CN106758786A - A kind of prefabricated assembled concrete-filled double skin steel tube lattice bridge pier - Google Patents
A kind of prefabricated assembled concrete-filled double skin steel tube lattice bridge pier Download PDFInfo
- Publication number
- CN106758786A CN106758786A CN201611042839.7A CN201611042839A CN106758786A CN 106758786 A CN106758786 A CN 106758786A CN 201611042839 A CN201611042839 A CN 201611042839A CN 106758786 A CN106758786 A CN 106758786A
- Authority
- CN
- China
- Prior art keywords
- concrete
- steel
- steel tube
- double skin
- filled double
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/02—Piers; Abutments ; Protecting same against drifting ice
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2101/00—Material constitution of bridges
- E01D2101/20—Concrete, stone or stone-like material
- E01D2101/24—Concrete
- E01D2101/26—Concrete reinforced
- E01D2101/268—Composite concrete-metal
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
The present invention relates to a kind of prefabricated assembled concrete-filled double skin steel tube lattice bridge pier, belong to technical field of bridge engineering.The bridge pier is made up of Concrete-filled Double Skin Steel Tube Columns, presstressed reinforcing steel, anchor slab, cover plate, Wavelike steel webplate, concrete leveling layer, anti-shear ring, bolt, connecting plate.Described Concrete-filled Double Skin Steel Tube Columns are a kind of superposed columns, with hollow section form;Seam crossing of the described concrete leveling layer for Concrete-filled Double Skin Steel Tube Columns;Described cover plate is on described Concrete-filled Double Skin Steel Tube Columns top;Described anchor slab is embedded in cushion cap;Described Wavelike steel webplate is used to connect adjacent Concrete-filled Double Skin Steel Tube Columns.The invention provides a kind of prefabricated assembled concrete-filled double skin steel tube lattice bridge pier, can be used in the steel concrete composite bridge system of municipal highway overpass, highway overpass, with high capacity, anti-seismic performance is good, be capable of achieving assembled in situ, construct it is convenient the characteristics of.
Description
Technical field
The present invention relates to a kind of prefabricated assembled concrete-filled double skin steel tube lattice bridge pier, belong to composite bridge
Engineering field.
Background technology
The on-site concrete construction of concrete filled steel tube pillar bridge pier typically uses cast-in-place concrete, and wet trade amount is big.To protect
The globality of bridge pier is demonstrate,proved, concrete filled steel tube pillar bridge pier does not use sectional making steel core concrete column and field erected side typically
Method.
Concrete-filled Double Skin Steel Tube Columns are a kind of new shapes that be developed on the basis of traditional steel core concrete column
Cylindricality formula, with axial bearing capacity it is high, shear-carrying capacity is high, energy dissipation capacity is strong, member dead weight is light, easy construction etc. is many excellent
Point.In existing document, there is not yet concrete-filled double skin steel tube lattice bridge pier is applied in bridge structure, therefore,
The present invention combines the prefabricated assembled technology of combining structure, the prefabricated assembled concrete-filled double skin steel tube lattice bridge of proposition
Pier is a kind of new shape bridge pier, can effectively accelerate speed of application, and reduce situ wet operation amount has superior stress performance simultaneously.
Hollow sandwich steel pipe in prefabricated assembled concrete-filled double skin steel tube lattice bridge pier proposed by the present invention is mixed
Solidifying earth pillar and Wavelike steel webplate can be prefabricated in the factory, and the segmentation of the particularly Concrete-filled Double Skin Steel Tube Columns in bridge pier is prefabricated
Bridge pier from the great caused inconvenient problem of transport is solved with installation.Because rectangular steel pipe out of plane constraint is weak, easily occur outside plane
Unstability, concrete-filled circular steel tube column is laid between interlayer steel tube can effectively reduce concrete-filled double skin steel tube forfeiture bearing capacity
Speed, so as to improve the ductility of concrete-filled double skin steel tube;Perfusion high-strength concrete in round steel pipe, it is common mixed outside round steel pipe
Solidifying soil can constrain the deformation of round steel pipe, improve the bearing capacity of concrete-filled circular steel tube column, so as to effectively improve hollow sandwich steel
The axial carrying capacity power of pipe concrete column, and then column cross-section size can be reduced.Presstressed reinforcing steel can effectively suppress hollow sandwich steel
The generation and development in pipe concrete lattice bridge pier crack under geological process.It is traditional to sew for example flat batten plate of material and angle steel is volatile
Surely, Wavelike steel webplate then has Out-of Plane Stiffness higher, and stability bearing capacity is high.Mixed using Wavelike steel webplate connection hollow sandwich steel pipe
Solidifying earth pillar limb can effectively improve concrete-filled double skin steel tube lattice bridge pier overall stability.Prefabricated assembled hollow sandwich
Concrete filled steel tube lattice bridge pier has good ductility and an energy dissipation capacity, and speed of application is fast, the characteristics of situ wet operation is few
The content of the invention
To solve the problems, such as the factorial construction of bridge structure concrete-filled double skin steel tube lattice bridge pier, the present invention is provided
A kind of prefabricated assembled concrete-filled double skin steel tube lattice bridge pier, Concrete-filled Double Skin Steel Tube Columns are using overlapping rod structure
Form, it is possible to achieve the prefabricated assembled construction of concrete-filled double skin steel tube lattice bridge pier.The structure type has antidetonation
High capacity, ductility is good, the characteristics of good integrity, post limb and waveform steel abdomen in concrete-filled double skin steel tube lattice bridge pier
Plate is using factory process making, site-assembled form of construction work, live welding operation, form work engineering and concrete situ wet
Operation is less, and it is convenient to construct, and is conducive to shortening the duration.
The technical scheme is that:
A kind of prefabricated assembled concrete-filled double skin steel tube lattice bridge pier, it is characterised in that:Its bridge pier includes hollow
Interlayer steel tube concrete column, anchor slab, cover plate, presstressed reinforcing steel, anti-shear ring, concrete leveling layer, Wavelike steel webplate, bolt, connection
Plate.There is pre-stressed steel pipe high-strength concrete between inner layer steel pipe and outer layer pipe in the Concrete-filled Double Skin Steel Tube Columns limb of use
Post, during the installation of Concrete-filled Double Skin Steel Tube Columns, before one section of Concrete-filled Double Skin Steel Tube Columns often is installed,
The top surface of concrete leveling mounted Concrete-filled Double Skin Steel Tube Columns need to be used.The cover plate of use is mixed in hollow sandwich steel pipe
The top of solidifying earth pillar limb;The anchor slab of use is embedded in cushion cap;Presstressed reinforcing steel one end is anchored at anchor slab in the presstressed reinforcing steel of use
On, other end tensioning on the cover board strengthens the globality of Concrete-filled Double Skin Steel Tube Columns limb;During the connecting plate of use is welded on
On empty interlayer steel tube concrete column limb;The Wavelike steel webplate of use is connected by bolt with connecting plate.
The present invention has following effective effect:
1. the factorial construction of the concrete-filled double skin steel tube lattice bridge pier in science of bridge building is solved the problems, such as.
2. round steel pipe high-strength concrete column, interlayer steel are had between the interlayer steel tube of the Concrete-filled Double Skin Steel Tube Columns for using
Normal concrete restrained circle pipe deformation between pipe, improves the bearing capacity of post, and column cross-section size can be smaller.Rectangular steel pipe is easily sent out
The outer unstability of dough, the presence of round steel pipe high-strength concrete column can effectively reduce the speed of columns bearing capacity reduction, improve the change of post
Shape and ductile performance.
3. under geological process, column section occurs the trend of tension.The tensile strength of concrete is low, easily cracking.
Tensioned prestressing bar can make column section produce compression, so as to the crack of concrete-filled double skin steel tube lattice bridge pier can be suppressed
Produce and develop.
4. material is sewed as bridge pier using Wavelike steel webplate, compared with common batten plate and angle steel, outside Wavelike steel webplate face just
Degree is big, with stability bearing capacity higher.
5. the Concrete-filled Double Skin Steel Tube Columns and Wavelike steel webplate in concrete-filled double skin steel tube lattice bridge pier are equal
It is prefabricated in the factory, particularly post limb uses factory's sectional making, is conducive to component conveying and in-site installation.
Brief description of the drawings
Fig. 1 is the plan of prefabricated assembled concrete-filled double skin steel tube lattice bridge pier of the invention.
Fig. 2 is the half elevation figure and semi-section of prefabricated assembled concrete-filled double skin steel tube lattice bridge pier of the invention
Figure.
Fig. 3 is the Wavelike steel webplate end connection of prefabricated assembled concrete-filled double skin steel tube lattice bridge pier of the invention
Schematic diagram.
Fig. 4 is the anchor slab schematic diagram of prefabricated assembled concrete-filled double skin steel tube lattice bridge pier of the invention.
Specific embodiment
Below in conjunction with accompanying drawing, the present invention is described in further detail.
As shown in drawings, the present invention is a kind of prefabricated assembled concrete-filled double skin steel tube lattice bridge pier, by prefabricated
Concrete-filled Double Skin Steel Tube Columns, anchor slab, presstressed reinforcing steel, cover plate, Wavelike steel webplate, connecting plate, bolt, anti-shear ring, concrete
Screed-coat is constituted.Its assemble sequence is as follows:
Prefabrication:
A. be prefabricated in the factory each basic element of character of bridge pier:Bolt 3, Wavelike steel webplate 4, cover plate 8, anchor slab 9, hollow sandwich
Steel core concrete column 10, connecting plate 13.
B. pass through steel pipe, tensioned prestressing bar 2 that high-strength concrete is poured in steel pipe presstressed reinforcing steel 2, maintenance is fabricated to
Steel pipe high strength concrete column reinforcing 1.
C. bolt hole is opened on connecting plate 13, then connecting plate 13 is welded on steel pipe 5.
D. steel pipe 6 is put into steel pipe 5, the steel pipe high strength concrete column reinforcing 1 that will be made is placed on inner layer steel pipe 6 and outer layer
In interlayer between steel pipe 5, normal concrete is poured between inner layer steel pipe 6, outer layer pipe 5 and steel pipe high strength concrete column reinforcing 1,
Maintenance forms Concrete-filled Double Skin Steel Tube Columns 10.
Assembled in situ:
E. the one end of presstressed reinforcing steel 7 is anchored on anchor slab 9, presstressed reinforcing steel 7 is positioned on cushion cap together with anchor slab 9, will
The Concrete-filled Double Skin Steel Tube Columns installation for being welded with anti-shear ring 12 is positioned on cushion cap, pours the concrete of cushion cap part.
F. it is using pea gravel concreten that the top surface of already installed Concrete-filled Double Skin Steel Tube Columns 10 is levelling, install hollow
Interlayer steel tube concrete column 10, installs according to this method and as requested some Concrete-filled Double Skin Steel Tube Columns 10.
G., cover plate 8, the tensioned prestressing bar 7 on cover plate 8 are installed.
H. four Concrete-filled Double Skin Steel Tube Columns are formed according to e~g, the mode being connected by screw bolts is by Wavelike steel webplate
4 are arranged on Concrete-filled Double Skin Steel Tube Columns 10.
The invention provides a kind of prefabricated assembled concrete-filled double skin steel tube lattice bridge pier, bridge structure is solved
The factorial construction problem of middle concrete-filled double skin steel tube lattice bridge pier, by prefabrication and field erected construction party
Formula, save the duration, improve construction quality, with superior anti-seismic performance, can be used for urban viaduct, highway overpass and
In the steel-concrete combined structure bridge system of elevated bridge of high speed railway.
Claims (9)
1. a kind of prefabricated assembled concrete-filled double skin steel tube lattice bridge pier, it is characterised in that:The bridge pier include it is prefabricated in
Empty interlayer steel tube concrete column 10, bolt 3, Wavelike steel webplate 4, presstressed reinforcing steel 7, cover plate 8, anchor slab 9, concrete leveling layer 11,
Anti-shear ring 12, connecting plate 13.Described prefabricated hollow interlayer steel tube concrete column 10 is a kind of superposed column, special with hollow section
Levy, be made up of steel core concrete column 1, presstressed reinforcing steel 2, outer layer pipe 5, inner layer steel pipe 6 and anti-shear ring 12, it is arranged on cushion cap
On, after cast-in-place concrete, entirety is formed with cushion cap;Described concrete leveling layer 11 is mixed for levelling prefabricated hollow interlayer steel tube
Solidifying earth pillar section stitching portion;Described anchor slab 9 is embedded in cushion cap;Described cover plate 8 is placed in Concrete-filled Double Skin Steel Tube Columns 10
Top;Described one end of presstressed reinforcing steel 7 is anchored on anchor slab 9, and the other end is anchored on cover plate 8;Described bolt 3 and connecting plate
13 are used to connect Concrete-filled Double Skin Steel Tube Columns 10 and Wavelike steel webplate 4;Described connecting plate is welded on outer layer pipe 5.
2. a kind of prefabricated assembled concrete-filled double skin steel tube lattice bridge pier according to claim 1, its feature exists
In:Described prefabricated hollow interlayer steel tube concrete column 10 is mixed by outer layer pipe 5, inner layer steel pipe 6, presstressed reinforcing steel 2, steel pipe high strength
Solidifying earth pillar 1 and anti-shear ring 12 are constituted;Described presstressed reinforcing steel 2 is built in the kernel of section of steel pipe high strength concrete column reinforcing 1;Described steel
High-strength concrete is poured in the steel pipe of pipe high-strength concrete column 1, and is evenly arranged between outer layer pipe 5 and inner layer steel pipe 6;Institute
Between the outer layer pipe 5 and inner layer steel pipe 6 stated, the region in addition to steel pipe high strength concrete column reinforcing 1 has poured normal concrete.
3. a kind of prefabricated assembled concrete-filled double skin steel tube lattice bridge pier according to claim 1, its feature exists
In:Described prefabricated assembled Concrete-filled Double Skin Steel Tube Columns 10 are a kind of superposed columns, and its shaft is prefabricated in factory's segmentation, existing
Field overlapping is installed, and overlapping stitching portion is levelling using concrete leveling layer 11.
4. a kind of prefabricated assembled concrete-filled double skin steel tube lattice bridge pier according to claim 1, its feature exists
In:Connected by Wavelike steel webplate 4 between described each Concrete-filled Double Skin Steel Tube Columns 10, form lattice bridge pier;It is hollow
Connected using bolt 3 between interlayer steel tube concrete column 10 and Wavelike steel webplate 4.
5. a kind of prefabricated assembled concrete-filled double skin steel tube lattice bridge pier according to claim 1, its feature exists
In:Described presstressed reinforcing steel 2 uses pre-tensioning system tensioning;Described presstressed reinforcing steel 7 uses post stretching tensioning.
6. a kind of prefabricated assembled concrete-filled double skin steel tube lattice bridge pier according to claim 1, its feature exists
In:Described one end of presstressed reinforcing steel 7 is anchored on anchor slab 9, and one end is anchored on cover plate 8, makes prefabricated assembled hollow sandwich steel
Pipe concrete column forms entirety.
7. a kind of prefabricated assembled concrete-filled double skin steel tube lattice bridge pier according to claim 1, its feature exists
In:Described anti-shear ring 12 is welded on the steel pipe high strength concrete column reinforcing 1 at the suspension column of Concrete-filled Double Skin Steel Tube Columns 10.
8. a kind of prefabricated assembled concrete-filled double skin steel tube lattice bridge pier according to claim 1, its feature exists
In:At the suspension column of prefabricated assembled Concrete-filled Double Skin Steel Tube Columns 10, steel pipe high strength concrete column reinforcing 1 stretches out outer layer pipe 5
With the section of inner layer steel pipe 6, it is anchored in cushion cap.
9. a kind of prefabricated assembled concrete-filled double skin steel tube lattice bridge pier according to claim 1, its feature exists
In:The described two ends of Wavelike steel webplate 4 are provided with screw, are connected using bolt 3 between Wavelike steel webplate 4 and connecting plate 13.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611042839.7A CN106758786B (en) | 2016-11-11 | 2016-11-11 | A kind of prefabricated assembled concrete-filled double skin steel tube lattice bridge pier |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611042839.7A CN106758786B (en) | 2016-11-11 | 2016-11-11 | A kind of prefabricated assembled concrete-filled double skin steel tube lattice bridge pier |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106758786A true CN106758786A (en) | 2017-05-31 |
CN106758786B CN106758786B (en) | 2018-08-21 |
Family
ID=58974151
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611042839.7A Active CN106758786B (en) | 2016-11-11 | 2016-11-11 | A kind of prefabricated assembled concrete-filled double skin steel tube lattice bridge pier |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106758786B (en) |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107130513A (en) * | 2017-06-30 | 2017-09-05 | 东北大学 | A kind of composite steel tube concrete folding bridge pier |
CN107988896A (en) * | 2017-12-18 | 2018-05-04 | 清华大学 | A kind of concrete-filled double skin steel tube bridge pier |
CN108103926A (en) * | 2017-12-25 | 2018-06-01 | 中交第二公路勘察设计研究院有限公司 | Assembled hollow pier and its construction method based on end plate welding |
CN109322792A (en) * | 2018-11-06 | 2019-02-12 | 重庆大学 | A kind of concrete filled steel tube lattice wind power tower based on corrugated steel web box beam |
CN109404224A (en) * | 2018-12-10 | 2019-03-01 | 重庆大学 | It is a kind of based on edge put more energy into combined shell wind-powered electricity generation mix tower |
WO2021056253A1 (en) * | 2019-09-25 | 2021-04-01 | 邹胜斌 | Modular composite lattice column and construction method therefor |
CN112681132A (en) * | 2020-11-18 | 2021-04-20 | 中交一公局集团有限公司 | Positioning support of suspension bridge prestressed anchoring system and construction method |
CN113445670A (en) * | 2021-08-13 | 2021-09-28 | 西安建筑科技大学 | Prefabricated and assembled composite steel pipe concrete lattice column and construction method |
CN113699884A (en) * | 2021-08-27 | 2021-11-26 | 四川省公路规划勘察设计研究院有限公司 | Rectangular concrete-filled steel tube cable tower adopting prefabricated web plates |
CN113789718A (en) * | 2021-09-29 | 2021-12-14 | 天津大学 | Self-resetting hollow sandwich concrete-filled steel tube segment assembled pier |
CN113832840A (en) * | 2021-08-26 | 2021-12-24 | 广州市公用事业规划设计院有限责任公司 | Double-wall hollow pier column top support connecting node and construction method |
CN114737476A (en) * | 2022-03-09 | 2022-07-12 | 四川省公路规划勘察设计研究院有限公司 | Corrugated steel plate concrete composite web plate for cable tower of square steel tube suspension bridge |
CN115110432A (en) * | 2022-07-28 | 2022-09-27 | 北京城建设计发展集团股份有限公司 | Installation method of vertical prestressed steel strand for connecting prefabricated bridge pier |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH084031A (en) * | 1994-06-17 | 1996-01-09 | P S Co Ltd | Building method of lower part structure |
JPH0959933A (en) * | 1995-08-23 | 1997-03-04 | Fujita Corp | Filled and coated steel pipe concrete structure and construction method |
CN101245584A (en) * | 2007-02-15 | 2008-08-20 | 韩国大学工业和学术合作基金会 | Modularization pole system of hollow pole unit using internal constraint and building method |
CN102251476A (en) * | 2011-04-19 | 2011-11-23 | 中铁二十三局集团第三工程有限公司 | Measurement control method for field installation of steel tube lattice pier |
CN103628403A (en) * | 2013-09-16 | 2014-03-12 | 安徽省交通规划设计研究院有限公司 | Tubular concrete bridge pier |
CN103967206A (en) * | 2014-05-14 | 2014-08-06 | 福建工程学院 | Combined lattice type hollow component |
CN105113389A (en) * | 2015-09-18 | 2015-12-02 | 河海大学 | Assembled type bridge pier column member with steel-concrete composite structure |
-
2016
- 2016-11-11 CN CN201611042839.7A patent/CN106758786B/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH084031A (en) * | 1994-06-17 | 1996-01-09 | P S Co Ltd | Building method of lower part structure |
JPH0959933A (en) * | 1995-08-23 | 1997-03-04 | Fujita Corp | Filled and coated steel pipe concrete structure and construction method |
CN101245584A (en) * | 2007-02-15 | 2008-08-20 | 韩国大学工业和学术合作基金会 | Modularization pole system of hollow pole unit using internal constraint and building method |
CN102251476A (en) * | 2011-04-19 | 2011-11-23 | 中铁二十三局集团第三工程有限公司 | Measurement control method for field installation of steel tube lattice pier |
CN103628403A (en) * | 2013-09-16 | 2014-03-12 | 安徽省交通规划设计研究院有限公司 | Tubular concrete bridge pier |
CN103967206A (en) * | 2014-05-14 | 2014-08-06 | 福建工程学院 | Combined lattice type hollow component |
CN105113389A (en) * | 2015-09-18 | 2015-12-02 | 河海大学 | Assembled type bridge pier column member with steel-concrete composite structure |
Cited By (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107130513A (en) * | 2017-06-30 | 2017-09-05 | 东北大学 | A kind of composite steel tube concrete folding bridge pier |
CN107988896A (en) * | 2017-12-18 | 2018-05-04 | 清华大学 | A kind of concrete-filled double skin steel tube bridge pier |
CN108103926A (en) * | 2017-12-25 | 2018-06-01 | 中交第二公路勘察设计研究院有限公司 | Assembled hollow pier and its construction method based on end plate welding |
CN108103926B (en) * | 2017-12-25 | 2019-07-16 | 中交第二公路勘察设计研究院有限公司 | Assembled hollow pier and its construction method based on end plate welding |
CN109322792A (en) * | 2018-11-06 | 2019-02-12 | 重庆大学 | A kind of concrete filled steel tube lattice wind power tower based on corrugated steel web box beam |
CN109404224A (en) * | 2018-12-10 | 2019-03-01 | 重庆大学 | It is a kind of based on edge put more energy into combined shell wind-powered electricity generation mix tower |
WO2021056253A1 (en) * | 2019-09-25 | 2021-04-01 | 邹胜斌 | Modular composite lattice column and construction method therefor |
CN112681132A (en) * | 2020-11-18 | 2021-04-20 | 中交一公局集团有限公司 | Positioning support of suspension bridge prestressed anchoring system and construction method |
CN113445670A (en) * | 2021-08-13 | 2021-09-28 | 西安建筑科技大学 | Prefabricated and assembled composite steel pipe concrete lattice column and construction method |
CN113832840A (en) * | 2021-08-26 | 2021-12-24 | 广州市公用事业规划设计院有限责任公司 | Double-wall hollow pier column top support connecting node and construction method |
CN113832840B (en) * | 2021-08-26 | 2023-08-22 | 广州市城建规划设计院有限公司 | Double-wall hollow pier column top support connecting node and construction method |
CN113699884A (en) * | 2021-08-27 | 2021-11-26 | 四川省公路规划勘察设计研究院有限公司 | Rectangular concrete-filled steel tube cable tower adopting prefabricated web plates |
CN113789718A (en) * | 2021-09-29 | 2021-12-14 | 天津大学 | Self-resetting hollow sandwich concrete-filled steel tube segment assembled pier |
CN113789718B (en) * | 2021-09-29 | 2022-11-18 | 天津大学 | Self-resetting hollow sandwich concrete-filled steel tube segment assembled pier |
CN114737476A (en) * | 2022-03-09 | 2022-07-12 | 四川省公路规划勘察设计研究院有限公司 | Corrugated steel plate concrete composite web plate for cable tower of square steel tube suspension bridge |
CN115110432A (en) * | 2022-07-28 | 2022-09-27 | 北京城建设计发展集团股份有限公司 | Installation method of vertical prestressed steel strand for connecting prefabricated bridge pier |
Also Published As
Publication number | Publication date |
---|---|
CN106758786B (en) | 2018-08-21 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106758786B (en) | A kind of prefabricated assembled concrete-filled double skin steel tube lattice bridge pier | |
CN105908621B (en) | It is a kind of to damage controllable Self-resetting precast segment steel-pipe assembly concrete pier and the practice | |
CN105113389B (en) | Assembled type bridge pier column member with steel-concrete composite structure | |
CN110512647B (en) | Partial assembly type subway station structure design and construction method | |
CN107165272A (en) | Prestressing force assembly concrete frame joint attachment structure and its construction method | |
WO2019149270A1 (en) | Assembled pier for mixed reinforcement of normal steel rebar and finished threaded steel bar | |
CN104790424B (en) | The hardened system on generation power foundation of wind power ring basis and reinforcement means thereof | |
CN2784490Y (en) | Prestress connection node for beam column of assembled concrete frame structure | |
CN207194146U (en) | Prestressing force assembly concrete frame joint attachment structure | |
CN209619858U (en) | A kind of combination assembled bridge framed bent pier system of steel-concrete | |
CN104963336A (en) | Anti-seismic prefabricated concrete solid square pile and production method thereof | |
CN109629403B (en) | Concrete support column structure and manufacturing method thereof | |
CN108677690B (en) | Energy dissipating Self-resetting bilayer rectangle hollow concrete filled steel tube waves Bridge Pier Structure System | |
CN107190635A (en) | Concrete-filled steel tube with dumbbell sections assembled pier and the connection structure and method with cushion cap | |
CN211113140U (en) | Equal cast-in-place assembly type hollow pier system | |
CN107905402A (en) | A kind of assembled RPC/ Combined concretes frame energy-dissipating and shock-absorbing node | |
CN208533868U (en) | A kind of novel arrangement of reinforcement hollow steel pipe high-strength concrete column | |
CN111733692A (en) | Segment pre-pressing assembly type concrete pier structure and construction method thereof | |
CN107905091A (en) | A kind of section assembling FRP using SMA presstressed reinforcing steel systems strengthens concrete pier of steel tube | |
CN107246109B (en) | The frame and its construction method that real compound concrete filled steel tube coupled column combination beam is constituted | |
Zhou et al. | Seismic behavior of a novel prefabricated thin-walled CFST double-column pier system for simple on-site assembly | |
CN110029569A (en) | A kind of Wavelike steel webplate-purlin formula chord member UHPC combined box beam and its construction method | |
CN108590037A (en) | A kind of novel arrangement of reinforcement hollow steel pipe high-strength concrete column | |
CN208136920U (en) | A kind of triangle prestressing force foundation pit supporting pile and its connection structure | |
CN202644386U (en) | Post-tensioned method prestressed steel pipe high-strength concrete composite bridge pier |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |