CN208251629U - A kind of highway slope protection is marked time template - Google Patents

A kind of highway slope protection is marked time template Download PDF

Info

Publication number
CN208251629U
CN208251629U CN201820766525.XU CN201820766525U CN208251629U CN 208251629 U CN208251629 U CN 208251629U CN 201820766525 U CN201820766525 U CN 201820766525U CN 208251629 U CN208251629 U CN 208251629U
Authority
CN
China
Prior art keywords
interior
plate
template
slope protection
front apron
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820766525.XU
Other languages
Chinese (zh)
Inventor
谢建权
谢建奇
席晓东
谢凌通
谢晓旭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ningxia Lifeng Agricultural Machinery Manufacturing Co Ltd
Original Assignee
Ningxia Lifeng Agricultural Machinery Manufacturing Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ningxia Lifeng Agricultural Machinery Manufacturing Co Ltd filed Critical Ningxia Lifeng Agricultural Machinery Manufacturing Co Ltd
Priority to CN201820766525.XU priority Critical patent/CN208251629U/en
Application granted granted Critical
Publication of CN208251629U publication Critical patent/CN208251629U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

It marks time template the utility model discloses a kind of highway slope protection, including interior side form and outer side mold, wherein interior side form is made of several modular units of marking time, modular unit of each marking time includes at least two interior plates and several front aprons, two interior plates and a front apron assembling constitute level-one step, front apron is accordingly increased between two interior plates, forms multi-stage stairs;Outer side mold is the plate mould being mounted on the outside of two interior plates, is attached along interior side form side wall.The slope surface of both sides of highway is dexterously utilized as bed die in the utility model, the groove that certain depth is set in the place digging in advance marked time is poured in needs accordingly, only need to be connected and installed in interior side form with outer side mold to need to pour when group mould can pour after completion template assemblies in the groove marked time, compared with prior art, with quick for installation, convenient advantage is removed, while reducing transportation cost, improves construction efficiency.

Description

A kind of highway slope protection is marked time template
Technical field:
The utility model belongs to road engineering die plate equipment technical field, more particularly to a kind of public for cast-type concrete Road slope protection is marked time template.
Background technique:
Existing highway marks time a part as cast in situs, needs to splice various templates according to step dimension when pouring, pass Unite template construction after, there is a problem of form removable trouble, be easy truncation lack angle and installation and dismantling operation inconvenience;Another portion It is divided into and shifts to an earlier date prefabricated completion in concrete prefabricated factory, then transport construction site to again and installed, there are transportation cost height, are transporting The shortcomings that also cement products being be easy to cause to damage in the process.
Summary of the invention:
Of the existing technology in order to overcome the problems, such as, the utility model provides a kind of installation and to remove convenient cast-type mixed Solidifying soil highway slope protection is marked time template.
In order to solve the above technical problems, the utility model takes following technical scheme:
A kind of highway slope protection is marked time template, including interior side form and outer side mold, wherein in side form by several template lists of marking time Member composition, modular unit of each marking time include at least two interior plates and several front aprons, two interior plates and a front Board group dress constitutes level-one step, and front apron is accordingly increased between two interior plates, forms multi-stage stairs;Outer side mold is installation Plate mould on the outside of two interior plates is attached along interior side form side wall.
Above-mentioned two interior plate is made of left plate and right side plate mirror symmetry, and left plate is set respectively with right side board ends There is unit connecting plate, unit connecting plate is for the connection between two neighboring modular unit of marking time;Left plate and right side plate it is interior Side is respectively equipped with several front aprons connection channel steel, and front apron connects channel steel and is used between front apron and left plate and right side plate Connection;The upper end of left plate and right side plate is respectively welded support angle steel, the both ends of support angle steel and left plate and right side plate two The unit connecting plate at end welds together, and support angle steel plays the role of fixed cell connecting plate and guarantees side plate straightness.
Above-mentioned front board ends are equipped with connecting flange, and connecting flange connect channel steel with front apron and is correspondingly connected with when organizing mould.
Further, above-mentioned front apron connection channel steel is cuboid channel steel, and the wide face of channel steel is equipped with leg mould mandril wire hole, For fastening leg mould mandril, i.e., after the completion of mixed mud pours, leg mould mandril only need to be fastened, side form level can be ejected, it is complete At leg mould.
Further, above-mentioned highway slope protection marks time template using the slope surface of both sides of highway as bed die, in pre- by size in slope surface It first digs and sets the groove of certain depth, interior side form and outer side mold are installed in groove, that is, complete a set of highway slope protection and mark time template Assembling.Length when site operation according to slope surface can connect the highway slope protections that cover more and mark time template.
The utility model has the beneficial effects that: the utility model highway slope protection is marked time, highway two is dexterously utilized in template The slope surface of side pours the groove that certain depth is set in the place digging in advance marked time in needs accordingly, only needs when organizing mould as bed die By interior side form and outer side mold be connected and installed in needs pour complete template assemblies in the groove marked time after can pour, and it is existing There is technology to compare, have it is quick for installation, remove convenient advantage, while reducing transportation cost, improve construction efficiency.
Detailed description of the invention:
Fig. 1 is that the utility model highway slope protection is marked time the structural schematic diagram of template;
Fig. 2 is that the utility model highway slope protection is marked time the structural schematic diagram of left plate in template;
Fig. 3 is that the utility model highway slope protection is marked time the structural schematic diagram of front apron in template;
In figure: side form in 1-, 2- outer side mold, 3- front apron, 4- left plate, 5- right side plate, 6- unit connecting plate, 7- front Plate connects channel steel, 8- support angle steel, 9- connecting flange, 10- leg mould mandril wire hole, 11- leg mould mandril.
Specific embodiment:
The technical solution of the utility model is described in detail with reference to the accompanying drawing.
As shown in FIG. 1 to 3, a kind of highway slope protection is marked time template, including interior side form 1 and outer side mold 2, wherein in side form 1 It being made of several modular units of marking time, modular unit of each marking time includes at least two interior plates and several front aprons 3, and two A interior plate and an assembling of front apron 3 constitute level-one step, and front apron 3 is accordingly increased between two interior plates, is formed Multi-stage stairs;Outer side mold 2 is the plate mould being mounted on the outside of two interior plates, is attached along interior side form side wall;It is described Two interior plates are made of left plate 4 and 5 mirror symmetry of right side plate, and left plate 4 and 5 both ends of right side plate are respectively equipped with unit company Fishplate bar 6, unit connecting plate 6 is for the connection between two neighboring modular unit of marking time;The inside of left plate 4 and right side plate 5 point Not She You several front aprons connect channel steel 7, front apron connect channel steel 7 be used between front apron 3 and left plate 4 and right side plate 5 Connection;The upper end of left plate 4 and right side plate 5 is respectively welded support angle steel 8, the both ends and left plate 4 and the right side of support angle steel 8 The unit connecting plate 6 at 5 both ends of side plate welds together, and support angle steel 8 plays fixed cell connecting plate 6 and guarantees side plate straightness Effect;3 both ends of front apron are equipped with connecting flange 9, and connecting flange 9 connect channel steel 7 with front apron and is correspondingly connected with when organizing mould.
Further, the front apron connection channel steel 7 is cuboid channel steel, and the wide face of channel steel is equipped with leg mould mandril wire hole 10, for fastening leg mould mandril 11, i.e., after the completion of mixed mud pours, leg mould mandril 11 only need to be fastened, it can be by side form level Leg mould is completed in ejection.
When site operation: first marking time the place of template needing to pour the highway slope protection, be using the slope surface of both sides of highway Interior side form 1 is installed in groove by bed die in digging the groove for setting certain depth in slope surface in advance by size with outer side mold 2;? After the completion of mixed mud pours, leg mould mandril 11 is fastened, side form level is ejected, completed leg mould, that is, complete a set of highway slope protection and step on Walk the assembling of template.Length when site operation according to slope surface can connect the highway slope protections that cover more and mark time template.

Claims (5)

  1. The template 1. a kind of highway slope protection is marked time, it is characterised in that: including interior side form (1) and outer side mold (2), wherein interior side form (1) It being made of several modular units of marking time, modular unit of each marking time includes at least two interior plates and several front aprons (3), Two interior plates and front apron (3) assembling constitute level-one step, accordingly increase front apron between two interior plates (3), multi-stage stairs are formed;Outer side mold (2) is the plate mould being mounted on the outside of two interior plates, is carried out along interior side form side wall Connection.
  2. The template 2. highway slope protection according to claim 1 is marked time, it is characterised in that: described two interior plates are by left plate (4) it is constituted with right side plate (5) mirror symmetry, and left plate (4) and right side plate (5) both ends are respectively equipped with unit connecting plate (6), it is single First connecting plate (6) is for the connection between two neighboring modular unit of marking time;Distinguish the inside of left plate (4) and right side plate (5) Channel steel (7) are connected equipped with several front aprons, front apron connects channel steel (7) for front apron (3) and left plate (4) and right side plate (5) connection between;The upper end of left plate (4) and right side plate (5) is respectively welded support angle steel (8), and the two of support angle steel (8) It holds and welds together with the unit connecting plate (6) of left plate (4) and right side plate (5) both ends, support angle steel (8) plays fixed cell Connecting plate (6) and the effect for guaranteeing side plate straightness.
  3. The template 3. highway slope protection according to claim 2 is marked time, it is characterised in that: front apron (3) both ends, which are equipped with, to be connected Acting flange (9), connecting flange (9) connect channel steel (7) with front apron and is correspondingly connected with when organizing mould.
  4. The template 4. highway slope protection according to claim 2 or 3 is marked time, it is characterised in that: the front apron connects channel steel (7) Wide face for cuboid channel steel, channel steel is equipped with leg mould mandril wire hole (10), for fastening leg mould mandril (11).
  5. The template 5. highway slope protection according to claim 1 is marked time, it is characterised in that: the highway slope protection marks time template with public affairs The slope surface of road two sides is bed die, and in digging the groove for setting certain depth in slope surface in advance by size, interior side form and outer side mold are installed In groove, that is, completes a set of highway slope protection and mark time the assembling of template.
CN201820766525.XU 2018-05-22 2018-05-22 A kind of highway slope protection is marked time template Active CN208251629U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820766525.XU CN208251629U (en) 2018-05-22 2018-05-22 A kind of highway slope protection is marked time template

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820766525.XU CN208251629U (en) 2018-05-22 2018-05-22 A kind of highway slope protection is marked time template

Publications (1)

Publication Number Publication Date
CN208251629U true CN208251629U (en) 2018-12-18

Family

ID=66481018

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820766525.XU Active CN208251629U (en) 2018-05-22 2018-05-22 A kind of highway slope protection is marked time template

Country Status (1)

Country Link
CN (1) CN208251629U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108532945A (en) * 2018-05-22 2018-09-14 宁夏力丰农机制造有限公司 A kind of highway slope protection is marked time template

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108532945A (en) * 2018-05-22 2018-09-14 宁夏力丰农机制造有限公司 A kind of highway slope protection is marked time template

Similar Documents

Publication Publication Date Title
CN102561681B (en) Casting molding template and casting molding process for constructional columns of infilled walls
CN108149706A (en) A kind of cast-in-place hidden girder and the prefabricated assembled pipe gallery and its construction method of superimposed sheet splicing
CN203977309U (en) A kind of shuttle type culvert linear steel form carrier
CN104878924A (en) Stair step concrete pouring-molded template and stair cast-in-situ construction method
CN106351180B (en) The all-hydraulic unlatching self-propelled template system of aqueduct
CN109208632A (en) A kind of precast hollow module block type concrete retaining wall
CN208251629U (en) A kind of highway slope protection is marked time template
CN206844275U (en) Mutual buckle type precast concrete cover ditch and its suspender
CN205688792U (en) Beam slab post-cast strip cleanout formula template construction structure
CN214144682U (en) Early structure of tearing open of floor template and building frame template structure
CN211948946U (en) Novel post-cast strip construction structure
CN210597794U (en) Connecting device of prefabricated plate
CN108532945A (en) A kind of highway slope protection is marked time template
CN110080299A (en) A kind of shallow embedding mountain tunnel open-cut engineering method
CN109057331A (en) A kind of full construction method for disconnecting Long-span Cantilever system support at construction joint
CN211038666U (en) Sleeve lining pouring construction structure based on assembled scaffold
CN209040844U (en) Pin-connected panel shield dregs pond
CN210768793U (en) Two-lining construction system at intersection of main tunnel and double-layer construction transverse channel
CN211547140U (en) Concrete precast slab made of recycled materials
CN208396295U (en) A kind of open-cut station construction stair formwork erecting structure
CN204781953U (en) Stair concrete placement shaping template of marking time
CN214219758U (en) Ground monitoring point concreting protection block die carrier
CN106321116A (en) Construction method for parallel working of tunnel excavation and concrete lining
CN210141137U (en) U-shaped mold for subway central ditch and special combined mold for central ditch
CN206053128U (en) A kind of special-shaped speed connects formula steel column

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant