CN208236000U - New increasing steel beam and concrete column hinged joint - Google Patents

New increasing steel beam and concrete column hinged joint Download PDF

Info

Publication number
CN208236000U
CN208236000U CN201820585572.4U CN201820585572U CN208236000U CN 208236000 U CN208236000 U CN 208236000U CN 201820585572 U CN201820585572 U CN 201820585572U CN 208236000 U CN208236000 U CN 208236000U
Authority
CN
China
Prior art keywords
steel
new increasing
steel beam
stiffener
concrete column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820585572.4U
Other languages
Chinese (zh)
Inventor
赵恩鹏
毛艺帆
郭传林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SIPPR Engineering Group Co Ltd
Original Assignee
SIPPR Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SIPPR Engineering Group Co Ltd filed Critical SIPPR Engineering Group Co Ltd
Priority to CN201820585572.4U priority Critical patent/CN208236000U/en
Application granted granted Critical
Publication of CN208236000U publication Critical patent/CN208236000U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model discloses a kind of new increasing steel beam and concrete column hinged joint, including concrete column, the side of the concrete column is connected with the first steel buried plate and the second steel buried plate by bar planting;The first steel buried plate is connected by connecting plate and high-strength bolt with new increasing steel beam, and stiffener on stiffener and second is provided on first on the new increasing steel beam;The steel corbel being connected on the second steel buried plate below new increasing steel beam, it is provided with cushion block between the steel corbel and new increasing steel beam and is bolted by installation, the corresponding with Board position of putting more energy on described first first lower stiffener is provided on steel corbel on the downside of the cushion block, and steel corbel end is additionally provided with the corresponding with Board position of putting more energy on described second second lower stiffener.The utility model stabilized structure, stress are clear, are easy to construct, and construction quality can satisfy the stress and detailing requiments of corresponding node.

Description

New increasing steel beam and concrete column hinged joint
Technical field
The utility model relates to concrete columns, and reinforcement technique field is transformed, more particularly, to a kind of new increasing steel beam and concrete Column articulated node.
Background technique
In the transformation and reinforcing project of concrete column, if necessary to increase girder steel in column side face, generally use hinged Design.Traditional method is that steel buried plate is fixed on pillar side by bar planting, then passes through connecting plate and high-strength bolt for girder steel It is connected on steel buried plate.The hinged joint structure is simple, stress is clear, is easy to construct.But when new increasing steel beam is located at concrete When column end, the burial place of bar planting is generally in the nucleus that reinforcing bar is more intensive inside beam column built from concrete, at this time bar planting Drilling corresponding position and depth are difficult to ensure that construction quality is not easy to control, lead to the stress and construction that are not able to satisfy corresponding node It is required that.
Summary of the invention
To solve the above-mentioned problems, the utility model provides a kind of construction quality easily controllable new increasing steel beam and concrete Column articulated node.
To achieve the above object, the utility model can take following technical proposals:
New increasing steel beam described in the utility model and concrete column hinged joint, including concrete column, the concrete column Side the first steel buried plate and the second steel buried plate are connected with by bar planting;The first steel buried plate passes through connecting plate and high-strength bolt It is connected with new increasing steel beam, and is provided on first stiffener on stiffener and second on the new increasing steel beam;Second steel buries The steel corbel being connected with below new increasing steel beam on plate is provided with cushion block and passes through peace between the steel corbel and new increasing steel beam Dress is bolted, and is provided on the steel corbel on the downside of the cushion block and is put more energy into under Board position corresponding first of putting more energy on described first Plate, and steel corbel end is additionally provided with the corresponding with Board position of putting more energy on described second second lower stiffener.
Stiffener is arranged along new increasing steel beam bilateral on stiffener and second on described first, and with newly-increased steel beam flange etc. It is wide.
Described first lower stiffener and the second lower stiffener are arranged along steel corbel bilateral, and wide with the steel corbel edge of a wing.
New increasing steel beam provided by the utility model and concrete column hinged joint, in the side of concrete column, setting is for branch The steel corbel for supportting new increasing steel beam, due to a height of steel bottom elevation of steel corbel top mark, so that the steel buried plate bar planting of connection steel corbel is bored Hole site is lower than the beam column built from concrete nucleus of original structure, and stabilized structure, stress are clear, are easy to construct, and matter of constructing Amount can satisfy the stress and detailing requiments of corresponding node.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model.
Specific embodiment
As shown in Figure 1, new increasing steel beam described in the utility model and concrete column hinged joint, including concrete column 1, Side is connected with the first steel buried plate 3 and the second steel buried plate 4 by bar planting 2.Wherein, the first steel buried plate 3 passes through connecting plate 5 and high-strength Bolt 6 is connected with new increasing steel beam 7, and the second steel buried plate 4 is connected with the steel corbel 10 for being used to support new increasing steel beam 7.First steel buried plate 3 Mainly as constraint support to guarantee the out-of-plane stabilization of new increasing steel beam 7, bar planting herein and the specification selection of high-strength bolt can be only From the aspect of construction loads.10 pressure-bearing of steel corbel has newly increased new increasing steel beam 7 and the articulated connection node of concrete column 1, has made to hold The the second steel buried plate 4 sheared moves down into except 1 nucleus of concrete column, so that steel planting is convenient to carry out, thus preferably Ground controls construction quality.To guarantee to carry out clear power transmission between new increasing steel beam 7 and steel corbel 10, usually setting is padded therebetween Block 11, cushion block size 11 are designed according to plate bearing, while being correspondingly arranged on to be located above and below cushion block 11 and be increased newly On girder steel 7 first on stiffener 8 and the first lower stiffener 13 on steel corbel 10;To prevent new increasing steel beam 7 because of amount of deflection It is larger, generate with the contact power transmission of 10 end of steel corbel, need 10 end of steel corbel welding second under stiffener 14, Yi Ji Stiffener 9 on welding is opposite with the second lower 14 position of stiffener on new increasing steel beam 7 second, the part that steel corbel is effectively ensured are steady It is fixed.Stiffener 9 is welded on new 7 bilateral of increasing steel beam and wide with the edge of a wing on stiffener 8 and second on above-mentioned first, puts more energy under first Plate 13 and the second lower stiffener 14 are welded on 10 bilateral of steel corbel and wide with the edge of a wing.For convenient for construction and installation, in steel corbel 10 It is connected between 7 lower flange of top and new increasing steel beam with installation bolt 12, the section that the part should be included in when designing steel corbel 10 is cut It is weak.

Claims (3)

1. a kind of new increasing steel beam and concrete column hinged joint, including concrete column (1), it is characterised in that: the concrete column (1) side is connected with the first steel buried plate (3) and the second steel buried plate (4) by bar planting (2);The first steel buried plate (3) passes through Connecting plate (5) and high-strength bolt (6) are connected with new increasing steel beam (7), and are provided with stiffener on first on the new increasing steel beam (7) (8) stiffener (9) and on second;The steel corbel being connected on the second steel buried plate (4) below new increasing steel beam (7) (10), it is provided with cushion block (11) between the steel corbel (10) and new increasing steel beam (7) and is connect by installing bolt (12), it is described The corresponding with stiffener (8) position on described first first lower stiffener is provided on steel corbel (10) on the downside of cushion block (11) (13), and steel corbel (10) end is additionally provided with corresponding with stiffener (9) position on described second second lower stiffener (14).
2. new increasing steel beam according to claim 1 and concrete column hinged joint, it is characterised in that: put more energy on described first Stiffener (9) is arranged along new increasing steel beam (7) bilateral on plate (8) and second, and wide with new increasing steel beam (7) edge of a wing.
3. new increasing steel beam according to claim 1 and concrete column hinged joint, it is characterised in that: put more energy under described first Plate (13) and second lower stiffener (14) are arranged along steel corbel (10) bilateral, and wide with steel corbel (10) edge of a wing.
CN201820585572.4U 2018-04-24 2018-04-24 New increasing steel beam and concrete column hinged joint Active CN208236000U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820585572.4U CN208236000U (en) 2018-04-24 2018-04-24 New increasing steel beam and concrete column hinged joint

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820585572.4U CN208236000U (en) 2018-04-24 2018-04-24 New increasing steel beam and concrete column hinged joint

Publications (1)

Publication Number Publication Date
CN208236000U true CN208236000U (en) 2018-12-14

Family

ID=64585396

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820585572.4U Active CN208236000U (en) 2018-04-24 2018-04-24 New increasing steel beam and concrete column hinged joint

Country Status (1)

Country Link
CN (1) CN208236000U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110107109A (en) * 2019-04-24 2019-08-09 西安长庆科技工程有限责任公司 A kind of steel and concrete structure extend beam-column joint connecting structure method
CN111794513A (en) * 2020-07-23 2020-10-20 中亿丰建设集团股份有限公司 Construction method of assembled floor slab
CN114808716A (en) * 2022-04-27 2022-07-29 中铁高新工业股份有限公司 Construction method of hinged steel pier

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110107109A (en) * 2019-04-24 2019-08-09 西安长庆科技工程有限责任公司 A kind of steel and concrete structure extend beam-column joint connecting structure method
CN111794513A (en) * 2020-07-23 2020-10-20 中亿丰建设集团股份有限公司 Construction method of assembled floor slab
CN114808716A (en) * 2022-04-27 2022-07-29 中铁高新工业股份有限公司 Construction method of hinged steel pier

Similar Documents

Publication Publication Date Title
CN208236000U (en) New increasing steel beam and concrete column hinged joint
CN106567458B (en) Assembled steel-is mixed to combine Beam-post Frame Structure system
CN207959600U (en) A kind of precast shear wall horizontal joint connection structure with I-steel
CN108412128A (en) A kind of connection structure of steel core concrete column
CN202706332U (en) Steel reinforced concrete composite structure post bracket
CN103866693A (en) Installing method of reinforced concrete bowstring rod arch bridge arch ribs and hanging auxiliary bridge
CN205712590U (en) A kind of fabricated shear wall and the attachment structure of Prefabricated concrete-filled steel tube post
CN202324203U (en) Connecting node structure for existing concrete column and new steel column
CN114396176B (en) Reinforcing device and reinforcing method for steel beam column connecting node
CN108643219A (en) A kind of assembled transmission line of electricity anchor rod static pressure Minitype pile foundation and its construction method
CN211172412U (en) Connecting joint of beam main rib and cross steel rib column
CN108867885A (en) The damping energy dissipation assembly node and its construction method of prefabricated post and integral preform beam slab
CN206360399U (en) The existing reinforced concrete coupling beam bracing means of one species " doubly-linked beam "
CN205935193U (en) Concrete frame with high steadiness beam column node
CN206360706U (en) A kind of screwed joint attachment structure being used between extra-large shield-driven tunnel section of jurisdiction
CN102359185A (en) Connecting structure of large steel structural member and concrete member and construction method
CN208981567U (en) A kind of assembly concrete shear wall connecting joint structure
CN217872835U (en) Tunnel top-lifting arch bracket tool suitable for assisting tunnel-to-main-tunnel construction
CN206016305U (en) Viscous damping wall integration support system
CN205604283U (en) Building bar planting concrete column
CN205778936U (en) A kind of support bracket and supporting construction
CN211499835U (en) Auxiliary device for installing prefabricated part
CN203113368U (en) Communication tower valve base
CN104775608B (en) Integrated lifting platform attachment device for special layer height position
CN211143826U (en) Node connecting device for newly adding beam on existing reinforced concrete column beam

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant