CN208251057U - Post-tensioning pile composite foundation - Google Patents
Post-tensioning pile composite foundation Download PDFInfo
- Publication number
- CN208251057U CN208251057U CN201820402024.3U CN201820402024U CN208251057U CN 208251057 U CN208251057 U CN 208251057U CN 201820402024 U CN201820402024 U CN 201820402024U CN 208251057 U CN208251057 U CN 208251057U
- Authority
- CN
- China
- Prior art keywords
- muscle body
- pile
- anchorage
- post
- tensioning
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 239000002131 composite material Substances 0.000 title claims abstract description 27
- 210000003205 muscle Anatomy 0.000 claims abstract description 67
- 239000002184 metal Substances 0.000 claims description 15
- 229910052751 metal Inorganic materials 0.000 claims description 15
- 238000007789 sealing Methods 0.000 claims description 5
- 239000002689 soil Substances 0.000 claims description 3
- 230000015271 coagulation Effects 0.000 claims 1
- 238000005345 coagulation Methods 0.000 claims 1
- 238000007667 floating Methods 0.000 abstract description 5
- 229910001294 Reinforcing steel Inorganic materials 0.000 abstract description 3
- 239000012141 concentrate Substances 0.000 abstract 1
- 230000006835 compression Effects 0.000 description 5
- 238000007906 compression Methods 0.000 description 5
- 238000010276 construction Methods 0.000 description 4
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 4
- 230000000694 effects Effects 0.000 description 3
- 229910000831 Steel Inorganic materials 0.000 description 2
- 230000003321 amplification Effects 0.000 description 2
- 238000004873 anchoring Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 238000003199 nucleic acid amplification method Methods 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 241000208340 Araliaceae Species 0.000 description 1
- 235000005035 Panax pseudoginseng ssp. pseudoginseng Nutrition 0.000 description 1
- 235000003140 Panax quinquefolius Nutrition 0.000 description 1
- 230000002411 adverse Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 150000001875 compounds Chemical class 0.000 description 1
- 238000005260 corrosion Methods 0.000 description 1
- 230000007797 corrosion Effects 0.000 description 1
- 239000010881 fly ash Substances 0.000 description 1
- 235000008434 ginseng Nutrition 0.000 description 1
- PCHJSUWPFVWCPO-UHFFFAOYSA-N gold Chemical compound [Au] PCHJSUWPFVWCPO-UHFFFAOYSA-N 0.000 description 1
- 239000010931 gold Substances 0.000 description 1
- 229910052737 gold Inorganic materials 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Abstract
The utility model relates to a kind of post-tensioning pile composite foundations, structure base slab including pile body and at the top of pile body, the bottom of the structure base slab is laid with mattress layer, muscle body is set between the pile body and structure base slab, being located at the part in pile body on the muscle body is lower muscle body, the outer sheath of the lower muscle body is installed with lower disrance sleeve, being located at the part in mattress layer and structure base slab on the muscle body is upper muscle body, the outer sheath of the upper muscle body is installed with disrance sleeve, the bottom end of the lower muscle body is equipped with bottom anchorage, and the top of the upper muscle body is equipped with top anchorage.The utility model increases presstressed reinforcing steel on rigid pile body and carries out tensioning, increase the anti-floating function of composite foundation, stress of the muscle body at mattress layer position when pile body plays compressive property is avoided simultaneously to concentrate, therefore post-tensioning pile composite foundation provided by the utility model has multifunctionality, has expanded the application field of composite foundation.
Description
Technical field
The utility model relates to foundation of civil work fields, and in particular to a kind of compressible type and by pull-up post-tensioning stake compoundly
Base.
Background technique
With the development and utilization of the underground space, it is more and more that the case where pulling out load, is born on building basis.In underground water
Position change greatly area or building using function vary widely when, structure foundation will not only bear structure basis
Compressive load, and the buoyancy effect of underground water is born simultaneously.
In order to meet the compression effect on building basis, the rigid pile composite foundations such as CFG using very universal.It is compound
One of the shortcomings that ground is exactly that pile body and structure basis are separated by mattress layer, cannot rely on pile body and solves underground structure
Anti-floating problem.The buoyancy that underground water is born to solve building basis generally requires in addition to use measure of anti float.
If presstressed reinforcing steel can be increased on the rigid piles pile bodies such as CFG and apply stretching force, not to compoundly
On the basis of the various mechanical properties such as base bearing capacity cause any adverse effect, the anti-floating function of composite foundation is increased, it will be big
The big application field for expanding rigid pile composite foundation.
Utility model content
The purpose of the utility model is to provide a kind of post-tensioning pile composite foundations, the post-tensioning with anti-floating function and resistance to compression function
Pile composite foundation.
The purpose of this utility model is to be achieved through the following technical solutions:
A kind of post-tensioning pile composite foundation, the structure base slab including pile body and at the top of pile body, the bottom of the structure base slab
Portion is laid with mattress layer, muscle body is arranged between the pile body and structure base slab, it is lower muscle that the part in pile body is located on the muscle body
Body, the outer sheath of the lower muscle body are installed with lower disrance sleeve, the part in mattress layer and structure base slab are located on the muscle body
For upper muscle body, the outer sheath of the upper muscle body is installed with disrance sleeve, and the bottom end of the lower muscle body is equipped with bottom anchorage, described
The top of upper muscle body is equipped with top anchorage.
In preferred embodiments, the junction of the lower muscle body and upper muscle body setting middle part anchorage and covering middle part anchor
The sealing off and covering anchorage body of tool.
In preferred embodiments, the top of the mattress layer is laid with plain concrete layer, the top of the plain concrete layer
Portion is laid with waterproof layer, and seal ring is equipped between the waterproof layer and upper muscle body.
In preferred embodiments, the top anchorage is equipped with metal cap, is equipped in the metal cap for top anchor
Has the stroke space moved up and down.
In preferred embodiments, the top anchorage includes billet and bolt-nut, the billet support gold
Belong to cap and bolt-nut, the bolt-nut are fixed on muscle body, the bolt-nut is located in metal cap.
In preferred embodiments, the bottom anchorage is the downward taper structure of arrow.
The utility model has the following beneficial effects:
The post-tensioning stake composite foundation of the utility model realizes resistance to compression function and resistance to plucking function, post-tensioning stake and structure base slab anchor
It is solidly connected the resistance to plucking function that can play post-tensioning stake.When playing the resistance to compression function of pile body, in order to avoid pile body plays crushing resistance
Stress of the muscle body at mattress layer position is concentrated when energy, in the external side setting disrance sleeve of muscle and in the anchoring of structure base slab and muscle body
Steel cap is arranged in end top, and muscle body has certain mobile space in steel cap when structure base slab is pressurized.
The utility model increases presstressed reinforcing steel on rigid pile body and carries out tensioning, increases the anti-floating function of composite foundation
Can, while avoiding stress of the muscle body at mattress layer position when pile body plays compressive property and concentrating, therefore the utility model provides
Post-tensioning pile composite foundation have multifunctionality, expanded the application field of composite foundation.
Detailed description of the invention
The utility model is described in further detail below according to attached drawing.
Fig. 1 is the overall structure figure of post-tensioning pile composite foundation described in the utility model embodiment;
Fig. 2 be in Fig. 1 A to amplification assumption diagram;
Fig. 3 be in Fig. 1 B to amplification assumption diagram.
In figure:
1, pile body;2, structure base slab;3, mattress layer;4, lower muscle body;5, lower disrance sleeve;6, upper muscle body;7, upper separation sleeve
Pipe;8, bottom anchorage;9, top anchorage;10, middle part anchorage;11, sealing off and covering anchorage body;12, plain concrete layer;13, waterproof layer;14, only
Water ring;15, metal cap;16, stroke space;17, billet;18, bolt-nut.
Specific embodiment
It is practical new below in conjunction with this to keep the objectives, technical solutions, and advantages of the embodiments of the present invention clearer
Attached drawing in type embodiment, the technical scheme in the utility model embodiment is clearly and completely described, it is clear that is retouched
The embodiment stated is the utility model a part of the embodiment, instead of all the embodiments.Usually here in attached drawing description and
The component of the utility model embodiment shown can be arranged and be designed with a variety of different configurations.Therefore, below to attached
The detailed description of the embodiments of the present invention provided in figure is not intended to limit the range of claimed invention,
But it is merely representative of the selected embodiment of the utility model.Based on the embodiments of the present invention, ordinary skill people
Member's every other embodiment obtained without creative efforts, belongs to the model of the utility model protection
It encloses.
The embodiments of the present invention are described below in detail, examples of the embodiments are shown in the accompanying drawings, wherein from beginning
Same or similar element or element with the same or similar functions are indicated to same or similar label eventually.Below by ginseng
The embodiment for examining attached drawing description is exemplary, it is intended to for explaining the utility model, and should not be understood as to the utility model
Limitation.
The utility model is further described with specific embodiment below with reference to accompanying drawings.
As shown in Figure 1-3, a kind of post-tensioning pile composite foundation of the utility model embodiment, including pile body 1 and it is located at pile body 1
The bottom of the structure base slab 2 at top, the structure base slab 2 is laid with mattress layer 3, and muscle is arranged between the pile body 1 and structure base slab 2
Body, muscle body are preferable at the center that pile body 1 is arranged in, and the quantity of muscle body can be multiple.It is located at the portion in pile body 1 on the muscle body
It is divided into lower muscle body 4, the outer sheath of the lower muscle body 4 is installed with lower disrance sleeve 5, is located at mattress layer 3 and structure on the muscle body
Part in bottom plate 2 is upper muscle body 6, and the outer sheath of the upper muscle body 6 is installed with disrance sleeve 7, the bottom end of the lower muscle body 4
Equipped with bottom anchorage 8, the top of the upper muscle body 6 is equipped with top anchorage 9.
The lower muscle body 4 and the junction setting middle part anchorage 10 of upper muscle body 6 and the sealing off and covering anchorage body 11 of covering middle part anchorage 10,
Sealing off and covering anchorage body 11 can prevent the corrosion of middle part anchorage 10, can be by the tensioning work of muscle body relative to this structure in traditional construction technology
Skill is placed on before pouring sole plate, and stake top position directly applies straight up pre- after 1 intensity of pile body reaches design requirement
Stress avoids stretching construction and intersects with sole plate construction technology, and the concrete without sole plate reaches intensity requirement
Waiting time further improves construction efficiency.
Apply prestressing force at the top of pile body 1, the driven stake top of uplift force impetus for being subject to pile body 1 is transferred to pile body
1 bottom plays 1 side soil frictional resistance of pile body as the load increases and gradually from bottom to up, can give full play to 1 side of pile body soil
Frictional resistance, and pile body 1 has been applied prestressing force, and entire pile body 1 can be made to be in pressured state.Due to traditional resistance to plucking pile body 1
Uplift force acts on stake top position, and whole pile body 1 is in tension state, and pile body 1 is caused to be also easy to produce crack, and this structure makes pile body 1
At pressured state, the drawbacks of tension for solving traditional pile body 1 is also easy to produce crack.
The top of the mattress layer 3 is laid with plain concrete layer 12, and the top of the plain concrete layer 12 is laid with waterproof layer 13,
Between the waterproof layer 13 and upper muscle body 6 be equipped with seal ring 14, plain concrete layer 12 can smooth mattress layer 3 upper surface, make to tie
The bottom uniform force of structure bottom plate 2 improves the support stability of entire mattress layer 3.
The top anchorage 9 is equipped with metal cap 15, is equipped with the row moved up and down for top anchorage 9 in the metal cap 15
Journey space 16.When post-tensioning pile composite foundation plays resistance to compression function, since mattress layer 3 mostly uses rubble, aggregate chips, sand, flyash
Equal materials, pressure cross conference squeeze mattress layer 3 deformation occurs, the bottom for changing structure base slab 2 supports distribution of force, makes muscle body
Stress at 3 position of mattress layer is concentrated, therefore upper disrance sleeve 7 is arranged on the outside of upper muscle body 6, and be arranged on top anchorage 9
Metal cap 15, if structure base slab 2 is pressurized, muscle body has certain mobile space in the stroke space 16 in metal cap 15,
To solve the problems, such as that muscle body is broken, bends because stress is concentrated.
The top anchorage 9 includes billet 17 and bolt-nut 18, and the billet 17 supports metal cap 15 and anchoring
Nut 18, the bolt-nut 18 are fixed on muscle body 6, and the bolt-nut 18 is located in metal cap 15, and metal cap 15 is detained
On billet 17.
The bottom anchorage 8 is the downward taper structure of arrow, when 1 anti-plug of pile body of construct is placed in muscle body structure from
To positioning and guiding function, and reduce resistance when merging.
When the post-tensioning pile composite foundation is constructed, pile body 1 of constructing first, the pile body 1 is mostly rigid pile body 1, then by band
In the lower muscle body 4 merging pile body 1 of lower disrance sleeve 5, when the intensity of pile body 1 reaches requirement, muscle body is applied at 1 top of pile body
Locking middle part anchorage 10, is then laid with mattress layer 3 at the top of pile body 1 after prestressing force, finally at the top of the installation of the top of upper muscle body 6
Anchorage 9, pouring structure bottom plate 2 realize the anchor connection of post-tensioning stake and structure base slab 2, form post-tensioning pile composite foundation.
Finally, it should be noted that above-described each embodiment is merely to illustrate the technical solution of the utility model, rather than
It is limited;Although the utility model is described in detail with reference to the foregoing embodiments, those skilled in the art
It is understood that it can still modify to technical solution documented by previous embodiment, or to part of or whole
Technical characteristic is equivalently replaced;And these modifications or substitutions, it does not separate the essence of the corresponding technical solution the utility model
The range of each embodiment technical solution.
Claims (6)
1. a kind of post-tensioning pile composite foundation, the structure base slab including pile body and at the top of pile body, the bottom of the structure base slab
It is laid with mattress layer, it is characterised in that: muscle body is set between the pile body and structure base slab, the portion in pile body is located on the muscle body
It is divided into lower muscle body, the outer sheath of the lower muscle body is installed with lower disrance sleeve, is located at mattress layer and structure base slab on the muscle body
Interior part is upper muscle body, and the outer sheath of the upper muscle body is installed with disrance sleeve, and the bottom end of the lower muscle body is equipped with bottom
The top of anchorage, the upper muscle body is equipped with top anchorage.
2. post-tensioning pile composite foundation according to claim 1, it is characterised in that: the junction of the lower muscle body and upper muscle body
The sealing off and covering anchorage body of middle part anchorage and covering middle part anchorage is set.
3. post-tensioning pile composite foundation according to claim 1, it is characterised in that: the top of the mattress layer is laid with plain coagulation
The top of soil layer, the plain concrete layer is laid with waterproof layer, and seal ring is equipped between the waterproof layer and upper muscle body.
4. post-tensioning pile composite foundation according to claim 1, it is characterised in that: the top anchorage is equipped with metal cap,
The stroke space moved up and down for top anchorage is equipped in the metal cap.
5. post-tensioning pile composite foundation according to claim 4, it is characterised in that: the top anchorage includes billet and anchor
Gu nut, the billet support metal cap and bolt-nut, the bolt-nut are fixed on muscle body, the bolt-nut
In metal cap.
6. post-tensioning pile composite foundation according to claim 1, it is characterised in that: the bottom anchorage is the downward cone of arrow
Physique structure.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820402024.3U CN208251057U (en) | 2018-03-23 | 2018-03-23 | Post-tensioning pile composite foundation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820402024.3U CN208251057U (en) | 2018-03-23 | 2018-03-23 | Post-tensioning pile composite foundation |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208251057U true CN208251057U (en) | 2018-12-18 |
Family
ID=64609234
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820402024.3U Expired - Fee Related CN208251057U (en) | 2018-03-23 | 2018-03-23 | Post-tensioning pile composite foundation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208251057U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111395347A (en) * | 2020-02-21 | 2020-07-10 | 湖南大学 | Method for controlling upward floating of existing tunnel striding on foundation pit by adopting prestressed uplift pile |
-
2018
- 2018-03-23 CN CN201820402024.3U patent/CN208251057U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111395347A (en) * | 2020-02-21 | 2020-07-10 | 湖南大学 | Method for controlling upward floating of existing tunnel striding on foundation pit by adopting prestressed uplift pile |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104790424B (en) | The hardened system on generation power foundation of wind power ring basis and reinforcement means thereof | |
CN102383418B (en) | Anti-seismic prefabricated concrete solid square pile and production method thereof | |
CN201722789U (en) | Prestressed steel bar-pressed flat joint cement joint pedestal | |
CN106758786A (en) | A kind of prefabricated assembled concrete-filled double skin steel tube lattice bridge pier | |
CN201661009U (en) | Concrete-filled square steel tubular column | |
CN208415082U (en) | Unit construction bridge formed precast concrete pier stud and bent cap bell and spigot frame | |
CN106836463A (en) | The constructing device and construction method of cushion cap and ground girder construction | |
CN210458914U (en) | Connecting structure of prefabricated bridge pier stud and capping beam | |
CN208251057U (en) | Post-tensioning pile composite foundation | |
CN102363957A (en) | Post-tensioned pre-stressed compound uplift pile | |
CN102345292A (en) | Composite prestressed uplift pile with expansion heads | |
CN202187340U (en) | Socketed pile with concrete-filled steel tube core column | |
CN112227353A (en) | Assembled integral static pressure pile | |
CN206941799U (en) | The prestressing force assembling type node construction of beam-ends friction energy-dissipating | |
CN112195957B (en) | Reinforced connecting structure of fan tower and foundation and construction method | |
CN209775994U (en) | High strength sculpture structure | |
CN105862871A (en) | Prestressing anchor body assembly type frame hoop slope protection device and construction method | |
CN110206020B (en) | Prefabricated snowflake type concrete steel sheet pile and construction method thereof | |
CN218597130U (en) | Side expands resistance to plucking rubble pile foundation structure that slip casting combines | |
CN204174616U (en) | Pile for prestressed pipe anti-floating pile raft structure | |
CN202610830U (en) | Bracket type material-blocking wall and umbrella-shaped roof | |
CN202039355U (en) | Sand filling composite pile and pile forming device thereof | |
CN205205847U (en) | Frame construction of stake cushion cap | |
CN204898944U (en) | Steel plate concrete that cracks combination power consumption shear force wall | |
CN210031776U (en) | Prefabricated RPC tubular pile structure of flute formula type |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20181218 |