Google Patents
Novel cold regeneration asphalt pavement structure Download PDFInfo
- Publication number
- CN208266614U CN208266614U CN201820850711.1U CN201820850711U CN208266614U CN 208266614 U CN208266614 U CN 208266614U CN 201820850711 U CN201820850711 U CN 201820850711U CN 208266614 U CN208266614 U CN 208266614U
- Authority
- CN
- China
- Prior art keywords
- asphalt
- cold
- road surface
- upper hopper
- base
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
Novel cold regeneration asphalt pavement structure.Its composition includes: soil layer, the top of the soil layer is laid with bed course, the top of the bed course is laid with base, the top of the base is laid with cold recycled asphalt and combines road surface, the cold recycled asphalt combines road surface, the bed course, the base is provided with the water seepage hole communicated, the water seepage hole is inserted into soakaway trench, the bottom of the soakaway trench connects lower funnel, the top of the soakaway trench connects upper hopper, the outside diameter circle of the lower funnel is less than bottom circular diameter, the outside diameter circle of the upper hopper is greater than bottom circular diameter, the top of the upper hopper covers sieve, top surface 1cm of the sieve lower than the cold recycled asphalt combination road surface.The utility model is used for cold recycled asphalt road surface.
Description
Technical field:
The utility model relates to a kind of Novel cold regeneration asphalt pavement structures.
Background technique:
It is to carry out being laid with road surface, the cost of cold recycled asphalt using cold recycled asphalt that existing highway pavement, which has some,
It is low, but anti-aging property is not so good as heat regeneration asphalt, so when being laid with road surface using cold recycled asphalt, the mass of foundation on road surface
It is better, the long service life of cold recycled asphalt can be made;But there is the phenomenon that very ponding on existing road surface, ponding will reduce
The service life of cold recycled asphalt.
Summary of the invention:
The purpose of the utility model is to provide one kind, and the ponding on road surface can be made quickly to exhaust, and extending cold recycled asphalt makes
With the Novel cold regeneration asphalt pavement structure in service life.
Above-mentioned purpose is realized by following technical scheme:
A kind of Novel cold regeneration asphalt pavement structure, composition includes: soil layer, and the top of the soil layer is laid with bed course,
The top of the bed course is laid with base, and the top of the base is laid with cold recycled asphalt and combines road surface, the cold renewal
Pitch combination road surface, the bed course, the base are provided with the water seepage hole communicated, and the water seepage hole is inserted into soakaway trench, institute
The bottom for the soakaway trench stated connects lower funnel, and the top of the soakaway trench connects upper hopper, and the tip circle of the lower funnel is straight
Diameter is less than bottom circular diameter, and the outside diameter circle of the upper hopper is greater than bottom circular diameter, and the top of the upper hopper covers sieve,
Top surface 1cm of the sieve lower than the cold recycled asphalt combination road surface.
The junction of the Novel cold regeneration asphalt pavement structure, the soakaway trench and the upper hopper passes through steel
Silk screen connection, the top of the soakaway trench pass through the mesh of the steel wire, and the lower funnel is embedded in the soil layer
Interior, the steel wire is located at the cold recycled asphalt and combines road surface.
The Novel cold regeneration asphalt pavement structure, the cold recycled asphalt combination road surface includes cement stabilized macadam mixing
Layer, the bottom connection of the cement stabilized macadam mixed layer base, the top of the cement stabilized macadam mixed layer connects water
The top of mud the hoggin grass root, the cement soil additive connects asphalt concrete cutting optimal,
Surface layer in the top connection asphalt concrete of the asphalt concrete cutting optimal, the asphalt concrete
The top of middle surface layer connects cold recycled asphalt supercrust, the upper hopper be located in the asphalt concrete surface layer with
In the cold recycled asphalt supercrust, the soakaway trench penetrates the bed course, the base, the cement stabilized macadam
Mixed layer, the cement soil additive, the asphalt concrete cutting optimal.
The utility model has the advantages that
1. the outside diameter circle of the upper hopper of the utility model is smaller, generally between 4-8 cm, surface area is small, and low
It is not easy to be subject to crushing in cold recycled asphalt supercrust, infiltration effect is good, can make cold recycled asphalt supercrust not ponding, and rain
Snow-broth will not enter other levels other than soil layer, can greatly extend the service life of cold recycled asphalt supercrust.
The phenomenon that sieve of the utility model can stop sundries to enter upper hopper, soakaway trench is avoided to be blocked, infiltration
It is smooth, effect is good.
The steel wire of the utility model can be good at the position between fixed soakaway trench, seep during being laid with highway
Water pipe is not easy skew, be able to maintain infiltration it is unimpeded, increase the ability of infiltration.
The cold recycled asphalt supercrust of the utility model can greatly reduce cost of building the road, and can accelerate to build the road
Speed, using effect are very good.
Detailed description of the invention:
Attached drawing 1 is the structural schematic diagram of this product.
Specific embodiment:
Below in conjunction with the attached drawing of the utility model, the technical scheme in the embodiment of the utility model is carried out clear, complete
Site preparation description.
Embodiment 1:
A kind of Novel cold regeneration asphalt pavement structure, composition include: soil layer 1, and the top of the soil layer is laid with bed course
2, the top of the bed course is laid with base 3, and the top of the base is laid with cold recycled asphalt and combines road surface, it is described it is cold again
Raw pitch combination road surface, the bed course, the base are provided with the water seepage hole 4 communicated, and the water seepage hole is inserted into soakaway trench
5, the bottom of the soakaway trench connects lower funnel 6, and the top of the soakaway trench connects upper hopper 7, the lower funnel
Outside diameter circle is less than bottom circular diameter, and the outside diameter circle of the upper hopper is greater than bottom circular diameter, covers at the top of the upper hopper
Lid sieve 8, top surface 1cm of the sieve lower than the cold recycled asphalt combination road surface.
The soakaway trench is connect with the junction of the upper hopper by steel wire 9, the top of the soakaway trench
Across the mesh 10 of the steel wire, the lower funnel is embedded in the soil layer, and the steel wire is located at described
Cold recycled asphalt combines road surface.
The cold recycled asphalt combination road surface includes cement stabilized macadam mixed layer 11, the bottom of the cement stabilized macadam mixed layer
Portion's connection base, the top of the cement stabilized macadam mixed layer connects cement soil additive 12, described
The top of cement soil additive connects asphalt concrete cutting optimal 13, below the asphalt concrete
The top of layer connects surface layer 14 in asphalt concrete, and the top of surface layer connects cold renewal in the asphalt concrete
Blacktop 15, the upper hopper are located at surface layer and the cold recycled asphalt road surface in the asphalt concrete
In layer, it is steady that the soakaway trench penetrates the bed course, the base, the cement stabilized macadam mixed layer, the cement
Determine graded broken stone base, the asphalt concrete cutting optimal.
Working principle:
Be laid with soil layer first, then by lower funnel, soakaway trench is endways stands in soil layer, be then sequentially laid with bed course, base,
Cement stabilized macadam mixed layer, cement soil additive, asphalt concrete cutting optimal, face in asphalt concrete
Steel wire, is laid on the junction of upper hopper and soakaway trench by layer, in connection upper hopper and soakaway trench, is leaked covering sieve
On bucket, it is finally laid with cold recycled asphalt supercrust.
Claims (3)
1. a kind of Novel cold regeneration asphalt pavement structure, composition includes: soil layer, it is characterized in that: the top of the soil layer is spread
If bed course, the top of the bed course is laid with base, and the top of the base is laid with cold recycled asphalt and combines road surface, described
Cold recycled asphalt combination road surface, the bed course, the base are provided with the water seepage hole communicated, and the water seepage hole is inserted into infiltration
Pipe, the bottom of the soakaway trench connect lower funnel, and the top of the soakaway trench connects upper hopper, the top of the lower funnel
Circular diameter is less than bottom circular diameter, and the outside diameter circle of the upper hopper is greater than bottom circular diameter, and the top of the upper hopper covers
Sieve, top surface 1cm of the sieve lower than the cold recycled asphalt combination road surface.
2. Novel cold regeneration asphalt pavement structure according to claim 1, it is characterized in that: the soakaway trench with it is described
The junction of upper hopper connected by steel wire, the top of the soakaway trench passes through the mesh of the steel wire, described
Lower funnel be embedded in the soil layer, the steel wire is located at the cold recycled asphalt and combines road surface.
3. Novel cold regeneration asphalt pavement structure according to claim 2, it is characterized in that: the cold recycled asphalt group
Combining face includes cement stabilized macadam mixed layer, the bottom connection of the cement stabilized macadam mixed layer base, the cement
The top of rubble mixed layer connects cement soil additive, the top connection of the cement soil additive
The top of asphalt concrete cutting optimal, the asphalt concrete cutting optimal connects face in asphalt concrete
Layer, the top of surface layer connects cold recycled asphalt supercrust in the asphalt concrete, and the upper hopper is located at described
Asphalt concrete in surface layer and the cold recycled asphalt supercrust, the soakaway trench penetrate the bed course,
The base, the cement stabilized macadam mixed layer, the cement soil additive, the plain asphalt coagulation
Native cutting optimal.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820850711.1U CN208266614U (en) | 2018-06-04 | 2018-06-04 | Novel cold regeneration asphalt pavement structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820850711.1U CN208266614U (en) | 2018-06-04 | 2018-06-04 | Novel cold regeneration asphalt pavement structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208266614U true CN208266614U (en) | 2018-12-21 |
Family
ID=64689512
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820850711.1U Expired - Fee Related CN208266614U (en) | 2018-06-04 | 2018-06-04 | Novel cold regeneration asphalt pavement structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208266614U (en) |
-
2018
- 2018-06-04 CN CN201820850711.1U patent/CN208266614U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101446082B (en) | Construction method of building anti-permeability channel using soil curing agent | |
CN106193066B (en) | A kind of Loess landslide administering method based on restoration of the ecosystem | |
CN206928164U (en) | A kind of drainage type concrete road | |
CN207227890U (en) | A kind of environment protection asphalt pavement structure | |
CN103510441A (en) | Three-dimensional-drainage roadbed structure for preventing water damage of road in cold region and construction method thereof | |
CN107881858A (en) | A kind of new railway sub-grade surface structure and its laying method | |
CN209024909U (en) | A kind of sponge Multifunctional City pavement structure | |
CN101403209B (en) | Fast water-permeable brick for stopping pad and laying method | |
RU2492290C1 (en) | Method to construct motor roads and motor road design | |
CN109594567A (en) | A kind of shotcrete protection rock slope ecological safeguard structure arrangement and its method | |
CN207259961U (en) | A kind of Reflection Cracking type heavy traffic drainage pavement paving structure | |
CN104674842B (en) | Solidified earth barricade and constructional method thereof | |
CN106012971A (en) | Vegetation concrete protection slope and construction method thereof | |
CN104452515B (en) | A kind of anti-row's convolution comprehensive road surface drainage system | |
CN208266614U (en) | Novel cold regeneration asphalt pavement structure | |
CN209211198U (en) | A kind of urban environmental protection road surface | |
CN105332328B (en) | The collapsible loess road structure of water-impervious and the process for constructing with the structure road | |
CN206768838U (en) | A kind of Protection of Expansive Soil structure | |
CN203113635U (en) | Heavy-grade planted roof structure | |
CN206752237U (en) | Stealthy passageway for fire apparatus | |
CN206553848U (en) | Embankment section road surface edge structure | |
CN105525551B (en) | To the remodeling method and grass planting pavement structure of Wind Power Stations temporary construction road | |
CN209010890U (en) | A kind of triangular concrete gutter structure for highway drainage | |
CN208486146U (en) | A kind of novel filter infiltration garden road step and sunk type square laying structure | |
CN209010891U (en) | A kind of multi-functional lobby drainage facility |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20181221 Termination date: 20190604 |