CN208236429U - A kind of new pipe-roof method active well ruggedized construction - Google Patents

A kind of new pipe-roof method active well ruggedized construction Download PDF

Info

Publication number
CN208236429U
CN208236429U CN201820554294.6U CN201820554294U CN208236429U CN 208236429 U CN208236429 U CN 208236429U CN 201820554294 U CN201820554294 U CN 201820554294U CN 208236429 U CN208236429 U CN 208236429U
Authority
CN
China
Prior art keywords
pipe
active well
supporting ring
ring beam
roof method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820554294.6U
Other languages
Chinese (zh)
Inventor
郭勇
韩仲慧
王焕
王可用
李占先
李腾
仲文强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 14th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 14th Bureau Co Ltd
Original Assignee
China Railway 14th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 14th Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 14th Bureau Group Co Ltd, Second Engineering Co Ltd of China Railway 14th Bureau Co Ltd filed Critical China Railway 14th Bureau Group Co Ltd
Priority to CN201820554294.6U priority Critical patent/CN208236429U/en
Application granted granted Critical
Publication of CN208236429U publication Critical patent/CN208236429U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The utility model discloses a kind of new pipe-roof method active well ruggedized constructions, it is provided with supporting ring beam around the push pipe pipe curtain at tunnel piercing hole, the supporting ring beam includes the arrangement of reinforcement layer of annular orifice pipe nest of tubes and the annular orifice pipe nest of tubes inner side and outer side, the supporting ring beam and the main structure of the active well are integrated by concreting, and are connect by connector with push pipe.The utility model improves the integrated degree of tunnel piercing structure of the window in the active well of new pipe-roof method, keeps hole more firm, and consumed cost and time are less.

Description

A kind of new pipe-roof method active well ruggedized construction
Technical field
The utility model relates to new pipe-roof method fields, in particular to the reinforcing of active well in new pipe-roof method, more specifically For be related to the ruggedized construction at tunnel piercing hole in new pipe-roof method active well.
Background technique
New pipe-roof method is completely new tunneling engineering method, is a kind of improvement to pipe-roof method.The diameter of steel tube of pipe-roof method jacking Typically small, ready-built structure also only constructs the inside in pipe curtain.In a broad sense, Construction Principle is similar to pipe shed method, and general Temporary support as construction uses.And new pipe-roof method utilizes the jacking construction of major diameter, diameter, can generally in 1800mm or more Directly ready-built structure (structure base slab, top plate, wall etc.) is performed in the pipe that pushed up steel pipe is formed is arranged with the phase after construction, from And all or part of permanent reinforced concrete structure is formed, herein under the supporting of permanent reinforced concrete structure, carry out tunneling knot Structure earthwork heavy excavation, is finally completed whole underground structures.New pipe-roof method construction only has a few countries to use more at present, and China is new Pipe-roof method construction is started late, and seldom with amount, and there are many advantages of new pipe-roof method construction, can be good at adapting to high speed development Process of Urbanization Construction need, therefore the application of new pipe-roof method will be more and more.
Jacking solid matter Large-diameter Steel nest of tubes is needed in new pipe-roof method work progress, pipe curtain is formed, by active well main body knot Structure and building enclosure cutting, cause main structure stress to weaken, the tunnel piercing hole side wall of active well are easily caused to collapse.
Existing reinforcing technology be pipe curtain construction before, on structural wall design jacking tube curtain position outer ring and Hole collar tie beam is respectively set in inner ring, is linked together collar tie beam and main structure by the way that anchor bar is arranged in collar tie beam.Then exist After the completion of pipe curtain internal structure, liner wall construction is set on the outside of structural wall, by welding anchor bar on the outside of pipe curtain steel pipe Pipe curtain steel pipe and top, side, bottom liner wall are linked together, so that pipe curtain is linked together with main structure, reinforced Active well side wall.
There are several disadvantages for the ruggedized construction of the prior art.Firstly, hole collar tie beam be by anchor bar additional extremely On structural wall, rather than it is integrally formed with main structure;Pipe curtain steel pipe is only to be located between inside and outside collar tie beam, and pipe curtain has no with collar tie beam Direct connection relational;Pipe curtain steel pipe is indirectly connected to main structure by liner wall construction.Therefore, the company of pipe curtain and main structure It connects and built on the sand.Secondly, liner wall construction consumable material is more, setting and installation operation are time-consuming and laborious, dramatically increase active well and add Solid cost, operation difficulty and operating time.
Summary of the invention
The utility model provides a kind of new pipe-roof method active well ruggedized construction in view of the foregoing drawbacks, improves tunnel in active well The soundness at hole is tunneled, and significantly shortens consolidation time.
The utility model relates to the ruggedized constructions of new pipe-roof method active well, set around the push pipe pipe curtain at tunnel piercing hole It is equipped with supporting ring beam, the supporting ring beam includes: annular orifice pipe nest of tubes, for the ring junction being made of more steel orifice tubes Structure, for every root hole mouth pipe sleeve outside corresponding push pipe, the internal diameter of orifice tube is greater than the outer diameter of push pipe;Arrangement of reinforcement layer, for along the ring The steel hoop grid of the inner side and outer side setting of shape orifice tube nest of tubes.The main structure of the supporting ring beam and the active well It is integrated by concreting, the supporting ring beam is connect by connector with push pipe.Every push pipe is provided at least two institutes Connector is stated, is separately positioned on inside and outside pipe curtain, the connector can at most be covered with every push pipe and branch adjacent to each other The interface of support ring beam.The connector includes bolt and T-shaped piece, wherein the bolt is preset in the arrangement of reinforcement layer, the T Type part one end is welded on the outside of push pipe, and the other end is connect by the bolt with the supporting ring beam.
The T-shaped piece by being welded to form T-type, has screw hole on the transverse direction steel plate by lateral steel plate and longitudinal steel plate, It is bolted with preset in supporting ring beam, the longitudinal direction steel plate is soldered to the outside of the push pipe.The size of the T-shaped piece needs It to be determined according to structural stress analysis checking computations.
Preferably, it is connected between the arrangement of reinforcement layer and the orifice tube by multiple L-type steel muscle, the one of the L-type steel muscle On end is welded on the outside of the orifice tube, the other end is deep into the arrangement of reinforcement layer.The L-type steel muscle can reinforce orifice tube with The bonding strength of arrangement of reinforcement layer, further increases structural soundness.
Preferably, cement slurry is filled in the gap between the orifice tube and the push pipe, to generate waterproof action, prevented The moisture and mud at main structure rear ooze out.
The utility model has the following beneficial effects: compared with the ruggedized construction of the prior art, the ruggedized construction of the utility model By forming supporting ring beam integrated with active well main structure around push pipe pipe curtain, to strengthen the structure at tunnel piercing hole Intensity.By connecting every push pipe and supporting ring beam with connector, pipe curtain is further consolidated.Thus during reducing constructing tunnel Disturbance to soil layer above active well main structure rear and pipe curtain, reduces Supporting Structure deformation degree, reduces surface subsidence, Promote construction quality.In addition, compared with prior art, the connector for aiming at push pipe and supporting ring beam design reduces active well and adds Gu required cost and time.
Detailed description of the invention
Fig. 1 show the sectional schematic diagram of the new pipe-roof method active well ruggedized construction of the utility model.
Fig. 2 show the connection schematic diagram of push pipe and supporting ring beam.
Fig. 3 show the position view of connector.
Fig. 4 show the structural schematic diagram of T-shaped piece.
In figure, 1. active wells, 2. supporting ring beams, 3. orifice tubes, 4. push pipes, 5. building enclosures, 6. bolts, 7.T type part, 7- 1. lateral steel plate, the longitudinal direction 7-2. steel plate, 8.L steel bar.
Specific embodiment
The technical side of the utility model is described in detail in the utility model in order to better understand with specific example below Case, but the utility model is not limited thereto.
Embodiment 1
Referring to Fig. 1 to 3, a kind of new pipe-roof method active well ruggedized construction is set around the 4 pipe curtain of push pipe at tunnel piercing hole It is equipped with supporting ring beam 2, the supporting ring beam 2 includes:
Annular orifice pipe nest of tubes, for the ring structure being made of more steel orifice tubes 3, every 3 sets of orifice tube in phase It answers outside push pipe 4, the internal diameter of orifice tube 3 is greater than the outer diameter of push pipe 4;
Arrangement of reinforcement layer, for the steel hoop grid being arranged along the inner side and outer side of the annular orifice pipe nest of tubes;
The supporting ring beam 2 and the main structure of the active well 1 are integrated by concreting, the supporting ring beam 2 It is connect by connector with push pipe 4.
Wherein, the outer diameter of push pipe 4 is 2.00m, and the internal diameter of orifice tube 3 is 2.05-2.15m, preferably 2.10m.The ring The spacing of reinforcing bar in shape reinforcing bar grid is preferably 20cm.The width of supporting ring beam 2 is preferably 3.7m.Supporting ring beam is by push pipe pipe Curtain is integrated with active well main structure, thus reinforcing pipe curtain structure.
As shown in figure 3, every push pipe 4 is provided at least two connectors, it is separately positioned on inside and outside pipe curtain. According to the soil pressure size for calculating 4 position of push pipe, it can also arrange more, the size of connector can also be increased, make to bear Power is bigger.The connector can be covered with the interface of every push pipe 4 Yu supporting ring beam 2 adjacent to each other.The connector includes spiral shell Bolt 6 and T-shaped piece 7, wherein the bolt 6 is preset in the arrangement of reinforcement layer, and described 7 one end of T-shaped piece is welded on 4 outside of push pipe, separately One end is connect by the bolt 6 with the supporting ring beam 2.The connector connects every push pipe and supporting ring beam, further Firm pipe curtain and tunnel portal structure.
As shown in figure 4, the T-shaped piece 7 is by lateral steel plate 7-1 and longitudinal direction steel plate 7-2 by being welded to form T-type, the cross There is screw hole on steel plate 7-1, connect with bolt 6 preset in supporting ring beam 2, the longitudinal direction steel plate 7-2 is soldered to the top The outside of pipe 4.The transverse direction steel plate 7-1 is the square steel plate of high 30cm wide 30cm thickness 2cm, and the longitudinal direction steel plate 7-2 is height The orthogonal steel plate of 30cm wide 30cm thickness 2cm.
The T-shaped piece material is easy to get, low in cost convenient for manufacture.It compared with prior art, can be in every push pipe jacking Implement connection immediately after the completion, it is not necessary to wait whole pipe curtains that could apply after the completion.The connector can be directed to every push pipe Stress difference carry out specific configuration, to improve process efficiency, and there is no the concrete curing phase, thus save significantly on cost and Time.
Preferably, as shown in Fig. 2, being welded with multiple L-type steel muscle 8, institute inside and outside the annular orifice pipe nest of tubes The one end for stating L-type steel muscle 8 is welded on 3 outside of the orifice tube, and the other end is deep into the arrangement of reinforcement layer, by orifice tube with match Muscle layer securely connects.
Preferably, cement slurry has been filled in the gap between orifice tube 3 and push pipe 4, so as to generate waterproof action, The moisture and mud for preventing main structure rear ooze out into active well.
In short, compared with prior art, the present embodiment uses orifice tube and arrangement of reinforcement layer building supporting ring beam, by push pipe pipe curtain It is integrated with active well main structure, to improve the structural strength of active well tunnel portal wall in new pipe-roof method, reduces and collapse Risk is obviously improved construction quality.And simple process, material are easy to get, and it is low in cost, it is time-consuming less.
The above is only the preferred embodiment of the utility model, not does limit in any form to the utility model System, done any modifications, equivalent replacements, and improvements etc., should be included in this reality within the spirit and principle of the utility model Within novel protection scope.

Claims (6)

1. a kind of new pipe-roof method active well ruggedized construction, which is characterized in that set around push pipe (4) the pipe curtain at tunnel piercing hole It is equipped with supporting ring beam (2), the supporting ring beam (2) includes:
Annular orifice pipe nest of tubes, for the ring structure being made of more steel orifice tubes (3), every orifice tube (3) covers in phase Answer push pipe (4) outside, the internal diameter of the orifice tube (3) is greater than the outer diameter of the push pipe (4);
Arrangement of reinforcement layer, for the steel hoop grid being arranged along the inner side and outer side of the annular orifice pipe nest of tubes;
The supporting ring beam (2) and the main structure of the active well (1) are integrated by concreting, the supporting ring beam (2) it is connect by connector with push pipe (4).
2. new pipe-roof method active well ruggedized construction according to claim 1, which is characterized in that every push pipe (4) is provided with At least two connectors, the connector are separately positioned on inside and outside pipe curtain.
3. new pipe-roof method active well ruggedized construction according to claim 2, which is characterized in that the connector includes bolt (6) and T-shaped piece (7), wherein the bolt (6) is preset in the arrangement of reinforcement layer, and described T-shaped piece (7) one end is welded on push pipe (4) outside, the other end are connect by the bolt (6) with the supporting ring beam (2).
4. new pipe-roof method active well ruggedized construction according to claim 3, which is characterized in that the T-shaped piece (7) is by transverse direction Steel plate (7-1) and longitudinal steel plate (7-2) have screw hole on the transverse direction steel plate (7-1), with bracing ring by being welded to form T-type Preset bolt (6) connection, the longitudinal direction steel plate (7-2) are soldered to the outside of the push pipe (4) on beam (2).
5. new pipe-roof method active well ruggedized construction according to any one of claim 1 to 4, which is characterized in that described to match It is connect between muscle layer and the orifice tube (3) by multiple L-type steel muscle (8), one end of the L-type steel muscle (8) is welded on described On orifice tube (3) outside, the other end is deep into the arrangement of reinforcement layer.
6. new pipe-roof method active well ruggedized construction according to claim 1, which is characterized in that the orifice tube (3) and institute It states in the gap between push pipe (4) and fills cement slurry.
CN201820554294.6U 2018-04-18 2018-04-18 A kind of new pipe-roof method active well ruggedized construction Active CN208236429U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820554294.6U CN208236429U (en) 2018-04-18 2018-04-18 A kind of new pipe-roof method active well ruggedized construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820554294.6U CN208236429U (en) 2018-04-18 2018-04-18 A kind of new pipe-roof method active well ruggedized construction

Publications (1)

Publication Number Publication Date
CN208236429U true CN208236429U (en) 2018-12-14

Family

ID=64584103

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820554294.6U Active CN208236429U (en) 2018-04-18 2018-04-18 A kind of new pipe-roof method active well ruggedized construction

Country Status (1)

Country Link
CN (1) CN208236429U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108343450A (en) * 2018-04-18 2018-07-31 中铁十四局集团有限公司 A kind of new pipe-roof method active well ruggedized construction and reinforcement means
CN110439590A (en) * 2019-08-06 2019-11-12 中铁十四局集团有限公司 Method for tunnel construction
CN113338947A (en) * 2021-04-14 2021-09-03 浙江交工集团股份有限公司 Sand-flowing-preventing water-gushing working well for water-rich sand layer and construction method thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108343450A (en) * 2018-04-18 2018-07-31 中铁十四局集团有限公司 A kind of new pipe-roof method active well ruggedized construction and reinforcement means
CN108343450B (en) * 2018-04-18 2023-11-03 中铁十四局集团有限公司 Novel pipe curtain method working well reinforcing structure and reinforcing method
CN110439590A (en) * 2019-08-06 2019-11-12 中铁十四局集团有限公司 Method for tunnel construction
CN113338947A (en) * 2021-04-14 2021-09-03 浙江交工集团股份有限公司 Sand-flowing-preventing water-gushing working well for water-rich sand layer and construction method thereof
CN113338947B (en) * 2021-04-14 2024-04-09 浙江交工集团股份有限公司 Water-rich sand layer anti-flowing sand water-surge working well and construction method thereof

Similar Documents

Publication Publication Date Title
CN110017144B (en) Loess tunnel three-step construction method considering substrate reinforcement treatment
CN104533446A (en) Construction method and structure of two-layer preliminary support for preventing geological disaster of large-section weak surrounding rock tunnel
CN112228082B (en) Tunnel collapse treatment method by combined grouting of pipe shed and advanced small guide pipe
CN108278116B (en) Shallow-buried large-span pipe curtain supporting system and construction method thereof
CN208236429U (en) A kind of new pipe-roof method active well ruggedized construction
CN103321659A (en) Large-diameter tube curtain support underground excavation construction super-shallow burying large-section subway station structure and construction method
CN108343450A (en) A kind of new pipe-roof method active well ruggedized construction and reinforcement means
CN110318772B (en) Large-span small-clearance asymmetric section tunnel supporting structure in loess area and construction method
CN108412128A (en) A kind of connection structure of steel core concrete column
CN111502696A (en) Dense-mesh type advanced support system of underground excavation tunnel and construction method
CN107965341A (en) A kind of large-section underground pipe canopy pipe network concrete support method
CN106400820A (en) Cofferdam formed by latched steel tube and concrete combined piles and construction method
CN115324591A (en) Saturated soft loess tunnel subsection precipitation-support comprehensive construction method
CN109538236B (en) Tunnel entering structure and tunnel entering construction method
CN110230496A (en) A kind of three step of big cross section soft stratum tunnel, four step is interlocked construction method
CN115467690A (en) Shallow-buried large-span underground excavation subway station new structure system and construction method thereof
CN112302687B (en) Support-changing and jacking construction method for entering main tunnel of tunnel inclined shaft
CN110924985A (en) Long rock pillar construction method suitable for overlying thin rock stratum
CN112282771A (en) Rapid construction method for super-large-span highway tunnel
CN219157638U (en) Pile type ground wall joint
CN214574083U (en) High formwork foundation structure
CN117967323B (en) Reinforcing ring structure at hydraulic tunnel fork-to-branch hole interface and roof-picking construction method
CN220890202U (en) Prefabricated forming structure of underground excavation small pilot tunnel body
CN219061652U (en) Middle-short range underground pipeline jacking pipe tunnel construction device
CN212534232U (en) Protection device for construction of penetrating large-scale rigid box culvert under power pipe gallery

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant